0% found this document useful (0 votes)
68 views12 pages

Plant Life Management International Atomic Energy Cernavoda NPP Strategy PDF

This document discusses Plant Life Management (PLiM) at S.N. Nuclearelectrica S.A., the state-owned nuclear power company in Romania. It owns and operates two units at the Cernavoda NPP. A PLiM program was started in 2003 to manage aging and ensure long-term reliable operation of critical systems, structures, and components (SSCs) through 2023 and beyond. The program involves strategies for component life assessment, maintenance, inspection, replacement, and licensing. Major SSCs selected for the PLiM program include fuel channels, feeders, steam generators, heat exchangers, piping, cables, transformers, and turbines. The program is ongoing with some

Uploaded by

mihaela_filip_8
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views12 pages

Plant Life Management International Atomic Energy Cernavoda NPP Strategy PDF

This document discusses Plant Life Management (PLiM) at S.N. Nuclearelectrica S.A., the state-owned nuclear power company in Romania. It owns and operates two units at the Cernavoda NPP. A PLiM program was started in 2003 to manage aging and ensure long-term reliable operation of critical systems, structures, and components (SSCs) through 2023 and beyond. The program involves strategies for component life assessment, maintenance, inspection, replacement, and licensing. Major SSCs selected for the PLiM program include fuel channels, feeders, steam generators, heat exchangers, piping, cables, transformers, and turbines. The program is ongoing with some

Uploaded by

mihaela_filip_8
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

PLANT LIFE MANAGEMENT

for LONG TERM OPERATION


S.N. NUCLEARELECTRICA S.A.
ROMANIA
BACKGROUND

• S. N. NUCLEARELECTRICA S.A. (SNN) – STATE OWNED COMPANY (Public


Company since 2013)

• 2 SUBSIDIARIES : - Cernavoda NPP: 2 X 706,5MW


- Nuclear Fuel Plant in Pitesti

• NPP : - U1 - in operation since 1996;


- GCP since in operation 90,37%;
- shutdown for refurbishment
predicted in 2023
- U2 - in operation since 2007;
- GCP since in operation 94,54%
- U3&4 – planned for completion
STRATEGY & PLANNING
• Development of a PLiM Program strategy for Cernavoda Unit 1 was started
in 2003.
• Pilot projects for PLiM (8 projects) were initiated in 2002 (Define PLiM
Program, implementation strategy and prepare generic instructions for
documenting PLiM programs; Life Assessment of Major Components;
Criticality Ranking of Cernavoda Unit 1 SSC; Monitoring of Maintenance
Programs efficiency at system and component level; Equipment
Obsolescence Identification and Prioritisation; EQ Program (EQ and Shelf
Life); Passive Components Aging Management ; Plant equipment data
bases and systems definition reconciliation (MEL, piping and supports
components database validation, prerequisite for SSC’s criticality ranking)
• An initial aquisition strategy for PLiM components approved in 2010;
revised in 2013 to cope for problems encountered;
• Plant life extension strategy was preliminary approved through BoD
Decision and General Shareholders Assembly Decision (2013) – to approve
PLiM planning and allocation of funds required for acquisition of
remaining studies.
STRATEGY & PLANNING
STRATEGY & PLANNING
• Timeframe:
2023 – shutdown for refurbishment

4 to 5 years procurement and fabrication

2018 contract signed

2017 investment final approval

Feasibility Study approved before 2017

Support studies for input to FS available even sooner
LICENSING
• No specific norm available for Plant Life Extension.
• Preliminary discussions held with the Regulator :
- NSN-02 (design and construction of NPP) and NSN-10 (PSR for NPP)
will apply;
- Norm for operation of NPP expected to be issued by Regulator in
2015, and will contain certain requirements for Plant Life Extension;
- licensing will be supported mainly by PSR and Aging Management
(integrated PLiM);
- PSR would have to be completed early enough to allow for
Regulator review, but not to early - in order to remain relevant (≈ 2021);
- design changes will be required (dealing with severe accidents –
already committed for Units 3&4);
- certain studies will be required (site re-evaluation, exclusion zone re-
evaluation)
- Licensing Basis Document to be issued asap
Cernavoda NPP PLIM program
• Cernavoda NPP strategy to ensure critical SSCs reliability is based on WANO/INPO-AP 913 “Continuous
Equipment Reliability Process” recommendations:
• Scoping and identification of Critical Components;
• SSC Performance Monitoring;
• Corrective Actions;
• Continuing Equipment Reliability Improvement (CER Process);
• Long Term Planning and Life Cycle Management (PLiM Programmes);
• Preventive Maintenance Implementation (PM Programmes).

• Experience from other countries has shown that, if adequate measures are taken to counteract the effects
of aging and degradation on systems, structures, and components (SSCs), many plants are able to meet
nuclear safety and economic efficiency requirements and operate for a long time over their design life.

• In some cases, the Preventive Maintenance Programmes are not an efficient method to mitigate the
degradation mechanisms encountered in some major, very complex critical SSC.

• In these cases a Life Management Program (PLiM) has to be developed and implemented to control in a
comprehensive manner the ageing process ensuring that SSCs age in a predictable manner and continue
to meet the performance standards

• Objectives : - implement & document technical programs for selected major Structures and Components;
- implement and document CHM Plans for selected Structures and Components;
- optimize CHM Plans through periodic condition assessment and ramaining life assessment.
Cernavoda NPP PLIM program
- STATUS -
• Procedures and Instructions issued to support the elements required by PLiM
Program (maintaining SSC reliability, selection of critical components, critical
systems health monitoring, critical components health surveillance program,
plant life management);
• Major critical components selected for PLIM:
- fuel channels
- feeders
- steam generators
- HXs
- piping (errosion-corrosion; buried pipes; supports; snubbers; expansion joints; small bore
pipe)
- cables
- Large Power Transformers
- Digital Control Computers (DCCs)
- Turbogenerator
- Reactor Building
- SDGs (added later)
• For all selected components the program manuals were issued, except for
SDGs (to be issued in 2015)
Cernavoda NPP PLIM program
- STATUS -
• Plant Life Cycle Plan approved , to ensure that activities are planned and
resourced for PLiM programs implementation.

• Our approach: - external support from companies with proven experience


(B&W, GE, CANDU etc.);
- collaborations (COG programs for CANDU specific
components: fuel channels, feeders, system chemistry;
some local engineering and research companies; EPRI for
HXs and piping; original equipment manufacturers)

• A typical long term complete services package (Framework Agreement) for


PLiM covers life assessment evaluation, complex inspection, maintenance
/repair activities and periodic condition assessment studies.
Cernavoda NPP PLIM program
- STATUS -
• Status:
– Fuel channels: Framework Agreement in place; LA study to be issued in 2015 (first
issue); revision in 2018
– Feeders: Framework Agreement in place; LA study to be issued in 2015 (first issue);
revision in 2018
– Turbogenerator: Framework Agreement in place; LA study issued in 2012 (one
recommendation with budgetary impact, related to the replacement of old
Generrex system with a new generation excitation system in 2016)
– Steam generator: Framework Agreement in place; LA study issued in 2012 (no
recommendation with budgetary impact)
– HXs: Framework Agreement in place; LA study for Main condenser issued in 2012
will be revised in 2015 to include the results of metallographic analysis (no
recommendation with budgetary impact so far)
– DCCs: Framework Agreement in place to preserve the strategic stock of Spare
Parts; LA study issued in 2014 (no recommendation with budgetary impact)
– SDGs: LA study issued in 2013 (some recommendation to improve the reliability of
electronic components will be implemented on medium term, others during U1
Refurbishment Outage).
CHALLENGES
• Delays encountered in aquisition of services for program implementation
(sometime due to the slow aquisition process, late validation of some
programs, or new components being added to the program, etc.):
– LA studies still to be contracted for Power Transformers and R/B;
– Complete services for snubbers, expansion joints, cables, buried pipes.
However, execution of approved activities as identified in Program Manuals was not
affected, for active nor for passive PLiM components.
Adherence to the purchasing phases is closely monitored as per the Action Plan issued
and by the end of 2015 the LA studies will be obtained for the most important PLiM
components: Fuel Channels, feeders, Main condenser, Reactor Building, Power
Transformers.

• CTRF : Feasibility Study issued but not approved by SNN CTES.


– Delays in project implementation will adversely impact the Refurbisment Project.
Ideally, CTRF should be in service for 3 years before Refurbishment starts.
THANK YOU !