MOS Temporary Hoarding
MOS Temporary Hoarding
CADANGAN PEMBINAAN PENCAWANG MASUK UTAMA 132 kV MRT BUKIT SERDANG GIS
PEKAN SERDANG, DAERAH PETALING,
SELANGOR DARUL EHSAN
METHOD OF STATEMENT
TEMPORARY HOARDING
APPROVALS
PREPARED BY REVIEWED BY APPROVED BY
( KBK SDN BHD) ( KBK SDN BHD ) (PERUNDING ZE SDN BHD)
REVISION RECORD
REV DATE ISSUED
1.0 OBJECTIVE
This method of statement covers the requirement to carry out a installation of temporary
hoarding at PMU 132kV MRT Bukit Serdang.
2.0 REFERENCE
This method statement shall be read together with the following document:-
3.0 RESPONSIBILITY
KBK Sdn Bhd shall execute a installation of temporary hoarding. The consultant, PZE shall do
the supervision and verification in order to ensure the works are done in accordance to the
required specification.
5.2.1 Determine the location of the temporary hoarding will be established with
confirmation from the surveyor.
5.2.2 After getting confirmation, using the given point and mark the main pole as per
alignment shown in the drawings. Center to center of the main column is
3000mm.
5.2.3 Preparation of the main pillars started by using hand digging to the depth
650mm.
5.2.4 Pole-sized 50X50X1.6mm thk SHS M.S constructed using equipment such as
spirit level, water level, and tape measure. Two workers used to establish the
main pillars.
5.2.5 Pillars need to ensure accurate position along the fence line at 3.0m (panel
width) intervals and make sure the base are sitting on an even level surface.
5.2.6 Erect the remaining pillars along the line as noted previously until the hoarding
line is complete.
5.2.7 50x25x1.2mm thk noggin need to install three (3) lines to support metal deck
panels.
5.2.8 Metal deck panels will be installed with the frame hoarding as per drawing
shown.
5.2.10 Entrance gate will be erected at remaining area with support at both side (left
and right) using welded angles.
6.0 ENVIRONMENTAL & SAFETY REQUIREMENT