14 - JSA For Replacement of Tube Bundles of (100-EA4-C3, C8) & 284-E52 & 810E7 With New One

This document provides a job safety analysis for replacing the tube bundle of several pieces of equipment. It identifies potential hazards such as falling, injuries from tools or materials, and unauthorized access. It lists required personal protective equipment including safety helmets, shoes, coveralls, fire extinguishers, radios, gloves, lifelines, and gas masks. Control measures are outlined for each step, including permitting, inspections, authorized operators, barricades, and proper supervision. Responsibilities are assigned to ensure safety procedures are followed.

Uploaded by

SHAH NAWAZ SAEED
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
437 views1 page

14 - JSA For Replacement of Tube Bundles of (100-EA4-C3, C8) & 284-E52 & 810E7 With New One

This document provides a job safety analysis for replacing the tube bundle of several pieces of equipment. It identifies potential hazards such as falling, injuries from tools or materials, and unauthorized access. It lists required personal protective equipment including safety helmets, shoes, coveralls, fire extinguishers, radios, gloves, lifelines, and gas masks. Control measures are outlined for each step, including permitting, inspections, authorized operators, barricades, and proper supervision. Responsibilities are assigned to ensure safety procedures are followed.

Uploaded by

SHAH NAWAZ SAEED
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

JOB TITLE: REPLACEMENT OF TUBE BUNDLE OF (100-EA4-C3, C8) & 284-E52

JOB SAFETY ANALYSIS


& 810-E7 with new one.
JSA No. Unit No.-XXX
PARCO- Mid Country Refinery DOC. #: PAR-MCR-HSE/HS-SOP-020-F-001
ANALYSIS BY: REVIEWED BY: Issue # 02 Issue Date:
JOB SAFETY ANALYSIS
Page 1 of 3 15-09-2017
Name: Name:

Name: Name: DATE: 24-11-2018

Name: Name:

Scope (Description of work): REPLACEMENT OF TUBE BUNDLE OF (100-EA4-C3, C8) & 284-E52 & 810-E7 with new one.

Required and recommended PPEs: Safety Helmet, Safety Shoes, Coverall, Fire Extinguisher, Radio Sets, Lather glove, Life line, Gas mask,
Goggle. Full body harness

Required Tools, Drawings and materials etc. for the job:

Basic Job Steps Potential Hazards Control Measures Responsibility


1. Shifting of scaffolding 1. Falling hazard. 1. PTW for Vehicle entry to be followed.
material at site through 2. Hand/foot injury. 2. Safety helmet, safety shoes, spectacles and gloves should be used. DESCON/ PARCO
trolley. 3. Striking. 3. During driving speed limit does not exceed 20 KM per hour. Process
4. Over speeding. 4. Barricade the working area with caution tape.
5. Unauthorized access. 5. Only authorized driver to drive the vehicle.

2. Shifting of scaffolding 1. Uninspected crane and 1. Cold work permit should be obtained.
material through crane at lifting tackles. 2. Inspected crane and lifting tackles to be used. DESCON/ PARCO
site. 2. Falling hazard. 3. Authorized crane operator to operate the crane. Process
3. Unaided crane movement 4. Barricade the working area with caution tape.
5. Trained banks man must be guided the crane.
3. Erection of scaffolding. 1. Pinch point 1. PTW procedure to be followed.
2. Tool may slip. 2. All person involved in the job will use cotton gloves, Helmet, safety
3. Falling hazards harness, spectacles and safety shoes. DESCON HSE/
4. Unauthorized access. 3. Trained Scaffolder will perform the job under the supervision of EXECUTION
supervisor.
4. Use tool lane yard during erection of scaffolding.
5. Wear full body harness while working at height for erection of
scaffolding at Fin fan cooler.
6. Nobody can do any type of job under the working area during
scaffolding erection.
7. Scaffolding should be erected according to OSHA checklist.