Project Report
Project Report
BACHELOR OF TECHNOLOGY
By
R.AKILAN 161051101006
A.MOHAN 161051101055
M.GAYATHRI 161051101027
R.DANIEL SANTHOSH 161051101019
DEPARTMENT OF CIVIL ENGINEERING
DECLARATION
I affirm that the project work titled “Design Of Prefabricated Slab Using
(Gfrg) Panel” being submitted in the partial fulfillment for the award of
the degree in BACHELOR OF TECHNOLOGY in Civil Engineering
is the original work carried out by us. It has not formed the any part of
any other project submitted for award of any other diploma,either in this
or any other university.
R.AKILAN 161051101006
A.MOHAN 161051101055
M.GAYATHRI 161051101027
R.DANIEL SANTHOSH 161051101019
R.AKILAN 161051101006
A.MOHAN 161051101055
M.GAYATHRI 161051101027
R.DANIEL SANTHOSH 161051101019
This review paper compiles and retrospect the developments in the field of
prefabricated building systems using GFRG construction technology also
known as Rapid wall construction technology in India. Glass fiber reinforced
gypsum panels, manufactured in standardized parts are sections prepared for
rapid erection of buildings, as they are ready-made gypsum structural panels
with hollow cavities. GFRG walls can be used both for esthetical as well as
structural component as walls and slabs, with no external columns and
beams needed. It has currently found great utilization, even without
exercising complicated codes of structural design, largely for the reason that
they are environmental friendly.
CHAPTER No. TABLE OF CONTENT PAGE.NO
1 INTRODUCTION
1.1 GENERAL
1.2 OBJECTIVE
1.3 SCOPE
2 METHODOLOGY
2.1 GENERAL
2.2 DESIGN METHODOLOGY
3 DRAWINGS
3.1 PLAN
3.2 CROSS SECTION
4 CALCULATION
4.1 DESIGN OF GFRG SLAB
4.2 DESIGN OF SLAB
6 CONCLUSION
7 REFERENCE
INTRODUCTION
1.1 GENERAL
1.3 SCOPE:
2.1 GENERAL
The major element of this work is estimating the total cost of the
construction work for a residential house based on the Quotation
gathered from five different zones for each part of work.
The estimation work is carried out for both types of building system
of wall panel system and conventional building system.
The approximate time requirement and time difference for every work
of Prefabrication system and conventional Building system was also
taken into account to calculate the cost due to time elapsed as time
also plays an important role in determining the cost of the
construction
5. The panel contains cavities that can be filled with concrete and
reinforced with steel bars to provide additional strength and ductility,
if required. Experimental researches and studies have shown that
GFRG panels, when properly filled with reinforced concrete, acquires
significant strength to act not only as load-bearing elements, but also
as shear walls, able of resisting lateral forces due to earthquake and
wind.
6. GFRG panels are originally white in color (due to gypsum) and have a
smooth finished surface. They can be whitewashed or painted without
cement plastering the walls, therefore, providing some scope of
creativity for the client.
3.1 PLAN
(b)
FLOWCHART
LITERATURE REVIEW
PLAN
DESIGN
MODEL PREPARATION
COST ANALYSIS
DESIGN CALCULATION
EFFECTIVE SPAN:
The distance between the centers of support, or the clear
distance between supports plus the effective depth of the beam or
slab, the lesser value being taken
.
Effective depth assuming 12mm diameter bars,
d=(124+50-15-8-12/2)=145mm
Accordingly,
Effective span =4.124m
LOADING:
= 2.6/mm2
pt = 0.876
Ast =(0.876/100)×230×145=292mm2
tu =(11.27×103)/[230×145] =0.34N/mm2
A) DATA
LX = 4 m
LY = 5 m
FCK =20 N/mm2
FY =415 N/mm2
Two way slab simply supported on all the sides with provision for
at corners
B) DEPTH OF SLAB
Depth (span/25)-(4000/25)-160 mm
Adopt effective depth, d = 145 mm
Overall depth, D = 170 mm
C) EFFECTIVE SPAN
D) LOADS
Mu =( 0.87x415 A, x 145)(10'x145x20)
41SA(12.8x10-10'x 135 x 20
Considering the short span 4 and unit width of slab, the shear stress
is given by,
Refer Table-19 (IS: 456) and read out the permissible shear stress
as,
1) Quicker Construction
Conventional buildings with G+1 that are usually constructed in a
span of 6-8 months can be constructed in a month with GFRG
panels.
2) Economical
GFRG reduces the consumption of cement by almost 50%, steel by
35% and sand by an astonishing 76%.
3) Fire Resistant
In an event of fire, GFRG panels release 15-20% moisture of its
own weight which largely reduces the surface temperature and fire
damage.
4) Earthquake Resistant
GFRG panels have been found to be successful at resisting the
impacts of earthquakes in the fifth seismic zone as their panels can
be turned into shear walls as well.
7) Water Resistant
Certain chemicals are added to the mix during the manufacture of
GFRG panels which make them impervious to the attack of water.
DISADVANTAGES: