PMP-ITTO Overview
PMP-ITTO Overview
5.2.Collect Requirements
Input
1.Project charter
2.Project management plan
-Scope management plan
-REquirements management plan
-Stakeholder engagement plan
3.Project documents
-Assumption log
-Lessons learned register
-Stakeholder register
4.Business documents
-Bussiness case
5.Agreements
6.EEF
7.OPA
Tools & Techniques
1.Expert judgment
2.Data gathering
-Brainstorming
-Interviews
-Focus groups
-Questionnaires and surveys
3.Data analysis
-Documents analysis
4.Decision making
-Voting
-Multicriteria decision analysis
5.Data representation
-Affinity diagrams
-Mind mapping
6.Interpersonal and team skills
-Nominal group technique
-Observatio/conversation
-Facilitation
7.Context diagram
8.Prototypes
Outputs
1.Requirements documentation
2.Requirements traceability matrix
5.3.Define Scope
Input
1.Project charter
2.Project management plan
-Scope management plan
3.Project documents
-Assumption log
-REquirements documentation
-Risk register
4.EEF
5.OPA
Tool & Techniques
1.Expert judgment
2.Data analysis
-Alternatives analysis
3.Decision making
-Muliticriteria decision analysis
4.Interpersonal and team skills
-Facilitation
5.Product analysis
Output
1.Project scope statement
2.Project documents updates
-Assumption log
-Requirements documentation
-Requirements traceability matrix
-Stakeholder register
5.4.Create WBS
Input
1.Project management plan
-Scope management plan
2. Project documents
-Project scope statement
-REquirements documenation
3.EEF
4.OPA
Tools & Techniques
1.Expert judgment
2.Decomposition
Output
1.Scope baseline
2.Project documents updates
-Assumption log
-Requirements documentation
6. Project 6.1.Plan Schedule Management
Schedule Input
Management
1.Project charter
2.Project management plan
-Scope mp
-Development approach
3.EEF
4.OPA
Output
1.Schedule management plan
6.2.Define Activities
Input
1.Project mp
-Schedule mp
-Scope baseline
2.EEF
3.OPA
Tool & Techniques
1.Expert judgment
2.Decomposition
3.Rolling wave planning
4.Meetings
Output
1.Activities list
2.Activity attributes
3.Milestone list
4.Change request
5.Project mp updates
-Schedule baseline
-Cost baseline
6.3.Sequence Activities
Input
1.Project mp
-Schedule mp
-Scope baseline
2.Project documents
-Activity attributes
-Activity list
-Assumption log
-Milestone list
3.EEF
4.OPA
Tools & Techniques
1. Precedence diagramming method
2.Dependency determination and integration
3.Leads and Lags
4. Project management information system
Ouputs
1.Project schedule network diagrams
2.Project documents updates
-Activity attributes
-Activity list
-Assumption log
-Milestone list
6.4.Estimate Activity Durations
Input
1.Project mp
-Schedule mp
-Scope baseline
2.Project documents
-Actitity attributes
-Activity list
-Assumption logs
-Lessons learned register
-Milestone list
-Project team assignments
-Resource breakdown structure
-Resource calendars
-Resource requirements
-Risk register
3.EEF
4.OPA
Tools & Techniques
1.Expert judgment
2.Analogous estimating
3.Parametric estimating
4.Three-point estimating
5.Bottom-up estimating
6.Data analysis
-Alternatives analysis
-Reserve analysis
7.Decision making
8.Meetings
Output
1.Duration estimates
2.Basiss of estimates
3.Project documents updates
-Activities attributes
-Assumption log
-Lessons learned register
6.5.Develop Schedule
Input
1.Project mp
-Schedule mp
-Scope baseline
2.Project documents
-Actitity attributes
-Activity list
-Assumption logs
-Basis of estimates
-Duration estimates
-Lessons learned register
-Milestone list
-Project schedule network diagrams
-Project team assignments
-Resource calendars
-Resource requirements
-Risk register
3.Agreements
4.EEF
5.OPA
Tools & Techniques
1.Schedule network analysis
2.Critical path method
3.Resource optimization
4.Data analysis
-What-if scenario analysis
-Simulation
5.Leads and lags
6.Schedule compression
7.Project management information system
8.Agile release planning
Ouput
1.Schedule baseline
2.Project schedule
3.Schedule data
4.Project calendars
5.Change request
6.Project mp
-Schedule mp
-Cost baseline
7.Project documents updates
-Activity attributes
-Assumption log
-Duration estimates
-Lesson learned register
-Resource requirements
-Risk register
7. Project Cost 7.1.Plan Cost Management
Management Input
1.Project charter
2.Project mp
-Schedule mp
-Risk mp
3.EEF
4.OPA
Output
1.Cost management plan
Output
1.Accepted deliverables
2.Work performance information
3.Change request
4. Project document update
-Lessons learned register
-Requirements documentation
-Requirements traceability matrix
5.6. Control Scope
Input
1.Project management plan
-Scope management plan
-REquirements mp
-Change mp
-Configuration mp
-Scope baseline
-Performance measurement baseline
2.Project documents
-Lessons learned register
-REquiremetns documentation
-REquirements traceability matrix
3.Work performance data
4. OPA
Tools & Techniques
1.Data analysis
-Variance analysis
-Trend analysis
Output
1.Work performance information
2.Change request
3.Project management plan update
-Scope mp
-Scope baseline
-Schedule baseline
-Cost baseline
-Performance measurement baseline
4.Project documents updates
-Lessons learned register
-Requirements documents
-Requirements traceability matrix
6.6.Control Schedule
Input
1.Project mp
-Schedule mp
-Schedule baseline
-Scope baseline
-Performance measurement baseline
2.Project documents
-Lessons learned register
-Project calendars
-Project schedule
-Resource calendars
-Schedule data
3.Work performance data
4.OPA
Tool & Techniques
1.Data analysis
-Earned value analysis
-Iteration burndown chart
-Performance reviews
-Trend analysis
-Variance analysis
-What-if scenario analysis
2.Critical path method
3.PMIS
4.Resource optimization
5.Leads and lags
7.Schedule compression
Outpus
1.Work performance information
2.Schedule forecasts
3.Change request
4.Project management plan updates
-Schedule mp
-Schedule baseline
-Cost baseline
-Performance measurement baseline
5.Project documents updates
-Assumption log
-Basis of estimates
-Lessons learned register
-Project schedule
-Resource calendars
-Risk register
-Schedule data
7.4. Control Cost
Input
1.Project management plan
-Cost mp
-Cost baseline
-Performance measurement baseline
2.Project documents
-Lessons learned register
3.Project funding requiremetns
4.Work performance data
5.OPA
Tools & Techniques
1.Expert judgment
2.Data analysis
-Earned value analysis
-Variance analysis
-Trend analysis
-Reserve analysis
3.To-complete performance index
4.PMIS
Output
1.Work performance information
2.Cost forecasts
3.Change request
4.Project management plan updates
-Cost management plan
-Cost baseline
-Performance measurement baseline
5.Project documents updates
-Assumption log
-Basis of estimates
-Cost estimates
-Lessons learned register
-Risk register
8.2.Manage Quality 8.3.Control Quality
Inputs
1.Project mp 1.Project mp
-Quality mp -Quality mp
2.Project documents 2.Project documents
-Lessons learned register -Lessons learned register
-Quality control measurements -Quality metrics
-Quality metrics -Test and evaluation documents
-Risk report 3.Approved change requests
3.OPA 4.Deliverables
5.Work performance data
6.EEF
7.OPA
s documents
agement plan
documentation
ents updates
Establishing policies and procedures for planning, managing and controlling the project schedule
Identifying and documenting the specific actions to be performed
Identifying and documenting relationship among the project activities
Estimating the number of work periods need to complete individual activities with the estimated resource
Analyzing activities sequences,durations, resource requirements and contrains to create the project schedule
Monitor status of project to update the project schedule and mange changes to the schedule baseline
Defining how the project costs will be estimated, budgeted, managed and monitored
Developing/Estimating how much money would be need for activities
Aggregating the estimated cost of individual activities or work pakages to establish an authorized cost baseline
Monitor status of the project to update the project cost and manage changes to cost baseline
Identifying and documents quality requirements and standards for the project
Translating the quality management plan into execuable quality activities
Monitoring and Recording results of executing the quality management activities to access performance
Define how to estimate, acquire and manage physical and team resource
Estimating the type and quantities of resource needed
Obtaining resources necessary to complete the project work
Improving competencies, team member interaction, and overall team environment to enhance project performance
Track teamthat
-Ensuring member performance,
the resources providing
assigned feedback,
to project resolve issues, and manage team changes to optimize project performa
are available
-Monitoring the planned vs actual use of resource
Documenting project procurement decisions, specifying the approach and identifying potential sellers
Obtaining seller responces, selecting a seller, and awarding a contract
Managing procurement relationships, monitoring contract performance, making changes and corrections and closing out contr