MOS Temporary Hoarding

This document provides a method statement for installing a temporary hoarding at a 132kV substation project site. It outlines the objectives, references, responsibilities, manpower, equipment, and sequence of works. The key steps include site preparation, setting out the hoarding alignment, constructing the main support pillars, installing horizontal and diagonal bracing members, erecting metal deck panels, and constructing an entrance gate. Safety and environmental requirements are also described, such as wearing protective equipment, controlling site access, handling waste properly, and stopping work during rain. The consultant will supervise and verify that the hoarding installation meets the required specifications.

Uploaded by

aniesbaek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
90% found this document useful (10 votes)
4K views4 pages

MOS Temporary Hoarding

This document provides a method statement for installing a temporary hoarding at a 132kV substation project site. It outlines the objectives, references, responsibilities, manpower, equipment, and sequence of works. The key steps include site preparation, setting out the hoarding alignment, constructing the main support pillars, installing horizontal and diagonal bracing members, erecting metal deck panels, and constructing an entrance gate. Safety and environmental requirements are also described, such as wearing protective equipment, controlling site access, handling waste properly, and stopping work during rain. The consultant will supervise and verify that the hoarding installation meets the required specifications.

Uploaded by

aniesbaek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

METHOD STATEMENT

Doc. No : 003 Rev. No. : 0

Date Issued : 28/01/2019

PMU 132kV MRT BUKIT SERDANG GIS

CADANGAN PEMBINAAN PENCAWANG MASUK UTAMA 132 kV MRT BUKIT SERDANG GIS
PEKAN SERDANG, DAERAH PETALING,
SELANGOR DARUL EHSAN

MAIN CONTRACTOR: KEJURUTERAAN BINTAI KINDENKO SDN BHD


CLIENT: TENAGA NASIONAL BERHAD

METHOD OF STATEMENT

TEMPORARY HOARDING

APPROVALS
PREPARED BY REVIEWED BY APPROVED BY
( KBK SDN BHD) ( KBK SDN BHD ) (PERUNDING ZE SDN BHD)

Signature : Signature : Signature :

Name : Name : Name :

Designation :: Project Engineer Designation : Safety & Health Officer Designation :

Date : Date : Date :

REVISION RECORD
REV DATE ISSUED
1.0 OBJECTIVE

This method of statement covers the requirement to carry out a installation of temporary
hoarding at PMU 132kV MRT Bukit Serdang.

2.0 REFERENCE

This method statement shall be read together with the following document:-

 TNB Technical Specification


 Hoarding site plan
 Authority approval
 Site Safety Plan

3.0 RESPONSIBILITY

KBK Sdn Bhd shall execute a installation of temporary hoarding. The consultant, PZE shall do
the supervision and verification in order to ensure the works are done in accordance to the
required specification.

4.0 MANPOWER, PLANT, MATERIAL & EQUIPMENT

4.1 General equipment


 Cordless drill
 ladder
 hoe
 welding set with generator
 cement
 sand
 ¾ aggregate stone
 Auto level
 Spirit level

4.2 Supervisors and skilled & unskilled workforce.


5.0 SEQUENCE OF WORKS / PROCEDURES

5.1 SITE PREPARATION

Setting out boundaries of ground in the proposed perimeter.

5.2. METHOD OF WORK

5.2.1 Determine the location of the temporary hoarding will be established with
confirmation from the surveyor.

5.2.2 After getting confirmation, using the given point and mark the main pole as per
alignment shown in the drawings. Center to center of the main column is
3000mm.

5.2.3 Preparation of the main pillars started by using hand digging to the depth
650mm.

5.2.4 Pole-sized 50X50X1.6mm thk SHS M.S constructed using equipment such as
spirit level, water level, and tape measure. Two workers used to establish the
main pillars.

5.2.5 Pillars need to ensure accurate position along the fence line at 3.0m (panel
width) intervals and make sure the base are sitting on an even level surface.

5.2.6 Erect the remaining pillars along the line as noted previously until the hoarding
line is complete.

5.2.7 50x25x1.2mm thk noggin need to install three (3) lines to support metal deck
panels.

5.2.8 Metal deck panels will be installed with the frame hoarding as per drawing
shown.

5.2.9 This work will be repeated until completion.

5.2.10 Entrance gate will be erected at remaining area with support at both side (left
and right) using welded angles.
6.0 ENVIRONMENTAL & SAFETY REQUIREMENT

6.1 QUALITY ISSUES


 Boundaries demarcation required to ensure no double handling or trespassing to
others people land.
 View inspection required during the process of erection hoarding.
 Regular inspection to be carried out by weekly basis to ensure the hoarding in good
condition.

6.2 SAFETY ISSUES


 Safety helmets and safety footwear should always be worn.
 All soft spots or holes shall be identified and barricade if necessary.
 The site shall be kept clear of unnecessary obstruction.
 First aid kit boxes will be provided at site office.
 During raining, no erection hoarding activities are allowed to work.

6.3 ENVIRONMENTAL ISSUES


 All workers shall ensure that tools and machinery are in a good condition to avoid any
oil leakage that could harm to environment.
 Construction waste from construction area must be collected into centralized garbage
bin and disposed at the designated area.