SHD ACT PMC DDR 009 R0 Design Development Report
SHD ACT PMC DDR 009 R0 Design Development Report
Distribution
(company) (names)
UNIQUIE HOTELS &
Noor Ali, Nadiha Ali, Carol Kfouri, Senthil Nathan ;Limon Mahmud,
RESORTS Pvt. Ltd. -
Tanveer Azad &Mahbub.
Owners
Starwood (SW) Steven Tan, WengLeong Chan, Vikas Malik
Operator
Consultants
Ascentis (ASC) – Salil Khare, Rahul Jain, Anand Gautam, Asim Biswas, Somnath
Project Manager Chakraborty, Aashu Jain
Place, Description
# Date Key Points / Agenda
& attendees
past Fortnight(1st Feb’16 – 15th Feb’16 - )
Coordination Meeting
1 02-02-16 MEP coordination
WSP – ASC SITE
CONCALL
Structural update meeting to discuss and close pending issues
3 Coordination Meeting
03-02-16 and update on progress.
AIT – ASC SITE
07-02-16 SITE OFFICE
4 Site Meeting Meeting with Sunil Khemani (APOSTLE) and site walk
APOSTLE & ASC SITE
VZ OFFICE
08-02-16 : Further coordination on receiving of Aedas Layouts
5 Coordination Meeting
VZ – ASC SITE
Design Update
Meeting Design Coordination meeting to discuss and close pending
6 09-02-16
UHR- ASC SITE- ASC issues and update on progress.
HO
VZ OFFICE To discuss and coordinate façade revisions and shop drawings /
10-02-16 Coordination Meeting
7 quotations
VZ – ASC SITE-
ARMAAN ENGG.
Client’s office
11-02-16 Volume Zero- façade presentation at Unique Oval.
8 Presentation meeting
VZ, UHR, ASC
SITE OFFICE Coordination meeting with ZOHA / WSP , after receiving the ID and
Coordination Meeting BOH revised layouts. To expedite resolving MEP decisions to move
9 14-02-16
WSP, ADS-HPG– ahead.
ASC SITE & HO
Discussion on pending reports & ballroom roof report
15-02-16 CONCALL
10
AIT, ASC
Site office
Kick off meeting with Tilottoma team at site for ID mock up works
1 16-02-16 Kick off meeting
Tilottoma & ASC
Site office Discuss and resolve Critical Drawings requirement for Structure
17-02-16
2 Coordination meeting coordination & Civil work Execution
VZ & ASC
SITE OFFICE Kick off meeting with Armaan Engineering team at site for façade
3 17-02-16 Coordination Meeting works
ASC SITE &Armaan
Site
Mock up RFI meeting with Tilottoma at Site
4 22-02-16 Site meeting
Tilottoma & ASC
CONCALL Concall meeting with AIT : for structural report Discuss
5 23-02-16
AIT, ASC
Risk
# Ref. No. Start Date Description Due By Status
À $
RFP
STATUS -CLOSED
• RFP SENT – Quote awaited –
27th Nov
• Quote received and forwarded to Site &UHR- Under review by
20 Dec
client.
• RFP SENT to DRSS ON 16thDec’15, Quote Received
1 ----- 6th Nov’15 Appointment of IT consultant 10Jan16
• UHR wants Additional scope of work to be added in RFP- Sent H H
25 Jan16
for comments to Techno consultants. They have accepted to
16th Feb16
incorporate points without any commercial implication
• Negotiation and award to be planned.
• Techno consultants appointed
20th Nov STATUS -CLOSED
15 Dec • RFP Sent & Quote received
Appointment of FLS Consultant 10Jan16 • Quote forwarded to UHR - Under review.
2 ----- 6th Nov’15 30Jan16 • More RFPs to be sent for comparative quotations. H H
16th Feb16 • RFP sent to Mr. Mujumdar- Kolkata, quote received and forwarded to
site.
• Fyrprotek appointed
STATUS -OPEN
• RFP sent to “ Lifestyle fitness” & “Sansha world”
• Lifestyle Quote received and forwarded to SW for comments.
• Also forwarded to Site &UHR& SW
• Reverts on the New RFPs sent, expected by 12Jan16
27th Nov
• Additional RFPs to be sent to SPA Consultants suggested by SW
15 Dec
on 28THDEC’15
24th Dec
Appointment of SPA consultant. • RFP Sent to “A.W Lake” & “International Leisure consultants” on
3 ----- 6th Nov’15 30Jan16
29thDec’15. Reverts expected by 12Jan16 H H
05 Feb16
• “A.W Lake”- REVERTED ON 12thJan16
29TH Feb
• Comparative statement to be made.
• Scope of spa RFP changed. Revised quote requested from
Consultants.
• Revised Comparative to be made.
• COMPARATIVE AND ALL DOCUMENTS SENT TO SITE. Under
review from UHR - 8.02.2016
STATUS – CLOSED
15 Jan 16
Brief on up-gradation of shopping • Scope for up-gradation of shopping area need to be finalized and
8 ----- 12 Jan’16
area
05 Feb16
interior design consultant to be appointed. Under review from UHR H H
• VOLUME ZERO Appointed
9 ----- 7 Dec’15 Appointment of AV consultant. 29TH Feb ‘16 STATUS -OPEN
RFP sent to Techno consultants. 18Dec’15,
RFP sent to CCW – 12Jan 2016 H H
Comparative and recommendation sent to site. 23/Feb 2016
Under review from UHR
10 ----- 8Feb’16 Appointment of ACCOUSTIC 29th Feb’16 STATUS -OPEN
consultant. RFP sent to Techno consultants, CCW, Ask consultants, ACVIRON
One quote received from Ask Consultants. Techno & ACVIRON H H
expressed regret, CCW did not reply.
Recommendation to be sent.
6
STR 01.11.15 Validation by structure peer review
consultant
the areas of concern to further review by local structure AIT 15th Feb’16 H H
designer 29th Feb’16
• Analysis for balance floors is still pending
7 STATUS: CLOSED.
Coordination with the Façade Vendor and VZ in progress.
20 Jan 2016
FACADE 24.12.15 Extending the curtain wall upto the
edge of the Façade.
Changes captured in VZ architectural base set, to be discussed VZ
20th Feb’16 M M
with Façade vendor.
Façade completely developed and approved. – 15-02-16
8 STATUS: OPEN
• VZ instructed to develop construction drawings for the ADD,
as conceptualized by AEDAS. This includes Extension of ADD
ARC 24.12.15 New construction for the ADD, on the
16th level
on the Ball room Roof, And ADD roof. VZ 29th Feb’16 H H
• Conceptual elevations and plans developed and
approved by UHR. Working drawings to proceed.
10 Status – OPEN
2 Service lifts on the south side- STR asked to develop the structural GFC for further
STR structural drawings for the same to construction of the Lifts
STR TBD H H
be given by STR.
11 Status – OPEN
STR asked to develop the GFC for further construction of
STR Swimming pool Drawings to be
developed by STR the swimming pool based on VZ architectural drawings.
STR TBD H H
12 Status – OPEN
Openings in the shear walls coming STR to evaluate if the openings are possible.
STR in the presidential suite, as asked for STR TBD H H
by AEDAS
3 ID Aedas Public Area Blockplans markups (ID layouts on base architectural set) 19.02.16
4 ARCH VZ Volume Zero Block Plan Set (UPDATED WITH ID AND FACILITY LAYOUTS) 20.02.16
5 Lighting PLD Revised MUR Lighting Specifications Booklet and Corridor Drawing 16.02.16
Suggestions / comments given by the client & operator in the Design presentation Meeting ON 23RDDec’15to be
incorporated and final concept design report to be submitted.
1 ID ADS TBD M M
1. PUBLIC AREAS
2. GUEST ROOMS
3. Corridor layouts
LIGHTIN
6 PLD Layouts on ID base set TBD
G
Baseline Risk
Completion À
DISCIPLINE STAGE Date Progress Status
27.07.17
• All GFC’s has been issued to site.
19.09.15
• Further Changes proposed and approved. Revised GFC’s to be
ID – MUR CD 100%
issued. H
12.01.16
• Revised MUR package received from ADS. – 12.01.16
20.09.15
MEP– MUR CD 100% • Revisions to be addressed through RFIs
15.01.16
04.12.15
Review to start during design development/ after finalization of 100%
IT Concept 0%
schematic stage of ID and MEP L
15.01.16
04.12.15
Review to start during design development/ after finalization of 100%
FLS Design Dvpt. 0%
schematic stage of ID and MEP M
30.01.16