ADIS MGL Haresh Final
ADIS MGL Haresh Final
ON
SAFETY REQUIREMENTS IN CITY GAS
DISTRIBUTION
AT
Mahanagar Gas Limited; Mumbai
AS PRESCRIBED BY
MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION,
MUMBAI.
COURSE CONDUCTED BY
Submitted By
HARESH PARAB
FORWARD
2
ACKNOWLEDGEMENT
HARESH PARAB
3
SUBMISSION
Signature
Internal Examiner
4
INDEX
Sr. Description Page No.
No
1 Preface 6
2 Scope of the Project. 7
3 Objective 8
4 Methodology 9
5 Organization Profile 10
6 HSE Policy 14
7 Safety Organization: Safety Management System & 16
Safety Committee
8 Safety Training : Employees, Contractors, Visitors 19
Rules, Manuals, Classroom etc
9 Safety Promotion: Safety Day / Week, Contests, 25
Awards, Posters, Suggestions, Coordinators etc.
Awards won by organization
10 Nearmiss/Hazards Statistics (calendar years) 30
11 Housekeeping : Plant Layout, Roads, Location of 32
Machines Ventilation, Noise, Illumination
12 Ergonomics 34
13 P.P.E : Availability, Use, Training, Comfort 40
14 Risk Assessment : HAZOP, JSA, Audit, Inspection 42
HIRA etc
15 Work Permit Systems 45
16 Fire Prevention / Control : Extinguishers, Hydrants, 48
Training Sprinklers
17 Emergency Preparedness : Plan, Training, Mock drill 51
18 Safety of Contractors / Visitors 55
19 Findings & Recommendations 56
20 Conclusion 58
21 Annexures 59
5
CHAPTER 1
PREFACE
To protect the human being from industrial hazards direct & indirect
cost of accidents death & injuries, pain & various social losses the
need of accident prevention & safety at work place is increasing.
Safety being the human instinct & basic need of man kind, it is not
true that industry always bring hazard. The science of safety is also
increased & modern scientific control measures are always trying to
decrease accident and injuries. We have to study this aspect in much
detail, because it is only use full subject to avoid accidents and
increase safety.
Safety is a way of life, let us always maintain safety and solve our
problems in safe atmosphere only. Lets us perform this safety duty
first, enjoy the right. This is the only good motivating force to mould
the human behaviour to maintain safety.
This approach constituent the fire and safety requirements, the code
of practice describes specific techniques that can help in attaining
such objectives. The overall methodology presented in this code
allows systematic identification of hazard as well as qualification of
the risk associated with the processes or activities. Applied with due
expertise and rigor the prescribed methodology can help the user
understand the relative level of hazards and risk potential in the
process. This aids the selection and prioritization of necessary
strategies for accident prevention and limiting their consequences.
7
CHAPTER 3
OBJECTIVES
The project on Safety in City Gas Distribution has been carried out at
Mahanagar Gas Ltd. located at Mumbai. This company specially chosen
for project due to the risk involved in its operations. The organisations
infrastructure is spread across the city passing through the public places.
All these involved variety of hazards that needs careful attention secondly
company has well established safety department and hence interaction
with it is surely helpful.
To find out the existing risk inside the industry along with their
corrective measures and check its adequacy.
METHODOLOGY
9
CHAPTER 5
ORGANISATION PROFILE
Mahanagar Gas Limited (MGL) incorporated on 8th May 1995 is engaged in the
distribution of Natural Gas in the city of Mumbai. It is a Joint Venture with Gas
Authority of India Limited (GAIL), a Navratna Public Sector Undertaking, BG Plc.
(Formerly British Gas), a leading International Gas Distribution Company and
Government of Maharashtra.
MGL is engaged in distribution of Natural Gas, a clean and alternative source of
energy through safe, efficient and cost effective means. 1.5 MMSCMD of Natural
Gas has been allocated to Mumbai city to meet the energy requirements covering
Domestic, Commercial, Transport (CNG) & Industrial sectors.
The main objective of the company is to substitute other fuels with Natural Gas
in accordance with internationally recognized standards of practice. MGL
supplies gas to Domestic consumers and Commercial / Industrial consumers
plus compressed Natural Gas to Vehicles.
Natural Gas can be used by all Industries which at present use fuel, oils, LPG,
Electricity, coal etc. Natural Gas is not only economical but it also considerably
reduces the pollution in the city.
Natural Gas is also used as a fuel for automobiles in both private vehicles and
public transport. This considerably reduces the pollution in the city of Mumbai.
Nature of Business:
Mahanagar Gas limited is into transmission & distribution of natural gas to the
city of Mumbai & adjoining areas.
Natural Gas produced from Mumbai High offshore is transported to MGL’s City
Gate Station in Wadala after processing, from where MGL distributes the gas
through its vast network of steel and medium density polyethylene pipelines all
over the city of Mumbai.
10
Flow Process Diagram:
11
PNG- Piped Natural Gas:
PNG today is widely recognized as being the preferred fuel for domestic,
commercial and industrial applications. It offers the convenience of gas on tap
with no storage and refilling requirements. PNG is economical when compared to
LPG. A versatile gas, the use of PNG can range from cooking to geysers to air
conditioners and other household equipment.
The benefits of Compressed Natural Gas over other automobile fuels are well
known. It not only has the lowest environmental emissions, but is also cost
effective. CNG is good for both, the business and the environment
CNG as a fuel is provided through filling stations to all the vehicles running in
the city of Mumbai. At present 105 filling stations are catering this services of
providing this environment friendly natural gas to vehicles in the city of Mumbai
12
Potential Hazards:
MGL Risk exposure is categorized into to
Asset Integrity hazards
Occupational Health & Safety Hazards
Workers in the CGD business are exposed to risk of harm due to various hazards
which are inherent in carrying out above activities
13
CHAPTER NO 6
Our Goal is zero injuries because we believe they are all preventable. We conduct
our business in a responsible manner and to internationally accepted good
practice. HSE performance is everyone’s responsibility and we each have a duty
to intervene to prevent unsafe actions and to reinforce good behaviours through
demonstrating HSE leadership. Safety in all our operations is a critical success
factor for our business.
14
Report on our HSE objectives together with our performance and work with
industry and government agencies to improve HSE practices
Observation:
The policy reflects the clear intension towards occupational health safety
environment by providing training, implementation by providing
education, condition monitoring and assigns at various levels of hierarchy
to all statutory obligation.
This Policy reflects the Desire Management, Organisation set up and
Arrangement.
Recommendation:
This Policy should be widely published in all employees.
Make available appropriate resources to implement this policy.
This policy has also been displayed at prominent locations make the policy
available to visitors, suppliers, customers.
15
CHAPTER 7
SAFETY ORGANISATION
HSSE Management System has been established to ensure that the MGL HSE
risk exposure is well below the ALARP. The occupier is the accountable person
for the safety of the organisation. To ensure the safety of employees, safety of the
people who are affected by MGL operations, and to protect the environment, MGL
has established its HSSE management system for the effective implementation of
its safety programme. The HSE Management is underpinned by the integrated
framework of responsibilities and functions driven from top management down to
operational levels, covering all aspects of risk, most notably OHS risk, equipment
failure and operational risk (including legal, regulatory, and human resources
risk).
Safety has always been the top most priority at MGL. In keeping with standards
that are best in the world, MGL has adapted and implemented a robust Health,
Safety Security & Environment (HSS&E) management system with risk control
system and operator instruction in place. The system insures continual
improvement in HSS&E performance.
This apart, MGL has also taken several pro-active measures to further
strengthen safety and security and provide uninterrupted supply of PNG and
CNG to consumers.
16
These include,
A toll-free number for consumers, in case of any emergency, offering 24 x 7
service.
A network of 18 offices around Mumbai, who ensure that help is just and arm’s
length away.
A team of fully equipped emergency vans having an impeccable record of
reaching any site under 30 minutes that is available 365 days a year, 24 x 7.
MGL’s initiatives in areas of health, safety and environment have been recognized
by renowned institutions like BG Group, CII and the Greentech foundation.
MGL has already set up a Safety Management System in accordance with OHSAS
18001:2007, an Environmental Management System in accordance with ISO
14001:2004 and Quality Management System in accordance with ISO
9001:2008. These Management Systems have been audited by a third party
Certification Body viz D N V and found to conform to the requirements of the
respective standards mentioned above. The success of the system has been due
to the commitment from all levels and functions of the organization, and
especially from top management.
BBS is a data driven decision-making process. BBS believes that what gets
measured gets done and each employee can make a difference in organizational
safety. Employees are the basic source of expertise of behavioral change (observe
and correct). BBS begins by briefing sessions for all work areas and depts. BBS
is a teamwork; it is company wide and people driven. BBS purpose is not to
enforce safety rules, force change, gossip about others, reporting to boss. Its
purpose is to identify safe and at- risk behaviors, identify possibility for injury,
communicating the risk and helping to identify safer solutions. An
implementation team or BBS steering committee monitors its progress.
Essentially BBS is not a management driven tool for safety. It’s an employee
driven approach with management support.
17
Safety Committee:
MGL has established its HSE management system to meet organization’s safety
goal i.e. Zero injury. As a part of the system several initiatives have been taken.
Some of the initiatives are much beyond the legal/ statutory requirements. Top
management along with the Heads of the departments as well as union
representatives reviews the effectiveness of the safety programs and takes
corrective actions which include ensuring adequate resource.
Observation:
MGL has its HSE management system who takes initiative to arrange
safety programs.
Recommendation:
18
CHAPTER 8
SAFETY TRAINING
MGL has established HSSE Training Framework has been approved by the
HSS&E Steering Group, and has been published under the authority of MGL for
use throughout the existing and expanding geographical limits of the Company.
MGL has adopted “NO STC NO WORK” policy. It is the responsibility of every
Manager of the respective department to ensure that every person is STC (Safety
Technical Competency) trained and possesses valid STC Card.
MGL requires that all personnel who are required to undertake work on gas
supply network, throughout lifecycle of Design, Construction, Operation,
Maintenance and Disposal must be competent to undertake the tasks.
HSSE Training wing of MGL facilitates every individual who works in MGL
business process in developing his competency. Broadly there exist two areas
one is all MGL direct employees and other is all Contract Employees.
For all MGL direct employees (except personnel and finance dept) competency
levels O, E & M will be developed based on job responsibilities, competency
matrix and competency assessment as described in MGL Competency
Framework.
For all Contract employees, specific activity based or risk based training will be
imparted through in-house training programs or through external agency. They
will be assessed to ensure their competency.
Random surveillance will be carried out to assess training and competency
effectiveness so as to enable improvement in this HSSE Training Framework.
Goal of HSSE training is to inculcate safety consciousness in every direct and
indirect employee. It develops awareness of hazard which is the first step
towards accident prevention efforts. It educates them safe procedure and
practices and in a way make them eligible to work safely
Steel Construction
CNG Construction
PE/GI-Cu Construction
Planning
O&M
Asset Integrity
HSSE
19
Safety And Technical Competency (STC) Training Program:
In accordance with “NO STC TRAINING NO WORK” policy of MGL, concerned
department shall ensure that everyone in the department (MGL + Contract
Worker) must undergo safety & competency training (STC) prior to starting any
work. To facilitate this policy following program is planned.
20
Evaluation Of Training Effectiveness:
It is ensured that all training programs are measured and reviewed for their
effectiveness through the following:
Assessing the quality of training and training facility during training session by
HSS&E representative on sampling basis.
Obtaining feedback from the participants observing and periodically assessing
safe work practices after training at sites by AIC’s as well as HSS&E
representatives.
Observation:
MGL conducts safety training for every workers i.e. MGL employee as well
as contractor employee for safety consciousness.
MGL adopt one policy that ‘NO STC NO WORK’ which help in organisation
to give better result in safety.
Recommendation:
MGL should posses some new training method like audio visual film, use
of working model, transparencies slides etc.
Give first aid and fire fighting training to all site representatives and
workers.
21
Safety & Technical Competence Training Process for PNG:
Outsourced
Fail
Training
(Theory / Practical)
Assessment by AIC
Pass
22
Safety & Technical Competence Training Process for Steel Project:
Internal Training at
Fail
CGS Training Hall
Assessment by AIC
Pass
23
Safety & Technical Competence Training Process for Labour briefings:
At next opportunity
Renewal after one year Training van visits the site
and brief them and issues
STC card
24
CHAPTER 9
SAFETY PROMOTION
Enhancing safety in the every facet of MGL business operation is top priority for
MGL. Educating the organisation, MGL is actively involved with safety education
across the organisation for promoting safety
Safety must be sold to everyone in the chain of command, from the Top
management down to the migrant labors working with contractors. MGL
approached three pronged approach for safety promotion.
STC process:
STC process gives a consistent approach to educate all the direct employees and
contractor employees with respective to safety. Below photograph shows safety
training for the contractor employees as well as MGL employees.
25
Safety Training for Employees
by External Faculty
Safety Reminders:
26
Following are the some examples of posters and pictograms.
27
Safety Events:
Following were the various activities scheduled during the safety week of
2013.
4th March – Safety Pledge Administration
5th March – CNG Safety Awareness program for BEST Drivers & Mockdrill at
CNG outlet
6th March – Awareness session on Pictogram
7th March – Health Checkup Camp for Migrant Labor
8th March – Rangoli Competition for employees & families
9th March – Rewards by Senior Management & Safety Quiz
28
National Safety Week Celebration
29
CHAPTER 10
Near miss/Hazards Statistics
As a part of MGL HSSE management system, employee and contractor
employee’s suggestions are sought and technically feasible suggestions are
implemented. Employee suggestions reports are monitored. Providing
suggestions are the part of employees Key performance indicators.
Closeout Status
YEAR Repo close Repo close Repo close Repo Close Repo close Repo close Repo close Repo close Repo close
2011 rted d rted d rted d rted d rted d rted d rted d rted d rted d
30
Near
miss 7 6 11 10 6 5 9 9 6 5 4 4 7 4 7 5 8 6
Hazards
Reported 6 6 4 2 5 4 5 5 1 0 4 4 7 2 8 2 2 0
Rubber
Tube
Damage
Complain
ts 4 4 13 13 8 8 0 0 0 0 5 5 6 6 14 14 14 14
100 mbar
damages 53 53 28 28 32 32 40 40 18 18 28 28 28 28 22 22 23 23
Site
Hazard(
MGL TPI
&
Contract
or
Related) 1929 1929 2501 2501 2827 2827 3093 3093 3326 3326 3721 3721 3995 3995 4058 4058 4173 4173
Observation:
Recommendation:
Above all recommendations follow by everyone will minimize the accident, hazard
in the working area.
31
CHAPTER 11
House Keeping
MGL believes good housekeeping is one of the surest ways to identify a safe
workplace. One can tell how workers feel about safety just by looking at their
housekeeping practices. Good housekeeping is not the result of cleaning up once
a week or even once a day. Its the result of keeping cleaned-up all the time. It’s
an essential factor in a good safety program, promoting safety, health,
production, and morale.
At MGL housekeeping is responsibility of every ones. Clean work areas and aisles
help eliminate tripping hazards. Respecting "wet floor" signs and immediately
cleaning up spills prevents slipping injuries. Keeping storage areas uncluttered
reduces the chances of disease and fire as well as slips, trips, and falls.
Accumulated debris can cause fires, and clutter slows movement of personnel
and equipment during fires. MGL ensures good house keeping practices by
considering all the above factors.
In fact the MGL facilities are designed with good layout and this is also helping in
maintaining good house keeping practices.
MGL also follows other housekeeping practices include keeping tools and
equipment clean and in good shape or keeping hoses and cables or wires
bundled when not in use. MGL advises its employees that be aware of open
cabinet drawers, electric wires, sharp corners or protruding nails. To ensure good
hose keeping hazard reporting practice is in place. Either correct the unsafe
condition if you are able and it is safe to do so, or notify the person responsible
for overall maintenance that something should be done.
32
How a workplace looks makes an impression on employees and visitors alike. A
visitor’s first impression of a business is important because that image affects
the amount of business it does. Good housekeeping goes hand-in-hand with good
public relations. It projects order, care, and pride.
Besides preventing accidents and injuries, good housekeeping saves space, time,
and materials. When a workplace is clean, orderly, and free of obstruction; work
can get done safely and properly. Workers feel better, think better, do better
work, and increase the quantity and quality of their work
Photo graph showing neat & clean premises and pedestrian path at on of
the MGL facilities showing good layout and house keeping.
Machines:
Noise:
The acoustic enclosures are good enough to bring down the noise levels as low as
ambient level. MGL conducts noise monitoring monthly at all CGS (City Gas
33
Station) and MGL offices @ 60-65 db. Noise measurement is carried out at the
0.5m distance from the fence of the retail outlet. It was observed that noise level
are well below the norms.
Illumination:
CHAPTER 12
Ergonomics
The term "ergonomics" is derived from two Greek words: "ergon," meaning work,
and "nomoi," meaning natural laws.
Ergonomists aim to provide working conditions which are well above the
minimum required to ensure health and safety of the workforce. Thus, in
achieving a comfortable, productive and satisfying office environment, any
musculoskeletal complaints would also be minimized. To design such an
environment, it is necessary to consider not only furniture and equipment, but
also the job designs, lighting, noise, air quality, office landscaping and personal
space. This paper concentrates on furniture and equipment which both have a
strong influence on postures.
34
Figure. Some critical dimensions for chair design.
Seat Width:
The checklists recommend a minimum width of 450mm. This gives a little extra
space above the 97.5th percentile hip width for British women of 445mm. The
97.5th percentile hip width for British males is less than this (417mm).
Seat Slope:
Related to seat height is the slope from front to back of the seat. Since the seat
height should be selected to minimize pressure on the thighs, the backward slope
should be minimized, and the front edge well rounded. The option of making the
slope adjustable is increasingly available on adjustable office chairs.
Unfortunately, this results in the possibility of the slope being left at a setting
where there is a substantial backward slope. This could lead to excessive
pressure on the thighs and an impairment of blood circulation to the legs. For
this reason, a maximum backward slope of 5 degrees is recommended.
All work activities should permit the worker to adopt several different, but
equally healthy and safe postures.
Where muscular force has to be exerted it should be done by the largest
appropriate muscle groups available.
Work activities should be performed with the joints at about mid-point of
their range of movement. This applies particularly to the head, trunk, and
upper limbs.
35
Office Ergonomics:
36
9. Employees should be made aware of the different signs and symptoms of
all kinds of discomforts caused by continuous computer usage so that they
can identify these from the beginning and treat with appropriate
medications.
10. Training on the methods of using and adjusting all the computer
components correctly as well as the environmental factors should be
imparted.
Ventilation Ergonomics:
Feasible Solutions:
1. If the air conditioning vents are not designed to redirect the flow of air
away from the underneath areas of the vents, desks, chairs, and other
office furniture in these areas should not b placed.
2. Diffusers or blocks should be used in order to redirect and mix airflows
from ventilation systems.
3. Airflow rates must be maintained within three and six inches per second
(7.5 and 15 centimeters per second). In fact, these airflow rates are barely
noticeable or not noticeable at all.
4. The relative humidity of the air should be maintained between 30% and
60%.
5. During hot season, maintain the ambient indoor temperature between 68°
and 74° F (20° and 23.5° C). During cold season, the recommended
temperature is between 73° and 78° F (23° and 26° C).
37
Probable Risks:
The users will have discomfort and several health problems if they are exposed to
chemicals, volatile organic compounds (VOCs), ozone, and other particles from
computers and their peripherals (say, laser printers).
Feasible Solutions:
All the industries which are covered under the provisions of Water (Prevention &
control of Pollution) Act, 1974 and Air (Prevention & control of Pollution) Act,
1981 are required to obtain ‘consent to establish’ for establishment of any new
unit or before commencing construction / laying of pipelines and ‘ Consent to
Operate’ before commencing supplies of the products in the public premises.
The units after establishment are required to obtain ‘consent to operate’ before
commencing commercial production and supplies. Consent to operate is also
required for all the existing units which are covered under the provisions of
Water (Prevention & control of Pollution) Act, 1974 and Air (Prevention & control
of Pollution) Act, 1981. Consent to establish is one time and required only at the
time of establishment of new unit or before carrying out expansion
/modernization in the existing unit whereas consent to operate is granted for a
specific period and needs to be got renewed every time after expiry.
For obtaining NOC from MPCB, the organizations are required to apply in
prescribed application form and also required to attach some documents as
prescribed by the MPCB
After detailed scrutiny of the applications by the regional offices of the MPCB the
application is forwarded to head quarter of the MPCB wherein deliberations are
held in the clearance committee meeting (normally held once in three months)
and the proposal is either cleared or rejected. Once the proposal is cleared
initially Consent to Establish is granted to the industry which is valid for a period
38
of three years and within these three years the organization has to initiate the
construction of the project. Once the construction phase is complete, before
starting actual supplies of the product the industry has to obtain Consent to
operate in a similar fashion following the steps as in case of Consent to
Establish.
MGL is accredited with ISO 14001 certificate since Nov. 2003. As per the
Hazardous waste (Management & Handling) rules 1989 as amended in May 2003
vide notification dated 20th May, 2003 by Ministry of Environment and Forests,
New Delhi, the following waste is considered under hazardous waste category:
Empty Ethyl Mercaptan Drums
Used Filters from Compressors
Activated Carbon.
Cotton waste containing waste oil
Hazardous wastes generated are mandatory to be stored, treated, transported
and disposed as per the Manufacturing Storage & Import of Hazardous
Chemicals
At MGL also Hazardous waste are stored in the designated area. Generating dept
files in the relevant form for storing the hazardous material. At the time of
disposal of Hazardous waste to M/s Mumbai Waste Management form 13 is filled
and copy is sent to MPCB also.
39
CHAPTER 13
PPE should always be regarded as the ‘last resort’ to protect against risks to
safety and health; engineering controls and safe systems of work should always
be considered first.
40
Real situation at site:
MGL also install G.I, ERW pipes on buildings, towers for domestic connections.
In that process manually handling of pipes, threading, welding, clamping etc
processes involved. For installation of these pipes on buildings & towers, work at
height permit should have been issued by authorised person at site. In this
process PETZL life saver equipment, permanent structure at building terrace,
electrical equipment, PPE like Safety Helmet, Safety Shoes, Gloves, Ear Plugs,
Safety Goggles etc, proper barricades, First aid box, Fire extinguisher, Water
bottle should be checked by site supervisor and site engineer at site. After
inspecting all these equipment work should start.
After laying and installing of Steel, P.E, and G.I./ERW pipe lines, it should
commissioned & tested by site engineer and then charged. After charging the gas
in building our team of workers, supervisor and engineer go to customer house
for installation of meter & copper pipe. In This process bending & soldering of
copper pipe should be done. So they should have to take safety precaution like
wear PPE, cut off gas supply, only skill person should do work etc. After this take
testing of copper pipe, meter, regulator by water manometer. Then only connect
the rubber tube to appliance. After completion of work, supervisor give demo to
customer of using/handling the gas and make them satisfied
41
CHAPTER 14
42
hazards created in the vicinity of the workplace by work-related activities
under the control of MGL;
infrastructure, equipment and materials at the workplace, whether
provided by M G L or others;
changes or proposed changes in M G L, its activities, or materials;
modifications to the OH&S management system, including temporary
changes, and their impacts on operations, processes, and activities;
the design of work areas, processes, installations, machinery/equipment,
operating procedures and work organization, including their adaptation to
human capabilities
Risk assessment is done by using a 5*5 matrix for Impact Vs Severity. The
ratings range from 1 to 5 the impacts & severity and is described in the table
below:
The event is expected to occur in most circumstances, incident could happen daily to
Almost certain 5
weekly
The event will probably occur in most circumstances, incident could happen weekly to
Most likely 4
monthly
The event will probably should occur at some time, incident could happen monthly to
Likely 3
yearly
43
All such unacceptable risks are controlled by applying the principles given
below:
Prioritize the risks and first control those, which have a major
risk impact on MGL
Deal with Major risks in a structured and systematic manner so
that the actions taken are legally defensible
Complicated systems are avoided when drawing up control
measures. Pragmatism is kept in mind
Staff is invariably involved, in order to make sure that what is
proposed will work in practice and will not introduce any new
hazards
The hazards posing legal concern are assumed to be not acceptable and hence
the corresponding control measures in the form of all the necessary compliance
of legal aspects is maintained thoroughly for e.g. Periodic Testing of Cascades
etc…and all such activities bearing legal concerns.
When determining controls, or considering changes to existing controls,
consideration is given to reduce the risks according to the following hierarchy:
a) Elimination;
b) Substitution;
c) Engineering controls;
The additional risk control measures drawn up to reduce the risk are recorded
in a suitable Format. These are set as OH & S Objectives based on which O H
& S Management programmes, Operational Control Procedures and Emergency
plans are drawn up as appropriate to closely monitor the additional control
measures.
Thereafter fresh risk assessment is carried out in the same manner as done
earlier and the controlled level of risk calculated to verify whether the
measures taken have now brought the risk rating within the acceptable limit.
CHAPTER 15
44
Work Permit Systems
Prior to carrying out any work, the person in charge of the site must carry out a
Risk Assessment to satisfy himself or herself that all reasonable and practicable
precautions have been taken to minimize risks or eradicate any potential
hazards.
Working at height.
Activities where work on the online gas flow line is required including
maintenance activities on the pipelines and in CNG Compressor
Stations
Other work where a risk assessment identifies the need for a Permit to
Work.
45
Types of Work Permits Followed in MGL:
1. Confined Space Entry Work permit.
2. Testing Charging and Commissioning.
3. Permit to Work at Height.
4. Hot Work Permit.
5. Permit to Work for Gas / Electrical Isolation for CNG Station.
6. Electrical Work Permit
Ref Annexure II for Formats of above mentioned work permits
The raising, issue and approval of Permits shall be organized such that due time
is available to inform all other (possibly) affected persons, e.g. construction
management, displaying on main and local notice boards.
The Authorizing Person should issue the Permit to Work on site at the location of
the proposed works following a personal inspection.
The Authorizing Person shall visit site (when issuing a Permit to Work) to confirm
that the conditions of the Permit can be met.
They should brief the Competent Person, advise any other persons (on or off site)
who may be affected accordingly and satisfy themselves that the work can
proceed in a safe manner.
The initial period of validity of the Permit to Work shall not exceed 7 days, and
the permit will be issued and signed off daily.
Should a Permit to Work be required beyond 7 days, then the site shall be
revisited by the Authorizing Person or their representative to assess and confirm
that the Permit conditions have NOT changed.
The pink copy of the permit will remain with the Competent / Issuing
department / Person.
The yellow copy will be issued to the agency / person carrying out the work and
should be displayed at site at all times
46
The filled in white copy shall remain in the book with the Authorizing Person and
the completed books to be returned to the HSSE department for retention.
The HSSE department shall issue the new book of the work permit only after
receipt of the completed filled in book issued earlier for the purpose.
Simultaneously all the work permit entries are to be made in the WPTS (Work
Permit Tracking System) before the execution of the work.
Issued Permits shall be displayed at the relevant worksite and within the Permit
Office and/or Control Room.
The PTW, certificates and risk assessments are retained at site by the Issuing
Authority for at least 30 days after completion and then archived for a specified
period of two years to enable an effective monitoring and audit process.
Audits and regular monitoring of the Permit to Work procedures shall be carried
out in accordance with MGL’s audit plan.
47
CHAPTER 16
Various fire prevention and protection equipment provided in MGL various office
and City Gas station
a) Fire Hydrant
b) Fire Alarm system
c) CO2 Flooding system/FM 200 system
d) Fire extinguisher
e) Smoke Detector
f) Emergency Hooter
g) Fire Extinguisher
h) First Aid Box
2. Emergency control room will inform & take action as per Emergency
Preparedness plan.
5. Ensure the operational people on site are required with necessary PPE.
6. Assess the situation to see any probable loss to life & property.
7. Isolate the section. Close up-stream downstream valves and all branch
Valves from the section
8. In conjunction with Mumbai Fire Brigade cool the nearby affected area by
spraying water and if required extinguish the fire.
9. Carry out necessary rectification work as per 1.2 & 1.3 procedure
10. Inform Emergency Control room and HOD about the completion of
Emergency.
11. Collect solid wastes and other scraps and deposit it in CGS scrape yard.
Confirm emergency is over/complete and inform it to emergency control
room.
48
ACTIONS TO BE TAKEN IN CASE OF FIRE IN ODARANT (ETHYL MERCAPTAN)
AREA:
2. Emergency control room will inform & take action as per Emergency.
5. Ensure the operational people on site are required with necessary PPE, and
breathing apparatus.
7. Use ABC type fire extinguishers & try to extinguish the fire
2. Control room to inform and take action as per emergency response plane.
6. Extinguish the fire by using fire extinguishers. (use co2 in case of fire in
electrical panel and use DCP/ABC powder in case of fire in compressor)
7. once the fire is fully extinguished then collect the extinguish powder and
deposit in designated location for disposal
8. Segregate the fire waste in to hazardous and non hazardous waste and store it
accordingly in the demarcated bins.
2. Control room to inform and take action as per emergency response plane.
5. Extinguish the fire by using fire extinguishers. (use co2 in case of fire in
electrical panel and use DCP/ABC powder in case of fire in d.g.set)
49
6. once the fire is fully extinguished then collect the extinguish powder and
deposit in designated location for disposal
7. Segregate the fire waste in to hazardous and non hazardous waste and store it
accordingly in the demarcated bins.
8. dispose the extinguish powder to Mumbai waste management ltd. and fill form
no. 3,8, & 9 as per hazardous waste management rule 1989
2 Control room to inform and take action as per emergency response plan.
5 Once the fire is fully extinguished then collect the extinguish powder and
deposited in designated location for disposal.
6 Segregate the fire waste in to hazardous and non hazardous waste and store it
accordingly in the demarcated bins.
7 Dispose the extinguish powder to Mumbai waste management ltd. and fill
form no. 3, 8, & 9 as per hazardous waste management rule 1989.
2. Control room to inform and take action as per emergency response plan.
5. Extinguish the fire by using DCP/ABC type fire extinguishers. once the fire is
fully extinguished then collect the extinguish powder and deposit in
designated location for disposal
6. Segregate the fire waste in to hazardous and non hazardous waste and store it
accordingly in the demarcated bins.
Dispose the extinguish powder to Mumbai waste management ltd. and fill form
no. 3,8, & 9 as per hazardous waste management rule 1989.
50
CHAPTER 17
MGL has produced an ERP for all the foreseeable incidents that may occur in
undertaking its operations. Where relevant they are written in English and
Hindi.
Hazard Particulars
1 Fire & Explosions All types of fires, smoking insulation & auto ignition
51
Off site disaster /emergency situations:
Sr.
Hazard Particulars
No.
All types of fires, smoking insulation & auto
1 Fire & Explosions ignition
Leakage of natural gas due to damage to the
Major leakage (4 high pressure Steel line & medium pressure
2
bar & 19 bar) polyethylene line by third party excavation
work.
Rupture of safety
3 Gas release due to rupture of safety disc.
disc.
A jet flame hitting humans will cause fatality due to high thermal radiations and
plant / material can suffer secondary damage due to impinging jet flame. A
colliding jet immediately loses its momentum with loss of air entrainment. The
vapour cloud will then begin to disperse downwind. Te dispersion phenomena
largely depends upon weather stability class and wind speed apart from other
factors such as ground roughness factor, terrain etc. there can therefore be two
outcome cases due to accidental gas release.
Turbulent free jet (non – colliding)
Turbulent free jet (colliding) followed by dispersion
The dispersing vapour cloud if ignited will result in a) flash fire b) vapour cloud
explosion with overpressure. Methane or methane rich mixtures have low reactivity.
From experience it is known that the vapour cloud explosion overpressure is not
likely to exceed 0.1 bar for semi – confined explosions.
For over ground mains in the open areas the likelihood is that of turbulent free jet
(non – colliding) will have limited consequences. In case of buried pipelines the
overburden will get undermined in course of time (depending upon the leak size).
Nevertheless an unobstructed jet is unlikely. The entire release will emerge as a
dispersing vapour cloud.
In case of a delayed ignition of the dispersing vapour cloud two outcomes are likely.
In one case the result is a flash fire without overpressure. Everyone in the burning
cloud will die due to extremely high thermal load, though the duration of flash fire
may be a fraction of one second. No adverse outcome occurs outside the cloud. In
the second case a vapour cloud explosion occurs with overpressure. For this to
happen partial confinement in the cloud path is necessary. As mentioned earlier for
methane rich mixture the maximum overpressure that can be generated is 0.1 bar.
At such an overpressure 10% of the buildings are likely to collapse and one in eight
persons in the buildings are likely to suffer fatality. In other words for 0.1 bar
overpressure 1% fatality may result. For various vapour cloud explosion scenarios in
this study 0.1 bar overpressure circles have been plotted. Within the 0.1 bar
overpressure circle people are likely to suffer injuries due to falling debris that would
need rescue and medical treatment services.
53
Mock Drill Plan 2013:
CHAPTER 18
Safety of Contractors/Visitors
54
DO’S:
1) In case of an emergency don’t panic.
2) Assemble near assembly point, back side of driver’s cabin Area floor wardens will
escort you towards the same.
3) Safety shoes, helmet & appropriate PPE in designated areas are mandatory inside
the plant premises excluding the administrative building.
4) Maximum speed limit inside factory premises is 10 km/hr.
5) Report any incident, hazard/near miss or safety suggestion through the ‘SEE
THINK DO’ card.
6) If you discover the fire, sound the alarm-break the glass on the nearest fire alarm
call point. [Every Monday 1030 hours fire alarm testing. Don’t panic.]
7) Follow instruction of the security or floor wardens in case of any emergency.
DONT’S:
1) No smoking in CGS office near CGS premises
2) Switch off the mobile phone when entering the CNG filling area.
3) Do not use lift in case of fire/any emergency use the staircase.
4) Visitors not allowed in the plant area and the CNG compressor area classified as
restricted area. Please do not enter the premises without an escort from MGL.
5) Photography is not permitted inside the plant premises for the visitors without
permission from the plant in charge.
6) Don’t touch any pipeline or equipment without permission.
CHAPTER 19
55
FINDINGS:
1. Zhoola used for work at height job which is not quite technical.
2. Communication about rescue method is missing at sites.
3. Nose mask not used during welding activity in trench at steel site & carrying
out welding activity in well ventilated area.
4. Sufficient area information signage not available in City Gas.
5. Workers are not quite comfortable in wearing helmet.
RECOMENDATIONS:
1. Work at height activity is carried out at MGL site for providing the PNG
Supply in the residential area. At present Practice Zhoola is used by the
plumber or worker for working in such condition. Zhoola is a kind of plank
tied with ropes at all the four ends and is then hanged from top of the roof
where is one side of the rope is tied with the permanent structure Though
Zhoola is safe still some alternative source can be opted which is more safer
and economical. Alternative sources could be:
a. Scissor Lift :
b. Mobile Platform
c. Scaffolds etc
2. Onsite awareness session related to rescue methods need to be conducted at
sites also it can be included in the training module which is imparted at all
levels.
a. During Excavation activity trench collapse may occur which can lead to
injury of personal working at site. In such cases site personal must be
aware of the measures to be adopted for rescuing the personnel, he
should know the proper chain of communication to inform about the
incident.
b. During work at height tools may fall on person which lead to any body
injury. In such situation personnel at site should know the right
methods of evacuation from site at safe place.
56
from harmful fumes and welding should be carried out in welding hoods which
has good quality of ventilation and exhaust system.
4. An information sign is a very legibly printed and very noticeable placard that
informs people of the purpose of an object, or gives them instruction on the use of
something. Visitors and contract employees visit MGL office premises on day to
day basis as they are new they may not be aware of some of the places like
assembly point and other facilities. Display of various signage’s are helpful to
identify the require location easily.
5. A helmet is a form of protective gear worn on the head to protect it from injuries.
There are various type of hazards present at sites during construction and
process activities, helmet protect form Impact from falling or flying objects, Head
bumping or laceration, Chemical drips or splashes, so use of helmet is mandatory
in MGL premises.Though helmets are being used at MGL sites but it was found
that few workers are not comfortable in working while wearing the helmets.
CHAPTER 20
CONCLUSION
57
We have prepared this project after the study of safety requirements in gas
distribution prescribed by various legal agencies have found that gas distribution
industry have lot of scope for the improvement approved on account of various safety
requirement.
The main hazards to deal in a gas distribution industry are Leakage of pressurised
gas, Spillage of ethyl mercaptan, ground excavation, lifting operation, Confines space
job, Work at height and driving.
Thus these are the major hazards carried with distribution of gas; also we come
across various small accidents occurring due to unsafe conditions and unsafe acts.
Thus we should provide safe working conditions and proper training for the
employees and contractor employees to avoid and prevent any incident in the
industry to run the industry with full efficiency.
58
CHAPTER 21
Annexure – I
PPE Specifications (Guidance)
60
BS EN 420 or a) General Use.
a) Leather Palm And/or b) Limited Hand
8 Rigger Gloves equivalent– IS
b) Sturdy Fabric. Protection.
6994 (PART 1)
B.S 7028 / BS
EN 166 - 167 - a) Lens Clear Or Dark.
b) Side Shields.
Eye Safety 168 GRADE 2 a) General Dust
9 c) Replaceable Lenses.
Protection Glasses IMPACT or Protection Only.
d) Adjustable Side
equivalent Arms.
– IS 8520
a) Contoured
B.S 7028 / BS fit /
a) Protection against
EN 166 - 167 - adjustable head
chemical
band.
Safety 168 GRADE 1 splashes.
10 b) Wide vision.
Goggles IMPACT or b) Grinding.
c) Discrete ventilation.
equivalent d) PVC or polycarbonate
– IS 8520 lenses.
PERSONNEL PROTECTIVE EQUIPMENT SPECIFICTIONS
PERSONNEL
PROTECTIVE STANDARD DESCRIPTIN TYPES OF USE
EQUIPMENT
B.S 7028 / BS
EN 166 - 167 – a) Lightweight.
168 GRADE 2 b) Made a) Total Eye and
In Acetate,
Face Protection.
11 Face Shields IMPACT or Polycarbonate
b) Handling
equivalent c) Can Be Secured To
Chemicals.
– IS 8521 Front Of Hard hats
(PART 1)
B.S 1542 a) Fiber-glass shields.
CLEAR LENS b) Hand held or helmet
mounted. a) Welding, cutting
GRADE 1
Welding c) Lens holders and etc.
12 IMPACT or
Shields welding filters are
equivalent supplied depending
- IS 8521 (PART on the job
2) requirement.
13 Hearing Ear Muffs BS EN 352 - 1 a) Consist of 2 rigid a) High level of
Protection or equivalent cups fitted with hearing
– IS 8520 absorbent material. protection.
b) Fit to the head by b) Check the
means of soft rings manufacturer
(ear seals). attenuation chart
c) Seals must be foam for the level of
filled. attenuation and
d) Ear defenders must the standard
be compatible with deviation.
the hard hats in use c) Stated
attenuation will
be achieved only
if equipment
properly fitted
and maintained.
61
a) Good level of
hearing
a) Foam ear plugs
protection.
which are
b) Check the
compressed in order
manufacturer
to fit into the ear and
attenuation chart
expand to maximize
for the level of
protection.
attenuation and
BS EN 352 - 2 b) Molded pre-shaped
the standard
14 Ear Plugs or equivalent plugs of rubber for
deviation.
– IS 8520 insertion into the ear
c) Stated
canal.
attenuation will
c) May be fitted with a
be achieved only
cord.
if equipment
d) Exist also as ear caps
properly fitted
(plugs fitted with thin
and maintained.
plastic band).
a) Disposable
respirators are made
from filtering
materials and are at
BS EN 149 or a negative pressure.
equivalent b) Half mask respirators a) To be used only if
Respirator – IS 8522 are designed to cover sufficient oxygen
nose and mouth. is present.
y (CHEMICAL
c) Full face piece b) Protection against
15 Protective Respirators CARTRIDGE);
respirators are a range of dust,
Equipmen IS 8523 designed to cover gases and vapors.
t (CANISTER nose, mouth and
TYPE –GAS eyes.
MASKS) d) It is imperative that
the correct filter
medium is used for
the particular
contaminant.
PERSONNEL PROTECTIVE EQUIPMENT SPECIFICTIONS
PERSONNEL
PROTECTIVE STANDARD DESCRIPTIN TYPES OF USE
EQUIPMENT
a) Escape Packs (5
a) It consists of a face to 15 minutes)
piece or a hood by are used only to
BS 4667 / BS which the wearer can leave the work
breathe compressed place in case of
EN 137 / BS
Breathing uncontaminated air. an emergency.
4275 or
Apparatus b) Self contained BA’s b) BA’s with over 30
equivalent include air cylinders minutes capacity
– IS 9623 to be carried on the and/or an airline
back. link may be used
for work or for
rescue purposes.
62
a) Pole belts comprising
an adjustable body a) Safety belts limit
belt combined with a the distance of
pole strap, which any fall thereby
may be integral or minimizing the
adjustable. risk of injury.
B.S EN 354 or b) General purpose b) It is very
16 Safety Belts equivalent belts which are important that
– IS:3521 provided with a line whenever a safety
or a lanyard to be belt is provided
attached to the there is an
structure allowing a effective mean of
free fall of fixing it to the
respectively 600 mm structure.
and 1.2 m.
a) Safety harness
Fall limits the
Arrestor distance of any
fall thereby
a) Chest harnesses, minimizing the
comprising a chest risk of injury.
belt and shoulders b) It is very
straps fitted with a important that
lanyard, which will whenever a safety
B.S EN 361 or limit the fall to 2 m harness is
Safety
17 equivalent or less. provided there is
Harness b) General purpose an effective
- IS:3521
harness with means of fixing it
shoulder and crutch to the structure.
straps and lanyard c) A safety harness
limiting the fall to 2 gives greater
m or less. protection than a
safety belt in the
event of a fall and
is therefore
preferable.