G 52 Pure Steam System Commissioning and Qualification - Sampling Plans
G 52 Pure Steam System Commissioning and Qualification - Sampling Plans
Introduction
This document recommends sampling locations, frequencies, and testing activities
associated with the commissioning and qualification of new installations or major
revisions of Clean/Pure Steam Systems (e.g. the addition of new subloops or other
system wide retrofitting).
This guidance defines the sampling location, frequency, and testing activities utilizing
a risk based approach for supporting the commissioning and qualification for a
clean/pure steam system. The recommended practices are derived from the latest
edition of the ISPE Good Practices Guide “Commissioning and Qualification of
Pharmaceutical Water and Steam Systems”.
Clean Steam is defined to be steam that does not contain any additives (e.g., boiler
additives), 1 is used where the steam and/or condensate have direct contact with
product, and the steam condensate meets USP/EP WFI requirements. In addition,
clean steam that is used for sterilization applications of “porous loads” for
international manufacturing also should meet the requirements of European Standard
EN 285. The USP states that “Pure Steam [Clean] is prepared from suitably pre-
treated source water analogously to either the pre-treatment used for Purified Water or
Water for Injection”.
This guidance does not cover the additional commissioning and qualification activities
associated with other aspects of system validation (e.g., drawing development, system
equipment/component installation/testing activities, cleaning/passivation, monitoring
equipment, etc.). Ongoing operations (i.e. routine monitoring) after qualification
activities are also outside of the scope of this guidance.
Regarding the quality of water feeding the clean steam generator, consider the
requirements for Bacterial Endotoxin Testing (BET) validation studies in order to
assure that there is no Bacterial Endotoxinbeing carried over in the steam during
generation for those applications that have an endotoxin specification.
For example, clean steam that is strictly used for the production of ophthalmic
products or non-sterile products would typically not have defined
bacterial endotoxin specification requirements.
The testing of clean steam systems includes the Generation System and associated
Distribution System piping starting with commissioning activities through the three
phases of qualification studies that is synonymous with high-purity water
systems. 1,2,3,4
Commissioning
Commissioning is defined in the ISPE Good Practice Guide as “a well planned,
documented, and managed engineering approach to the start-up and turnover of
facilities, systems, and equipment to the end-user that results in a safe functional
environment that meets established design requirements and stakeholder
expectations”. Sampling and monitoring of the Generation and Distribution Systems
for Clean Steam Systems during commissioning are considered Good Engineering
Practice. These activities help to define operational and maintenance practices and
procedures that will be challenged later during qualification. 3 The sampling and
testing activities include chemical testing as appropriate for the unit operation with the
maximum acceptable chemical levels of the condensate meeting the applicable
WFI compendial limits as determined by the associated compendial methods.
As for clean steam quality tests, prior to plant usage of the clean steam within
autoclaves for “porous loads” (as defined by the site) for products marketed in
Europe, there needs to be testing of the following quality attributes, with the test
conditions and specifications being listed within
It is important to clarify that these additional steam tests may not be initially required
as part of the installation of a new clean steam system or clean steam generator if the
initial application of clean steam will not involve the use of autoclave sterilization.
This testing may be deferred and documented within appropriate validation
documentation until such time that an autoclave installation and subsequent validation
is planned and connected to the clean steam system.
A Clean Steam quality attribute may be defined as critical based upon the need to
meet specific quality requirements where the quality is not enhanced further by
additional downstream operating steps. For example, conductivity is a critical attribute
that is measured at the outlet of a Clean Steam Generation System (e.g., condensate
outlet of the clean steam generator) for verifying the results meet necessary steam
quality requirements. Sampling the conductivity at this point would occur both during
commissioning and qualification activities. For details regarding the design of a
condensate collection apparatus for testing, refer to European Standard EN 285 –
Sterilization-Steam Sterilizers – Large Sterilizers.
Appendix: