DPR On EPC Project PDF
DPR On EPC Project PDF
NDP 4 associated Outcome By 2017, Namibia will have in place adequate base load energy to
2013/4-2017/8 support industry development through construction of energy
infrastructure and the production capacity would have expanded from
400 to more than 750 mega watts to meet demand.(Desired Outcome5:
5.2 on page 71).
UNPAF Outcome(s): Outcome 12: institutional frameworks and policies needed to implement
2014-2018 the Environmental Management Act (2007), National Climate Change
Policy (2011) and international conventions are in place and are being
implemented effectively.
UNDP Strategic Plan National and local governments and communities have the capacities
Environment and Sustainable to adapt to climate change and make inclusive and sustainable
Development Primary Outcome: environment & energy decisions addressing brown & green
environmental issues thereby increasing competitiveness and providing
greater certainty to private sector (CPD).
UNDP Strategic Plan Secondary National and local governments and communities have the capacities
Outcome: to adapt to climate change and make inclusive and sustainable
environment & energy decisions benefitting in particular under-served
populations
Expected CP Outcome(s): Outcome 1: Local entrepreneurs are engaged in supply chain for CSP
plants being constructed in Namibia; Outcome 2: Increased
investments in CSP technology; Outcome 3: Increased installed
capacity for CSP plants in Namibia.
Executing Entity/Implementing Renewable Energy and Energy Efficiency Institute (REEEI), Ministry of
Partner: Mines and Energy (MME).
Page 1
Country: Namibia
Project Title: Concentrating Solar Power Technology Transfer for Electricity
Generation in Namibia (CSP TT) NAM.
NDP 4 associated Outcome By 2017, Namibia will have in place adequate base load energy to support
2013/4-2017/8 industry development through construction of energy infrastructure and the
production capacity would have expanded from 400 to more than 750 mega
watts to meet demand.(Desired Outcome5: 5.2 on page 71).
UNPAF Outcome(s): Outcome 12: institutional frameworks and policies needed to implement the
2014-2018 Environmental Management Act (2007), National Climate Change Policy
(2011) and international conventions are in place and are being implemented
effectively.
Expected CP Outcome(s): Outcome 1: Local entrepreneurs are engaged in supply chain for CSP plants
being constructed in Namibia; Outcome 2: Increased investments in CSP
technology; Outcome 3: Increased installed capacity for CSP plants in
Namibia.
Executing Entity/Implementing Renewable Energy and Energy Efficiency Institute (REEEI), Ministry of Mines
Partner: and Energy (MME).
Page 2
Table of Contents
LIST OF ACRONYMS AND ABBREVIATIONS ............................................................................................................................................ 4
SITUATION ANALYSIS ..................................................................................................................................................................... 5
Context and Global Significance .................................................................................................................................................. 5
Defining the Challenge ................................................................................................................................................................ 14
Barrier Analysis ............................................................................................................................................................................. 17
Stakeholder Analysis ................................................................................................................................................................... 20
Baseline Analysis ......................................................................................................................................................................... 27
STRATEGY ....................................................................................................................................................................................... 29
Project Rationale and Policy Conformity ................................................................................................................................... 29
Country Ownership....................................................................................................................................................................... 30
Country Drivenness ...................................................................................................................................................................... 31
Design Principles and Strategic Considerations ...................................................................................................................... 32
Project Objectives, Outcomes and Outputs/Activities ............................................................................................................. 33
Key Indicators, Risks and Assumptions .................................................................................................................................... 42
Financial Modality ......................................................................................................................................................................... 43
Cost Effectiveness ........................................................................................................................................................................ 43
Sustainability ................................................................................................................................................................................. 44
Replicability ................................................................................................................................................................................... 45
PROJECT RESULTS FRAMEWORK ............................................................................................................................................ 47
Total Budget and Work Plan ....................................................................................................................................................... 51
MANAGEMENT ARRANGEMENTS .............................................................................................................................................. 54
MONITORING FRAMEWORK AND EVALUATION ..................................................................................................................... 57
LEGAL CONTEXT ............................................................................................................................................................................ 60
ANNEX 1: RISK ANALYSIS............................................................................................................................................................. 62
ANNEX 2: TERMS OF REFERENCE ............................................................................................................................................ 63
• PROVIDE OVERALL TECHNICAL OVERSIGHT FOR PROJECT OUTPUTS, DELIVERABLES AND INPUTS AS
REQUIRED AND RECOMMEND ACTIONS THAT FOCUS WORK PLANS ON ACHIEVING KEY MILESTONES IN A
TIMELY MANNER. ....................................................................................................................................................................... 64
ANNEX 3: ENVIRONMENTAL AND SOCIAL ISSUES ................................................................................................................ 67
ANNEX 4: FINANCIAL AND IMPLEMENTATION ISSUES......................................................................................................... 70
ANNEX 5: DETAILED CO2 CALCULATONS AND ASSUMPTIONS ........................................................................................ 74
TABLE 8: CALCULATION OF DIRECT POST-PROJECT EMISSION REDUCTIONS FROM CSP PLANTS (BASE CASE AND LOW END CASE) . 76
BASE CASE SCENARIO – TABLE A...................................................................................................................................................... 76
Page 3
List of Acronyms and Abbreviations
APR/PIR Annual Project Review/Project Implementation Reports APR/PIR
DRFN Desert Research Foundation of Namibia
ECB Electricity Control Board
ESI Electricity Supply Industry
GEF Global Environment Facility
GHG Greenhouse Gas
GRN Government of the Republic of Namibia
GW Gigawatt
GWh Gigawatt-hour
HRDC Habitat Research and Development Centre
INC Initial National Communication
IPCC Intergovernmental Panel for Climate Change
kW Kilowatt
M&E Monitoring and Evaluation
MET Ministry of Environment and Tourism
MME Ministry of Mines and Energy
MRLGHRD Ministry of Regional and Local Government, Housing and Rural Development
MW Megawatt
MWh Megawatt-hour
MWT Ministry of Works and Transport
NCCC Namibia Climate Change Committee
NEEP Namibia Energy Efficiency Programme
NGO Non-Governmental Organization
NIA Namibia Institute of Architects
NMA Namibian Manufacturers Association
POPP Programme And Operations Policies And Procedures
ProDoc UNDP/GEF Project document
RE Renewable Energy
RED Regional Electricity Distributor
REEEI Renewable Energy and Energy Efficiency Institute
SAPP Southern African Power Pool
UNDP United Nations Development Programme
UNFCCC United Nations Framework Convention on Climate Change
Currency Equivalents1
Currency Unit = Namibia Dollar, NAD
1 USD = 8.2 NAD
Page 4
SITUATION ANALYSIS
Context and Global Significance
1. The Republic of Namibia2 is a vast country, the 31st largest in the world, and covers an area of about
824,268 square kilometres. The country is located along the South Atlantic coast of Africa and shares
borders with South Africa, Angola, Zambia, Botswana and Zimbabwe (Fig. 1). Namibia is sparsely
populated with only one third of its 2.1 million inhabitants living in urban centres3. Namibia is currently
experiencing a population growth rate projected at 3% per annum by the Population Reference Bureau. It
is a lower middle-income country with a GDP per capita close to USD 1,800.
2. Namibia’s total electricity consumption was 3,910 GWh in 2010 of which about 39% was imported from
South Africa, whose 90% of grid supplied power is coal-based generation and 16% from Hwange coal–
fired powered station in Zimbabwe. NamPower has a 150MW firm supply contract with Zimbabwe. Of
Namibia’s 393 MW of in-country generating capacity, almost 36.6% is fossil fuel based. Average annual
growth in electricity demand is estimated at 3% over the next 30 years. At the same time, the Namibian
Government is pursuing a policy of energy security by promoting a diversified energy mix which will ensure
that the national economy does not become overly dependent on one source of energy4. With the projected
growth in demand and given the Government’s policy of seeking to achieve an energy mix that ensures
energy security, it is clear that the country’s electricity generating capacity needs to be enhanced with the
focus on developing its own energy sources, including renewable energy, and solar energy in particular.
Namibia has pristine conditions for solar energy based generation with high Direct Normal Irradiance (DNI)
of up to 3,000kWh/m2/annum and generally flat terrain.
3. According to the Electricity Control Board (ECB), total units generated into the Namibian electricity system
increased from 3,554 million kWh in 2006 to 3,767 million kWh in 2010, an increase of 1.5% per annum.
Moreover, energy consumption in the entire country has increased by an average of 4% per year between
1997 and 2003, 20% per year between 2003 and 2004, and 13% between 2004 and 2005.
4. More recently, a GRN-commissioned study indicates that Namibia faces a capacity deficit in its generation
capacity from 2015 due to current growth forecasts of its electricity demands. As regards its energy import
2
The Republic of Namibia: www.grnnet.gov.na.
3
Population Reference Bureau: http://www.prb.org/ (data for 2008).
4
White Paper on Energy Policy of 1998 is clear on the need for diversification in the national
energy mix
Page 5
agreements, it is recognized that the 150 MW contract with Zimbabwe (ZESA) will terminate in 2014 and
the 50 MW with Zambia (ZESCO) will be in force until 2020. Much of this deficit is due to strong growth
forecasts in the SADC region where energy exports from South Africa may be reduced during mid-peak to
peak periods. This represents over 1,932 TWh between 2013 and 2016, mainly during the dry season.
Other countries within the SADC such as Tanzania are already making short term investments in power
generation to fill in the generation gap with rental diesel plants. The estimated upfront capital cost for the
lease of diesel power generation sets to overcome Namibia’s short-term energy gap (2012-2015) is around
USD 1.0 million. The electricity from these plants, however, are costly both financially (~USD 0.50/kWh for
fuel costs) and environmentally (emissions of 1.02 tonnes CO2/MWh); meanwhile the opportunity costs of
the business-as-usual scenario are far greater from lost production and other economic activities. In light
of this crisis the GRN is urgently looking at a number of alternative investment scenarios to increase the
nation’s generation capacity, with CSP featuring prominently as an option. The Renewable Energy and
Energy Efficiency Institute (REEEI) at the Polytechnic of Namibia, on behalf of the Ministry of Mines and
Energy (MME) and with support from the Energy and Environmental Program with Southern and East
Africa (EEP S&EA), recently sought technical services on a pre-feasibility study for the establishment of a
Concentrated Solar Power plant in Namibia. The assignment was completed in June 2012 and final results
were presented to a high-level stakeholders meeting of energy sector stakeholders in August 2012. This
study and its recommendations have informed the development of this Project.
5. In terms of the impacts of climate change, the Initial National Communication (INC, 2002) classified
Namibia as highly vulnerable to the predicted effects of climate change. Climate change models used
during the process predicted that it will become increasingly hotter and drier in Namibia with shorter and
less reliable rainy seasons. Droughts will become more frequent. Climate sensitive sectors include
agriculture, water, energy, biodiversity, health, tourism and coastal zones. The Second National
Communication (SNC, 2010) underscores the most significant barrier to widespread implementation of
proven Renewable Energy Technologies (RETs) is the lack of reliable and commercially available financing
for end-users, developers, contractors, manufacturers and vendors. Recommendations are made for
measures which would strengthen the local capital market for the financing of such projects, and for
building capacity around CDM projects.
6. The project is fully consistent with Namibia’s Third National Communication (TNC) project – to be
implemented with support from UNDP – which involves preparation of the TNC for submission to the
Conference of Parties (COP) of the UNFCCC in accordance with its commitment as a party to the
Convention as mandated by Article 4 and 12 of the Convention. The 3rd TNC project activities will build on
and update the work carried out under the previous National Communications. The main components of
the 3rd TNC project are: a) Inventory of GHG Emissions; b) Programmes containing measures to facilitate
adequate adaptation to climate change; c) Measures to mitigate climate change; and d) Increased public
knowledge and awareness, research and technology transfer on climate change issues in Namibia. The
TNC project will be implemented over a three year period commencing in mid 2012 – December 2015. The
implementation activities will be done by the MET/DEA/MIA Climate Change Sub-division.
7. Namibia was estimated to be a net sink for carbon dioxide in 1994 due to the large uptake of carbon
dioxide by trees into their woody tissues. The woody biomass in Namibia’s vast areas of rangeland is
believed to be increasing. Namibia has a relatively small economy with little impact on global emissions
(i.e. it contributed less than 0.05% to global CO2 equivalent emissions in 1994, even when the carbon sink
is excluded). The amount of carbon estimated to be taken up by the natural vegetation in Namibia in 1994
constitutes about 0.1% of the total net uptake by land ecosystems throughout the world5.
8. Namibia has one of the best solar regimes in the world with an average direct insulation of 2,200 kWh
/m²/year and minimal cloud cover as shown on Figures 2 and 3. In recognition of this unique endowment,
the Government has actively promoted the use of solar energy and uptake of solar energy has increased
significantly as a result of Government efforts. This has been almost exclusively for off-grid applications.
Off-grid solar electrification is set to continue for the next 20 years, under the Off-Grid Energization Master
5 IPCC, 2000
Page 6
Plan. However, to more fully exploit its solar energy potential, Namibia is well placed for the development
of grid-fed solar thermal power-generated electricity, particularly considering the availability of vast areas of
land with ideal conditions for large scale solar power electricity generation. Solar thermal generated power
fed into the grid will help Namibia reduce the carbon intensity of its current electricity supply and contribute
to security of supply through lessened dependence on electricity imports by promoting an optimal energy
mix. Current estimates of Namibia’s excellent solar regime indicate that Namibia’s DNI ranking is the best
globally and that CSP in Namibia can provide more than 250,000 MW of power generation capacity.
9. CSP is a commercially available solar energy technology that uses direct sunlight (technically known as the
DNI) and mirrors to create high temperature steam to drive conventional steam turbines with or without
storage. A typical CSP power plant as shown on Figure 4 is comprised of the following components; solar
field (e.g. the Nevada Solar One as shown on Figure 5), power block, thermal storage (optional), cooling
tower and all other components found in any thermal power plant except the heat source. While a number
of CSP candidate technologies for utility-scale applications were recently studied, only parabolic troughs
and central receiving system (tower technology) are being considered for the initial CSP investments6. In
6 Ibid 5. Technologies included parabolic trough, central receiving (tower technology), lineal Fresnel reflectors, and Stirling engines with parabolic
Page 7
the last decade, several companies have emerged as leaders in the various CSP technologies. With
respect to the trough systems, key players include Abengoa Solar (Spain), Acciona (Spain), FPL Energy
(USA), Solar Millennium (Germany), Solel (Israel), and SkyFuel (USA). For tower systems, the market
players include Spanish company Abengoa Solar, and the US companies, Bright Source Energy, eSolar,
and Solar Reserve.
10. There are several projects at various stages of development around the world to develop CSP power such
as Andasol I-III in Spain (supported by the Royal Decree 436/20047), Aachen University (Germany),
Kuraymat (Egypt) and DESERTEC8 (North Africa).
11. CSP for electricity generation has proven its feasibility as an energy source for the “post-fossil fuel” era. At
present, a total of 354 MWe of installed capacity is operating commercially in the Californian desert. At the
same time, national and international investment in research, development, demonstration and
dissemination continues to yield important technical improvements. CSP is one of the most innovative
forms of solar technology that could meet a large portion of the world’s demand for electricity. Globally, the
number of CSP plants installed is more than 2,183 MW9 and studies show the technical market potential
CSP to be more than 600,000 MW over the next 20 years10. At this scale. CSP could therefore make a
major contribution to the reduction of greenhouse gas (GHG) emissions. However, due to the current costs
dishes.
7 http://www.solarpaces.org/Library/Legislation/docs/040327RD436-2004.pdf
8 http://www.desertec.org/en/foundation/
9
www.csp-world.com
10 Price Henry & Carpenter Stephen. 1999. The Potential for Low-Cost Concentrating Solar Power Systems. NREL, Colorado
Page 8
of USD 0.12 to 0.18 per kWh of electricity produced by CSP plants compared to the production from
conventional sources, applications of CSP are currently limited to areas that provide the best solar
radiation and investment framework. Moreover, sustainable energy production with CSP technology will
only be viable if energy production and capital costs are reduced.
12. Increased use of the technology through demonstrations and dissemination, coupled with research and
technological development as well as appropriate financial incentives, is expected to play a key role in
achieving the successful development of the industry. In terms of its commercial viability as a power
generation option, CSP falls between wind power and photovoltaics (PV) in terms of $/kWh and represents
a technology that is ready for scale-up in developing countries and has yet to experience cost reductions
resulting from significant scale-up of manufacturing volume.
13. The most significant added value of CSP is its potential for energy storage coupled with hybridization
potential with biomass and natural gas. Two technologies, parabolic troughs and power towers, can offer
storage while a third technology, linear Fresnel reflectors, can also play a role on all hybrid projects.
14. With this in mind, several Namibian stakeholders from both the private and public sector (supported by
various partners) are currently involved in initial discussions and actions focused on promoting the
development of the CSP technology in Namibia including:
• The Energy and Environment Partnership with Southern and East Africa (EEP S&EA), a sustainable
energy promotion programme funded by the Governments of Finland, Austria and the United Kingdom.
EEP S&EA provided funds for the July 2012 CSP pre-feasibility study by REEEI that has provided most
of the information used in the development of the ProDoc;
• Clinton Climate Initiative;
• Development Bank of Southern Africa;
• NamPower (state owned power utility);
• the Namibian Electricity Control Board;
• CENORED Pty Ltd and other Namibian electricity distribution companies;
• The Renewables Academy AG (RENAC), through the Transfer Renewable Energy & Efficiency
(TREE)11 project with financial support from the Germany Federal Ministry for the Environment, Nature
Conservation and Nuclear Safety, conducted CSP seminars in five (5) different countries including
Namibia in March and April 2009. Namibia’s CSP Seminar, held between 23 -25 March 2009 and
coordinated by REEEI, drew participants from both industry and academia;
• Rössing Uranium Limited (a Namibian Rio Tinto mining subsidiary) is exploring the use of CSP
technology to generate process heat based on the information received during the 2009 seminars.
Rössing has a research cooperation agreement with the Polytechnic of Namibia (PoN) and have
indicated their desire to collaborate on this particular project; and
• REEEI through its parent organisation, PoN, has cooperation agreements with FH Aachen which hosts
the Solar Institute Jülich (SIJ) and RENAC
15. The presentation of the CSP Pre-feasibility study on 25 July 2012 in Windhoek attracted participants from
South Africa, Germany Israel, Portugal and the United States of America. In addition, renewable energy
market-leading countries such as Spain, are exploring the possibility of tapping into the Namibian and
Southern African markets based on their global expertise.
Policy Context
16. White Paper on Energy Policy of Namibia published by the Ministry of Mines and Energy in 1998
embodied a new, comprehensive energy policy aimed at achieving security of supply, social upliftment,
effective governance, investment and growth, economic competitiveness, economic efficiency and
sustainability. Policies sought to affect energy demand (mainly households), supply and a number of cross-
11
The TREE project promotes capacity building and know-how transfer for both decision makers from politics and business, as well as
technicians and engineers: http://www.tree-project.de/course-program/course-details/course/16
Page 9
cutting issues, including energy efficiency and regional energy trade and cooperation. The White Paper on
Energy Policy, under the energy supply section, projects the exploitation and development of the electricity,
upstream oil and gas, downstream gas, downstream liquid fuels, and renewable energy (RE).
17. RE within the policy is clear with regards to the following interventions:
This energy policy set ambitious targets of meeting at least 100 percent of peak demand and at least 75
percent of total electricity requirements from internal sources by 2012, as well as matching Namibia’s
energy requirements in a cost-effective manner and sourcing 10 percent of the supply from internal RE
sources. NamPower has selected various supply and demand options to meet the Namibia’s energy
requirements driven by the Energy White Paper.
18. The Renewable Energy Policy Paper for NamPower was developed and approved by the Electricity Control
Board (ECB) and the Ministry of Mines and Energy. According to this policy, NamPower is expected to
intervene in broader areas of wind energy, biomass energy, hybrid mini-grid systems for off-grid areas,
solar energy, and skills development in the RE fields. The utility was expecting to reach its first target for
RE of about 40MW by the year 2011. As solar energy is a plentiful resource in Namibia, the Government’s
Ministry of Mines and Minerals (MME) made the necessary arrangements for the installation of solar water
heaters in all government and parastatal buildings.
19. In May 2012, the Minister of Mines and Energy established a Project Steering Committee (PSC) to oversee
implementation of Renewable Energy Procurement Methods (REPM). This follows the recommendations
by the 2011 study “Development of Procurement Mechanisms for Renewable Energy Resources in
Namibia” commissioned by the Electricity Control Board (ECB).
The procurement methods recommended by the REPM study and now under consideration by MME are:
- Tendering to be applied for solar (CSP) and large wind based generation systems, i.e. for CSP and wind
greater than 500kW in installed capacity;
- REFIT for small wind, small hydro and biomass including landfill gas;
- Net-metering for photovoltaics; and
- Other support measures like soft loans, grants, tax breaks, etc. to support all the above instruments and
continue promoting rural and off-grid electrification.
The REPM study recommended that a comprehensive approach to renewable energy deployment in
Namibia should include a mix of both small and large generating units. MME was therefore recommended
to promulgate regulations that provide for four procurement mechanisms. Since the establishment of the
PSC the different procurement methods are at different levels of implementation as described below:
- Because of the urgency for renewable energy capacity into the national power system, tendering for 30
MW PV will be issued in 4Q 2012.
- Net metering rules for roof top-based PV are being developed and are expected to be finalized in January
2013.
Page 10
- REFIT rules are being developed with the assistance of United States Agency for International
Development (USAID).
MME is also presently formulating the New Energy Regulatory Framework (NERF) which will look at
governing the approach of renewable energy and energy efficiency market development in Namibia by
facilitating fair market access, return on investment, quality of supply, standards, market support structures
and incentives and legal issues in Namibia. Although there is a regulator, ECB, the GRN needs to adopt a
formal power market model, as the market participants and IPP developers must understand the
Government’s policies for them to submit proposals consistent with the market rules. In addition, as
Namibia is a trader in the Southern African Power Pool, an established market model will help strengthen
Namibia’s long-term role as a potential power trading partner in the region.
Further changes of the regulatory framework conditions are anticipated in due course. The Electricity
Control Board (ECB) is set to be transformed into an energy regulator; the South West Africa Water and
Electricity Corporation Act of 1980 which governs NamPower is likely to be revised completely; and the Act
governing the Regional Electricity Distributors (REDs) has been earmarked for review to specifically
address the challenges faced by the REDs.
20. Regional energy trade and cooperation is an important cross-cutting theme of the Energy White Paper.
Namibia’s neighbour, South Africa, as part of the Southern African Power Pool (SAPP) has also
implemented a number of short-term measures to accelerate the region’s power shortage recovery, namely
guidelines for effective inter-utility transmission networks connectivity. On the supply side, the National
Energy Regulator of South Africa (NERSA) approved the Renewable Energy Feed-In Tariff (REFIT)
Guidelines in 2009. REFIT provided Power Purchase Agreements for R3.94 (USD 0.50) per kWh to CSP
developments in South Africa, a higher rate than for other renewable energy technologies for electricity
generation. The REFIT, however, was subsequently abandoned in favour of a bidding process due legal
challenges of implementing the REFIT.
21. VISION 2030 was adopted in 2003 with the goal of industrialising the Namibian economy such that by
2030, 80% of the GDP is derived from the manufacturing and service sectors. Sections 2 and 3 of
Namibia`s Development Plan (NDP) contain the directives of the White Paper on Energy Policy of 1998
that seeks to meet development challenges through improved access to RE sources, particularly in rural
electrification, rural water supply and solar housing and water heating. With regard to renewable energy,
NDP 3 sets the target of 10% total energy consumed are derived from renewable energy by 2012. NDP 4
has just been launched with sectoral discussions to commence soon.
22. Off-Grid Energisation Master Plan for Namibia (OGEMP) is another Vision 2030 project that was
initiated by the UNDP/GEF/MME Barrier Removal to Namibian Renewable Energy Programme (NAMREP).
The underlying objective of the OGEMP is to provide access to appropriate energy technologies to
everyone living or working in off-grid, pre-grid and ‘‘grey’’ areas.
23. Other relevant plans and strategies include the 2009 Climate Change Strategy and Action Plan, the 2010
National Policy on Climate Change in 2010 issued by the GRN, and the Electricity Control Board (ECB)
who the initiated National Integrated Resource Planning Study of 2010.
Institutional Context
24. The development of grid-connected renewable energy will contribute to the country’s energy security;
enable the country to meet the energy requirements of achieving Vision 2030 as well as increase
opportunity for new manufacturing industries. However, the White Paper recognises the need for
institutional capacities and planning frameworks to be conducive and facilitate the development of viable
renewable energy projects. Within this context, the following institutions will play critical roles in the
implementation of grid connected renewable energy projects including CSP.
Page 11
Government Ministries:
25. The Ministry of Mines and Energy (MME): The MME is responsible for ensuring the adequate and
affordable energy supply in a sustainable manner taking advantage of Namibia’s natural resources in
support of the nation's socio-economic development by formulating and implementing enabling policy
frameworks. One of the MME objectives is to make sure that increases of energy supply and utilization are
sustainable, competitive and economically efficient. At the same time MME aims to increase the proportion
of renewable energy in Namibia’s final energy consumption is increased. To this end, the Ministry of Mines
and Energy has published the Energy White Paper in 1998 and the Demand Side Management report
under the Electricity Control Board.
26. The Ministry of Environment and Tourism (MET): The MET has initiated capacity building for a
policymaker’s project that seeks to strengthen the national capacity of Namibia to develop policy options for
addressing climate change across different sectors and economic activities. This could serve as inputs to
negotiating positions under the United Nations Framework Convention on Climate Change (UNFCCC).
The national capacity building projects entail:
27. The Ministry of Trade and Industry (MTI) - To ensure a continually responsive, investor-friendly climate,
the ministry introduced a number of special incentives for manufacturers and exporters including:
• Widening the incentive range from the provision of significant tax deductions to concessional loans and
indirect subsidies on marketing and training costs;
• provision of tax abatement of 50% for manufacturing activity;
• writing off provisions of up to 20% or less annually on buildings erected for manufacturing purposes;
• Deductions for marketing, training, wage, and feasibility study costs; and
• Such incentives could increase the viability of renewable energy investors in Namibia.
28. The Electricity Control Board (ECB): The ECB is the regulator of the electricity supply industry. The core
mandate of the ECB is to exercise control over the electricity supply industry with the main responsibility of
regulating electricity generation, transmission, distribution, supply, import and export in Namibia through
setting tariffs and issuance of licenses.
29. One of ECB’s objectives is to ensure a competitive environment by facilitating the increase in the number
of participants in the electricity supply industry and encourage greater investment in generation. In this
regard, the ECB has completed a number of regulations aimed at encouraging entry into the market of
Independent Power Producers (IPPs), notably, the IPP and Investment Market Framework and Grid Code.
The ECB started also the process to develop a National Integrated Resource Plan (NIRP) to ensure that
new power stations are introduced according to a schedule that is consistent with national energy planning,
as well as to ensure the optimal utilisation of resources and the diversification of the generation mix in
Namibia to mitigate the risk of over-reliance on imports.
30. Since 2000, the ECB has introduced a number of measures aimed at improving the competitive
environment by moving towards cost reflective tariffs for grid-fed energy generation and increasing the
number of players in the industry, notably the formation of Regional Electricity Distribution Companies
(REDs) operating at the sub-national level (ERONGORED, CENORED and NORED). In Figure 6, the
Page 12
prevailing market structure in Namibia which is a ‘‘Single Buyer Model’’ is illustrated. Presently, the ECB
contemplates the creation of a modified single buyer market structure. The model will be similar to a
wholesale market where there are multiple buyers and sellers of electricity. REDs and other distributors
will be able to buy power directly from the IPPs.
31. NamPower is a semi-autonomous government agency that is currently the country’s only supplier of
electricity through its generation, transmission, trading and single-buyer activities. The electricity supply
industry is regulated by the Electricity Control Board (ECB) which sets tariffs and issues licences to
operators in the industry. NamPower’s role in a modified single buyer model remains critically important,
especially to maintain system balance in real time, and NamPower will also remain the supplier of last
resort.
32. The Regional Electricity Distributors (REDs): A “RED” is a regional electricity distributing company
tasked with supplying electricity to the residents in a specific region. In 1998, the MME recommended that
Namibia be divided into five areas and that a single electricity distributor be established for each area
solely responsible for electricity distribution in that area. In order to consolidate all distributions in an area,
all electricity distributors in such area voluntarily join their electricity businesses in a single private entity, a
RED. The Namibian Cabinet has approved the establishment of REDs in Namibia since 2000. REDs are
established through private companies with all initial shareholding by Government-owned or public entities.
They are concerned with electricity supply and creating conducive conditions for the achievement of Vision
2030.
Financial Institutions
33. Development Bank of Namibia (DBN) – The availability of suitably structured financing is critical for the
commercialisation of CSP in Namibia. The DBN is the premier provider of development financing in
Namibia. DBN fosters, empowers and finances bold new ventures. Whether large or small, a start-up or
expansion, private or public sector, the Development Bank of Namibia generates success, innovation,
12
ECB`s Development of a Procurement Mechanism for RE Resources in Namibia, November 2010
Page 13
growth and prosperity. The Bank provides finance for private sector start-ups and expansions, equity deals,
bridging finance, enterprise development finance, trade finance, small and medium enterprises, public
private partnerships, public sector infrastructure, local authorities, and bulk finance to responsible micro-
finance providers. The DBN only finances Namibian participation in projects.
34. The Renewable Energy & Energy Efficiency Institute (REEEI) of Namibia: The REEEI is a national
energy institute of the Polytechnic of Namibia dedicated to serve as a national information resource base
for RE, sustainable energy use and management, and conducting policy research. The institute has
provided energy management training and is enhancing its capacity to be able to work more effectively with
the private sector in promoting RE & EE and supporting activities on the ground. REEEI was established
and is funded by MME and the Polytechnic of Namibia to promote RE & EE through research &
development. The Institute was commissioned to undertake the CSP Pre-feasibility Study in January 2012.
REEEI is the implementing partner of CSP TT NAM.
35. Desert Research Foundation of Namibia (DRFN): The DRFN is a Namibian non-governmental
sustainability organization aiming to enhance decision making for sustainable development through
research, training and consultancy in the country’s land, water and energy sectors. DRFN provides
objective, relevant and professional services supporting decision makers from communities to traditional
and local authorities, from the highest decision making bodies and individuals in government and private
sector. This is achieved by developing, disseminating and implementing scientific, fact-based and
analytical options that form the backbone of policy development, planning and implementation, thereby
contributing to Namibia’s sustainable development. On the energy front, DRFN have a dedicated Energy
Desk who believes that the greater use of RE sources, diversification into alternative energy sources, and
greater efficiency in the use of power can all make Namibia’s energy consumption more sustainable. The
Energy Desk is involved in realizing some of these great opportunities.
38. The GRN recognizes its urgent need to develop additional generation capacity to meet the expected
electricity shortages forecast for 2015 and beyond. Building on the interest expressed among local actors,
Namibian stakeholders are now eager to take necessary steps to contribute to the development and
implementation of locally-specific CSP technology policies and platforms by engaging in technology
transfer and pre-commercial demonstration schemes. Moreover, the GRN views CSP as a key technology
to bridge the forecasted 2015 energy deficit13. The current challenge for the GRN, however, is to be able to
implement specific power projects included in their 2012 short-term strategy14 that would include a:
13 Ibid 5
14
Ibid 5
Page 14
• “1st step” that includes the development of 100 MW of wind, PV and backup diesel projects by mid-
2014; and
• “2nd” step that would include 100 MW of CSP by mid-2015.
An indicative timeframe to develop these power generation sources is shown on Figure 7. This approach
would not only guarantee the fastest development of local capacity as well as the least cost, it would also
promote the development of renewable technologies in Namibia. The funding available under the GEF-4
Resource Allocation Framework will provide a key strategic entry point to achieve that goal.
39. Namibia has one of the best solar regimes in the world peaking to 3000 kWh/m²/year in certain areas and
minimal cloud cover and aerosols, and is strongly intent on developing this important resource through
CSP projects as a part of its response to the challenge of sustaining and increasing its economic growth.
As such, the CSP industry will play an important role in Namibia in the years to come. As the Namibian
energy sector faces considerable financing needs which cannot be mobilized entirely from public sources,
overcoming funding constraints is a major challenge for Namibian policy makers. Furthermore, the way in
which these constraints are overcome will, to a large extent, determine the country’s ability to equip
industries and households with clean energy in the medium to long term utilizing Namibia’s excellent solar
regime that has the potential for more than 250,000 MW of power generation on suitable land.
40. The GRN through its policy framework, institutional and regulatory framework is in a position to
aggressively promote energy access through state-owned power utility NamPower and the REDs as well
as bringing on board IPPs in the country. The financial envelope for short, medium and long-term
investment projects is estimated at USD 1 billion. The power utilities and IPPs are rapidly rolling out new
approaches for grid-based, isolated and stand-alone electricity services. New generation capacities
through a recently developed hydropower master plan identified production for all potential hydro power
projects in the Lower Kunene, Kavango and Lower Orange Rivers while the CCGT Kudu gas project has
been in the pipeline for the past 20 years for development.
Page 15
Figure 7: Indicative Timeframe for Development of Power Generation Sources between 2012 and 201515
2012 – 2nd 2013 – 1st 2013 – 2nd 2014 – 1st 2014 – 2nd 2015 – 1st 2015 – 2nd
Semester Semester Semester Semester Semester Semester Semester
Negotiate PPA
Delivery and
under IPP regime
installation of
Operation startup (up to 150 MW)
Diesel backup
All renewable
1st Step promoters
engines
Wind or PV & required to
Backup diesel install and Installation of wind and solar PV projects
transfer(?) to (only wind projects with measurements can Operation startup reducing diesel oil
Nampower diesel provide energy in the required time frame) consumption
backup engines
Feasibility study
Environmental EPC procurement
2nd Step screening
CSP with Financial closing
Operation
Negotiation with Installation of CSP project startup
development Development
financing institutions Environmental
authorization
Selection of
Strategic partner
41. In the event that financial needs act as a “brake” on energy related project development, economic growth
will be hampered increasing poverty. Therefore, development of a robust and broad-based private sector
is the only means by which sustained growth of CSPs can be achieved in Namibia. The CSP TT NAM
project can catalyse the development of the CSP private sector. Financial market frictions can be the most
critical mechanism for generating persistent income inequality or poverty traps. There is also a significant
and robust relationship between financial depth and economic growth. Financial depth is not only
associated with a higher growth rate but it also has an additional pro-poor effect, disproportionately
boosting the income of the poor. A case in point is the Namibia Renewable Energy Programme (NAMREP)
which was designed to address some of the barriers experienced in the dissemination of renewable energy
technologies in Namibia. Indeed, the programme created demand for renewable energy technologies
(RETs) and maintain a large clientele base.
42. The acceleration of CSP projects and in general, renewable energy development in Namibia will need to
respond to its energy policy and planning that is guided by the Energy White Paper of 1998. Energy has
also been integrated as cross-cutting topic into the national vision and development plans, specifically
NDP3. Vision 2030 spanning a 20-year period has consequently been formulated to that effect for the
transformation of Namibia into an industrialised nation, with viable natural resources based export sector,
and increased size of skills-based industrial and service sectors as well as a market oriented production.
This vision necessitates a rapid industrialisation that will place significant pressure on the Namibian
electricity supply industry, and challenge its growth and ability to deliver electrical energy on demand.
43. The Vision will open new opportunities for independent power generation plants that the CSP TT NAM
Project aims to catalyse through improving the enabling environment for CSP investments. This would
include improving the assessment of the solar resource, thorough analysis of available technologies,
improved governmental support on potential CSP sites and regulatory permitting requirements, and
financial access. In addition, there are also capacity barriers and challenges within the mandated
15 Ibid 5
Page 16
institutions related to policy development and implementation that must be addressed to catalyse the
development of CSP projects.
Barrier Analysis
International Context
44. High initial capital costs are the most important barrier for the expansion of CSP. As much as 87 percent of
the cost of electricity produced by a solar thermal plant is related to the initial capital investment and
installation cost, with the remaining 13 percent being the cost of operating and maintaining the plant16.
Estimates range the capital costs between $4,000 and $6,000 per kW for typical capacity factors in the
range of 22-24 percent. Therefore, a CSP plant is still not competitive with fossil-fuel fired plants or even
with wind energy plants. For example, CSP plant costing $4,000/kW operating at capacity factors of 22-24
percent can be around four times as expensive as combined cycle gas turbine plants.
45. There is broad consensus within the industry circles, however, that there is high cost reduction potential for
CSP due to three factors:
First, manufacturers have to yet to benefit from economies of scale. The history of PV suggests that
doubling of capacity leads to a 20 percent reduction in costs. Scale benefits include longer and more
automated production runs, purchasing power on sourcing components and materials, and bigger R&D
budgets. Furthermore, if the average CSP system size increases to several hundred MW, this is likely
to work out cheaper per MWh because of the scale leverage on a central turbine and grid connection17.
There have been several estimates on the cost reduction possibilities; for example, one estimate
predicts a reduction from USD 4,943/kW for a 100 MW in 2007 to USD 3,157/kW for a 200 MW plant in
2015, reflecting a decrease of 8.6 percent per year18;
Second, technical improvements can be realized in certain components and accelerated when
companies R&D respond to increased global demand. For example, between 1991 and 2004
technology advances helped reduce O&M costs by 30 percent and improve annual solar-to-electric
efficiency by 20 percent for parabolic trough systems19. Solar thermal companies are exploring more
cost effective construction of collectors, wider diameter absorber tubes to reduce pumping costs and
direct steam generation in receivers. New optical configurations (mirror alignment, tracking systems,
and types of transfer of fluids) could lead to higher efficiencies or load factors. Companies are also
exploring different storage materials and reflective surfaces that could lead to higher efficiencies.
Finally, one third of the system cost is construction and installation; hence, improvements in structural
design and introduction of new materials would reduce the weight of systems (transport costs) and
complexity (installation costs). Storage technology in CSP plants also needs further development as
there is only one such commercial plant in operation in Spain. A large thermal storage system with a
storage capacity of up to 7 hours can provide electricity during periods without sunshine and thus
supply power during peak demand in the evening. The higher investment for a storage facility, such as
a molten salt thermal storage tanks (with a storage capacity of approximately 1,000 MW th) is
compensated by the higher reliability and flexibility that will allow the plant operator to dispatch the solar
energy to the grid when wholesale prices are higher;
Third, increased demand will result in a more diverse supply chain which will reduce component costs.
New entrants are entering the market for components that are currently supplied by a small number of
companies. Larger companies with experience in achieving economies of scale through mass
production are also entering the CSP market in anticipation of market growth. An example of this is the
recent acquisition of Solel solar systems by Siemens AG.
16 Grama 2008
17 Merrill Lynch
18
CSP Today, 2008
19 Electric Power Research Institute, EPRI, 2007
Page 17
46. A gigawatt-scale regional CSP deployment program has the potential to drive cost reductions by virtue of
volume production, increased plant size, and technological advance. Given the uncertainties of future
business, supply industries have operated on the basis of serving one-off customers instead of setting up
complete R&D, large-scale manufacturing, and operations and maintenance programs. The result is very
high cost, underexploited economies of scale and limited investment in R&D leading to technology
development and innovation.
47. A deployment program of 10 to 12 utility-scale CSP plants in a number of countries would send a strong
signal to the market that would enable industry to plan manufacturing capacity expansions, which is central
to driving down the costs of solar thermal technology and production processes. The proposed GEF CSP
program would thereby make a major contribution to accelerating global market momentum.
Namibian Context
48. There are still a number of barriers, however, that inhibit the establishment of CSP plants in Namibia
including those discussed in the following paragraphs.
49. Insufficient capacity and CSP awareness of local industry: The participation of local industry in the
supply of some components and services to a CSP project would potentially reduce costs. Components
such as civil works, installations on site, connecting piping, electronic equipment have been estimated to
constitute about 22% of the capital costs whilst services such as engineering project management services
amount to about 8% of the capital costs. Namibia has had a limited industrial development and continues
to import most of the manufactured products, mainly from South Africa. The largest manufacturing sector in
Namibia is the food sub-sector20 followed by chemicals and plastics. While the manufacturing sector does
have potential to participate in the CSP value chain, there is a lack of skilled technicians and labor. In
addition, there are a number of engineering consulting firms that have not yet had the exposure to CSP
projects, but could provide project management services and be given some exposure to CSP technology
and specific CSP project management knowledge. There have been recent efforts through to bring foreign
CSP players into the Namibian CSP market, a scoping and due diligence analysis of global players had
been done using some of the networks created through the CSP Pre-feasibility Study21 and TREE project
CSP Seminars in 2009. More sustained efforts to link local companies to foreign CSP equipment providers
can provide local companies with invaluable opportunities to participate in the CSP value chain when the
CSP projects are developed in Namibia.
50. Inadequate financial and regulatory frameworks: Investors in general have tended not to invest in large-
scale renewable energy technology in developing countries, including Namibia, due to the lack of support
mechanisms such as appropriate financial and regulatory frameworks. The recent CSP Pre-Feasibility
Study (July 2012)22 underscored the deficiencies of the current regulatory framework that is currently not
conducive to CSP investment. For renewable energy projects in Namibia:
Independent power producers (IPPs) must be able to have access to the electricity market and to sell
electricity at a price that provides a sufficient return on the high CSP investment. This can be
accomplished either through equitable regulated purchase tariffs or more generally through power
purchase agreements (PPAs) to a distribution company or distant consumer (wheeling). Unfortunately,
in Namibia, purchase tariffs are nonexistent, PPAs are poorly designed, and regulators do not allow the
wheeling of excess power production through existing national grids;
Transmission costs of a CSP plant can be significant since most suitable CSP sites are located far from
population centres;
Local grid codes, guidelines and standards are not well-suited for renewable energy generation which
is variable and different from conventional generation sources from fossil fuels;
The procurement methods recommended by the REPM study and now under consideration by MME are:
• Tendering to be applied for solar (CSP and photovoltaics-PV) and large wind based generation
systems, i.e. for CSP, PV and wind greater than 500kW in installed capacity;
• REFIT for small wind, small hydro and biomass including landfill gas;
• Net-metering for roof top based PV; and
• Other support measures like soft loans, grants, tax breaks, etc. to support all the above instruments
and continue promoting rural and off-grid electrification.
The REPM study recommended that a comprehensive approach to renewable energy deployment in Namibia
should include a mix of both small and large generating units. MME was therefore recommended to
promulgate regulations that provide for four procurement mechanisms. Since the establishment of the PSC
the different procurement methods are at different levels of implementation as described below:
• Because of the urgency for renewable energy capacity into the national power system, tendering for 30
MW PV will be issued in 4Q 2012.
• Net metering rules for roof top-based PV are being developed and are expected to be finalized in
January 2013.
• REFIT rules are being developed with the assistance of United States Agency for International
Development (USAID).
51. Limited awareness, promotion and participation on technology transfer (TT) including inappropriate
policy support: There is a general lack of awareness amongst policymakers on the potential role of TT on
renewable energies which inhibits the adoption of appropriate and relevant policies and regulations that
would increase the diffusion of these technologies. In Namibia, there have been a number of recent CSP
seminars and visits by foreign CSP players that serves as a window to foreign CSP technologies to
Namibian policymakers. This includes the technical teams that prepared the CSP Pre-Feasibility Study
and the Capacity Building Roadmap and Technology Transfer Programme. A sustained and concerted
effort to raise CSP awareness amongst policymakers is required to provide Namibia with the appropriate
policy support.
52. Limited technical and financial capacities: Despite expressing their willingness to participate in CSP
technology diffusion, local investors (such as the mines and the development banks) lack the technical and
financial resources and expertise to develop and adopt the CSP technology. Recent visits by various CSP
players including the technical teams preparing MME’s Pre-Feasibility Study and Technology Transfer
Programme23 have helped raise the awareness of CSP opportunities; however, local financiers and
developers remain unfamiliar with CSP technologies, and are unable to design appropriate financing
packages and risk instruments for the technology. This lack of investment and financing capacity is a
chronic barrier for any capital-intensive infrastructure project in Sub-Saharan Africa and this inhibits the
ability of project developers to secure underlying financing for their projects.
23
Ibid 5
Page 19
53. Lack of investment grade data on solar resources: Namibia has sufficient satellite data on its solar
energy resources. With potential sites now identified for future CSP development, ground measurements
of the solar resource at specific locations are required to validate the satellite solar data. The ground
measurements will be required to quantify the solar resource available at specific sites due to topographical
variances.
Stakeholder Analysis
54. The main stakeholders of this project and their role in CSP development are assessed.
Government Ministries:
55. Ministry of Mines and Energy (MME) is the main stakeholder for this project and essential partner for the
realization of CSP technologies in the country. Its mission is to promote, facilitate and regulate responsible
development and sustainable utilization of Namibia’s mineral, geological and energy resources through
competent staff, innovation, and research and to collaborate with stakeholders in a favorable environment
for the benefit of all Namibians. As the custodian of Namibia’s energy sector, the MME sets policy and
provides funding to the industry, for example by providing monies for the extension of the country’s rural
electrification infrastructure. The MME has introduced independent power production schemes and reforms
through the ECB, such as increasing low electricity tariffs up to international levels. Institutional reforms of
existing power utility, including the establishment of independent power production schemes, aim to shift
the power sector away from its monopolistic and centralized structure. The Government of Namibia is
desirous to integrate RE into its national energy mix and has engaged the MME on its behalf to finalize a
RE policy and regulatory framework that is to draft a law facilitating a wider adoption of RE technologies
and methods for energy production and thus reduce dependence on electricity import.
56. Ministry of Environment and Tourism (MET) develops policy options for addressing climate change
across different sectors and economic activities. MET is an essential partner to CSP TT NAM which is a
greenhouse gas abatement and clean technology driven project. As of June 2008, Namibia has an acting
Designated National Authority that has successfully reviewed and approved the first Clean Development
Mechanism (CDM) project to contend for registration with CDM Executive Board. Since the compliance and
voluntary markets are both designed to reduce global greenhouse gas emissions, both markets are in the
beginning stages of development in Namibia. The CSP TT NAM project lays the foundation for the CDM, a
mechanism to involve Namibia in GHG emission reductions activities.
57. Ministry of Finance (MOF) provides financial support through budget allocation to Line Ministries including
MME and GRN institutions involved in RETs, RE-EE development and RET/EE projects that may benefit
from budget allocation. Due to its broad networking and collaboration with international and local
stakeholders, MOF should strengthen its linkages with other development institutions such as the World
Bank, IFC, African Development Bank, the Development Bank of South Africa (DBSA), donors such as
JICA, KfW/GTZ, AFD, to mainstream investment planning of CSP projects whether public or private.
58. There is, however, a need to consider what governmental structure is needed to ensure that CSP TT Nam
is mainstreamed into development planning and poverty reduction plans at Ministry of Finance level in
collaboration with the National Planning Commission (NPC). If a significant portion of the investment
comes from the private sector, the required fund flows to create a CSP industry or market will surpass the
capacity of the relevant government agencies. As such, GRN through MOF will need to devise policies,
incentives and regulation to turn private initiatives towards strengthening CSP industry in Namibia. MoF’s
selection criteria for the CSP TT NAM Project will need to address issues such as the Project meeting
Namibia’s sustainable development strategies, its objectives to reduce poverty, and its goals on providing
new jobs or stimulating a new industry.
59. Ministry of Trade and Industry (MTI) ensure a continually responsive, investor-friendly climate with
incentives. CSP TT NAM project may benefit from MTI-backed incentives to stimulate investment and
Page 20
generate employment. Many of these are covered by acts of Parliament that are passed from time to time
and by short-term tax breaks contained in budget statements. General incentives for companies setting up
projects in Namibia under the MTI that could increase the viability of renewable energy investors include:
• Widening the incentive range from the provision of significant tax deductions to concessional loans and
indirect subsidies on marketing and training costs.
• Provision of tax abatement of 50% for manufacturing activity;
• Writing off provisions of up to 20% or less annually on buildings erected for manufacturing and
processing purposes; and
• Deductions for marketing, training, wage, and feasibility study costs.
60. Electricity Control Board (ECB) has the core responsibility of regulating electricity generation,
transmission, distribution, supply, import and export in Namibia and as such,responsible to control and
regulate the provision, use and consumption of electricity in Namibia, to oversee the efficient functioning
and development of the industry, and security of electricity provision, to ensure that a competitive
environment in the electricity industry is maintained, and to promote private sector investment in the
electricity industry. Importance to the CSP TT NAM Project, the ECB defines quality of supply standards,
approves tariffs, and grants generation, transmission and distribution licenses. The main task of the ECB
on the CSP project will be issuing of a license for the independent power producer (IPP) and to monitor
that the licensee fulfils the requirements and conditions included in the license. Figure 8 shows the steps a
CSP IPP application will go through before a license is finally issued or refused.
61. NamPower is the national power utility of Namibia and specializes in the generation and transmission of
electricity. NamPower’s main objectives are the availability, affordability and accessibility of electricity to as
many Namibians as possible within the shortest possible time. NamPower's main sources of power are the
thermal coal-fired Van Eck Power Station outside Windhoek, the hydroelectric plant at the Ruacana Falls in
the Kunene Region, and the standby diesel-driven Paratus Power Station at Walvis Bay. NamPower also
has a world-class transmission network. As an electricity company NamPower understands that electricity
invariably plays an important role in the socio-economic development of Namibia and is supportive to a
number of renewable energy projects in the country such as the Tsumkwe Hybrid Energy project and
Page 21
Combating Bush Electricity for Namibia Development (CBEND) project. Presently, NamPower is the only
bulk supplier of electricity. The national utility generates electricity, transmits this via its transmission
networks, and also manages all electricity imports and exports to/from Namibia. The electricity supply value
chain is shown on Figure 9. NamPower is an essential partner in CSP TT NAM project.
62. Other actors within the ESI are the Regional Electricity Distributors (REDs), of which NORED, CENORED
and ErongoRED are currently operational. The CSP TT NAM Project is earmarked to be constructed either
in Erongo Region in the west or Karas Region in the south or Otjozondjupa Region in the central; the
Southern RED is pending operationalization. Of importance to the CSP IPP will be the REDs who are the
potential off-takers or investors in the CSP TT NAM project.
Activities
Operations of power High-voltage, long- Regional Sale of electricity to
stations and distance distribution of end users
production of transmission of electricity from the
electricity, i.e. the electricity between national grid
120MW Van Eck generator and
coal-fired plant, the distributor
24MW HFO
powered Paratus
plant and the
249MW Ruacana
plant (hydro)
63. From an international perspective, the large volume for the finance of CSP plants (USD 4 to 6 million/ MW)
is often provided by many different institutions such as banks. On the Spanish CSP market, several special
purpose vehicles have been founded by a project consortium. Andasol 1 has been financed in the
beginning by the companies like Solar Millennium (25%) and ACS Cobra (75%). Later Solar Millennium
sold all share to ACS in 2009 after commission of the project. Andasol 3 is in the ownership of the special
purpose vehicle “Marquesado Solar S.L.” on which RWE AG, Stadtwerke Munich, Rheinenergie and MAN
Ferrostaal and Solar Millennium have ownership. In Algeria, the ISCC plant was also financed by a
consortium of the engineering and EPC contractor Abener and Sonelgaz (NEAL). For these first projects,
the risk was consequently shared between the project developers and larger investors. The project
Page 22
developers tried to issue a fund to increase their limited financial resources to be able to hold these shares
of approximately 25%. After completion of the project, the project development company often sells its
share to other owners for the operation. The World Bank and African Development Bank have played a
very important role in Egypt and Morocco and GEF has had strong involvment on the financing of CSP
plants. Under a feed-in scheme, the risk for private investors and banks is limited if the state guarantees
for the payments over 10 to 20 years. When several investors and banks have gained their first
experiences with the CSP projects and their rates of return from electricity sales, CSP projects will become
more bankable for creditors.
64. Within the Namibian context, the availability of suitably structured financing is critical for the
commercialisation of CSP project in Namibia. The Development Bank of Namibia (DBN) is the premier
provider of development financing in the country. DBN fosters, empowers and finances bold new ventures.
Whether large or small, a start-up or expansion, private or public sector, the Development Bank of Namibia
generates success, innovation, growth and prosperity. The above arguments emphasise the need for DBN
to provide an appropriate incentive framework for the CSP TT NAM concept to get established and thus
paving the way for the local commercial banks to involve in financing CSP projects. The commercial banks
in Namibia include; Bank Windhoek, NedBank, First National Bank and Standard Bank of Namibia. Of note
is that Bank Windhoek has been involved in financing RETs during the NAMREP programme followed by
First National Bank for the same programme and the local commercial banks will be receptive on the
creation of proper financial conditions for economic viable CSP industry in the country.
Research/Academia Institutions
65. Renewable Energy and Energy Efficiency Institute (REEEI) is an institute affiliated with the Polytechnic
of Namibia that focuses on the establishment of a national information resource base for renewable
energy, sustainable energy use and its management. The REEEI is primarily supported by the Government
of the Republic of Namibia. It has a “leadership role in the transition of knowledge from traditional energy
sources and usage to a more sustainable energy economy” (www.reeei.org.na) and works in close
partnership with the Ministry of Mines and Energy (MME), serving as an information platform. Currently,
several projects are being conducted at the REEEI including the NEEP project with its focus on energy
efficiency improvement in buildings, and the preparation of a master plan (with MME support) for the
provision of electricity in off-grid areas by means of the establishment of “Energy Shops” that will provide
access to affordable, sustainable energy technologies, fuels, appliances and services in off-grid and “pre-
grid” areas.
66. The Institute worked closely with the MME/UNDP funded Namibia Renewable Energy Programme
(NAMREP) in addressing various barriers to renewable energy in Namibia. In 2009, REEEI in collaboration
with the Transfer Renewable Energy & Efficiency (TREE) project funded by the German Federal Ministry of
Environment, Nature Conservation and Nuclear Safety conducted a training seminar in Namibia on solar
thermal power plants. The Institute is linking up various Polytechnic of Namibia departments with various
organizations for research and development in CSP technologies. Research & development is ordered on
a superior level. To bring the technology forward project partners should work together with research
institutions.
67. The Polytechnic of Namibia (PoN) became an independent educational institution in 1996 with its
education programs aligned mostly with Namibia’s industrial demands. The largest faculty is the School of
Business and Management followed by the School of Engineering. Along with a number of other technical
courses, PoN has centers of learning for “Teaching & Learning”, Entrepreneurial Development, Applied
Research and Technology, Business Innovation, and the aforementioned REEEI. In the field of renewable
energy, PoN focuses on solar home systems, wind generators as well as the energy efficiency.
68. The University of Namibia (UNAM) has its main campus in Windhoek with an additional ten campuses
throughout Namibia. UNAM has a faculty for renewable energy located in Ongwediva as of January 2008.
Page 23
UNAM also conducts research in capacity building and training through workshops covering topics such as
the development of the research policy, institutional research and strategy implementation.
Industry Representatives
69. The Namibian Institute of Architects (NIA) promotes architecture and sound architectural practice
among the Namibian architectural profession and general public of Namibia. The NIA is also in close
affiliation with the Namibian Council for Architects and Quantity Surveyors. Against this background, the
maximal slope of a site for a parabolic trough plant is 2-3°. With excavators the site is flattened to match
the requirements of the collectors. The pylon foundations of the collectors require excavations of about 2
meters depth on a square of 2.5 x 2.5 meters. Pylon foundations are individually designed for end pylons,
drive pylons, middle and shared pylons as well as in reinforced design for the outer areas of the field,
where higher wind loads are expected. Sometimes, an additional wind barrier has to be added to avoid
large wind loads or sand pollution of the solar field. Additional civil works includes all construction for
infrastructure like roads to the building site or machine houses, assembling halls, engineering offices and
logistic centers as a feed stock for material and components. These works are basic construction work and
not CSP specific. Therefore, local companies; architects, consulting engineers and surveyors provide this
service for the installation of the plant as well as relevant practice documentation, such as contracts.
70. Namibia Manufacturers Association (NMA) developed a strategic plan with the vision to facilitate a
sustainable, competitive and prosperous manufacturing and processing industry for all stakeholders’
benefit in the country. In the event that a CSP industry is realized in Namibia which involve amongst others;
parabolic trough receiver production processes, bent glass mirrors production processes and metal
structure production processes, the manufacturers association being the watch dog and mouthpiece of
Namibian member manufacturers representing 61 manufacturers, and offering them and others, services to
help improving their businesses, the CSP industry present a new opportunity for manufacturers to venture
into CSP sector. The on-site jig-assembly, the antireflective coating and galvanization seem to be most
likely to be performed in Namibia. On the other hand it is very difficult to give a clear final judgment as a
production complex is never based on one single process. Nevertheless, this overview is based on recent
production technologies. It is therefore likely that the approach undergoes a continual change, during the
development of a competition-based CSP market for Namibia.
71. Another important step for Namibia manufacturers are Joint Ventures of CSP companies. To borrow from
elsewhere:
‘‘For instance Flabeg erected a whole mirror production in the USA and every German CSP company has
a Spanish and American subsidiary to be regarded as a local and not as an intruder looking for government
subsidies. A good example is Egypt, where almost the whole erection of the CSP power plant was
managed by a local company. As these companies have excellent connections to the state and know the
local specifics it was important to include them’’.
72. On Table 1 and in accordance with the CSP value chain, early indication shows that local Namibian
companies and through the Namibia Manufacturers Association could be potential commercial participants
in the CSP market development for Namibia.
73. In the final analysis, the participation of local companies in the implementation of CSP projects would
potentially reduce the costs of implementation; create new jobs and CSP technology transfer. Table 2
shows the CSP value chain and possible areas of local participation.
74. The CSP value chain in Table 2 consists of the CSP core value chain and contains six main phases with
varying degrees of participation for local players:
Project Development: This is the first phase in the implementation of a CSP project. At the beginning
the decision-making process with technical and economic feasibility studies, the site selection and
financing opportunities provide the basic scope of the project. After a first draft with these basic
Page 24
decisions the conceptual engineering starts with a proposal for the technical specifications. With the
conceptual design the permission process and contract negotiations start and these phases will get
determined with the financing of the whole project. In current projects engineering experts with
specialization on power plant projects offer all the services needed for the project development. Often
this phase tends to be the longest due to the fact that feasibility studies, permissions and public
decision-making processes take very much time.
Raw Materials and Components: The second phase of the CSP core value chain is the raw materials
and components. Some of them are provided by the world market others are supplied locally depending
on costs and logistic aspects. The highly specialized components are supplied mainly by a few
international players who have specialized in CSP components such as the trough systems. This is
dominated by a few CSP developer companies. Other components such as reflectors, mirrors, reflector
film, heat collection element, are supplied by companies in related manufacturing activities but who
have added a production line to cater for CSP components. This is a larger group of companies than
the specialized CSP developers, but also tend to be large international companies. Other components
sourced from this group of companies include those components used in power plant production but
not unique to concentrating solar and include natural gas boilers, stream turbines, condensers, and
cooling towers. Components such as steel structures, piping, and insulation can be locally
manufactured by industries already engaged in related manufacturing activities;
Plant Engineering & Construction: The fourth phase of the value chain is the plant engineering &
construction done by the engineering, procurement and construction (EPC) contractor. The EPC
contractor is responsible for the whole plant construction. As project manager he/she selects all the
suppliers and awards most of the jobs to subcontractors. As a project manager the main task of the
EPC contractor is to coordinate all partners. EPC contractors are mostly subsidiary companies of
industrial groups who can resort to building companies and engineering consultants in their own
company group.
Operation: as the fifth phase includes the operation and maintenance (O&M) for several years (up to
25-30 years). The tasks for operation and maintenance can be split into different groups of areas: Plant
administration, operation and control, technical inspection of the power block and the solar field
operation and maintenance. The task of operations is well suited to local contractors / IPPs to
undertake and provides long-term employment opportunities;
Transmission and Distribution: This is the final step that delivers the electricity from the plant to the
consumers. Large utility companies take the responsibility for the distribution (wheeling).
Page 25
City Concrete (Pty) LTD Foundations
Concretech industries Foundations
Concrete-Simply In Foundations
NAMSLAB Foundations
COASTAL PRECAST & PAVING Foundations
WIBEKU CC Foundations
Precast Walls Foundations
Coupar Contrete (Pty) Ltd Foundations
Barloworld Concrete Industries Foundations
Kraatz Steel (Pty) Ltd Steel structures
Namibia Engineering Corporation Steel structures
Pro-Edge Steel Steel structures
Coastal Steel Works Steel structures
Stainless Engineering Steel structures
Exacto Engineering CC Steel structures
Invo Stahlbau CC Steel structures
Steel & Wire Steel structures
Steel Force CC Steel structures
Suresteel Steel structures
Steeldale Reinforcing & Trading (Namibia) Steel structures
Aurecon Engineering
Burmeister & Partners Engineering
EMCON Engineering
CSA Engineering
CMB Namibia Ltd Engineering
Meyer Consulting Engineers Engineering
Lithon Project Consultants Engineering
Windhoek Consulting Engineers (WCE) Engineering
Danie Nel Consulting Engineering
Corona Consulting Engineering
RMB bank Financial services
Project
Components Plant Engineering & Transmission &
Core value Development Materials Generation
(Namibia & construction Distribution
chain (Namibia & (Namibia) (Namibia)
beyond) (Namibia & beyond) (Namibia)
beyond)
Concept Concrete Mirrors EPC Contractor: Operation and Utility
Element of the engineering Steel Mounting Detailed maintenance of (NamPower)
core value chain Geographical Sand structure engineering the plant (IPP) Transport &
determination Glass Receiver Procurement distribution of
Determination of Silver HTF Construction electricity (REDs)
general Copper Connection
requirement Salt piping
Other Steam
chemicals generator /
heat
exchanger
Pumps
Storage
system
Power block
Grid
Page 26
connection
Essential Finance & Ownership (Namibia & beyond)
partners Research & Development (Namibia & beyond)
Political Institutions (Namibia)
Baseline Analysis
75. Namibia and the Southern African Power Pool have been experiencing severe power deficits since the
beginning of 2008. Namibia has an installed capacity of 393 MW, while having a peak demand of 477 MW
(excluding Zinc Scorpion mine) in 201024. The supply deficit has been filled through imports from
Mozambique, South Africa, Zambia and Zimbabwe. The inter-connector with South Africa is capable of
transmitting up to 600 MW, while the newly constructed High Voltage Direct Current (HVDC) Caprivi Link
Interconnector has a capacity of 300 MW and is upgradeable to 600 MW. Electrical energy units into
NamPower system from 2007 to 2010 has been steadily increasing from 3,554 GWh in 2006 rising to 3,767
GWh in 201025. Future demand scenarios are shown in Figure 10. When taking the limited national
electricity supply capacity of 393 MW into consideration, the figure illustrates Namibia’s precarious electricity
supply situation in 2010. Figure 11 gives the breakdown of energy resources while Figure 12 gives energy
situation in Namibia.
76. Namibia is vulnerable to power supply disruptions since its foreign suppliers are also facing a power deficits.
Step loads, largely from increased mining activities, will continue to place pressure on national supplies. To
address the current shortfall, MME through NamPower is contemplating a number of generation options as
summarised in Table 3.
900
6.000
800
700 5.000
600
4.000
GWh
MW
500
3.000
400
300 2.000
200
1.000
100
- -
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
77. In 2010, there were 8 IPPs that were conditionally licensed by ECB, intending to generate power from coal,
gas, heavy fuel oil, wind, hydro and biomass as shown on Table 4. The licensees are at various stages of
negotiating power purchase agreements (PPAs) with NamPower as expected in the single buyer market
27 REEEI 2010
Page 28
model. As yet, only Bush Energy Namibia has established an operational power plant (250 kW fuelled by
biomass, inaugurated in September 2010), while none of the other licensees has put up any power
generation infrastructure.
78. As mentioned in Para 37, the GRN views CSP as a key technology to bridge the forecasted 2015 energy
deficit and are aware through the CSP Pre-Feasibility Study28 of the actions required to build the requisite
capacity and technology transfers to catalyze a local CSP industry. The aforementioned barriers in Paras
46 to 51, however, need to be addressed in order to implement CSP projects to that will mitigate the 2015
energy deficit.
STRATEGY
Project Rationale and Policy Conformity
79. Overall, the CSP TT NAM project is set against a background of rising electricity consumption in Namibia
coupled with a growing power deficit in South Africa, the country’s main energy supplier. Like most
developing countries which are energy importers, the likely increase in future energy costs or disruption in
energy supply could jeopardize Namibia’s economic growth. These developments and risks contrast with
the limited application of renewable energy and energy-efficient measures and technologies in the country,
particularly among local authorities (including the REDs) who are the largest single electricity consumers
with the domestic/residential sector accounting for almost 50% of current energy consumption. Measures
to promote CSP projects can be expected to improve energy security, and also generate employment and
serve as a cost-effective GHG emission reduction option. As part of the historical legacy between Namibia
and South Africa, Namibia has inherited South Africa’s energy-inefficient mind-set, technologies,
28 Ibid 5
Page 29
applications and regulations as well as the general lack of awareness regarding the cost advantages of
renewable energy and energy-efficient technologies and equipment.
80. The project will help Namibia to develop its capacity in CSP technology through a facilitation of commercial
solar thermal plant, which is regarded as one of the cleaner and more mature technologies through south-
south and north-south transfer opportunities.
81. The project, which aims at mitigating the impacts of climate change through the promotion of on-grid
renewable energy, is an element of the GEF-4 Resource Allocation Framework. The project idea responds
directly to the GEF aim to promote low-GHG energy technologies, through the increased production of
renewable energy in electricity grids.
82. The proposed project is relevant to the ongoing MET climate change program, in particular to its efforts to
develop a national mitigation plan and support the development of technologies that reduce GHG
emissions, including renewable energy technologies (RETs).
Country Ownership
83. Climate change is considered one of the most serious threats to Namibia’s environment, human health and
well-being, and its economic development. Namibia has ratified the UNFCCC on 16 May 1995 and met its
obligation by completing Namibia’s First National Communication (the INC) to the UNFCCC in 2002, and
subsequent implementation of Namibia’s Second National Communication in 2010 (SNC)29. Both the INC
and SNC technical and research studies contributed to GHG inventories and identified key vulnerability
issues and priority policy measures for Namibia. A policy on National Climate Change was issued in 2010.
MET became the national focal point for climate change issues.
84. Another action implemented under the national climate change program is the establishment of the
Namibia Climate Change Committee (NCCC) in 2001. The NCCC is a multi-stakeholder committee to
advice government on the needed policies and strategies to adopt for preparing the country to the
predicted and, in some cases actual, effects of climate change. Currently, the committee consists of
representatives from the government, NGOs and parastatals such as NamWater and NamPower, private
sector representatives and tertiary academic institutions such as the University of Namibia and the
Polytechnic of Namibia. The MME has also taken other important steps to improve the performance of the
energy sector through its White Paper on Energy Policy. In this policy, the Government of Namibia
recognises the importance of RE and EE.
85. With the Energy Paper of 1998 and the complementary Vision 2030 approach towards renewable energy,
electricity supply has become a major issue for Namibia and indeed the entire SADC Region. The role that
the Energy White Paper played in the development of the Namibian renewable energy technologies
development cannot be over emphasised as the following extract in Box 1 underpins the Government’s
commitment to changing the playing field for the implementation of adequate RE technologies.
29 www.met.gov.na
30
Energy White Paper of 1998
Page 30
86. In this context Namibia has quite a long history with renewable energy (RE), energy efficiency (EE), and
technology transfer (TT) platforms. The Government of Namibia’s social obligation to electrify rural areas
and the need to provide electricity for the rural poor was a major initiative following independence in March
21, 1990. The rural poor population is dispersed over large parts of the country, making electricity grid
extensions often not a viable option, hence leading to the development of off-grid platforms. These early
assumptions drove government to implement several projects in support of the adoption of renewable RE,
EE, and TT solutions. The need to bring rural communities into the mainstream economy saw the initiation
of projects focusing on the development of different forms of energy, including from renewable sources.
Country Drivenness
87. Namibia is committed to the development of its renewable energy resources as articulated in the White
Energy Paper of 1998. The Government further recognizes the important role renewable energy and
particularly solar energy can play in the primary energy mix and energy security. Indeed Namibia supported
by catalytic resources from the GEF has put concrete measures in place to promote solar energy use. With
GEF support, Namibia has made great strides by removing some of the previous technical and institutional
and market barriers to successful adoption of RET in the country. However, new innovations and
opportunities for development still need to be supported, such as the opportunities for CSP TT. Within the
regional context, the development of CSP will add much needed electricity generating capacity towards the
objectives of Vision 2030, Namibia’s long-term development aspiration, which aims to develop the country
into a knowledge-based fully industrialized country. At the same time, the National Development Plan 3
(2007-12) has set a target for 10% of the national energy demand to be sourced from renewable energy by
2012.
88. In the White Paper on Energy Policy (1998), the Government of Namibia recognizes the importance of
renewable energy in the country’s energy mix. Further the Government has put in place concrete measures
to promote the greater use of solar energy and has successfully managed a large scale GEF supported
project that aimed at removing barriers to adoption and promotion of RETs and solar energy technologies
(SETs). In particular, this component will support the country’s “Off-Grid Energization Master Plan” which
has mobilized financing for the use of primarily solar energy in extending electricity services to off-grid
areas.
89. In addition, the Country Program Document (CPD) and United Nations Partnership Assistance Framework
(UNPAF) 2014-2017 of the Government of Namibia and UNDP/UN identify energy and environment for
sustainable development as a key strategic point to support Namibia’s long-term development aspirations.
The project idea is based on the CPD as well as the UNDP’s evolving strategic business plans (2008/11-
2013) and directly contributes to the attainment of the Millennium Development Goals (MDGs) and
sustainable energy for all (SE4ALL). In line with the proposed draft United Nations Partnership Assistance
Framework (UNPAF): 2014 -2017, the UNDP specific support for this areas falls under PC 1:
Environmental Sustainability and Climate Change under the NDP 4 Institutional Environment desired
outcome DO1). PC 1 will mainly focus on creating enabling conditions, and individual capabilities,
synergistically and complementary, with existing national initiatives, for safeguarding Namibia’s renewable
and non-renewable resources to ensure that Namibia remain and sustain international and regional
competitiveness by capitalizing on a nature-based economy. PC 1 is aimed at strengthening technical and
institutional capacities to deal with and manage environmental degradation including climate change
adaptation and mitigation in support of Namibia’s obligations and commitments to the national and
international (Multilateral Environmental Agreements (MEAs) and Rio plus 20 outcomes.
90. Firstly, UNDP’s support is premised on improving green environmental management issues to sustain
provision of ecosystem services and goods as well as to enhance environmental governance, management
and leadership capacities. Secondly, UNDP support will address environmental brown agenda issues,
particularly those related to wastes generated by extractive, transportation and agricultural industries and
protection of landscapes in specific biodiversity hotspots areas and forested lands. Thirdly, UNDP support
aims to enhance national participation and contributions to transitioning to a green economy in line with the
Page 31
Rio plus 20 outcomes and advocating for better environmental standards, creating awareness and
improving environmental education, and scaling-up tested and proven renewable energy innovations in
support of the SE4ALL.
91. MME is presently formulating the “New Energy Regulatory Framework” (NERF), which will look at
governing the approach of renewable energy and energy efficiency market development in Namibia by
facilitating fair market access, return on investment, quality of supply, standards, market support structures
and incentives and legal issues in Namibia.
92. It is expected that CSP TT NAM will provide valuable input to NERF and at the same benefit from a
successful energy regulatory framework. CSP TT NAM will benefit from the fact that both executing
partners, MME and REEEI, have collaborated in executing REEECAP and are still working together to
coordinate both NERF and the Off-Grid Energisation Master Plan (OGEMP).
93. This project also builds on the latest efforts of the World Bank Group (WBG) and African Development
Bank (AfDB) to pursue a Concentrated Solar Power (CSP) scale up in the Middle East and North Africa
(MENA) as well as the CSP Project in South Africa as part of their Clean Technology Trust Fund. The WB
and AfDB Regional Investment Plan (www.worldbank.org/cif) to implement a Gigawatt-scale CSP program
in the MENA region that will accelerate the global adoption of CSP technology. They note in the Investment
Plan that a confluence of factors provides a unique opportunity to provide scaled-up financing for the
demonstration, deployment and transfer of a low-carbon technology such as CSP with significant potential
for long-term greenhouse gas emissions savings. The South African 100 MW CSP project to be
implemented by Eskom with funding from the World Bank, African Development Bank and other donors will
serve as another regional scaling up opportunity. Government of Botswana is also undertaking a feasibility
study on a 200 MW CSP plant.
94. Most recently and importantly, the GRN funded its own pre-feasibility study during the July 2011 to July
2012 period under the auspices of MME, EEP and Polytechnic of Namibia, to determine its best options to
ensure the development of sufficient electricity generation capacity to overcome the 150 MW energy deficit
forecast for 2015. It also concluded that it will require short-term investments that includes CSP
development of 100 MW by 201531.
95. The CSP TT NAM Project was designed with extensive inputs from the major line ministries involved with
the Namibian White Paper on Energy Policy and its Strategic Action Plan on RE. The Project would
address key issues in the government’s strategy to improve institutional capacity for CSP promotion and
development, increase capacity of the local private sector to participate in the CSP supply chain, and to
develop 100 MW of CSP generation capacity prior to 2015.
96. MME is presently formulating the New Energy Regulatory Framework (NERF) which will look at governing
the approach of renewable energy and energy efficiency market development in Namibia by facilitating fair
market access, return on investment, quality of supply, standards, market support structures and incentives
and legal issues in Namibia. NAM CSP TT will provide valuable input to NERF and at the same benefit
from a successful energy regulatory framework. NAM CSP TT will benefit from the fact that the
implementing partner, MME, and other collaborators like REEEI, have collaborated in executing NAMREP,
REEECAP and are still working together to coordinate NEEP, NERF and the Off-Grid Energization Master
Plan (OGEMP). Synergies created during the implementation of those national initiatives will be replicated
to ensure smooth and timely implementation and execution of work.
31 Ibid 6
Page 32
97. The Project has had key inputs from the recent MME pre-feasibility assessment of CSP completed in July
201232. The activities of CSP TT NAM will be tailored to build the requisite national capacity for Namibia to
control its development of CSP projects, and to catalyse the financing, construction and installation of 50
MW of a CSP generation capacity by 2014. These activities are designed to minimize the expected energy
shortfalls of 2015. As such, GRN has been specific in terms of its need for assistance from this project that
includes:
• Strengthening linkages between local CSP stakeholders and foreign technology partners to the extent
that a local CSP technology industry is established;
• Developing a market policy framework that enables GRN to effectively promote CSP technology;
• Preparation of bankable feasibility studies and EIA reports for two promising CSP sites in Namibia;
• Setup of appropriate business models for implementing the initial CSP plants in Namibia.
The outcomes of these actions will be increased capacity of local stakeholders to become involved with the
CSP value chain, increased investor confidence through a developed regulatory framework for CSP plant
development, and the increased likelihood of raising funds for the design and construction of a CSP plant
in 2014.
98. The proposed CSP project will build on various project interventions supported by Namibia’s development
partners, notably DANIDA, GTZ and GEF, particularly from the TNA undertaken under the SNC as well as
various report under the NAMREP projects. In 2007, Namibia under the leadership of MET successfully
enacted the Environmental Management Act which provides for compulsory Environmental Impact
Assessment (EIA) and Strategic Environmental Assessment (SEA), including the establishment of a
conducive and enabling environment for appropriate technologies. Water availability will be a significant
factor in siting the first CSP plants since the use of dry cooling technology lowers plant efficiency by an
estimated 20%, and is costlier adversely affecting the rate of return.
99. UNDP’s previous experience shows that RE programmes are most effective when the process involves all
stakeholders from the onset and when all analyses, interactions and decisions are open to full scrutiny by
all parties. The CSP TT NAM Project will catalyse development of Namibia’s first Concentrated Solar
Power Plant. The GEF’s experience on CSP projects in North Africa points to the lesson that “risks should
be shared among all program participants.” The development and implementation of this project will be as
transparent as possible, with the active involvement and joint risk-sharing of the government, industry
(including equipment manufacturers), Non-Governmental Organizations (NGO), utilities, and technical and
professional bodies.
Project Objective
100. The key objective of the proposed project is to increase the share of renewable energy resources in the
Namibian energy mix by developing the necessary technological framework and conditions for the
successful transfer and deployment of CSP technology for on-grid power generation, thereby reducing
greenhouse gas emissions. This would be achieved through:
• Firstly, the establishment of CSP technology partnership agreements between foreign providers and
Namibian stakeholders in the private sector, government and academia. In turn, this would contribute to
enhanced knowledge of applicable CSP applications in Namibia, and the eventual outcome of local
entrepreneurs being engaged in the supply chain for CSP projects being constructed in Namibia;
32
Ibid 6
Page 33
• Secondly, the development of market policy framework for CSP technology that would lead to the
approval of policies supportive of its application and the eventual outcome of increased investments in
CSP technology applications in Namibia; and
• Thirdly, the provision of INV and TA for the development of feasibility-level engineering designs, EIAs,
business plans and financing agreements for the approved construction and commissioning of a 50MW
CSP project. This would lead to the design, engineering, construction and operation of the plant which
is expected to result in an increased installed capacity of CSP plants in Namibia via replication projects.
This outcome will improve the confidence of the government and citizenry on the techno-economic
viability of CSP with the completed CSP project and financing arrangements serving as a possible
template for subsequent CSP projects in the country. The financing arrangement for the CSP plant built
under this project would be mainstreamed into and help inform the standardization of procurement
mechanisms for large scale (>5 MW) renewable energy plants under the REPM.
Overall, these outcomes are expected to be realized considering the current rise in electricity
consumption and prices in Namibia and the power deficit in South Africa, the country’s main electricity
supplier. The subsequent threat to the country’s economic growth, and the vulnerability to developments
in South Africa, contrasts with Namibia’s sufficient solar resources and a demonstrated need for
additional generating capacity.
101. The project will consist of three components, each of which has expected outputs and a number of
specific activities planned to achieve them.
102. Component 1: CSP Investment Partnerships in Namibia. CSP technology is still confined to a few
players in the world in Germany, Israel, Italy, Spain, United States of America and other developed
countries with active applied research. To bring some of these players into the Namibian CSP market, a
recent scoping and due diligence analysis of global players had been done using some of the networks
created through the CSP Pre-feasibility Study33 and TREE project CSP Seminars. However, to realize
growth in the number of CSP players in the Namibian market in concert with the GRN’s power generation
expansion plans to 2015, concerted efforts are required to accelerate local CSP investment through
focused knowledge transfers and increased number of meetings between foreign and local players. This
growth of interest in CSP needs to be facilitated in a systematic manner, covering local businesses that are
equipment suppliers to installers, project management and engineering service providers to financers.
Once this interest has been established through capacity building workshops and conferences to catalyse
business links between local and foreign firms, a number of CSP partnerships can be finalized through
memoranda of understanding that would facilitate TT. These efforts can be accelerated associations such
as Namibia Manufacturers Association and the Namibia Institute of Architects. The expected outcome
from the deliverables under this component is local entrepreneurs engaged in the manufacturing, supply
and installation of CSP systems:
• Output 1.1: Finalized technology partnership agreements. Activities leading to the delivery of this output
includes:
o Scoping and due diligence analysis of global CSP players using some of the networks created
through the CSP Pre-feasibility Study and TREE project CSP Seminar;
o Formulation and establishment of partnership MOU agreements with at least two partners: South-
South and North-South to facilitate technology transfer;
o Establishment and operationalization of a National Technology Transfer Coordinating Body
(NTTCB).
GEF support is required to augment the current scoping and due diligence analysis of global CSP
players through the network of UNDP and international project personnel; formalizing the due diligence
33
MME, July 2012. ‘‘CSP Pre-Feasibility Study, Capacity Building Roadmap and Technology Transfer
Program’’
Page 34
process for global CSP players; facilitating linkages between foreign CSP players and local businesses
through expositions and workshops; facilitate MOU agreements between foreign and local partners;
and setting up an operational NTTCB in collaboration with MME and other relevant government
agencies.
• Output 1.2: Enhanced knowledge of applicable CSP applications in Namibia. To support nascent and
ongoing CSP knowledge transfers within PoN and REEEI, a focused capacity building programmes will
be required that targets policymakers, engineering consultants, equipment suppliers and
manufacturers, construction contractors, and financing institutions. This will develop a broad base of
participation of local players, and provide to them the necessary knowledge to justify further
investments that will enable them to be a participant in the local CSP supply chain. Topics to be
covered within the capacity building programmes will include energy policy and planning; CSP project
design, development and operation; resource assessment and analysis; technical and manufacturing
requirements of related CSP industries; and financial and economic evaluation of CSP projects.
103. Component 2: Policy Frameworks for CSP Initiatives in Namibia. While Namibia currently does not
have any supportive policy framework to encourage CSP investments, it recognizes that such a framework
is required to avert predicted shortfalls in its future generation capacity. Direct policy instruments are
required to support CSP market development in Namibia that includes both financial and non-financial
measures. The financial measures would provide financial incentives to market parties to facilitate CSP
investments. Non-financial measures would raise the interest of potential investors into the CSP market
through increased levels of understanding of the available solar resources, facilitating business
relationships between potential CSP suppliers, service providers and financers. From the expected
outputs under this project component, the expected outcome is increased investments in CSP technology
applications in Namibia:
• Output 2.1: Investment grade solar resource data: Currently, MME has satellite information on solar
irradiation, and no operating ground level solar radiation metering stations. Ground level solar
irradiation information is required to measure the actual solar irradiation levels at potential CSP project
sites; this is important considering the sensitivity of irradiation to aerosols at different locations due to
topography, variable cloud cover and unique weather patterns. Moreover, with the projected high
capital investment of the proposed CSP projects, potential CSP sites do require solar resource data to
be “investment grade” through this thorough analysis as this will provide more confidence on the project
rates of return. The July 2012 Pre-feasibility Study for the Establishment of a Pre-Commercial CSP
Plant34 in Namibia provided its top 5 CSP sites for further development that includes the collection of
investment grade solar resource data. To date, these sites only have satellite solar data that need
correlation with ground solar measurements. Assistance is required to analyze the combination of
accurate ground measurements and long-term satellite data including site-specific correlations of at
least one year that is recommended for sites where there is no available high quality long-term
irradiation data. GEF support is required to:
34 Ibid 5
Page 35
o Select suitable ground measurement spots that are less than 3 km from the 5 top CSP sites in
Namibia as determined by the July 2012 pre-feasibility report funded by MME ;
o Finalize the site to be selected for initial CSP development through consultation with all
stakeholders. At this time, the Ausnek, Kokerboom or Gerus sites appear to be the most promising
50 MW CSP sites;
o Prepare plans for the continuance of ground solar measurements at other promising CSP sites; and
o Carry out ground measurements for the 5 top CSP sites in Namibia over one year. Ground
measurements will augment the available and less accurate satellite data.
• Output 2.2: CSP planning and implementation mechanisms established within MME. This output
essentially provides further support for planning activities recommended by the July 2012 pre-feasibility
study funded by MME on the suitability of CSP technology throughout Namibia. As noted, the study
ranked almost 40 CSP sites (of which 5 are to be selected for ground measurements in Output 2.1) in
terms of their direct normal radiation (DNI), temperature, access and slope as well as access to the
electricity grid and water availability. The output will also support MME in its efforts to promote CSP
technology, including its application with existing fossil-fuel and renewable electricity generation plants.
This output will be delivered by two main activities: (i) preparation of detailed information (to a
reconnaissance level) of the most promising CSP sites (including hybridization options with natural gas
and biomass ); and (ii) conducting a policy dialogue with national stakeholders according to a working
agenda agreed upon with partner organizations.
As regards the facilitation of planning for the first CSP plant to be supported under Component #3, the
generation profile and likely technology specifications for the top five sites selected for highest
prioritization in the near term by the pre-feasibility study (most likely scenario to be built) are presented
below in the tables below. The top three sites are expected to be CSP with storage (no hybridization).
Estimated Generation Profile/Technical Specifications of Top 5 CSP sites for Build Prioritization in
Near Term35
35
Ministry of Mines and Energy, ‘‘Pre-feasibility Study for the Establishment of a Pre-Commercial
Concentrated Solar Power Plant in Namibia’’, July 2012.
Page 36
GEF support is required for the preparation of reconnaissance level reports for the 40 most promising
CSP sites (with sufficient information to interest potential investors), and workshops and conferences to
facilitate policy dialogue on accelerated development of CSP projects in Namibia based on the
reconnaissance level reports.
• Output 2.3: Approved and enforced regulations for promoting development and operation of CSP plants
in Namibia: These regulations will essentially provide confidence to potential public and private
investors of the soft costs required to develop CSP projects in collaboration and under the auspices of
the GRN. Delivery of this output will require: (i) ranking of the best CSP technologies and their
reference costs based on the July 2012 MME Pre-Feasibility Study; (ii) identification of financial
incentives and options for local financing institutions with regards to risk mitigation for CSP
investments36; (iii) defining the legal status of a private CSP operator in the modality of an IPP; (iv) a
resolution regarding land tenure and water use rights for CSP projects; (v) regulation concerning
environmental constraints and management of CSP areas; (vi) creating streamlined procedures for
permits and concessions for CSP electricity generation and distribution37; and (vii) guidelines for the
financing and development CSP projects and requirements for monitoring of these projects that would
include close involvement of DBN and other local financial institutions.
GEF support is required for technical assistance in the ranking of the best CSP technologies and their
reference costs, drafting of the aforementioned technical regulations to the extent that they are
accepted, approved and used for promoting development of CSP plants in Namibia.
• Output 2.4: “High precision" stations or RSI (Rotating Shadowband Irradiometer) stations in place for
remote sites to obtain investment grade solar resource
To facilitate CSP investments within the GRN’s 2015 timeframe for the expansion of power generation
sources, GEF resources assistance will be required to purchase appropriate instruments that will
provide the required on-site ground measurements using appropriate measurement systems that would
include either “thermopiles” or “rotating shadowband irradiometers (RSI) stations” as well as long term
satellite solar irradiation data.
36
This will involve the assessment, design and implementation of measures intended to reduce the perceived risks for private and public investors in
CSP projects. This may include sovereign guarantees, defining clear liability responsibilities in case of default, and security of property rights and
concessions, amongst other potential measures.
37
These streamlined procedures would include calls for tender (with standardized documentation for tender documents, CSP contracting, standardized
PPP agreements and IPP contracts) and a comprehensive outreach campaign that targets potential developers, investors, suppliers and local
stakeholders.
Page 37
104. Component 3: Facilitation of the first CSP plant in Namibia. This component will support activities
that will facilitate the securing of project finance and the construction and implementation of a 50 MW
CSP plant. Expected outputs towards this outcome are the bankable feasibility study and the
environmental impact assessment, both crucial documents that will increase lender confidence on the
planned CSP projects, their costs, rates of return and the environmental impacts. With the construction
of the first CSP plant, expected outcome from this project component is the increased installed capacity
of CSP plants in the country:
• Output 3.1: Completed feasibility study of selected CSP site: This output will support the
preparation of a bankable feasibility study and financial model that will provide sufficient CSP
project details of the Ausnek, Kokerboom or Gerus sites for the approval of financing of these
projects. MME will coordinate activities to deliver this output including:
GEF support is required to prepare the terms of reference for selection of a qualified engineering
team, setting up the thermodynamic model, finalization of the plant configuration, CSP plant
economic and financial analysis and completion of the full feasibility study and implementation plan
that will comply with international standards for such studies. It should be noted that as part of the
pre/feasibility study an economic analysis was conducted of all the sites surveyed taking into
consideration the following factors: 1) DNI averaged over the considered project area; 2) An
estimate of temperature losses; 3) Estimated cost of grid connection, as % of total investment for 50
MW; 4) Estimated cost of access construction, as a % of total investment for 50 MW; and 5) Slope.
The estimate of temperature losses was carried through the calculation of lost yield, due to
temperature changes. This assumes a simple linear relation between production and DNI. Note
that, this simplification is not totally accurate as there are differences in the annual energy
productions for projects with similar yearly DNI, but it is considered to be enough for a first
screening. In addition, for the grid connection evaluation, the linear distance to the nearest
substation was calculated and all grid connection and adsorption issues were factored into both the
technical specifications and cost estimates of the sites. The full feasibility study will build on the
results from the pre-feasibility study.
• Output 3.2: Completed environmental impact assessment: Completion of an EIA report will be a
condition to obtain the necessary environmental permits and concessional financing from donors
and government development banks. As such, the report will need to comply with EIA standards of
Page 38
various IFIs such as the World Bank as well as the Namibian environmental regulations. MME will
coordinate activities towards the realization of this output that will include:
GEF support is required to prepare the terms of reference for selection of a qualified environmental
team to complete the EIA study in parallel with the bankable feasibility study that will comply with
IFC or World Bank standards for such studies.
• Output 3.3: Approved institutional, financial and business arrangements for initial CSP plant
development: To facilitate the financing and implementation of a CSP plant, business arrangements
need to be completed and approved between the GRN, NamPower (the proposed implementing
agency) and external financiers such as DBSA. Based on estimates from the pre-feasibility study
the estimated capital costs of a 50 MW CSP plant for the 5 sites ranges from USD 200-300 million.
The government has already fully confirmed its commitment to secure the appropriate funding
(through a combination of equity and debt) for the construction and commissioning of a CSP plant
by 2015. The July 2012 pre-feasibility study recommends that MME should undertake preliminary
conversations with the Ministry of Finance and other state agencies to understand the risks
resulting from a sovereign guarantee for this CSP project. Furthermore, the study recommends that
NamPower and the Development Bank of Namibia (DBN) take an equity stake in the project with
the debt portion being arranged with a concessionary lender backed by a sovereign guarantee.
Having a GRN entity as the majority owner would facilitate access to concessionary debt from
development institutions such as DBSA, who have already confirmed their intention to provide debt
financing for the plant as well as pre-investment advisory assistance. Debt incentives and tax
exemptions would also likely feature as part of the financing package. GRN may also encourage
offers from the private sector for equity positions of the first CSP plant. The Clinton Climate Initiative
will be providing due diligence, modelling and investment advisory assistance. The final financial
model and capital structure will be decided after the full feasibility study.
MME will coordinate the following activities required to deliver this output including:
o Setup a special purpose entity (SPE) dedicated towards engineering, constructing and
operating the initial 50 MW CSP plant that will offset risks to NamPower and provide a platform
for private equity of the CSP plant. The SPE will setup REEEI as the Project Management Unit
(PMU) that will provide overall project management and monitoring according to GRD and IFI
rules and regulations;
o Design specific financial mechanisms to finance the first CSP plant through the SPE with
concessional financing from development banks and private equity. The financial mechanism
will likely contain a negotiated fixed tariff, debt incentives and tax exemptions;
o Development of specific plans for improving MRV capacity within the SPE and the feasibility of
accessing specific carbon funds (building onto Output 2.4). Existing or planned technical
assistance and carbon funds that may be available to the CSP developments will be explored
pending the ability of the CSP project development group to monitor, report, and verify their
GHG emissions to an international standard.
o Where possible, mainstreaming of the outputs and financial arrangements mentioned above
into NERF regulations and REPM outcomes for future procurement of large-scale RE plants
Page 39
GEF support is required to assist MME to facilitate support from NamPower and ECB for their
involvement in the 50 MW CSP project; facilitate discussions and investment with MoF, DBN and
IFIs on sovereign guarantees and equity stakes on the CSP project, as well as pre-investment
assistance; set up the SPE and financing arrangements for implementation of the CSP project; and
strengthen capacity of the SPE to monitor and report GHG emissions to an international standard.
It is important to note that given the urgency of moving forward with the financing and construction
of the 50 MW CSP plant as soon as possible the approved financial framework for the first CSP
Plant that emerges from activities under Output 3.3 will be prioritized based on the most rapid route
to deployment and cost considerations. Nonetheless it is fully expected that whatever specific
contractual arrangements and financing mechanisms used for this project will be mainstreamed into
the NERF and REPM efforts and that collaboration will be sought between activities under this
project and REPM so that broader financial barriers are removed for the long-term benefit of the RE
industry and sustainable future replication of CSP plants.
• Output 3.4: Signed EPC contract and commencement of CSP construction: With the securing of
financing of the initial CSP plant through the SPE, construction of the CSP plant will need to be
executed through an engineering-procure-construct (EPC) contracting arrangement. To secure the
services of the EPC contractor, detailed engineering drawings and a construction and
implementation plan need to be prepared for the EPC tender documents. Once the EPC contract is
signed, construction can commence for the initial CSP plant. Activities required to deliver this
include:
o Preparation of detailed engineering plans with sufficient detail for an EPC contractor to prepare
tendered bids for CSP plant construction38;
o Preparation of an EPC tender and contract that will foster participation of local companies in the
supply chain (i.e. supply of technology, engineering, financial, technical and managerial
services) for constructing the 50 MW CSP plant;
o Obtaining all legal permits39;
o Setup tendering process for the construction of the CSP;
o Opening of tenders, and negotiating and signing the EPC contract; and
o Preparing and managing implementation plans for constructing the CSP plant.
GEF support is required for senior oversight to the preparation of detailed engineering plans for the
EPC tender and contracting process; negotiating and signing of the EPC contract; preparation of
implementation plans; and senior oversight to the management of implementation.
• Output 3.5: Workshops to disseminate lessons learned in the development of the 50 MW CSP
plant. This will be done for the benefit of other private and public entities interested in financing and
developing other 50 MW CSP projects that replicate the first CSP investment.
GEF support is required for the arrangement of the workshops and the preparation and
dissemination of the workshop proceedings.
105. Figure 13 provides an illustration of the interrelationship between the various components of the CSP
TT NAM Project. The overall project outcome will be a scenario where financing for a 50 MW CSP can
be secured based on the completion of a thorough feasibility study of the CSP projects, the finalization
of a business and financial model on which to implement these CSP project, the emergence of a
38
These plans would include amongst other designs the routing of the site access road to the site; provision of appropriate foundation
designs of the various structures according to site geological conditions; review of the site design of against floods, wind storms and
seismic events; precise layout of the solar field; thermal storage system design; and detailed design of the balance of plant (i.e. power
plant, cooling system, substation).
39
This would include preparing applications for the environmental clearance of the project, and application for the license to construct
the CSP.
Page 40
market policy framework on which government can support its promotional efforts for CSP development
in Namibia, and the increased confidence of the private sector in Namibia to participate with foreign
technology leaders in CSP development in Namibia.
106. CSP TT NAM has been designed as a 3-year project to achieve the Government’s goal of increasing
the CSP installed capacity in Namibia prior to the end of 2015. As such, the aforementioned activities
have been designed to be supportive towards achievement of this goal. Critical path activities of CSP
TT NAM includes the generation of investment-grade solar data (Output 2.1), feasibility and EIA reports
(Outputs 3.1 and 3.2), senior oversight to detailed engineering for EPC tender drawings (Output 3.4),
and the tender process leading to a signed EPC contract (Output 3.5). Through the timely completion
of these activities, construction of the first CSP plant in Namibia would commence prior to the EOP or
the end of 2015. The sequencing of Project activities is illustrated in Figure 14.
Overall
Shortfall of outcome:
Rising Namibian Outcome 2: Increased Project
Reduced
global Objective:
electricity investments in CSP power
fossil fuel Increased
generation technology applications sector-
prices share of RE
capacity in Namibia related
in Namibia
by 2015 GHG
emissions
Technical assistance/
Awareness raising / training programs
Page 41
Figure 14: Project Schedule of Activities
Intense Activity
Intermittent Activity
INDICATORS
107. The most direct impact of the project as it relates to core GEF objectives is the reduction in CO2
emissions from the power sector in Namibia. Associated impacts such as (i) increased access to clean
energy in Namibia and, (ii) a transformed local market for CSP technologies and practices will
contribute to the overall sustainability of the project and are thus critical to the continued reduction in
nationwide CO2 emissions.
108. The following indicators are an estimate of the impact of the CSP TT NAM Project:
• Cumulative direct post-project CO2 emissions (assumes a 10-year influence period of GEF
interventions);
• % share of CSP in the power generation mix of Namibia;
• Number of government-endorsed CSP partnerships established;
• Number of local CSP engineering design firms with CSP design experience established and
operational;
• Number of local CSP-related manufacturing, supply and installation companies;
• Number of sites where investment grade solar resource data is available;
• Number of CSP investments facilitated by the CSP development guidelines;
• Number of planned and approved CSP technology application projects that are funded by local
financing institutions;
• Number of CSP investments supported by carbon finance;
• Number of planned, approved and financed CSP projects that replicate the first CSP investment;
and
• Cumulative installed power generation capacity from replicated CSP plants.
Page 42
109. The overall project risk is moderate. While all possible efforts have been made in the design of CSP TT
NAM to mitigate perceived project risks, there are inevitably some unavoidable residual risks that will
have to be carefully monitored and managed to ensure project success. Recommended mitigation
measures are provided in detail in the “Offline Risk Log” in Annex 1.
Financial Modality
110. GEF resources will be used as technical assistance to remove barriers and catalyze financing of CSP
projects, and to support activities that will sustain the development of CSP. As such, GEF resources will
be used to:
• Strengthen relationships between international CSP technical experts and suppliers and Namibian
CSP practitioners and service providers;
• Assist government policies towards the promotion and development of CSP projects in Namibia;
• Prepare the necessary documentation of CSP projects that will increase confidence of financial and
lending institutions towards the first CSP projects; and
• Assist project stakeholders to determine the optimal business arrangements and financial
frameworks for implementing the first CSP projects in Namibia.
111. As the Project will be a NIM implemented project, financial modality will be in accordance with direct
payments and or quarterly advance payment requests (according to HACT is direct cash transfer) using
the FACE form (i.e. cash not being transferred or cash being advanced to the implementing agency
through NEX/NIM Advances). Under this modality, the MME will still maintain full programmatic and
accountability control of the Project. If advances will be required, MME will request the Namibia Ministry
of Finance to endorse and authorize MME to open a project account where funds will be advanced. In
line with the UNDP supported projects, this project will be VAT exempted as per SBAA agreement. See
annex of a FACE form to be used.
Cost Effectiveness
112. The GEF Alternative Scenario would result in a rapid increase in renewable electricity generation,
especially from CSP technologies as developed by qualified Namibian professionals with financial
support from local institutions. The learning-by-doing approach to be adopted by this project will create
confidence amongst the local players so that future CSP technology deployment will have a larger local
component, thus increasing the cost effectiveness of the technology. CSP is of particular interest to
utilities because it is lower cost and more scalable than, for instance, photovoltaic technologies. Thus,
the critical involvement of NamPower reduces the uncertainties over power purchase agreement
policies and the adequacy of transmission infrastructure; this will subsequently reduce the cost of
capital on an investment where the IRR is low. Specifically, plant costs will be significantly reduced at a
proposed plant location, where a turbine generator with a capacity of approximately 24 MVA will be
connected to an existing substation with the same adequate voltage level close to the solar plant site.
Meanwhile, the comparatively reduced terrestrial footprint of the parabolic trough (land required by CSP
plants per MW of installed capacity) and the tower technology versus other CSP technologies (e.g.
dish-engine), as well as the shorter lead time of implementation, will translate into significant cost
reductions (levelized cost of energy).
• Under a base case scenario (with storage) direct post-project emission reductions of 177,583 CO2
per year, resulting from the investment in one 50 MW CSP commercial plant leading to substitution
of an estimated 175 GWh per year of fossil fuel based electricity (depending on load factor and
storage capacity). The estimated unit abatement cost (base case) considering the US$ 1.7 million
GEF contribution to this project is about USD 0.36/tonne CO2eq based on a 10-year cumulative
Page 43
GHG emission reductions of 4.79 million tonnes CO2eq from three CSP projects implemented over
the next 3 years after the end of the Project40;
• Under a low end case scenario (without storage) direct post-project emission reductions of 88,791
tCO2 per year, resulting from the investment in one 50 MW CSP commercial plant. The 10-year
cumulative GHG emission reductions from three CSP projects implemented over the next 3 years
after the end of the Project would be 2.40 million tons CO2eq (without storage). See Annex E for
more information on the two scenarios.
• The possible CO2 emission reductions from the Gerus scenario (hybridization with biomass) were
not addressed in the pre-feasibility study but will be analyzed as part of the project under
Component #3.
• CSP is a technology that can be deployed as a decentralized power source at several locations in
Namibia. Namibia being a vast and sparsely populated country providing power for development in
remotely located areas of the country. This in itself will contribute to attainment of various MDGs
targets, including ensuring environmental sustainability, reducing poverty and promoting education
for all;
• International partnerships in a CSP gplant will allow the nascent Namibian CSP industry to become
familiar with the technology and local capacity will be built paving the way for a future competitive
CSP market. This will result from the training workshops and symposiums on CSP technology held
by REEEI and its partners such as Fraunhofer ISE and Lahmeyer International;
• CSP technology is modular and its components can largely be manufactured from conventional
materials using well-known and proven technologies. This presents the potential for the technology
to be absorbed and adapted by local industry leading to more effective technology transfer
practices. Taking a two-step process whereby the initial project implementation phase will focus on
setting and codifying the appropriate market, regulatory and set-up environment, will ensure that the
technology to be transferred will be sustainable in the long-term, and not only end as a
demonstration project. Despite past global experience, a significant take-off of this market is
expected nationally and regionally, with the consequent reduction in GHG emissions. The proposed
50 MW CSP project will have a far-reaching impact;
• Namibia’s potential for greater manufacturing and innovation will be developed into a vibrant and
dynamic renewable energy private sector industry. The Renewable Energy and Energy Efficiency
Capacity Building (REEECAP) study funded by DANIDA on the Electricity Supply and Demand
Management Options for Namibia identified that a mix of electricity generation options including
CSP would be the best strategy to avert the imminent power shortage and increase energy security
in the country. This study, together with other REEECAP studies, also identified solar, biomass and
wind energy development as the best low carbon energy options for Namibia.
Sustainability
114. From a technical point of view, the viability of grid-connected CSP electricity generation has been
proven in the international market, both in the context of developed and developing countries. By
addressing the non-technical barriers that impede the development of CSP on-grid electricity
generation in Namibia, the project will assist in creating a sustainable niche through strengthening the
policy, institutional, legal, regulatory and operational capabilities of the key national institutions,
supporting the development of on-grid and off-grid CSP through a market-driven approach, developing
national capabilities and disseminating information. These efforts should ensure the long-term
sustainability of CSP on-grid and off-grid electricity generation in the country.
115. Since the proposed GEF project comprises a strong capacity building element, the main outputs of this
project will not only be new CSP partnerships, but also enhanced institutional capacity to effectively
40 This assumes a Namibian grid emissions factor of 1.0136 tonnes CO2eq/MWh from a UNEP Riso Center Study on “Analysis of the Grid Emissions
Factor for the Electricity Sector, the Case of the Southern Africa Power Pool”.
Page 44
maintain energy saving services and revise the regulatory and policy framework over time. The project
will specifically focus on addressing issues related to awareness barriers by increasing institutional
capacity and awareness as well as providing information on CSP technologies to improve the
knowledge of the existing opportunities for thermal power generation technologies and practices, for the
private sector (e.g. contractors, equipment manufacturers, service providers) and relevant government
agencies. The project will also promote sustainability by training Namibian professionals on CSP
technologies and catalyzing a new market in which they will be able to use their acquired knowledge.
Similarly, raising awareness on CSP products and projects in the financial sector will enable financial
institutions to become more familiar with the intricacies of CSP financing and develop appropriate
financial tools for the industry.
116. From the financial perspective, the project will first assist in the development of an appropriate
procurement policy structure for installed capacities above 50 MW. This will introduce more
transparency by developing a competitive institutional model for the award of CSP projects.
Furthermore, the project will support the integration of local industries into the CSP sector. This will be
achieved through the provision of focused support to local engineering firms and specialised
engineering workshops for the installation, operation, maintenance and repair of PV equipment. With
the increase in on-grid CSP installations, it is envisaged that such efforts will intensify with opportunities
being created for additional players to provide such services.
117. GEF resources will result in the leveraging of financial and human resources from government, private
sector and financial institutions, by supporting on a catalytic basis the removal of technical, financial
and institutional-policy barriers and will help not only the deployment of CSP in Namibia, but also
broader efforts aimed at large-scale RE deployment under REPM and NERF efforts. It can be assumed
that without GEF support most if not all of the proposed activities would not happen and the plant would
not be built; in fact the promise of GEF support and continual support of UNDP over the last two years
was a critical factor in the GRN deciding to co-fund the pre-feasibility study and commit to investing in
the CSP plant and other related activities.
Replicability
118. The project strategy is to catalyse construction of a CSP plant and to provide conditions that will result
in the replication of CSP investments in Namibia. To maximize replication potential for CSP
investments in Namibia, CSP TT NAM will facilitate the creation of the basic enabling conditions
necessary to catalyze private sector participation in the program and to maximize their involvement of
local entrepreneurs in the CSP supply chain of these projects. With these built capacities and a
suitable regulatory framework in place, there will be a higher likelihood of replication and successful
implementation of the future CSP projects. More specifically, the following scenarios will be realized by
the end of the project:
• A fiscal and regulatory framework will be in place with (i) national targets for CSP deployment; (ii)
concessionary financing arrangements; (iii) investor incentives for CSP; (iv) standardized PPAs for
CSP; (v) IPPs championing CSP development that will attract more players and investors to CSP
development in Namibia;
• A national solar resource assessment and CSP site identification programme will be in place. This
will include programmes for improved solar resource data acquisition and reconnaissance-level
CSP site assessments that will be accessible to potential investors and project promoters
maintained by REEEI and MME;
• Appropriate business models for CSP projects will have been setup within the framework of new
CSP fiscal and regulatory mechanisms. These mechanisms will include market-based financing
instruments that will address the high up-front costs of CSP investments;
Page 45
• Awareness of policymakers and the private sector will have been raised on CSP investment
opportunities as a result of training on CSP technical issues, CSP project management and
financing aspects;
• One CSP project will have been designed and be under development. This initial CSP investment
with key technology partners and local industry participants will demonstrate the potential of market-
based financing instruments and regulatory and investment framework for promotion of CSP
projects. Linkages will be established between this initial CSP investment and national level
agencies to maximize the guidance benefits of this project. Linkages with national level
policymakers will also be established to ensure lessons learnt during the implementation of the
project will inform the policy review process.
119. A SWOT analysis is provided on Table 5 as a guide to building the capacity of Namibia industrial
players to take on CSP technological challenges.
Page 46
PROJECT RESULTS FRAMEWORK
This project will contribute to achieving the following Country Programme Outcome as defined in CPAP or CPD:
CPD 2006-2010: By 2010 improved environmental living conditions and sustainable use of energy in Namibia, and establishment of sustainable living conditions in the
poorest provinces.
Country Programme Outcome Indicators: % of renewable energy used in Namibia
Primary applicable Key Environment and Sustainable Development Key Result Area (same as that on the cover page, circle one): 1. Mainstreaming
environment and energy OR
2. Catalyzing environmental finance OR 3. Promote climate change adaptation OR 4. Expanding access to environmental and energy services for the poor.
Applicable GEF Strategic Objective and Program: GEF-4 CC4 Strategic Program SP3: Increased production of renewable energy in electricity grids
Applicable GEF Expected Outcomes: Total avoided GHG emissions from on-grid RE electricity generation
Applicable GEF Outcome Indicators: Market penetration of on-grid renewable energy (% from renewables); GHG emissions from electricity generation (tons CO2eq/
kWh); and $/ tons CO2eq
Outcomes Objectively Verifiable Indicator Baseline Targets Source of Verification Critical Assumptions
Project Objective41 Cumulative direct post-project CO2 0 5.83 42 Project final report as well as annual Economic growth in the country
To increase the emission reduction resulting from surveys of energy consumption & will continue
share of renewable the investment in CSP by end-of- reductions for each CSP pilot project.
energies in the project (EOP), Mtons CO2. Government support for RE
Namibian energy development and utilization will
mix by developing % share of CSP in the power 0 10 not change
the necessary generation mix of Namibia by EOP
technological
framework and
conditions for the
successful transfer
and deployment of
CSP technology for
on-grid power
generation
Outcome 1: 43 Number of government-endorsed 0 544 Approved partnership agreements Technical resources are
Local CSP partnerships established by between local companies and foreign available in MME and REEEI to
entrepreneurs are Year 3 CSP companies guide establishment of a
engaged in the coordination body and
manufacturing, Number of local CSP engineering 0 7 National TT Coordination Organization development of reports
41
Objective (Atlas output) monitored quarterly ERBM and annually in APR/PIR
42
Over a period of 10 years from 3 CSPs constructed during the 10-year period after the EOP, and with an assumed grid emissions factor of 1.0136 tonnes
CO2eq/MWh.
43
All outcomes monitored annually in the APR/PIR.
44 Three North-South and two South-South
Page 47
Outcomes Objectively Verifiable Indicator Baseline Targets Source of Verification Critical Assumptions
supply and design firms with CSP design approved and in place
installation of CSP experience established and MME and REEEI staff are
systems operational by Year 3 Knowledge products including: willing to commit sufficient time
⇒ Report on potential CSP for meeting and developing
Number of local CSP-related 0 1045 technologies and socio-economic CSP agreements
manufacturing, supply and impact monitoring
installation companies by Year 3 ⇒ Study of technical and Government staff is willing to
manufacturing requirements of commit sufficient time for
related CSP industries identifying the needs of
⇒ Report on policy instruments, different stakeholders to
standards, financial incentives, and develop different policy
financial and economic evaluation instruments, standards, and
of CSP financial incentives to
⇒ Proceedings from the capacity encourage CSP.
building workshops
Government staff is willing to
commit sufficient time for
participating in training activities
and deepen their knowledge on
CSP.
Outcome 2: • Number of sites where investment • 047 • 548 Report on solar resource assessment Investment grade solar
Increased grade solar resource data is correlated with ground measurements resource data is made available
investments in available46 by Year 2 and a determination of the best CSP to potential CSP investors
CSP technology site that will developed as the first CSP
applications in • No. of CSP investments facilitated • 0 • 1 investment project in Namibia All stakeholders needed for
Namibia by the CSP development technical or financial resources
guidelines by Year 3 that are Drafted guidelines for CSP are available to enable the
streamlined with REPM outcomes development for potential investors achievement of the project
• 0 • 2 complete with reconnaissance-level objective
CSP sites and strategic actions and
• Number of planned and approved
policies on CSP resource development, Government staff is willing to
CSP technology application
ranking of CSP technologies, financial commit sufficient time for
projects that are funded by local
incentives, legal status of an IPP, identifying the needs of
financing institutions by EOP and in
environmental and management of CSP different stakeholders to
line with REPM outcomes
areas, and streamlined procedures for develop different policy
45 Local firms could be involved with assembly and installation of solar fields, storage facilities, heat transfer equipment, boilers, steam turbines and condensers.
46Investment grade solar resource data is solar satellite data correlated with ground measurements for a period of one
year
47
Satellite irradiation data only available
48
These data are at priority sites for CSP development in Namibia as defined in the July 2012 Pre-Feasibility Study of CSP as funded by MME
Page 48
Outcomes Objectively Verifiable Indicator Baseline Targets Source of Verification Critical Assumptions
Outcome 3: • Number of planned, approved and • 0 • 2 Bankable feasibility-level of first CSP The Namibian REEEI is willing
Increased installed financed CSP projects that project investment in Namibia to invest sufficient time in
capacity of CSP replicate the first CSP investment creating resourceful information
plants in Namibia by EOP EIA report of the first CSP project site on CSP and supporting MME
that complies with international and ECB.
• Cumulative installed power • 0 • 50 standards for EIA studies
generation capacity from CSP MME and REEEI staff have
plants by EOP, MW dedicated staff for government
Business plan for the first CSP plant oversight of CSP development
with institutional, financing and business
• Set of specific regulations arrangements; initial CSP plant Global capital markets have
• 0 • 1 development that includes formation of
promoting the development and sufficient capital funds for CSP
operation of CSP plants that are in a SPE and concessional finance with plants
turn mainstreamed into the NERL fixed tariffs and tax incentives; evidence
and REPM guidelines that ownership structures and financial
incentives have been streamlined into EIAs for the planned sites are
NERF and officially approved REPM approved
procurement guidelines
MME and stakeholders can
EPC tender documents for CSP plant agree on a mutually beneficial
complete with thermo-dynamic ownership structure for the
modeling, detailed engineering plant
drawings and report
The Ministry of Finance
Signed EPC contract complete with all provides the requisite sovereign
legal permits and implementation plans guarantees for facilitate
for construction of the CSP plant concessional debt lending
Page 49
Outcomes Objectively Verifiable Indicator Baseline Targets Source of Verification Critical Assumptions
Page 50
Total Budget and Work Plan
Responsible Atlas
GEF Donor Budgetar Amount Amount Amount
Party/ ATLAS Budget Total
Outcome/Atlas Fund ID Name y Year 1 Year 2 Year 3 Notes
Implementing Description (USD)
Activity Account (USD) (USD) (USD)
Agent Code
International
71200 1
Consultants 6,000 6,000 6,000 18,000
Page 51
Total GEF Outcome 3 383,445 274,545 252,745 910,735
Total Outcome 3 383,445 274,545 252,745 910,735
International
71200 11
Consultants 0 12,000 15,000 27,000
71300 Local Consultants 33,696 33,696 33,696 101,088
72200 Equipment 0
72400 Communications 2,500 3,000 3,000 8,500
PROJECT Materials and
MME/REEEI 62000 GEF 72300
MANAGEMENT Goods 2,000 2,000 2,000 6,000
+ M&E COSTS 72500 Office Supplies 0
71600 Travel 4,000 5,000 5,000 14,000 12
Professional
74100
Services 5,500 5,000 4,500 15,000
72500 Office Supplies 0
Total GEF Project Management 47,696 60,696 63,196 171,588
Total Project Management 47,696 60,696 63,196 171,588
GEF Total 741,300 548,000 428,700 1,718,000
UNDP Total
Grand Total 741,300 548,000 428,700 1,718,000
Summary of Funds:
Page 52
Notes:
1. An average of 4 weeks per year for the Chief Technical Advisor (CTA) to assess capacity building requirements of local entrepreneurs and to guide the
delivery of capacity building activities for the private sector and academia.
2. Local consultants will consist of the National Project Manager (NPM) for an average of 10 weeks/yr, and a Capacity Building Advisor (CBA) (average of 26
weeks/yr to assist in networking local entrepreneurs, doing needs assessments, designing and delivering workshops and on-the-job training sessions.
3. Travel costs related to per diems and airfares for international staff.
4. The CTA will bring international practices to developing the regulatory regime for CSP including all activities in Outcome 2. His/her time requirement for
Outcome 2 will be 6 weeks per year.
5. Around 50% (or 25 weeks per year) of the NPM’s time will be expended in working with MME to improve the CSP site inventories, solar irradiation databases,
regulatory regime and developing carbon finance linkages.
6. Outsourcing of Solar data collection programme for USD 100,000 (Output 2.1 during yrs 1 and 2)
7. USD 165,000 for 2 "high precision" stations and/or 3 RSI (Rotating Shadow Band Irradiometers) stations for remote sites.
8. The CTA will provide oversight to the recruitment of appropriate engineering firms and contractors who can provide services for all outputs from Outcome 3.
9. Local consultants on Outcome 3 will consist of the NPM (4 weeks/year) to will assist in the recruitment of engineering firms and contractors; a civil engineer
(Yr. 1 - 20 wks, Yr.2 – 26 wks, Yr.3 – 52 wks) to oversee the feasibility and EIA studies in Yrs 1 and 2 and engineering drawing preparations for tendering;
and a legal contracts advisor (Yr.2 – 20 wks, Yr.3 – 10 wks) to provide guidance to the development of the CSP EPC contract as well as other contractual
issues.
10. $350,000 for feasibility study (yrs. 1 and 2), $150,000 for EIA (yrs 1 and 2), $175,000 outsourced assistance to prepare and manage tendering process (Yrs 2
and 3)
11. These are M&E costs for the mid-term and terminal evaluations.
12. USD 3,000 in both Yrs 2 and 3 are towards M&E travel costs for mid-term and terminal evaluators
Page 53
MANAGEMENT ARRANGEMENTS
120. CSP TT NAM will be managed according to the National Implementation Modality (NIM)
of the UNDP and will follow the reporting requirements agreed upon by the UN System
in line with harmonised reporting requirements as part of the UNPAF. MME is proposed
as the Implementing Partner and will be accountable to the GRN, UNDP and the GEF
for ensuring: (i) the substantive quality of the project, (ii) the effective use of both
international and national resources allocated to it, (iii) the availability of time for national
contributions to support project implementation, and (iv) the proper coordination among
all project stakeholders, in particular national parties. MME will be responsible to UNDP
for the achievement of the project objectives and for all reporting, including the
submission of work plans and financial reports. As national implementing partner (NIP),
MME will ensure the delivery of all the project outputs and the judicious use of the
project resources. MME may hire or sub-contract other appropriate entities to deliver the
project outputs, if deemed appropriate and feasible.
121. The project will establish a Project Steering Committee (PSC) and a Project
Management Unit (PMU) during the inception phase of the project. The PSC will meet
at least every six months and will be convened and supported logistically by the PMU.
The PSC is responsible for making management decisions for a project in particular
when guidance is required by the Project Manager. The Steering Committee plays a
critical role in project monitoring and evaluations by quality assuring these processes
and products, and using evaluations for performance improvement, accountability and
learning. It ensures that required resources are committed and arbitrates on any
conflicts within the project or negotiates a solution to any problems with external bodies.
If deemed appropriate, the role of project assurance can be played by an independent
official recruited by UNDP and MME jointly to be dedicated to the project. In addition,
PSC approves the appointment and responsibilities of the Project Manager and any
delegation of its Project Assurance responsibilities. Based on the approved Annual
Work Plan, the Steering Committee can also consider and approve the quarterly plans (if
applicable) and also approve any essential deviations from the original plans.
122. The PSC will be chaired by the MME and will provide overall guidance for the project
throughout its implementation. Specifically, the PSC will be responsible for:
123. To ensure MME’s ultimate accountability for project results, Steering Committee
decisions will be made in accordance with the standards that shall ensure management
for development results, best value money, fairness, integrity, transparency and effective
international competition. To further enhance capacities and promote local ownership
and future sustainability of results, efforts will be made to cater for capacity
Page 54
development, where appropriate and if feasible. In case consensus cannot be reached
within the PSC, the final decision shall rest with the MME in consultation with the UNDP
as advised by the Project Manager. Ultimately, the MME in terms of NIM will be
accountable for decisions made on behalf of the project.
Project Board
Steering Decisional
Executive:
Committee Level
Representative
(SC) of the MME
Senior
Supplier UNDP
Namibia GEF Senior
Climate Beneficiary
Change MME,
Regional NamPower,
REEEI, MET,
ECB
Project Management
Management National Project
Manager, Admin Project Support Level
Unit (PMU)
Assistant REEEI (Polytechnic)
Off- National
IPP takers Consultants
NamPow
er ECB
124. Potential members of the Steering Committee are reviewed and recommended for
approval during the project appraisal, the inception workshop and PSC meetings.
Representatives of other stakeholders can be included in the Committee as appropriate.
The Steering Committee contains three distinct roles including:
• An Executive: individual representing the project ownership to chair the group such
as a representative of the Government Cooperating Agency who can be deputised
by UNDP;
• Senior Supplier: individual or group representing the interests of the parties
concerned which provide funding for specific cost sharing projects and/or technical
Page 55
expertise to the project. The Senior Supplier’s primary function within the Board is to
provide guidance regarding the technical feasibility of the project who can be a
representative of the Implementing Partner and/or UNDP; and
• Senior Beneficiary: individual or group of individuals representing the interests of
those who will ultimately benefit from the project. The Senior Beneficiary’s primary
function within the Board is to ensure the realization of project results from the
perspective of project beneficiaries, and can be a representative of the Government
or Civil Society.
125. The Project Assurance role supports the Project Board Executive by carrying out
objective and independent project oversight and monitoring functions. The Project
Manager and Project Assurance roles will not be held by the same individual for the
same project. A UNDP Staff member typically holds the Project Assurance role. In this
case, the project may hire an individual to play this role under the guidance and
leadership of UNDP.
126. The administration of the project will be carried out by a Project Management Unit
(PMU) under the overall guidance of the PSC. The PMU will be led by the National
Project Director, who will be responsible for authorizing and singing project expenditures
in line with the delegation of authority by the MME Permanent Secretary. The Project
Manager has the authority to run the project on a day-to-day basis on behalf of the
Implementing Partner within the constraints laid down by the PSC. The Project
Manager’s prime responsibility is to ensure that the project produces the results, deliver
outputs and provide reporting and monitoring as specified in the project document, to the
required standard of quality and within the specified constraints of time and cost. More
specifically, the role of the PMU will be to:
Detailed TOR for key PMU and consultant staff members are contained in Annex 2.
127. The project will be closely coordinated with the PON/REEEI while Rössing Uranium
Limited, Navachab AngloGold Ashanti, REDs and NamPower are expected to serve as
the off-taker of electricity and waste heat. The Renewables Academy AG as the
provider of the technical training and overall capacity development; and Fraunhofer
Institute ISE and/or Lahmeyer International as providers of technical expertise. The
exact partnership structure and implementation arrangement of the plant installation will
be decided based on the final choice of operator (whether SUNTEC Namibia (Pty) Ltd or
another entity) and the investors involved. Further, if deemed appropriate and necessary
the role of MME, NAMPOWER and ECB on behalf of the Government of Namibia will be
considered.
Page 56
MONITORING FRAMEWORK AND EVALUATION
128. The project team and the UNDP Office in Namibia supported by the UNDP-GEF
Regional Coordination Unit in Pretoria will be responsible for project monitoring and
evaluation conducted in accordance with established UNDP and GEF procedures. The
Project Results Framework provides performance and impact indicators for project
implementation along with their corresponding means of verification. The GEF CC
Tracking Tool will also be used to monitor progress in reducing GHG emissions. The
M&E plan includes: inception workshop and report, project implementation reviews,
quarterly and annual review reports, independent mid-term evaluation, and independent
final evaluation. The following sections outline the principle components of the
Monitoring and Evaluation Plan and indicative cost estimates related to M&E activities.
The M& E budget is provided on Table 6.
129. Project start: A Project Inception Workshop will be held within the first 4 months of the
project starting with those with assigned roles in the project organization structure,
UNDP country office and where appropriate/feasible regional technical policy and
programme advisors as well as other stakeholders will be invited. The Inception
Workshop is crucial to building ownership for the project results and to plan the first year
annual work plan. The Inception Workshop would address a number of key issues
including:
a) Assisting all partners to fully understand and take ownership of the project;
b) Detailing the roles, support services and complementary responsibilities of UNDP
CO and RCU staff vis-à-vis the project team;
c) Discussing the roles, functions, and responsibilities within the Project's decision-
making structure including reporting and communication lines, and conflict resolution
mechanisms. The Terms of Reference of project staff will be discussed again as
required;
d) Finalization of the first annual work plan based on the project results framework and
the relevant GEF Tracking Tool if appropriate. A review and agreement on the
indicators, targets and their means of verification will be required as well as a re-
check of assumptions and risks;
e) Providing a detailed overview and reach consensus on reporting, monitoring and
evaluation (M&E) requirements, the M%E work plan and budget;
f) Discussion of financial reporting procedures and obligations, and arrangements for
annual audit;
g) Planning and scheduling Project Board meetings;
h) Clarification of roles and responsibilities of all project organisation structures as well
as planned dates of meetings where the first PSC meeting should be held within the
first 12 months following the inception workshop.
130. An Inception Workshop report is a key reference document and must be prepared and
shared with participants to formalize various agreements and plans decided during the
meeting.
Progress made as reported in the Standard Progress Report (SPR) and monitored in
the UNDP Enhanced Results Based Managment Platform;
Page 57
Based on the initial risk analysis submitted, the risk log shall be regularly updated in
ATLAS (if applicable otherwise outside ATLAS). Risks become critical when the
impact and probability are high;
Project Progress Reports (PPR) as generated in the Executive Snapshot and based
on the information recorded in Atlas;
Other ATLAS logs that are used to monitor issues and lessons learned. The use of
these functions is a key indicator in the UNDP Executive Balanced Scorecard.
Budget US$
Type of M&E
Responsible Parties Excluding project team Time Frame
activity
staff time
Within first four
Inception Workshop and Project Manager
Indicative cost: 5,000 months of project
Report UNDP CO, UNDP GEF
start up
Measurement of Means UNDP GEF RTA/Project Manager will To be finalized in Inception Start, mid and end of
of Verification of project oversee the hiring of specific studies Phase and Workshop. project (during
results. and institutions, and delegate evaluation cycle) and
responsibilities to relevant team annually when
members. required.
Measurement of Means Oversight by CTA with support from the To be determined as part of Annually prior to
of Verification for Project Manager the Annual Work Plan's ARR/PIR and to the
Project Progress on Project team preparation. definition of annual
output and work plans
implementation
ARR/PIR Project manager and team Indicative cost: 5,000 for Annually by July
UNDP CO the first year for the
UNDP RTA completion and update of
UNDP EEG the GEF CCM Tracking
Tool
Project Board meetings Project Manager 7,000 x 3 years Following IW and
annually thereafter.
Periodic status/ Project manager and team None Quarterly
progress reports
Mid-term Evaluation Project manager and team Indicative cost: 15,000 At the mid-point of
UNDP CO project
UNDP RCU implementation.
External Consultants (i.e. evaluation
team)
Final Evaluation Project manager and team, Indicative cost : 18,000 At least three months
UNDP CO before the end of
UNDP RCU project
External Consultants (i.e. evaluation implementation
team)
Project Terminal Report Project manager and team At least three months
UNDP CO 0 before the end of the
local consultant project
Audit UNDP CO Indicative cost per year: Yearly
Project manager and team 5,000 x 3 years
Visits to field sites 5,000 x 3 years Yearly
UNDP CO
(UNDP staff travel costs
UNDP RCU (as appropriate)
to be charged to IA
Government representatives
fees)
TOTAL indicative COST 96,000
Excluding project team staff time and UNDP staff and travel expenses (+/- 5% of total budget)
Page 58
132. Audit Clause: Audit will be conducted according to UNDP Financial Regulations and
Rules and applicable Audit policies.
133. Annual Project Review /Project Implementation Reports (APR/PIR): APRs/PIRs are key
reports prepared to monitor progress since project start and in particular for the previous
reporting period (30 June to 1 July). The APR/PIR combines both UNDP and GEF
reporting requirements, and includes, but is not limited to, reporting on the following:
Progress made toward project objective and project outcomes, each with indicators,
baseline data and end-of-project targets (cumulative);
Project outputs delivered per project outcome (annual);
Lesson learned/good practice;
AWP and other expenditure reports;
Risk and adaptive management;
ATLAS QPR;
Portfolio level indicators (i.e. GEF focal area tracking tools) that are used by most
focal areas on an annual basis.
134. Periodic Monitoring through site visits: UNDP CO and the UNDP RCU staff will conduct
visits to project sites based on the agreed schedule in the project's Inception
Report/Annual Work Plan to assess first hand project progress. Other members of the
Project Board may also join these visits. A Field Visit Report/BTOR will be prepared by
the CO and UNDP RCU and will be circulated no less than one month after the visit to
the project team and Project Board members.
135. Mid-term of project cycle: The project will undergo an independent Mid-Term Evaluation
at the mid-point of project implementation. The Mid-Term Evaluation will determine
progress being made toward the achievement of outcomes and will identify course
correction if needed. It will focus on the effectiveness, efficiency and timeliness of
project implementation; will highlight issues requiring decisions and actions; and will
present initial lessons learned about project design, implementation and management.
Findings of this review will be incorporated as recommendations for enhanced
implementation during the final half of the project’s term. The organization, terms of
reference and timing of the mid-term evaluation will be decided after consultation
between the parties to the project document. The Terms of Reference for this Mid-term
evaluation will be prepared by the UNDP CO based on guidance from the Regional
Coordinating Unit and UNDP-GEF. The management response and the evaluation will
be uploaded to UNDP corporate systems, in particular the UNDP Evaluation Office
Evaluation Resource Center (ERC). The relevant GEF Focal Area Tracking Tools will
also be completed during the mid-term evaluation cycle.
136. End of Project: An independent Final/Terminal Evaluation will take place three months
prior to the final Project Board meeting and will be undertaken in accordance with UNDP
and GEF guidance. The final evaluation will focus on the delivery of the project’s results
as initially planned (and as corrected after the mid-term evaluation, if any such correction
took place). The final evaluation will look at impact and sustainability of results,
including the contribution to capacity development and the achievement of global
environmental benefits/goals. The Terms of Reference for this evaluation will be
prepared by the UNDP CO based on guidance from the Regional Coordinating Unit and
UNDP-GEF.
Page 59
137. The Final Evaluation should also provide recommendations for follow-up activities and
requires a management response which should be uploaded to PIMS and to the UNDP
Evaluation Office Evaluation Resource Center (ERC). The relevant GEF Focal Area
Tracking Tools will also be completed during the final evaluation. During the last three
months, the project team will prepare the Project Terminal Report. This comprehensive
report will summarize the results achieved (objectives, outcomes, outputs), lessons
learned, problems met and areas where results may not have been achieved. It will also
lay out recommendations for any further steps that may need to be taken to ensure
sustainability and replicability of the project’s results.
138. Learning and knowledge sharing: Results from the project will be disseminated within
and beyond the project intervention zone through a number of existing information
sharing networks and forums. In addition:
139. The project will identify, analyze, and share lessons learned that might be beneficial in
the design and implementation of similar future projects. Identifying and analyzing
lessons learned is an on-going process and the need to communicate such lessons as
one of the project's central contributions is a requirement to be delivered not less
frequently than once every 12 months. UNDP/GEF shall provide a format and assist the
project team in categorizing, documenting and reporting the lessons learned. To this end
a percentage of project resources will also need to be allocated for these activities.
LEGAL CONTEXT
140. This document together with the CPAP signed by the Government and UNDP which is
incorporated by reference constitute together a Project Document as referred to in the
Standard Basic Assistance Agreement or SBAA [or other appropriate governing
agreement] and all CPAP provisions apply to this document. Consistent with the Article
III of the SBAA, the responsibility for the safety and security of the implementing partner
and its personnel and property, and of UNDP’s property in the implementing partner’s
custody, rests with the implementing partner.
a) Put in place an appropriate security plan and maintain the security plan, taking into
account the security situation in the country where the project is being carried;
b) Assume all risks and liabilities related to the implementing partner’s security, and the
full implementation of the security plan.
142. UNDP reserves the right to verify whether such a plan is in place, and to suggest
modifications to the plan when necessary. Failure to maintain and implement an
Page 60
appropriate security plan as required hereunder shall be deemed a breach of this
agreement.
143. The implementing partner agrees to undertake all reasonable efforts to ensure that none
of the UNDP funds received pursuant to the Project Document are used to provide
support to individuals or entities associated with terrorism and that the recipients of any
amounts provided by UNDP hereunder do not appear on the list maintained by the
Security Council Committee established pursuant to resolution 1267 (1999). The list can
be accessed via http://www.un.org/Docs/sc/committees/1267/1267ListEng.htm. This
provision must be included in all sub-contracts or sub-agreements entered into under
this Project Document.
Page 61
K ANALYSIS
or October Financing P=2 Lessons from the implementation of Independent Power Producers (IPP)
global 2010 I=5 projects will be incorporated. Different PPP models and if necessary,
publicly financed projects will be considered. Technical assistance for
developing a robust framework for private sector participation would be
strengthened.
capital October Financing P=3 Project will be open to different types of CSP technologies and
2010 I=3 procurement approaches to ensure the best possible competitive
environment.
uel price October Technical P=3 SADC countries are undertaking price reform, although some are faster
its CSP 2010 I=3 than others. Like other IPPs, CSP projects will be subject to regulation by
contract with PPAs that incorporate above-average tariffs. SADC
countries are also increasingly seeing the virtues of CSP for saving
subsidized fuel for higher value-added uses than power generation.
Falling CSP capital costs through economies of scale will bring CSP
towards grid parity, and accelerate deployment. In short, the price
environment for CSP in Namibia is challenging, but is expected to
improve. Measures to reflect true cost of fuel and electricity prices will be
determined through conduct of energy cost and market studies.
ANNEX 2: TERMS OF REFERENCE
The National Project Director (NPD) will be appointed by MME in consultation with UNDP for overall
supervision of the project. The NPD will act as the Member Secretary to the Project Steering
Committee (PSC) and shall be responsible for overall implementation of the project.
Scope of work
• Ensures that the expected results of the project are of satisfactory substantive quality and
that they contribute to the achievement of the intended outcome identified in the CPD/RRF.
This will be discharged through the (i) approval of project work plans, TORs, reports, (ii)
follow-up on the implementation of recommendations made by regular project reviews and
external evaluations, and (iii) conduct of internal reviews and evaluations as/if needed.
• Ensures that project resources, national as well as international, are effectively utilized for
their intended purposes through the (i) verification of project budgets and payments, (ii)
approval of budget revisions within the agency flexibility limit, (iii) follow-up on the
implementation of recommendations made by external audits and (iv) conduct of internal
audits as/if needed.
• Ensures that counterpart funds are made available by the NIP in sufficient quantities and in
a timely manner to support project implementation.
• Ensures that project parties, particularly national parties (including the NIP and Other
Partners) fully participate in project implementation, effectively collaborate in project
activities and duly benefit from project results.
• Ensures that the results achieved and lessons learned by the project are properly
documented, proactively disseminated to and duly shared with all project parties, particularly
national parties.
• Selects, arranges for the appointment of and supervises the Project Manager, in
consultation with UNDP, to make sure that the PM and other national project staff are
empowered to effectively perform their day-to-day project duties.
• Selects, arranges for the appointment of and supervises the Senior/Chief Technical Advisor,
in consultation with UNDP, to make sure that the S/CTA and other international project
personnel contribute expert inputs of highest quality to the expected outputs of the project.
• Represents the NIP at major project reviews, evaluations, audits and other important events.
• The NPD signs the FACE forms to authorise payments made from the project.
• Organize/convene Project Steering Committee meetings as per UNDP procedures
• Facilitate interaction and communication with other governmental departments
• Provide overall guidance to the SC/NPM and the PMU.
• Approve Terms of Reference for PMU staff, including the NPM.
• Review project budget revisions, annual progress reports, quarterly progress reports,
facilitate audit, and other administrative arrangements as required by MME and UNDP
• Facilitate mid-term and terminal evaluations, and facilitate implementation of
recommendations
• Ensure timely progress of activities and project implementation as per the ProDoc, or any
agreed changes to the ProDoc based on changing circumstances or lessons learned during
project implementation.
• Ensure required government support required to achieve project milestones and quality of
outputs
Page 63
• Oversee the day-to-day planning, implementation and monitoring of project activities
• Act as the Secretary of the Project Steering Committee (PSC)
• Organize PSC meetings;
• Prepare Standard progress reports (quarterly and annual), APR/PIR, FACE, annual work plans and
budgets; facilitate audit, and any other necessary documentation required by UNDP, MME and the
PSC, and recommendations to the Project Steering Committee
• Allow for effective communication and decision-making between the PSC, UNDP, MME and all
stakeholders to ensure ongoing stakeholder cohesion and effective process management
• Develop a common understanding of what is needed to expedite the execution of the project with all
stakeholders;
• Review and advise on the main outputs of the project;
• Assist with the preparation of a project monitoring and evaluation plan
• Assist with minute taking and capturing and incorporating recommendations from PSC meetings into
project execution and monitoring and evaluation plan
• Keep track of project’s progress towards the attainment of the project outcomes and objectives
• Assist the NPD in strategic management and overarching implementation of the project and
achievement of its goals
• Coordinate and manage the project’s Inception Workshop and preparation of the Inception Report
• Lead efforts to assist MME on CSP planning mechanisms (Output 2.2) and drafting regulations to
promote the development and operation of CSP plants (Output 2.3)
• Support timely progress of activities and project implementation as per the ProDoc or agreed
changes to ProDoc
• Support the elaboration of monitoring & evaluation reports (midterm, terminal etc.) to MME and
UNDP/GEF
• Prepare and approve Terms of Reference for consultants and subcontracts and for equipment
procurement
• Manage disbursement of funds, maintenance of accounts as per requirements of UNDP & NIM
guidelines, and provide inputs to internal and external audits
• Liaise with counterparts and main stakeholders to ensure their roles are appropriately integrated into
the project as envisaged
• Delegate responsibilities to the appropriate Project officers
• Monitor the work of the agencies involved in managing specific components and outputs
• Provide technical expertise and guidance to all project components, and support the PM in the quality
check, quality reviews and quality control and technical clearances of all technical elements and
requirements of the project outputs
• Support the PM with the coordination of the implementation of planned activities under the project
• Serve in a mentoring and back stopping function to project staff, as relevant
• Contribute to the work of the Knowledge Management
• Assist the PM in the development of an effective and implementable project M&E plan; jointly design,
track and implement M&E activities.
• Advise on key policy and legal issues pertaining to the project, e.g. revolving around the long-term
planning of a CSP project; engage on and contribute to policy dialogues on all levels, including the
national level.
• Provide overall technical oversight for project outputs, deliverables and inputs as required
and recommend actions that focus work plans on achieving key milestones in a timely
manner.
• Provide technical and policy advisory support for technology assessment of solar
concentrator technologies including the development of performance measurement
standard and test protocols and minimum performance norms for solar concentrator
technologies for CSP applications
• Undertake and where unable to, recommend special expertise where appropriate to assist in
achievement of key milestones, and provide the interface between Project team and key
specialist consultants, both domestic and international.
Page 64
• Provide oversight to the development of technology application information packages and to
engineering plans and implementation of CSP development to ensure compliance with
global standards to implementation of CSP systems.
• Undertake regular reporting in line with project management guidelines. Ensure the timely
implementation of planned activities under the project as stipulated in the work plan.
• Review and evaluate the feasibility studies and EIA
• Assist PMU in the technical clearance/quality assurance of draft outputs and disbursement of GEF
funds for feasibility studies and EIAs
• Promote synergistic relationships amongst project proponents, suppliers, service providers, financers,
consultants and others involved in CSP project development
• Supervise, review quality assurance/control of draft technical outputs
• Assist PM to prepare the PIR
• Coordination of all activities under Component 1: Engaging local entrepreneurs in the CSP
supply chain
• Prepare training needs assessment, appropriate training modules and training materials,
and selection of agencies for conducting the required awareness and training programmes
• Oversee the design, delivery and evaluation of the awareness and training programmes
• Organize the development, launch and management of the project website and various
publications under the project
• Network with all stakeholders to strengthen the awareness and capacity building under the
project and to facilitate agreements between foreign technology groups and local CSP
interest groups
Page 65
• Facilitate annual financial audit of the project, management responses and action taken,
produce statements as needed, keeps checks and balances in place to ensure proper use
of finances under appropriate headings and report on financial progress
• Prepare quarterly expenditure reports and their timely submission to UNDP
• Be responsible for administrative and secretarial matters
• Arrange logistics, including travel and organization of meetings and workshops
• Assist in the processing and reporting project incomes and expenditures
• Set up and maintain project files
• Collect project related information data
• Update plans
• Administer Project Board meetings
• Administer project revision control
• Establish document control procedures
• Compile, copies and distribute all project reports
• Assist in the financial management tasks under the responsibility of the Project Manager
• Provide support in the use of Atlas for monitoring and reporting
• Review technical reports
• Monitor technical activities carried out by responsible parties
Page 66
ANNEX 3: ENVIRONMENTAL AND SOCIAL ISSUES
The construction and operation of CSP projects potentially leads to a variety of environmental and
social impacts that would need to be identified, assessed, monitored and mitigated. The World
Bank and African Development Bank have prior experience in this area based on the two GEF
funded CSP projects in Egypt (WB/JBIC) and Morocco (WB/AfDB) that are under implementation.
The projects have followed environment and social guidelines of the respective institutions. Table 7
summarizes the key impacts and their mitigation options. It is worth pointing out that most, if not all,
of these impacts are likely to be site-specific rather than regional or cross-boundary in nature.
Table 7: Key potential environmental and social impacts from CSP and mitigation options
Page 67
returned into the system, problem of dealing with where use of wet cooling would result in water
thermal discharges shortage, use of thermal discharges in nearby
industry where feasible.
Social
Loss of long-term livelihoods from inability to use Alternative livelihoods programs for local
land that now is the project area. communities.
These issues will be dealt with in the context of individual projects in line with relevant World
Bank/AfDB/IFC procedures49 based on the implementation experience of the Egypt Kureimat project
and the Morocco Ain Beni Mathar project, the social and environmental impacts are reasonably well
understood.
One of the key issues for the region while considering a CSP program is the availability of water.
The water requirements for a CSP plant are no different from the needs of conventional power
plants, except for cleaning, but this issue does need careful consideration because of the siting of
CSP plants in arid locations. In this regard, experience from Morocco and elsewhere indicates that
water savings from hybrid cooling systems and air cooling systems vis-à-vis wet cooling are
considerable. Additional water savings generated by air cooling over hybrid cooling outweigh the
rather marginal additional performance and cost penalty associated with this technology.
Nonetheless, the decision on the cooling technology ought to be made in each instance taking local
water availability and cost into account.
Water consumption has an increased significance in a geography such as Namibia where the water
availability is very low, and for that matter should be given priority for social uses, such as human
consumption and farming (irrigation). In light of this fact and regardless of the CSP technologies
selected, it was decided at the onset that any CSP plant proposed for Namibia must have a dry
cooling technology, meaning that the water consumption in this cases can be considered negligible.
The preferred technology for the top 5 sites selected all calls for dry cooling. A CSP project using
dry cooling technology presents a lower efficiency (about 20%) but this is appropriate for Namibia
and activities in component #3 (as regards the EIA and full f/s) have been designed factoring in dry
cooling applications.
In addition, desalination of seawater is considered to be one of the options to meet the water
requirements for the proposed CSP Scale-up in the Middle East and Northern Africa region
(MENA). While the MENA region is one of the world’s most water-stressed regions, with 16 out of
the 20 countries facing water stress, it is also a world leader in desalination deployment, with 55%
of the world’s desalination capacity. The desalination capacity additions are expected to increase by
2011, almost doubling from 2006 standards. Given the increasing demands for water across the
region, the increase in installations is expected to continue until 2025.
Desalination of seawater to reach levels acceptable for human consumption or industrial purposes
is a highly energy intensive process and is thus conducted only in regions of high water stress. Multi
Stage Flash (MSF) or Multi Effect Distillation (MED) evaporation techniques are the most commonly
used, while Reverse Osmosis (RO) use is growing. While MSF and MED rely on a mix of heat and
electricity input, RO relies exclusively on electricity input. MED is more efficient than MSF and is
increasingly leading the new capacity installations.
Given the assumptions of water requirements of 2.8 to 3.4 m3/MWh and capital costs of $1500-
2000/m3/d for MSF and $900-1700/m3/d for MED, the additional capital costs required for the
desalination equipment come to about $33-37/kW. For the MENA CSP plan of 1000MW, this
amounts to an additional $33m, assuming that each plant reaches the economies of scale required
for these costs. Since desalination is a mature technology in the region, these costs can be stated
with a reasonable degree of accuracy. The additional solar field required would be in the order of 1
49 Reference is made to World Bank procedures which are international norm for EIA
Page 68
to 3 percent. Over sizing the solar field can provide energy for a larger desalination plant, which
could provide drinking and/or potable water for the local community.
Page 69
ANNEX 4: FINANCIAL AND IMPLEMENTATION ISSUES
Grants: Grant funds would be utilized for advancing preparatory work with respect to each of the
program areas. In particular, preparatory funds are required for additional feasibility work,
structuring of private sector elements including agreements such as power purchase
agreements. The grants will assist clients implement the proposed projects in a manner that
would catalyze replication. At the same time, this will aim to solidify the long-term impact of
market transformation by strengthening local capacity, awareness, and know-how of CSP by
sharing lessons learned through market promotion activities. The lessons learned from initial
experiences could be cross fertilized in SADC region and beyond and reduce the learning curve
for new market entrants. The total preparatory funds required would be in the range of US$ 2-3
million50 related to CSP project. These preparatory funds would/are being supplemented by
other sources including EC, ESMAP, AfDB FAPA, Japan PHRD, PPIAF and others to the
extent of $ 2 million.
Loans: In addition to the expected DBSA debt financing, if needed the proposed project could
also apply to utilize the CTF loan instrument in conjunction with co-financing from other sources
including private sector, IBRD, African Development Bank, IsDB, AFD, SFD, KfW, EIB, JICA,
JBIC, Spanish agencies, private sector and other donors.
Guarantees: In addition to the above instruments, it is likely that the CSP scale-up program
would need risk mitigation instruments such as guarantees to stimulate private sector interest in
the program. The guarantees could be accessed through MIGA, IBRD and/or AfDB.
Carbon Finance: Carbon revenues (from an applicable voluntary carbon standard,) may be
incorporated in the revenue streams as part of the financing plan but these will need to be
validated during preparation of each project. A program of activities (POA) could also be
developed for a future program based on the existing methodology and new methodology to be
developed for projects involving export of power to SADC countries to appropriately account the
renewable energy imports and purchase of carbon credits that may be applicable only for the
part of energy consumed in the domestic markets.
Global Environment Facility (GEF): In addition to the above sources, GEF co-financing for
the identified projects, including for providing technical assistance support to the participating
countries.
The sources of investment in the financial modality varies as illustrated in Figure 15, hence
investments for CSP TT NAM Project could be financed from multiple sources (or jointly-financed)
as captured by the figure's overlapping circles of investment decisions.
The large volume for the finance of CSP plants (USD 4-6 million/ MW) is often provided by many
different companies, banks or financial institutions. On the Spanish CSP market several special
purpose vehicles have been founded by a project consortium. After finishing the project the project
development company very often sells its share to other owners for the operation. Large
international institutions have played a very important role in Egypt and Morocco. Under a feed-in
scheme the risk for private investors and banks is limited if the state guarantees for the payments
over 10 to 20 years. After many investors and banks have gained first experiences with the CSP
technology and reference time series for electricity output are provided to the investors, more and
more projects will become bankable for creditors in Namibia. However, Development Bank of
Namibia (DBN) must take a lead in the financing arena for CSP market development in the country.
With regard to ownership, there are 2 common operator models in the context of power plants
Namibia could adopt, i.e., build-own-transfer (BOT) and build-own-operate-transfer (BOOT)51.
50 The amount is subject to further verification after additional CTF preparation funds become available and its rules
finalized.
51 The BOOT was arrived at as alternative route to raise capital funding (venture capital
through an IPP) under the intense competitive structure of the GEF PIF and as a service
characteristic of technology item and technology commercialization strategies and
Page 70
Figure 15: Sources of investments to address RE52
Private Investment
decisions
Direct/indirect UNFCCC
and Protocol-stimulated
investments in mitigation
and adaptation
CSP TT NAM project is government led, development based and private sector driven. The above
operator models are both institutionally feasible, i.e. Suntec Namibia (private sector) is anticipated
to design, finance (debt/equity), construct, and operate the CSP plant for a certain concessionary
period. Suntec Namibia would assume responsibility for the completeness of the design, any risk
associated with construction, and the control of operational costs, all of which would be reimbursed
by the collection of revenue from the off-takers. Suntec would be granted a specific concessionary
period, after which time the contract might be renewed at the option of the government, or title
would be transferred from Suntec to a government agency. The life span of the project is 20 – 25
years. Suntec also recognize the value of having respected local participants on the project.
At the current state only with the political willingness CSP TT NAM project can be developed. If
political decision makers (MME & ECB) foresee their own benefits (like chances for employment or
a possible solution for domestic energy problems) a financial/political support from GRN should be
provided. This is on the backdrop that CSP projects do not (yet) pay for themselves, the project
financing is often the most difficult part of the project development. Feed-in tariffs ensure the
payment. Based on the feed-in tariff levels and specifications private investors calculate the
profitability of a potential plant. This support mechanism improves the process of making the project
bankable because of the long-term guarantees and continuous revenue flows to the owners and
consequently to the creditors. However, if the tariffs are set too liberal the country cannot control the
number of plants constructed, as it has happened in Spain in the PV market. In North Africa so
called PPA (power purchase agreements) assure the financing very often. A PPA works similarly to
a feed-in-tariff but the state controls the number of plants as every plant is tendered separately.
This leads to individual and always slightly different conditions for every built plant, but also it
prohibits a dynamic market evolution and replicability.
Page 71
Labour Impact: Job Creation
CSP TT NAM project will add valuable economic benefits to the economy of Namibia through the
creation of new jobs, GDP growth, and energy security. These prospective economic benefits are to
be taken into account in setting up the financial support plan, since they are key in the establishing
long-term economic benefits for the country. Further, the technical know-how in renewable energy
technologies would increase in Namibia.
In the following table, the results of the labor impact assessment give the numbers of direct job
creation during CSP plant construction. The operation and maintenance of the plant will also create
long-term employment in the solar sector as about 41 jobs are needed to run a reference (50MW)
power plant. Because of the replacement of components and equipment, the plant maintenance
also has an indirect impact on new jobs. Many new jobs in construction and O&M will also have an
impact on induced jobs in the region were the plant will be located. Number of indirect jobs for
construction and O&M will increase other induced jobs. This leads to higher wealth and income of
the region when new services and products for their private consumption are demanded.
Page 72
Table 8: Shares in the value chain as well as other important parameters for a typical CSP
plant
Components Cost share of Typical Annual Jobs created Direct Share Synergies
50 investment output of Jobs per of with
MW in new typical year / MW labor other
parabolic factory53 factory industries /
trough plant potential
with sidemarkets
storage (7h)
Civil Work Infrastructure: - - 250-350 oneyear 5-7 High High
5.8 % jobs per 50 Jobs/MW
Solar field: MW
3.1 %
Installations 5.3 % - - 100 one-year 2 High High
on the site jobs per 50 MW Jobs/MW
EPC 7.7 % - - 30 – 40 one-year 0.6 – 0.8 High High
Engineers and jobs per 50 MW Jobs/MW
Project
Managers
Assembling 2.5 % - - 50-100 one-year 1-2 High High
jobs per 50 MW Jobs/MW
Receiver 7.1 % 25 Mio 200 MW 140 jobs 0.3 – 0.7 Low Very low
Euro Jobs/MW
Mirror ~4% 26 Mio 1 Mio 250 jobs 0.6 – 1.2 Mediu High
flat Euro mirrors Jobs/MW m
(Float glass) 200-400
MW
Mirror 6.4 % 30 Mio 1 Mio 300 jobs 0.7 – 1.5 Mediu Low (if
parabolic Euro mirrors Jobs/MW m glass
200-400 production
MW is
included
then high)
Mounting 10.7 % 10 Mio 150-200 70 jobs 0.3 – 0.5 Mediu Medium
structure Euro MW Jobs/MW m
HTF 2.1 % Very large Large Not identified Low Low
Connection 5.4 % Low Medium
piping
Storage system 10.4 % - 50 jobs Low Low
Electronic 2.5 % Medium Medium Not identified Mediu Medium
equipment m
Reference CSP 100% - Current 500 one-year 10 High -
Plant (50 MW, plants jobs per 50 MW Jobs/MW
7,5 h 50 MW to (only on the plant only on
storage)54 100 MW site) the plant
site
Page 73
ANNEX 5: DETAILED CO2 CALCULATONS AND ASSUMPTIONS
Since the project does include activities that would directly result in GHG emission
reductions after the completion of the Project, direct post-project GHG reductions are
expected. They have been calculated as follows:
• Base case - With no estimates of MWh generated from proposed 50 MW CSP plants,
assumptions on MWh generated were made using an average net capacity factor of
40% based on July 2012 Pre-feasibility CSP Overview by MME (on pg 5) that assumes
CSP plant has thermal storage to meet peak demand in the evening;
• First CSP plant commissioned in 2016;
• Two other 50 MW CSP plants were assumed to be commissioned in 2017 and 2018;
• Average number of hours that CSP plant is 24 hrs, 365 days per year;
• Grid emission factor is 1.0136 t CO2eq /MWh55 that assumes carbon reductions are
resulting from the offsetting of power imported from South African thermal power
stations;
• One 50 MW plant will generate 175,200 MWh annually (50 MW x 24 hrs x 365 days x
0.40);
• With the 1.0136 t CO2eq /MWh grid emission factor, emission reductions are 177,583 t
CO2eq annually from each 50 MW CSP plant.
As such the ER calculation range for the two scenarios (base case and low end) are as follows:
- Direct post-project GHG reductions for this project will range from 177,583 tCO2/yr (for each 50
MW CSP plant with storage) to 88,791 tCO2 (for each 50 MW CSP plant without storage);
- The 10-year cumulative GHG emission reductions from three CSP projects implemented over the
next 3 years after the end of the Project will range from 4.79 million tons CO2eq (with storage) to
2.40 million tons CO2eq (without storage).
The summary of estimated emission reductions for the base case and low end case over the 10-
year GEF influence period is provided on Table 8.
55 UNEP Riso Center, GFE Envest GmbH, African Carbon Asset Development (ACAD) Facility,
‘‘Analysis of Grid Emission Factors for the Electricity Section in Sub-Saharan Africa, The
Case of the Southern African Power Pool’’
Page 74
C. Indirect emission reductions (bottom-up)
Indirect emission reductions were calculated by assuming a “top-down” 60% causality factor
(“substantial but modest”). The P10 based on 3 CSP plants (base case assumptions) constructed
after the end of CSP TT NAM is 4.795 million tonnes CO2eq. After applying the 60% causality
factor, indirect emission reductions from this project were calculated to be 2.877 million tonnes
CO2eq.
Page 75
Table 8: Calculation of Direct Post-Project Emission Reductions from CSP Plants (base case and low end case)
Installed
Energy generated by
Capacity
CSP plant (MWh)
(MW) 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Total
Ausnek 50 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 1,752,000
Kokerboom 50 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 1,576,800
CSP plant 3 50 175,200 175,200 175,200 175,200 175,200 175,200 175,200 175,200 1,401,600
CSP Plant 4 50 0 0 0 0 0 0 0 0
CSP Plant 5 50 0 0 0 0 0 0 0
CSP Plant 6 50 0 0 0 0 0 0
0
0
0
0
0
Total CSP Energy
Generated (MWh) 0 0 0 0 175,200 350,400 525,600 525,600 525,600 525,600 525,600 525,600 525,600 525,600 4,730,400
Annual Emission
Reduction (tCO2eq) 0 0 0 0 177,583 355,165 532,748 532,748 532,748 532,748 532,748 532,748 532,748 532,748 4,794,733
Page 76
Low End Case Scenario – Table B
Installed
Energy generated by
Capacity
CSP plant (MWh)
(MW) 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Total
Ausnek 50 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 876,000
Kokerboom 50 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 788,400
Gerus 50 87,600 87,600 87,600 87,600 87,600 87,600 87,600 87,600 700,800
CSP Plant 4 50 0 0 0 0 0 0 0 0
CSP Plant 5 50 0 0 0 0 0 0 0
CSP Plant 6 50 0 0 0 0 0 0
0
0
0
0
0
Total CSP Energy
Generated (MWh) 0 0 0 0 87,600 175,200 262,800 262,800 262,800 262,800 262,800 262,800 262,800 262,800 2,365,200
Annual Emission
Reduction (tCO2eq) 0 0 0 0 88,791 177,583 266,374 266,374 266,374 266,374 266,374 266,374 266,374 266,374 2,397,367
Page 77