0% found this document useful (0 votes)
201 views

Sample BOQ

This document appears to be a bill of quantities for construction materials and labor for a building project. It includes three divisions: general requirements, site works, and concrete. The concrete section lists quantities, unit costs, and total costs for various concrete pouring and formwork activities, including footings, tie beams, columns, and suspended floor slabs. It provides a detailed cost estimate for the concrete portion of the project.

Uploaded by

Clarise Almeria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
201 views

Sample BOQ

This document appears to be a bill of quantities for construction materials and labor for a building project. It includes three divisions: general requirements, site works, and concrete. The concrete section lists quantities, unit costs, and total costs for various concrete pouring and formwork activities, including footings, tie beams, columns, and suspended floor slabs. It provides a detailed cost estimate for the concrete portion of the project.

Uploaded by

Clarise Almeria
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 11

PROJECT:

OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST

DIVISION 1 - GENERAL REQUIREMENTS


1.0 Staff Salaries lot 1.00 -
2.0 Overhead Expenses lot 1.00 -
3.0 Temfacil lot 1.00 -
4.0 Bonds lot 1.00 -
Sub-total - - -
TOTAL - DIVISION 1 - - -
DIVISION 2 - SITE WORKS
1.0 Clearing and grubbing sq.m. - 11.10 - -
2.0 Batterboard Installation l.m. 62.50 - 20.36 - -
3.0 Layouting grid line included
4.0 Soil Poisoning sq.m. - 5.90 - -
a Soil Poison lit 4,017.86 - - -
5.0 Excavation cu.m. - 246.96 - -
6.0 Backfilling & Compaction cu.m. - 177.50 - -
7.0 Disposal cu.m. - 172.43 - -
8.0 General Cleaning & Lot Leveling sq.m. - 41.32 - -
Sub-total - - -
TOTAL - DIVISION 2 - - -
DIVISION 3 - CONCRETE
Wall Concrete Footings
WF
1.0 Gravel Bed Laying cu.m. 840.00 - 73.26 - -
2.0 Reinforcement kgs. 50.00 - 10.00 - -
a Rebars 10 mm dia x 6m (Grade 40) pcs
b GI Tie Wire #16 kgs. 88.00 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. 711.97 - -
a Portland Cement (40 kg) bags 247.50 - -
b Sand cu.m. 770.00 - -
c Gravel, 3/4" cu.m. 825.00 - -
Sub-total - - -
Footing Tie Beam
1.0 Gravel Bed Laying cu.m. 840.00 - 73.26 - -
2.0 Reinforcement kgs. 50.00 - 10.00 - -
a GI Tie Wire #16 kgs. 88.00 - - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/4" cu.m. 825.00 - - -
Sub-total - - -
Column Footings
1.0 Gravel Bed Laying cu.m. 840.00 - 73.26 - -
2.0 Reinforcement kgs. 50.00 - 10.00 - -
a Rebars 16 mm dia x 6m (Grade 60) pcs
b GI Tie Wire #16 kgs. 88.00 - - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/4" cu.m. 825.00 - - -
Sub-total - - -
Suspended Floor Slab
1.0 Reinforcement kgs. 50.00 - 10.00 - -
Rebars 10 mm dia x 6m (Grade 40) pcs
a GI Tie Wire #16 kgs. 88.00 - - -
2.0 Formworks sq.m. 194.62 - 182.09 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/8" cu.m. 825.00 - - -
4.0 Concrete Floor Finishing (straight to finish) sq.m. - - -
5.0 Plain cement to protect waterproofing sq.m. - 22.51 - -
a Portland cement bags 247.50 - - -
b Sand cu.m. 770.00 - - -
6.0 drip moulds@deck m - - -
7.0 exposed slab soffit sq.m. - - -
a Portland cement bags - - - -
b Sand cu.m. - - - -
Sub-total - - -
Slab on Fill
1.0 Gravel Bed Laying cu.m. 840.00 - 73.26 - -
2.0 Reinforcement kgs. 50.00 - 10.00 - -
Rebars 10 mm dia x 6m (Grade 40)
a GI Tie Wire #16 kgs. 88.00 - - -
3.0 Formworks sq.m. 194.62 - 182.09 - -

Page 1 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
4.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, G-1 cu.m. 825.00 - - -
5.0 Concrete Floor Finishing (straight to finish) sq.m. - - -
Sub-total - - -

Page 2 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
Beams
1.0 Reinforcement kgs. 50.00 - 10.00 - -
Rebars 10 mm dia x 6m (Grade 40) pcs
Rebars 16 mm dia x 6m (Grade 60) pcs
a GI Tie Wire #16 kgs. 88.00 - - -
2.0 Formworks sq.m. 194.62 - 182.09 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/4" cu.m. 825.00 - - -
Sub-total - - -
Lintel Beams
1.0 Reinforcement kgs. 39.93 - 5.90 - -
a GI Tie Wire #16 kgs. 88.00 - -
2.0 Formworks sq.m. 194.62 - 171.79 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. 678.06 - -
a Portland Cement (40 kg) bags 247.50 - -
b Sand cu.m. 770.00 - -
c Gravel, 3/4" cu.m. 825.00 - -
Sub-total - - -
Column
1.0 Reinforcement kgs. 50.00 - 10.00 - -
Rebars 10 mm dia x 6m (Grade 40) pcs
Rebars 16 mm dia x 6m (Grade 60) pcs
a GI Tie Wire #16 kgs. 88.00 - - -
2.0 Formworks sq.m. 194.62 - 182.09 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - 711.97 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/4" cu.m. 825.00 - - -
Sub-total - - -
Stairs
1.0 Reinforcement kgs. 50.00 - 10.00 - -
a GI Tie Wire #16 kgs. 88.00 - - -
2.0 Formworks sq.m. 194.62 - 182.09 - -
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. - 678.06 - -
a Portland Cement (40 kg) bags 247.50 - - -
b Sand cu.m. 770.00 - - -
c Gravel, 3/4" cu.m. 825.00 - - -
Sub-total - - -
Concrete Ledge
1.0 Reinforcement kgs. -
a GI Tie Wire #16 kgs. - -
2.0 Formworks sq.m. -
included in Suspended Slab
3.0 Concrete Pouring ( one-bagger ) 3000 Psi cu.m. -
a Portland Cement (40 kg) bags - -
b Sand cu.m. - -
c Gravel, 3/4" cu.m. - -
Sub-total - - -
TOTAL - DIVISION 3 - - -
DIVISION 4 - MASONRY
EXTERIOR/INTERIOR CHB Walls
1.0 CHB (6") Laying including Rebars sq.m. - 172.08 - -
a CHB 6" - 400 psi pcs 25.00 - - -
b Portland Cement (40 kg) bags 225.00 - - -
c Rebars 12 mm dia x 6m (Grade 40) pcs 174.07 - - -
d Rebars 10 mm dia x 6m (Grade 40) pcs 120.94 - - -
e Tie wires #16 kgs 88.00 - - -
f Sand cu.m. 650.00 - - -
2.0 Reinforcement to openings kgs - - -
a Rebars 16 mm dia x 6m (Grade 40) pcs - - -
b GI Tie Wire #16 kgs. - - -
3.0 Plastering (16mm thick); Class B sq.m. - 125.15 - -
a Portland Cement (40 kg) bags 225.00 - - -
b Sand cu.m. 650.00 - - -
INTERIOR CHB Walls
1.0 CHB (6") Laying including Rebars sq.m. - 172.08 - -
a CHB 6" - 400 psi pcs 25.00 - - -
b Portland Cement (40 kg) bags 225.00 - - -
c Rebars 12 mm dia x 6m (Grade 40) pcs 174.07 - - -
d Rebars 10 mm dia x 6m (Grade 40) pcs 120.94 - - -
e Tie wires #16 kgs 88.00 - - -
f Sand cu.m. 650.00 - - -
2.0 Reinforcement to openings kgs - - -

Page 3 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
a Rebars 16 mm dia x 6m (Grade 40) pcs - - -
b GI Tie Wire #16 kgs. - - -
3.0 Plastering (16mm thick); Class B sq.m. - 125.15 - -
a Portland Cement (40 kg) bags 225.00 - - -
b Sand cu.m. 650.00 - - -
Sub-total - - -
Pantry Counter Base & Sink
1.0 Formworks sq.m. 194.62 - 171.79 - -
2.0 Reinforcement kgs 5.90 - -
a Rebars, 10 mm dia x 6m (Grade 40) pcs 134.38 - -
b Tie wires #16 kgs 88.00 - -
3.0 Concrete Slab Base & Counter (Assume 2500psi) cu.m. - -
a Portland Cement (40 kg) bags 247.50 - -
b Sand cu.m. 770.00 - -
c Gravel cu.m. 825.00 - -
4.0 CHB Laying 4" including Rebars sq.m. 162.34 - -
a CHB 4" - 400psi pc 20.13 - -
b Portland Cement (40 kg) bags 247.50 - -
c Rebars 10 mm dia x 6m (Grade 40) pcs 134.38 - -
d Tie wires #16 kgs 88.00 - -
e Sand cu.m. 770.00 - -
5.0 Plastering (16mm thick); Class B sq.m. 228.31 - -
a Portland Cement (40 kg) bags 247.50 - -
b Sand cu.m. 770.00 - -
Sub-total - - -
Toilet Counter
1.0 Formworks sq.m. 194.62 - 171.79 - -
2.0 Reinforcement kgs 5.90 - -
a Rebars, 10 mm dia x 6m (Grade 40) pcs 134.38 - -
b Tie wires #16 kgs 88.00 - -
3.0 Concrete Slab counter (Assume 2500psi) cu.m. - -
a Portland Cement (40 kg) bags 247.50 - -
b Sand cu.m. 770.00 - -
c Gravel cu.m. 825.00 - -
Sub-total - - -
TOTAL - DIVISION 4 - - -

Page 4 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
DIVISION 5 - METALS
Roofing
a Rib type Long Span lm 1,500.00 - 450.00 - -
b Consumables lot - - -

Structural Steel (Roof Framing)


1.0 Rafters, cleats and runners
a W21 x 50 kgs -
b W16 x 31 kgs -
c W8 x 15 kgs -
d 100x 400x3mm tubular kgs -
e 100x 300x3mm tubular kgs -
f L 75 x 75 x 6mm thick kgs -
i Consumables lot -
2.0 Stiffeners, Gusset Plates, & Plates
a 10mm thick plate kgs -
b Consumables lot -
3.0 Purlins
a C 2" x 4" kg 100.00 - -
b Consumables lot - - -
4.0 Hooks & Tie Bars
a 10mm diameter, sag rods kg -
b 16mm diameter x 400mm long Anchor bolts pcs -
c 10mm diameter x 25mm long machine bolts pcs -
d Standard turnbuckle pcs -
e 25mmthk Non shrink levelling grout m2 -
5.0 Tie Bars
a 12mm diameter kg included included -
Stairs
1.0 Fabrication of Steel Stringer & Treads lot -
a L 100 x 100 x 6mm thick kgs 55.47 - 14.15 - -
b L 38 x 38 x 6mm thick kgs 55.47 - 14.15 - -
c L 50 x 50 x 6mm thick kgs 55.47 - 14.15 - -
d 8mm thick plate kgs 77.97 - 14.15 - -
e 6mm thick plate kgs 77.97 - 14.15 - -
f 16mm diameter x 150mm long A325 bolt pcs 55.00 - 10.84 - -
g 10mm diameter A325 bolt pcs 35.20 - 10.84 - -
h 12mm diameter machine bolt pcs 27.50 - 10.84 - -
i Consumables lot - - -
Column
a. 250x250x6mmthk tubular steel column kgs 91.71 - 14.15 - -
b. 200mmØ GI pipe kgs 55.47 - 14.15 - -
c Consumables lot - - -
Ledge
a. 100x200x3mmthk tubular steel stiffener ledge kgs 91.71 - 14.15 - -
b Consumables lot - - -
Lattice
a. 50mmx50mm tubular steel lattice m2 12,320.00 - included -
Trellis
a. 1/8"x3x6" tubular steel trellis kgs 91.71 - 14.15 - -
b Consumables lot - - -
Railings
1.0 Stainless Steel Railing
50x100mm stainless steel on 25x25mm tubular
a. m 10,411.56 - included -
steel vertical railings; 600mmH
b 50mm stainless steel; 1000mmH ramp railing m 5,791.67 - included -
2.0 Steel Railing @ stair tower
3/8"x2" vertical and 1/2"x2" flat bar railings;
a. m2 5,925.92 - included -
600mmH
3.0 Stainless Steel Railing @ stair to poooldeck
50x100mm stainless steel on 25x25mm tubular
a. m 10,411.56 - included -
steel vertical railings; 600mmH
Sub-total - - -
TOTAL - DIVISION 5 - - -
DIVISION 6 - WOOD & PLASTIC
Carpentry Works
1.0 Beam cladding 1" KD wood m2 - - -
Sub-total - - -
TOTAL - DIVISION 6 - - -
DIVISION 6 - THERMAL & MOISTURE PROTECTION

1.0 Prepainted metal roofing 0.50mm seamless longspan lot 484,780.74 - 168,300.00 - -
including guter and flashing (A=919.81m2)
2.0 Fascia Installation l.m 51.65 - -

Page 5 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
a Fascia board, 12mm thick x 10" x 8' pc 319.00 - -
b Fascia board, 12mm thick x 12" x 8' pc 357.50 - -
3.0 Waterproofing sq.m 195.00 - included included -
Sub-total - - -
TOTAL - DIVISION 6 - - -
DIVISION 7 - DOORS & WINDOWS
Doors
1.0 D1 pc 33,500.00 - 6,700.00 - -
2.0 D2 pc 23,500.00 - 4,700.00 - -
3.0 D3 pc 2,800.00 - 840.00 - -
4.0 D4 pc 4,000.00 - 1,200.00 - -
5.0 D5 pc 2,100.00 630.00 - -
6.0 Gate lot 30,000.00 - 9,000.00 - -
Sub-total - - -
Ironmongeries
1.0 Cylindrical lockset (surelockset) pc - - -
2.0 Hinges; to doors pc - - -
Sub-total - - -
Windows
1.0 W1 pc 50,375.00 - -
2.0 W2 pc 37,200.00 - -
3.0 W3 pc 23,250.00 - -
4.0 W4 pc 7,750.00 - -
5.0 W5 pc 6,000.00 - -
6.0 W6 pc 10,075.00 - -
7.0 W7 pc 3,900.00 - -
8.0 W8 pc 37,125.00 - -
9.0 W9 pc 37,125.00 - -
Sub-total - - -
TOTAL - DIVISION 7 - - -
DIVISION 8 - FINISHES
Interior Ceiling on metal furring
1.0 Ceiling Frame (light metal frame) sq.m. 467.43 - 93.86 - -
2.0 Ceiling Board Installation (at t&b) sq.m. 122.02 - -
a Moisture Resistant Cement board pc 506.00 - - -
b Consumables lot - - - -
3.0 Ceiling Board Installation - interior sq.m. 115.12 - -
a 12mm thick Gypsum board pc 396.00 - -
b Consumables lot - - -
4.0 Ceiling Board Installation - exterior
a 12mm thick Gypsum board pc 396.00 - -
b Consumables lot - - -
Sub-total - - -
T & B Tileworks
Floor Tiles (300x300 Ceramic Tiles) sq.m. 180.64 - -
a Floor Tiles pc 60.00 - - -
b ABC Tile Grout (2kg/bag) bag 147.84 - - -
c Cement Adhesive (25 kg) bag 348.81 - - -
d Tile Trim m - - -
Wall Tiles (300x300 Ceramic Tiles) sq.m. 180.64 - -
a Wall Tiles pc 60.00 - - -
b ABC Tile Grout (2kg/bag) bag 147.84 - - -
c Cement Adhesive (25 kg) bag 348.81 - - -
d Tile Trim m - - -
Sub-total - - -
Floor Finishes
1.0 Homogeneous ceramic tiles sq.m. 180.64 - -
a Homogeneous Tiles (600x600) pc 200.00 - - -
b ABC Tile Grout (2kg/bag) bag 147.84 - - -
c Cement Adhesive (25 kg) bag 348.81 - - -
2.0 Non-skid Homogenous Tiles sq.m. - 180.64 - -
a Homogeneous Tiles (600x600) pc 200.00 - - - -
b ABC Tile Grout (2kg/bag) bag 147.84 - - - -
c Cement Adhesive (25 kg) bag 348.81 - - - -
Sub-total - - -
Exterior wall

1.0 Façade Treatment sq.m. - - -

Sub-total - - -

Page 6 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
Painting Works
1.0 Exterior Wall - textured sq.m. 105.10 - -
a Flat Latex gal 600.00 - - -
b Textured Latex gal 700.00 - - -
c Consumables lot - - - -
2.0 Interior Wall sq.m. 105.10 - -
a Flat Latex gal 600.00 - - -
b Semi-gloss Latex gal 700.00 - - -
c Consumables lot - - - -
3.0 Interior Wall sq.m. 73.92 - -
a Flat Latex gal - - -
b Semi-gloss Latex gal - - -
c Consumables lot - - -
3.0 Ceiling sq.m. 105.10 - -
a Flat Latex gal 500.00 - - -
c Consumables lot - - - -
7.0 Doors sq.m. 98.56 - -
a Flat Wall Enamel gal 548.63 - -
b Quick Drying Enamel gal 612.15 - -
c Consumables lot - - -
8.0 Jambs - enamel l.m. 15.40 - -
a Flat Wall Enamel gal 548.63 - -
b Quick Drying Enamel gal 612.15 - -
c Consumables lot - - -
9.0 Pantry Counter Concrete sq.m. 73.92 - -
a Flat Latex gal 473.00 - -
b Semi-gloss Latex gal 544.50 - -
c Consumables lot - - -
10.0 Steel railing/louvers sq.m. 98.56 - -
a Flat Lacquer gal 792.05 - -
b Consumables lot - - -
Sub-total - - -
TOTAL - DIVISION 8 - - -
DIVISION 9 - SPECIALTIES
Mirrors
6mm Mirror with plywood backing and aluminum frame
1.0
in anodized finish
a. 3150mm wide x 900mm high m2
b. 2100mm wide x 900mm high m2
c 2850mm wide x 900mm high m2
Ledge
3.0 Pre-cast Ledge m2
Modular Counter / Cabinetry
4.0 Installation of Kitchen Cabinets m
5.0 Kitchen Counter sq.m.
a 2.4mm china granite countertop and splashboard sq.m.
Metal Louvers
8.0 Tubular metal Louvers sq.m.
Shower Enclosure
8.0 Glass Shower Enclosure lot
Sub-total - - -
TOTAL - DIVISION 9 - - -
DIVISION 10 - SANITARY
lot
A. WATERLINE
PIPES
20mm (1/2") x 4.0 meters pc. / s 295.00 - 88.50 - -
- - -
FITTINGS - PPR - - -
ELBOW - - -
Plain Elbow - - -
20mm pc. / s 24.00 - 7.20 - -
Threaded Elbow - - -
20mm pc. / s 28.00 - 8.40 - -
- - -
ADAPTOR - - -
Male Threaded Adaptor - - -
20mm pc. / s 185.00 - 55.50 - -
Female Threaded Adaptor - - -
20mm pc. / s 185.00 - 55.50 - -
- - -
TEE - - -
Plain Tee - - -
20mm pc. / s 25.00 - 7.50 - -

Page 7 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
Threaded Tee - - -
20mm pc. / s 30.00 - 9.00 - -
- - -
COUPLING - - -
Coupling - - -
20mm pc. / s 15.00 - 4.50 - -
- - -
CAP - - -
End Cap - - -
20mm pc. / s 15.00 - 4.50 - -
- - -
OTHERS - - -
Hose Bibb pc. / s 284.50 - 85.35 - -
Gate Valve pc. / s 255.00 - 76.50 - -
Check Valve pc. / s 272.50 - 81.75 - -
Shower Valve pc. / s 282.60 - 84.78 - -
Shower Head pc. / s 725.00 - 217.50 - -
Ordinary Faucet pc. / s 300.00 - 90.00 - -
Consumbales (Teflon, Solvent etc.) lot 2,621.60 - - -
- - -
- - -

Page 8 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
- - -
B. SANITARY AND VENT - - -
- - -
PIPES - - -
63mm x 3.0 meters PVC Pipe pc. / s 420.00 - 126.00 - -
110mm x 3.0 meters PVC Pipe pc. / s 980.00 - 294.00 - -
160mm x3.0 meters PVC Pipe pc. / s 1,125.50 - 337.65 - -
- - -
FITTINGS - - -
1/4 BEND - - -
110mm pc. / s 91.56 - 27.47 - -
160mm pc. / s 456.40 - 136.92 - -
1/8 BEND - - -
63mm pc. / s 42.50 - 12.75 - -
110mm pc. / s 92.15 - 27.65 - -
160mm pc. / s 92.15 - 27.65 - -
TEE - - -
63mm x 63mm pc. / s 43.40 - 13.02 - -
160mm x 160mm pc. / s 667.52 - 200.26 - -
WYE (Single Branch) - - -
63mm x 110mm pc. / s 121.80 - 36.54 - -
110mm x 110mm pc. / s 146.44 - 43.93 - -
110mm x 160mm pc. / s 1,193.36 - 358.01 - -
FLOOR CLEAN OUT - - -
110mm pc. / s 175.25 - 52.58 - -
160mm pc. / s 217.36 - 65.21 - -
P-TRAP - - -
63mm pc. / s 373.56 - 112.07 - -
Consumables lot 6,238.95 - - -
- - -
- - -
C. STORM DRAINAGE - - -
- - -
PIPES - - -
160mm x 3.0 meters PVC Pipe pc. / s 1,125.50 - 337.65 - -
Downspout 110mm pc. / s 367.64 - 110.29 - -
- - -
FITTINGS - - -
1/4 BEND - - -
160mm pc. / s 456.40 - 136.92 - -
COUPLING - - -
160mm pc. / s 410.76 - 123.23 - -
110mm pc. / s 287.53 - 86.26 - -
- - -
OTHERS - - -
Catch Basin pc. / s 3,930.40 - 1,965.20 - -
Consumbales lot 2,647.83 - - -
- - -
D. PLUMBING FIXTURES - - -
- - -
Supply and Installation of: - - -
- - -
Water Closet set / s 8,550.00 - 2,565.00 - -
- - -
Lavatory set / s 5,725.00 - 1,717.50 - -
- - -
Lavatory Faucet set / s 625.00 - 187.50 - -
- - -
Kitchen Sink set / s 3,450.00 - 1,035.00 - -
- - -
Kitchen Sink Faucet set / s 1,850.00 - 555.00 - -
- -
Shower enclosure sets 10,000.00 - -
- - -
MISCELLANEOUS - - -
- - -
4" X 4" Stainless Strainer for Floor Drain pc. / s 350.00 - 105.00 - -
- - -
Stainless Grease Trap for Kitchen Sink pc. / s 3,750.00 - 1,125.00 - -
- - -
E. SEPTIC TANK - - -
- - -
EARTHWORKS - - -
Excavation m3 - 340.26 - -

Page 9 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
Backfill m3 - 178.83 - -
Hauling and Disposal m3 - 545.45 - -
Gravel Bedding m3 950.00 - 168.83 - -
- - -
- - -
- - -
CONCRETE WORKS - - -
Formworks m2 584.82 - 519.48 - -
1/2" ordinary plywood and rough lumber - - -
Rebars kgs 58.44 - 15.58 - -
12mm dia. Deformed bar - - -
Pouring of Concrete m3 4,935.00 - 1,376.62 - -
3000 psi - - -
- - -
MASONRY WORKS - - -
4" CHB Layout m2 649.35 - 358.44 - -
including mortar and 10mm rebar - - -
Plastering m2 324.68 - 298.70 - -
one side - inside surface only

Sub-total - - -
TOTAL - DIVISION 10 - - -
DIVISION 11 - ELECTRICAL

WIRING METHODS
Conductors and Cables - - -
- - -
Main and Sub main Distribution - - -
THHN, 30sq mm m 217.60 - 62.14 - -
THHN, 14sq mm (G) m 102.00 - 62.14 - -
- - -
Lighting & Small Power Cables - - -
THHN, 2.0sq mm m 17.00 - 36.40 - -
THHN, 3.5sq mm m 25.50 - 36.40 - -
THWN, 2.0sq mm (G) m 17.00 - 36.40 - -
THWN, 3.5sq mm (G) m 25.50 - 36.40 - -
- - -
- - -
Raceways - - -
- - -
PVC, 25mm dia lght 97.20 - 72.00 - -
PVC, 25 Adapter w/ Locknut nr 8.00 - 5.00 - -
RSC, 32mm dia lght 1,187.31 - 159.00 - -
RSC, 32mm Elbow nr 185.00 - 90.00 - -
Octagonal Box nr 35.00 - 31.92 - -
Utility Box nr 35.00 - 31.92 - -
- - -
Wiring Devices - - -
- - -
1 gang switch, Panasonic/ National set 280.00 - 127.68 - -
2 gang switch, Panasonic/National set 310.00 - 127.68 - -
3 gang switch, Panasonic/National set 350.00 - 127.68 - -
Duplex Convenience Outlet, Panasonic/National set 270.00 - 127.68 - -
Range Outlet set 2,500.00 - 127.68 - -
REF Outlet set 270.00 - 127.68 - -
ACU Outlet set 330.00 - 127.68 - -
- - -
- - -
- - -
Panelboards - - -
Main: 100AT, 125AF, 2P set 15,000.00 - 1,500.00 - -

Page 10 of 11 03/06/2020
PROJECT:
OWNER:
LOCATION:

BILL OF QUANTITIES

MATERIALS LABOR
ITEM ITEM DESCRIPTION UNIT QTY. TOTAL
U/COST COST U/COST COST
Branches: 7- 15AT, 100AF, 2P - - -
10-20AT, 100AF, 2P - - -
4-30AT, 100AF, 2P - - -
Nema 1 - - -
- - -
KWHR Meter (by Meralco) set 3,500.00 - 1,500.00 - -
- - -
LIGHTING SUM - - -
Incandescent Bulb/ as per owner specs set 750.00 - 220.00 - -
Pinlight, 4" Horizontal Downlight 1xE27 with Center set 519.00 - 220.00 - -
Moisture/Dust Proof Fluorescent Lamp (Garage) set 1,500.00 - 220.00 - -
- - -
- - -

Sub-total - - -
TOTAL - DIVISION 11 - - -

GRAND TOTAL - - -

Page 11 of 11 03/06/2020

You might also like