'SEPCO
WHER
Master Gas System Expansion - Phase |
70 Saudi Arameo Tranemital No. NGSET-SEP-SA-1804 ]
arty, Saleh Al Wade! Transmittal Date ‘AUGUST 08, 2016
FROM Me, Wang Yuanhui Response Required ves
| contract Wo. 6600035463 (IK) |
ah Tesued For
TiRevew MApproval —_Clinfornaton! Records
SiGNEDBY |
CONTRACTOR Representative Purchase OFinal Doc. — C1 Construetion (2 wH 5 WOH),
Teta No, of Pages (nelaing Wanamita page 10 1
1 a )
reas Discipline
Gawac CMOPROCUREMENT | CIELECTRICAL | MIPIPING | CIMECHANICAL | Cl INSTRUMENTATION
HSE COPLANNING CinteRFAce | Ciprocess | OTELecom Ccimystructure |
CIGENERAL |DWVACTPLUMBING [CPPEUNE —[CsAFETY | Cerovect | D ARCHITECTURAL
SUBJEGT. | PIPING INTERNAL CLEANING PROCEDURE ]
Co Document No. Description Rev. | Doc. Type
+ | sepwcse-cu-souoro: | PIPING INTERNAL CLEANING PROCEDURE 1 | Pro
Originator: KTAQUI
FOR COMPANY
Remarks / Comments (any)
Received By: aR Pate
{> 08 ays-zoig |2
= me)
RECIPIENT RETURN S{GNED COPY
‘& Where approval or construction is required, Please respond (or advice ‘no comment’) within 15 working days of
receipt.
‘No response will be deemed as ‘no comment’.
Page 1 of 1pgnuull gSol! a Master Gas System Expansion — Phase |
‘Saudi Aramco
Bde le z SEPCO Electric Power Construction Corporation
Contract No: 6600035463 (Ik)
Document No: SEP-MGSE-CM-SCM-0101
ing Internal Cleaning Procedure
B= ety WT,
Pradish kumar
1 | o8/o82016 | LiDongyang | Dong Shibiao | Ahmad | ‘GA Nanager | Project
QC Manager
Shahbaz | radish kumar | “Ma Lixing
| 0 | 26/06/2016 | LiDongyang | Dong Shibiao | Ahmad
coc Manager | CA Manager | Project Manager
Checked by | Reviewed by Verified by
Approved by
Rev.| Date | Propared bySEPCO DOCUMENT NAME SEP-MGSE-CM-SCM-0101
WB Piping Internal Cleaning Procedure pevNe i
PAGE 2019
TABLE OF CONTENTS
1 Purpose...
Scope ..
References
Responsibilities
aoe on
General Requirements.
o
Procedure.
7 Inspection & Quality Records ..
8 Safety Requirements.
‘SEPCO Electric Power Construction CorporationSEPCO DOCUMENT NAME SEP-MGSE-CM-SCM-0101
WFR BIE | rcrnara ccomnperocoone | FeNO |
PAGE, 3of9
1 Purpose
The purpose of this document is to establish, implement and maintain a quality
work instruction/procedure of internal cleaning for newly construction piping in
accordance with applicable Saudi Aramco standard.
2 Scope
This document outlines the procedures, which shall be used for piping on
MGSE- Phase 1 project site at BGCS # 3 and BGCS # 5 during pipe installation
and prior to hydro test.
3. References
SAEP-388 Cleaning of Pipelines.
SAEP-327 Disposal of Wastewater from Cleaning, Flushing & Dewatering
from Pipelines and Vessels
SAES-A-004 — General Requirements for Pressure Testing
SAES-A-007 Hydrostatic Testing Fluids and Lay-Up Procedures.
SAES-L-150 Pressure Testing of Plant Piping and Pipelines
SAES-L-350 Construction of Plant Piping.
SAES-L-388 Pipelines Cleanliness Requirements for Hydrocarbon Services.
SATIP-A-004-01 Pneumatic Pressure Testing
SATIP-A-004-02 Hydrostatic Testing of on-Plot Piping
SATIP-A-004-03 Hydrostatic Testing of Pipelines
SATIP-L-350-01 On-plot Metallic Piping Installation
SATIP-L-450-03 Cross Country Above Ground Pipeline
SATIP-L-450-04 Cross Country Buried Pipeline
SAIC-L-2017 Piping / Equipment Internal Cleaning Inpection
GI-0002.100 Work Permit System.
4 Responsibilities
The Contractor is responsible for the overall cleaning and dry out activities of
new plant piping.
‘SEPCO Electric Power Construction CorporationSEPCO DOCUMENT NAME ‘'SEP-MGSE-CM-SCM-0101
Whee Piping Internal Cleaning Procedure BEVNO i
PAGE 409
4.1 Project Manager
Ensure compliance by all parties to this procedure, the project Quality
Assurance Manual, inspection and test plan and relevant customer
specification and drawings.
4.2 Construction Manager
Ensure compliance by all craftsmen of content of this procedure and
project quality plan.
4.3 Piping cleaning Supervisor
Ensure compliance by all pipe fitters, fabricators and other associated
craftsmen to this procedure Quality plan, Ensure relevant permits are
raised and received by authorized personnel prior to execution of the work.
4.4 Quality Control Supervisor
Review all project specific plant piping cleaning procedures prior to
submittal for approval, the document are complete where necessary, and
the appropriate inspection and testing personnel are available.
4.5 Quality Control Inspector
Conduct inspection as per this procedure and project quality control
inspection plan. Ensure all inspection records are placed in the applicable
SAIC & SATR.
4.6 Safety Supervisor
Ensure relevant safety precautions are in operation and work permits
have been obtained. Barriers and warning sign are post where necessary.
General Requirements :
‘As general requirement for cleaning fabricated piping in the shop or in the
field, the inside surface of the fabricated piping shall be made free from slag,
loose scale, dirt, construction debris and other foreign matters.
The extent of the system to be flushed will be indicated on the marked-up
P&ID with the following items included:
1) Extent of the system to be flushed.
2) Location of intake and flush out points.
3) Location of isolation blinds and valves.
SEPCO Electric Power Construction CorporationSEPCO DOCUMENT NAME SEP-MGSE-CM-SCM-0101
Whee Piping intemal Cleaning Procedure REVING 1
PAGE Soo
4) Temporary piping and strainer, if required,
5) Items of line instruments and others to be removed or isolated.
Operation valves to be set and prepared as per individual flushing scheme in the
field,
The Purpose for carrying out this blowing is:
To remove the slag, loose scale, dirt, construction debris and other foreign
matters.
5.1 Preparation and Precaution
It is necessary to take the following preparations and precautions before
the blowing:
1) Before Blowing, all related lines must be checked to be lined up as per
the marked up P&ID.
2) Temporary piping, suitable blind plates, screen, blow down popping
gaskets etc. are installed in accordance with the marked-up P&lD.
3) All in-line instrumentation like, flow meters, orifice plates, pressure gauge,
etc. are removed or isolated in accordance with the marked-up P&ID.
4) All sensitive equipments to damage during cleaning and flushing of the
piping system shall not be installed and shall be removed if installed prior
to commencing the cleaning process. The list of these equipments shall
be established during early stages of the execution of the project.
Examples of sensitive equipments are: rotating machinery, orifices,
control valves, flow-elements, soft-seated valves, globe valves, etc
(SAES-L-360, Para 14.1)
5) Barricade the area for safety and notify all concerned persons.
5.2 Based on the different operating requirements, working medium, system
loop, site condition and inner surface cleanliness, piping cleaning shall be
conformed in the following different cleaning methods.
1) Laue piping or gas piping whose diameter is larger than 36" is cleaned
manually cleaning, sweep and mop with scrapers, mops, and rags.
2) Gas piping whose diameter less than 12"'s cleaned by air blowing with
compressed air, liquid piping diameter less than 12"s cleaned by water
flushing with raw water.
SEPCO Electric Power Construction CorporationSEPCO DOCUMENT NAME SEP-MGSE-CM-SCM-0101
LWW FR FB FB | PpinginemarcteaningProceewe _|_REV.NO :
PAGE bof
3) Piping which have special requirements shall follow the provision about
pipe cleaning from Equipment manufacturers.
5.3 Confirm pipe support tightly and contentious parts must be reinforced.
5.4 Piping or facilities those disallowed sweeping and cleaning must be isolated.
5.5 The components of pipe system, such as gauges, instrumentation items,
orifice plates, injectors, filter elements, solenoid valves, regulating valves,
relief valves, check valves, etc. will be removed and replaced with
temporary spool pieces for sweeping, blowing and flushing. Subsequent to
completion of piping sweeping, cleaning and inspection the removed
components shall be restored,
6.6 Piping sweeping and cleaning shall follow a sequence that mainline then
branch and finally drainage. Dirty flowed out from piping sweeping and
cleaning shall not reenter the system.
5.7 Piping sweeping and cleaning area shall set restricted area and warning line,
hanging warning signs.
5.9 Restoration
After air blowing, the following restoration work shall be done.
1) All temporary equipment and connections shall be dismantled, and the
related flanges are tightened by using service gasket.
2) Allremoved parts and isolated sections shall be reinstalled,
3) Tag numbers and flow direction of all line instruments shall be checked if
they are in proper position.
4) Caution tag shall be completely removed.
5) After total completion of a Pre-Commissioning System Package, the
System will be completely reinstated with final gaskets as per P&ID and
conformity to P&ID check with punch list (if any) will be done.
6 Procedure
6.1 Utility Systems
1) Water Lines
Equipment which is sensitive to damage during water flushing shall be
removed, blocked off or isolated. A list shall be prepared and be part of the
flushing procedure. Ball valves shall be flushed in fully open position. All
piping systems shall be flushed using high pressure [60.8 mPa (8.8 ksi)
minimum] jet such as rotating hose or rotating nozzle. Below 4", use High
Velocity Water Flushing (HVWF). On systems where high pressure jet
SEPCO Electric Power Construction Corporation