Rencana Kerja 26 Agustus SD 25 September

This document contains the work plan of the Civil Engineering division for August to September 2018. It includes tasks such as project surveys, drawings, cost calculations, quality policies, fabrication and installation of a recenerator, fence and foundation repairs, creating a materials and work price database, civil engineering software trainings, and weekly/monthly reports. The schedule assigns tasks to specific dates and notes priorities, regular work, and holidays.

Uploaded by

addin wokatuba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
68 views2 pages

Rencana Kerja 26 Agustus SD 25 September

This document contains the work plan of the Civil Engineering division for August to September 2018. It includes tasks such as project surveys, drawings, cost calculations, quality policies, fabrication and installation of a recenerator, fence and foundation repairs, creating a materials and work price database, civil engineering software trainings, and weekly/monthly reports. The schedule assigns tasks to specific dates and notes priorities, regular work, and holidays.

Uploaded by

addin wokatuba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

RENCANA KERJA DIVISI CIVIL ENGINEERING

PERIODE : 26 AGUSTUS sd 25 SEPTEMBER 2018

AGUSTUS SEPTEMBER
NO URAIAN PEKERJAAN Mg Sn Sl Rb Km Jt Sb Mg Sn Sl Rb Km Jt Sb Mg Sn Sl Rb Km Jt Sb Mg Sn Sl Rb

26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

A TECHNICAL & DOCUMENT SUPPORT


A.1 Business Development
A.1.1 Project Survey & Analisis Support
A.1.2 Drawing Support
A.1.3 Engineering Calculation Support
A.1.4 Cost Calculation Support

A.2 Manager Repensetatif


A.2.1 Internal Auidit Support
A.2.2 Back Up Data Support

B MATERI PERSENTASI PT. WOKATUBA INDONESIA


B.1 Melengkapi Kekurangan Materi
B.1.1 Kebijakan Mutu Engineering
B.1.2 Kebijakan Mutu Procurement
B.1.3 Kebijakan Mutu Contruction
B.1.4 Kebijakan Mutu Instalation
B.2 Apporval

C DESIGN & BUILD/FABRICATION


C.1 RECERENATOR
C.1.1 Detail Drawing for Fabrication
C.1.2 Fabrication & Setting
C.1.2.1 Furnace Chamber (Support & Accessories)
C.1.2.2 Top Cone (Support & Accessories)
C.1.2.3 Pipe Spooling (Support & Accessories)
C.1.2.4 Chimney (Support & Accessories)
C.1.2.5 Water Storage Tank (Support & Accessories)

C.1.3 Installation On Site


C.1.3.1 Peperation Tool, Equipment & Man Power
C.1.3.2 Mob Tool, Equipment & Man Power
C.1.3.3 Installation On Site
C.1.3.4 Finishing & Cleaning
C.1.3.5 D Mob Tool, Equipment & Man Power

C.2 SETIA DHRAMA PROJECT


C.2.1 Perbaikan & Rekondisi Kerusakan Pagar Beton
C.2.2 Perbaikan & Rekondisi Kerusakan Pagar Beton & Pondasi Batu Kali

D PEMBUATAN DATA BASE


D.1 Harga Satuan Material Sipil & Struktur Baja
D.2 Harga Satuan Pelaksanaan Pekerjaan Sipi & Struktur
D.3 Koefesien Pelaksanaan Pekerjaan Sipil & Struktur
D.4 Analisa Harga Satuan Pekerjaan Sipil & Struktur (Otomatis)

E PELATIHAN APLIKASI SOFTWARE SIPIL


E.1 SAP 2000
E.2 ETAB 2016

F REPORT
F.1 Weekly Report
F.2 Monthly Report (Per Tanggal 26 Setiap Bulannya)

Note :
: Hari Minggu Dibuat Oleh, Diperiksa Oleh,
: Hari Libur Nasional
: Prioritas (Diutamakan jika ada Permintaan dari BD & MR)
: Rencana Kerja Leguler
Ade Yuhana Bambang Supriadi
Civil Engineer Direktur Oprational
SI CIVIL ENGINEERING
sd 25 SEPTEMBER 2018

SEPTEMBER
Km Jt Sb Mg Sn Sl

20 21 22 23 24 25

Disetujui Oleh,

Saebani
Direktur Utama