Prepare an arrow diagram and a list of starts, finishes and floats for a project involving the listed.
15 21 27
G J
5 6 8 6 11
D M
15 21 27
8 7
3 5
B E
8
0 3 6 188 22 27 32 36
A 5 H K N P
1 2 7 1000000 12 13
4 5 3 4 14
3 F
0 3 C 20 24 29 32 36
11 I’
44 77 0 O
10 17
I L 2
4 6 9
3 7
9 29 29
ACTIVITY DURATION ACTIVITY W/C IMMEDIATELY STARTS FINISHES FLOATS
PRECEDE FOLLOW ES LS EF LF TF FF
A 3 NONE B,C 0 0 3 3 0 0
B 5 A D,E 3 3 8 8 0 0
C 4 A F,I 3 5 7 9 2 0
D 7 B G 8 8 15 15 0 0
E 6 B H 8 14 18 20 6 4
F 11 C H 7 9 18 20 2 0
G 6 D J 15 15 21 21 0 0
H 4 E,F K 18 20 22 24 2 0
I 3 C K,L 17 19 10 22 12 0
J 6 G M 21 21 27 27 0 0
K 5 H,I N 22 24 27 29 2 0
L 7 I O 10 22 17 29 12 0
M 5 J P 27 27 32 32 0 0
N 3 K P 27 29 32 32 2 2
O 2 L P 17 30 32 32 13 13
P 4 M,N,O NONE 32 32 36 36 0 0