Over Head Sign Board

This document provides a cost estimate for overhead gantry sign boards with the following details: 1) It lists the materials used, quantities, weights, and costs for the steel structure components including vertical posts, horizontal beams, cross members, base plates, and anchor bolts. 2) It specifies the area, rate per square meter, and total cost for retro-reflective sheeting to be installed. 3) It gives the quantities and costs for excavation and concrete work required for foundations. 4) It provides reinforcement details, quantities in metric tons, and costs. 5) It states the quantity and cost for reinforced concrete work. 6) The total estimated cost for

Uploaded by

afifa kausar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views

Over Head Sign Board

This document provides a cost estimate for overhead gantry sign boards with the following details: 1) It lists the materials used, quantities, weights, and costs for the steel structure components including vertical posts, horizontal beams, cross members, base plates, and anchor bolts. 2) It specifies the area, rate per square meter, and total cost for retro-reflective sheeting to be installed. 3) It gives the quantities and costs for excavation and concrete work required for foundations. 4) It provides reinforcement details, quantities in metric tons, and costs. 5) It states the quantity and cost for reinforced concrete work. 6) The total estimated cost for

Uploaded by

afifa kausar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Analysis No.

X
: Analysis of rate for Overhead Gantry Sign Board

Providing and erecting overhead signs with a corrosion resistant aluminium alloy sheet reflected with high
intensity retro-reflective sheeting with vertical and lateral clearance given in clause 802.2 and 802.3 and installed
as per clause 802.7 over a designed support system of galvanized steel trusses of section and type to be mounted
by bolts and nuts over RCC structure as per drawing

(A) 300 mm
outside dia MS
1 pipe

(i) Vertical post


2x 6.00 .= 12.00 Rm
@ 49.5 Kg/m Total= .= 12.00 Rm 594.00 Kg

(ii) Horizontal
MS square tube
(60mmx60mm) 4x 12.60 .= 50.40 Rm
15 x 2x 0.90 .= 27.00 Rm
15 x 2x 0.60 .= 18.00 Rm

Stiffener
(60mmx60mm) 2x 2.5 .= 5.00 Rm
@ 6.71 Kg/m Total= .= 100.40 Rm 673.684 Kg

(B) Cross
member
-38mmx38mm
size 2x 14 x 1.30 .= 36.40 Rm
2x 14 x 1.10 .= 30.80 Rm
@ 3.95 Kg/m Total= .= 67.20 Rm 265.44 Kg

( C ) Base
plate 25mm
thickness 2x 0.80 x 0.80 .= 1.28 Sqm
@ 196.25 Kg/sqm Total= 251.2 Kg

Stiffener -10mm
thickness 2x 4x 0.30 x 0.3 .= 0.72 Sqm
@ 78.5 Kg/sqm Total= 56.52 Kg

Plate-10mm
thickness 2x 2x 0.20 x 0.6 .= 0.48 Sqm
@ 78.5 Kg/sqm Total= 37.68 Kg

Top Plate 12mm


thickness- 2x 2x 0.90 x 0.9 .= 3.24 Sqm
@ 94.2 Kg/sqm Total= 305.208 Kg

Stiffener at
top ,10mm
thickness 2x 4x 0.30 x 0.4 .= 0.96 Sqm
@ 78.5 Kg/sqm Total= 75.36 Kg
Rib-10mm
thickness 2x 2x 0.10 x 0.2 .= 0.08 Sqm
@ 78.5 Kg/sqm Total= 6.28 Kg
10mm thickness
plate - 2x 2x 0.20 x 0.2 .= 0.16 Sqm
2x 1x 0.10 x 0.1 .= 0.02 Sqm
Total= 0.18 Sqm
@ 78.5 Kg/sqm Total= 14.13 Kg

Pedestal-10mm
thickness- 2x 2x 0.80 x 0.8 .= 2.56 Sqm
@ 78.5 Kg/sqm Total= 200.96 Kg

Anchor bolts
-20mm dia.
x750mm long 2x 12.00 .= 24.00 Nos
.= 18.00 Rm
@ 2.47 Kg/M Total= 59.28 Kg
Total= 2539.74 Kg
15% for cutting,welding and wastage etc. 380.9613 Kg
Total= 2920.70 Kg
.= 2.92 Tonne

Rate per Sqm


(as per SOR
2013-14) @ 98500.00 per tonne Rs. 287689.275

Retro--
2 reflective sheet
Area = 2x 12.00 x 1.2 .= 28.8 Sqm

Rate per Sqm


(as per SOR
2013-14)

Cost of Retro-
reflecting Sheet @ 11000.00 Rs. 316800.00

E/W in
3 excavation

Quantity= 2x 1.50 x 1.50 x 1.65 .= 7.425 Cum


Rate per Cum
(as per SOR
2013-14) @ 108.00 per Cum Rs. 801.90

Cost of
Excavation

P.C.C work (M-


4 15) 2x 1.50 x 1.50 x 0.15 .= 0.675 Cum

Quantity = @ 5605.00 per Cum Rs. 3783.38

Rate per Cum


(as per SOR
2013-14)
Cost of PCC M-
15
5 12mm Jali 2x 2x 11 x 1.15 .= 50.6 Rm
@ 0.89 kg per .= 45.034 Kg
16 mm dia. TMT
@150 mm c/c 2x 24 x 2.75 .= 132.00 Rm
@ 1.60 kg per .= 211.2 Kg
Stirrups -8mm
dia. 2 x 14 x 4.25 .= 119.00 Rm
@ 0.39 kg per .= 46.41 Kg
Total= .= 302.644 Kg
Total= .= 0.302644 MT

Cost of
Reinforcement,
Rates per MT (as
per SOR 2013-
14) @ 73343.00 per Cum Rs. 22196.82

M 20 grade of
6 RCC work

Quantity= 2x 1.00 x 1.00 x 2.5 .= 5.00 Cum

Rate per Cum


(as per SOR
2013-14) @ 8761.00 per Cum Rs. 43805.00
Cost of RCC M-
20

Total= Rs. 675076.00

Executive Engineer,PWD,
Nagaon NH Division,Nagaon.