Installation Procedure

This document provides installation procedures for control system equipment for Phase 1 of the Sisi Nubi Fields Development Project. It details the installation of ICON consoles in the Tatun control room, a server cabinet in the instrument technical room, alarm and screen copy printers in the printer room, and an engineering work station in the Tatun control room. Responsibilities, safety requirements, necessary equipment, and the schedule for installations are also outlined.

Uploaded by

didin Muhidin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
384 views

Installation Procedure

This document provides installation procedures for control system equipment for Phase 1 of the Sisi Nubi Fields Development Project. It details the installation of ICON consoles in the Tatun control room, a server cabinet in the instrument technical room, alarm and screen copy printers in the printer room, and an engineering work station in the Tatun control room. Responsibilities, safety requirements, necessary equipment, and the schedule for installations are also outlined.

Uploaded by

didin Muhidin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 42

SISI NUBI FIELDS DEVELOPMENT PROJECT – PHASE 1

CONTRACT SN1 / EPSC 3

SN1-OCS-01, SN1-OCS-02 & SN1-ER-6204


INSTALLATION PROCEDURE

CLASS 1

B 24-Nov-06 OBO OBO YTA Approved

A 17 Nov 2006 OBO OBO YTA Issued for comments

DATE BY CHECK APPR APPR SPEC REPS


REV DESCRIPTION
COMPANY
SUBCONTRACTOR CONTRACTOR APPROVAL

STATUS CODE : A = Issued for comments – B = Issued for approval – C = Approved – D = As Built

TOTAL OR PARTIAL REPRODUCTION AND/ OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN


WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER

SISI NUBI FIELDS DEVELOPMENT PROJECT–PHASE 1


CONTRACT SN1 / EPSC 3 PT NISCONI
A565703-RP-002 Rev Status
Document Number
B C
SN1-62-022-302-P
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page2 - 24

TABULATION OF REVISED PAGES

SHEET REVISIONS SHEET REVISIONS


A B C D E F G H A B C D E F G H
1 X X 51 X
2 X X 52 X
3 X 53 X
4 X 54 X
5 X 55 X
6 X 56 X
7 X 57 X
8 X 58 X
9 X X 59 X
10 X X 60 X
11 X 61 X
12 X 62 X
13 X 63 X
14 X X 64 X
15 X 65 X
16 X 66 X
17 X 67 X
18 X X 68 X
19 X 79 X
20 X X 70 X
21 X 71 X
22 X 72
23 X 73
24 X 74
25 X 75
26 X 76
27 X 77
28 X 78
29 X 79
30 X 80
31 X 81
32 X 82
33 X 83
34 X 84
35 X 85
36 X 86
37 X 87
38 X 88
39 X 89
40 X 90
41 X 91
42 X 92
43 X 93
44 X 94
45 X 95
46 X 96
47 X 97
48 X 98
49 X 99
50 X 100

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page3 - 24

TABLE OF CONTENTS
1. INTRODUCTION.............................................................................................................................. 5
1.1. PURPOSE .............................................................................................................................................. 5
1.2. SCOPE ................................................................................................................................................... 5
1.3. DEFINITION ......................................................................................................................................... 6
2. ABBREVIATIONS ............................................................................................................................ 6

3. GENERAL INFORMATION ........................................................................................................... 7


3.1. SECTION OVERVIEW ........................................................................................................................... 7
3.2. RESPONSIBILITIES ........................................................................................................................ 7
3.3. POSSIBLE DISTURBANCE ON SYSTEM AND PLANT: ........................................................... 8
3.4. SAFETY REQUIREMENTS DURING THE DECOMMISSIONING ACTIVITIES ......................................... 9
3.5. EQUIPMENT ....................................................................................................................................... 10
3.6. REFERENCE DOCUMENTS ................................................................................................................. 10
4. ICON CONSOLES INSTALLATION IN TATUN CONTROL ROOM ................................... 11
4.1. SUPPORT CHASSIS INSTALLATION .................................................................................................... 11
4.2. ICON CONSOLES MECHANICAL INSTALLATION .............................................................................. 12
4.3. ICON CONSOLES POWER SUPPLY CONNECTION .............................................................................. 13
4.4. ICON CONSOLES FTE NETWORK CABLES CONNECTION ................................................................ 14
5. SERVER CABINET INSTALLATION IN TATUN INSTRUMENT TECHNICAL ROOM . 14
5.1. SUPPORT CHASSIS INSTALLATION .................................................................................................... 14
5.2. SN1-ER-6204 SERVER CABINET MECHANICAL INSTALLATION ..................................................... 15
5.3. SN1-ER-6204 SERVER CABINET POWER SUPPLY CONNECTION ..................................................... 16
5.4. SN1-ER-6204 SERVER CABINET FTE NETWORK CABLES CONNECTION ...................................... 17
6. ALARM PRINTER SN1-P-2180 INSTALLATION IN TATUN PRINTER ROOM................ 17
6.1. INSTALLATION IN PRINTER ROOM ................................................................................................... 17
6.2. ALARM PRINTER SN1-P-2180 POWER SUPPLY CONNECTION ........................................................ 18
6.3. ALARM PRINTER SN1-P-2180 FTE NETWORK CABLES CONNECTION .......................................... 18
7. SCREEN COPY PRINTER SN1-P-4700 INSTALLATION IN TATUN PRINTER ROOM .. 18
7.1. INSTALLATION IN PRINTER ROOM ................................................................................................... 18
7.2. SCREEN COPY PRINTER SN1-P-4700 POWER SUPPLY CONNECTION ............................................. 18
7.3. SCREEN COPY PRINTER SN1-P-4700 FTE NETWORK CABLES CONNECTION .............................. 19
8. ENG. WORK STATION SN1-EWS INSTALLATION IN TATUN CONTROL ROOM........ 19
8.1. INSTALLATION IN ENGINEERING OFFICE ........................................................................................ 19
8.2. ENG. WORK STATION SN1-EWS POWER SUPPLY CONNECTION .................................................... 19
8.3. ENG. WORK STATION SN1-EWS FTE NETWORK CABLES CONNECTION ..................................... 19
9. SCHEDULE/PLANNING ............................................................................................................... 20

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page4 - 24

APPENDIX A CPU1/2 UPS POWER SUPPLY PANEL SCHEDULE UPS-10 / DB-UPS-10


APPENDIX B TATUN CONTROL ROOM MODIFICATION LAYOUT
APPENDIX C TATUN CONTROL ROOM EQUIPMENTS LAYOUT, CABLES ROUTING &
SUPPORT DETAILS
APPENDIX D IMPLEMENTATION SCHEDULE/PLANNING

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page5 - 24

1. INTRODUCTION

1.1. PURPOSE

The purpose of this method statement is to define a clear and safe procedure for the
installation of Sisi Nubi project Honeywell Icon consoles (ICS) and related equipments
located in TATUN Control Room in addition to the associated Server cabinet located in
Instrument Technical Room.

The procedure covers the software modifications and the hardware steps necessary to
safely install the equipments in the Tatun Control Room.

The decommissioning of existing equipments is covered in a separate method


statements.

1.2. SCOPE

This Method Statement provides a safe procedure for the installation of the Sisi Nubi
project HMI consoles, alarm and screen copy printers and Server cabinet in the
Instrument Technical Room. The equipments detail is as follow:
• HMI Console SN1-OCS-01 Honeywell Icon Console.
• HMI Console SN1-OCS-02 Honeywell Icon Console.
• Alarm Printer SN1-P-2180 EPSON LQ 2180
• Screen Copy Printer SN1-P-4700 HP LaserJet 4700n
• Server Cabinet SN1-ER-6204 Dell P2850, C200, …
• EWS SN1-EWS Dell W470, Monitor 20”, kbd.

Site survey has been carried out on 1st and 2nd November 2006 in order to collect the
necessary information to write the present document.

Installation of the above mentioned equipments is part of CEGELEC (hereinafter called


TCSS) SISI NUBI scope of work. Nevertheless, TOTAL E&P Indonésie (hereinafter
called COMPANY) involvement is required and is clearly mentioned in the present
document whenever it is required.

This procedure formally documents:


• The reference documents
• The methods to be used
• The step by step procedure description
• The equipments set-up

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page6 - 24

1.3. DEFINITION

• COMPANY TOTAL E&P Indonésie


• CONTRACTOR PT NIPPON STELL INDONESIA (NISCONI)
• TCSS CEGELEC/ PT INDOKOMAS BUANA PERKASA
• VENDOR HONEYWELL (PCS/SSS Vendor)

2. ABBREVIATIONS

AC : Alternative Current
AI : Analogue Input
AO : Analogue Output
EMC : Electro Magnetic Compatibility
EMI : Electro Magnetic Interference
ESD : Emergency Shutdown System
EWS : Engineering Work Station
FCW : flow Control of Wells
FAT : Factory Acceptance Test
FGS : Fire & Gas System
FTA : Field Termination Assembly
HMI : Human Machine Interface
HMI : Human/Machine Interface
MTBF : Mean Time between Failures
MTTR : Mean Time to Repair
MTU : Master Terminal Unit
OCS : Operator Control Station
PCS : Process Control System
PDMS : Process Data Management System
PLC : Programmable Logic Controller
RFI : Radio Frequency Interference
RAID : Redundant Array of Independent Disks
SIL : Safety Integrity Level
SSS : Safety Shutdown System
TCR : Tatun Control Room
TR : Technical Room
UCN : Universal Control Network
UPS : Un-interruptible Power Supply
VDU : Visual Display Unit
VFC : Volt Free Contact

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page7 - 24

3. GENERAL INFORMATION

3.1. SECTION OVERVIEW

This section provides general information on the installation procedure requirements.

3.2. RESPONSIBILITIES

1. TCSS is responsible for the overall construction/decommissioning activities to ensure


that all safety measures are taken and that permits from plant operators and from
safety are obtained. TCSS supervising engineer shall always be present during these
modifications. TCSS supervising engineer shall make sure that his telephone number
is available to the COMPANY or Plant Operators.

2. TCSS shall be responsible for any damage to and/or tampering with existing facilities
and TCSS, in such instances, shall restore these back to original conditions
acceptable to COMPANY.

3. No alteration/tampering restoration will be carried out without prior COMPANY


approval.

4. TCSS shall be responsible for enforcing safety regulation and ensuring that work is
carried out according to construction practices and COMPANY Safety Manual and
Procedure.

5. TCSS Lead Engineer is responsible for obtaining an approval from the COMPANY
before any work can be started.

6. SUBCONTRACTOR will provide resources such as System Engineer to perform


software and hardware modification to the system.

7. TCSS will provide manpower such as instrument technician and / or helpers to open
the false floor, to install/decommission the cabinets/consoles and to install/remove
the cables.

8. TCSS supervisor is responsible to keep the working area clean and tidy.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page8 - 24

Representatives:

PT NISCONI Moh’d ASRI


Customer representative:

TOTAL E&P INDONESIE Frederic Besancon


End Customer representative

TCSS (CEGELEC) Yann TATARD


Responsible Project Manager:

TCSS (CEGELEC) Olivier Bourgogne


Responsible project engineer(s):

VENDOR Gito Gozali


Responsible project engineer(s):

3.3. POSSIBLE DISTURBANCE ON SYSTEM AND PLANT:

The installation of the Sisi Nubi project system cabinets and consoles in TATUN control
room requires equipments manipulation and construction works (e.g. support chassis
installation …). These tasks shall not affect the existing running units as no installation
nor connection to existing system equipment is required. In order to minimize operator
disruption, as far as possible all construction, preparation, … work is done in COMPANY
maintenance workshop.

Barricades and warning signs will be posted in the Tatun Control Room to indicate the
false floor opened areas.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page9 - 24

3.4. SAFETY REQUIREMENTS DURING THE DECOMMISSIONING ACTIVITIES

1. All personnel working within the existing plant area shall use Personal Protective
Equipment (PPE) as minimum:
a. Safety Helmet,
b. Safety Shoes,
c. Safety goggles,
d. Long sleeves,
e. Gloves.

2. Warning signs shall be provided and posted inside TATUN control room to segregate
the working areas from the other running system.

3. Competent supervisor shall be available at all working hours.

4. TCSS shall always be aware of the safety procedures adopted by the COMPANY
and in case of fire or emergency, emergency telephone numbers are always be
available with the workers involved with this work.

5. All work will be coordinated at all times with Company Plant Operators.

6. The engineers and supervisors will make sure that all the people who are working in
the control room for TCSS are always aware of the safety procedures to be followed
during any possible FIRE or GAS alarm.

7. Any hot work shall not be performed without a hot work permit signed by COMPANY
Control engineer , Operation supervisor and/or shift controller.

8. A daily permit will be obtained from the Company Plant Operators. The tag No. of the
cabinets/consoles to be manipulated shall be indicated on the work permit and a list
of the cable number shall be attached or indicated on the work permit. All the other
cabinets not associated with this activity will be locked. TCSS and subcontractor
personnel will not be allowed to open any cabinet other than what is indicated on the
work permit.

9. Barricades and warning signs will be posted in the Tatun Control Room to indicate
the false floor opened areas.

10. Separate hot work permits shall be issued for the use of a drilling machine and
caldwelding of the earth connections (if caldwelding is necessary).

11. All CTR/TCSS/Sub-Contractor staff that arrives on CPU or NPU sites shall follow Site
Safety induction by FO-Safety Officer at the first time of their arrival.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page10 - 24

12. Daily Safety talks shall be performed by CTR/TCSS Supervisors prior performing any
job in the morning.

3.5. EQUIPMENT

Specification of used equipments


Multi meter Fluke 787
Drilling machine
Electrical Tool box

3.6. REFERENCE DOCUMENTS

Reference documents for installation procedure are based on COMPANY as built


documents including mark-up and Sisi Nubi project documentation:

Reference drawings are:


• TATUN PCS/SSS EQUIPMENTS LIST
SN1-62-070-001-A Rev.CC
• TATUN PCS/SSS CABLE SCHEDULE/LIST
SN1-62-070-309-A Rev.B.A.
• TATUN CONTROL ROOM MODIFICATION LAYOUT
SN1-62-070-001-C Rev. B.A.
• TATUN CONTROL ROOM LAYOUT
SN1-62-070-401-C Rev. B.C.
• TATUN - CONTROL ROOM/ITR LAYOUT & ROUTING
SN1-62-070-002-C Rev. A.A.
• CPU1/2 NCR ESSENTIAL LIGHTING PANEL SCHEDULE LP-E-01
TMB-65-xxxx Rev. y
• CPU1/2 UPS POWER SUPPLY PANEL SCHEDULE UPS-10 / DB-UPS-10”
TMB-65-8004 Rev. 6
• ELECTRICAL ONE LINE DIAGRAM TCB-90-DB-11 (230V AC & 48V DC) UPS DB
TMB-61-0020 Rev. 3
• CPU1/2 ELECTRICAL GROUNDING LAYOUT NCR
TMB-64-NC02-8-001-C Rev. 2.C
• ICON CONSOLE MOUNTING DETAILS
Sisi Nubi Icon Consoles Support_Rev.B.A.
• TATUN – ICON GENERAL ARRANGEMENT DRAWING
SN1-62-070-359-C Rev. C.C.
• TATUN – SERVER CABINET GENERAL ARRANGEMENT DRAWING.
SN1-62-070-351-C Rev. D.C.
• TATUN – COMMUNICATION DRAWING
SN1-62-070-357-C Rev.B.B.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page11 - 24

4. ICON CONSOLES INSTALLATION IN TATUN CONTROL ROOM

4.1. SUPPORT CHASSIS INSTALLATION

Honeywell Icon HMI consoles are installed at former location of ICS consoles 69-OCS-
01, 69-OCS-02 and 68-OCS-05 as per TATUN CONTROL ROOM MODIFICATION
LAYOUT (SN1-62-070-001-C Rev. B.A).

Consoles Support chassis are built at CEGELEC/ PT INDOKOMAS Balikpapan


workshop as per SN1-62-070-002-C Rev. A.A. EQUIPMENT SUPPORT DETAIL sheet
21 specification drawing.

Support chassis for SN1-OCS-02 console is placed in order to follow the 5,5 m diameter
circle arrangement (this represent the average diameter value measured during site
survey). Icon console 15° elbow frame placed between consoles induce the same
orientation.

Chassis is bolted to the ground concrete floor using Dyna Bolt hanging screws in order to
allow level adjustment as per ground/false floors possible variation. Ref. ICON
CONSOLE MOUNTING DETAILS drawing for hanging system details.

Chassis is connected to the IPE earth loop. Ref. TATUN PCS/SSS CABLE
SCHEDULE/LIST.

Support chassis for SN1-OCS-01 console is placed in order to follow the 5,5 m diameter
circle arrangement (this represent the average diameter value measured during site
survey). Icon console 15° elbow frame placed between consoles induce the same
orientation.

Chassis is bolted to the ground concrete floor using Dyna Bolt hanging screws in order to
allow level adjustment as per ground/false floors possible variation. Ref. ICON
CONSOLE MOUNTING DETAILS drawing for hanging system details.

Chassis is connected to the IPE earth loop. Ref. TATUN PCS/SSS CABLE
SCHEDULE/LIST.

Chassis are ready to receive Icon Consoles.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page12 - 24

4.2. ICON CONSOLES MECHANICAL INSTALLATION

Honeywell Icon HMI console SN1-OCS-02 is unpacked at COMPANY maintenance


workshop in order to minimize control room disruptions.

Honeywell Icon HMI console SN1-OCS-02 is shifted from COMPANY maintenance


workshop to TATUN Control Room using a transpallet. Main Door is used to enter the
equipments in Control Room.

Honeywell Icon HMI console SN1-OCS-02 is placed on its support chassis and fixed
using 4 adjustable hanging screws. Ref. ICON CONSOLE MOUNTING DETAILS
drawing for hanging system details.

Console SN1-OCS-02 is connected to the IPE earth loop. Ref. TATUN PCS/SSS CABLE
SCHEDULE/LIST and TATUN – ICON GENERAL ARRANGEMENT DRAWING for
connection point detail.

15° elbows (Top and Bottom) are placed on Honeywell Icon HMI console SN1-OCS-02.

Honeywell Icon HMI console SN1-OCS-01 is unpacked at COMPANY maintenance


workshop in order to minimize control room disruptions.

Honeywell Icon HMI console SN1-OCS-01 is shifted from COMPANY maintenance


workshop to TATUN Control Room using a transpallet. Main Door is used to enter the
equipments in Control Room.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page13 - 24

Honeywell Icon HMI console SN1-OCS-01 is placed on its support chassis and fixed
using 4 adjustable hanging screws. Ref. ICON CONSOLE MOUNTING DETAILS
drawing for hanging system details.

15° elbows (Top and Bottom) are fixed on Honeywell Icon HMI console SN1-OCS-01.

Console SN1-OCS-01 is connected to the IPE earth loop. Ref. TATUN PCS/SSS CABLE
SCHEDULE/LIST and TATUN – ICON GENERAL ARRANGEMENT DRAWING for
connection point detail.

Consoles are ready for power supply connection.

4.3. ICON CONSOLES POWER SUPPLY CONNECTION

UPS-10-36 power supply cable is reused. Ref. Tatun 69-OCS-01 & 69-OCS-02
decommissioning procedure. Beforehand, COMPANY Electrical maintenance engineer
has performed continuity and megger tests.

UPS-10-36 power supply cable is wired to SN1-OCS-01 Power In terminal block. Ref.
TATUN – ICON GENERAL ARRANGEMENT DRAWING.

DB-UPS-10, MCB 36 shall remain Off until SAT procedure is performed. The SAT
procedure is covered in a separate document.

UPS-10-37 power supply cable is reused. Ref. Tatun 69-OCS-01 & 69-OCS-02
decommissioning procedure. Beforehand, COMPANY Electrical maintenance engineer
has performed continuity and megger tests.

UPS-10-37 power supply cable is wired to SN1-OCS-02 Power In terminal block. Ref.
TATUN – ICON GENERAL ARRANGEMENT DRAWING.

DB-UPS-10, MCB 37 shall remain Off until SAT procedure is performed. The SAT
procedure is covered in a separate document.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page14 - 24

4.4. ICON CONSOLES FTE NETWORK CABLES CONNECTION

The following network cables are laid from SN1-ER-6204 Server cabinet location in
Instrument Technical Room to SN1-OCS-01 and SN1-OCS-02 consoles located in
Control Room Ref TATUN PCS/SSS CABLE SCHEDULE/LIST:
• SN1ESF1-LINKA/SN1SWA-PORT8
• SN1ESF1-LINKB/SN1SWB-PORT8
• SN1ESF2-LINKA/SN1SWA-PORT9
• SN1ESF2-LINKB/SN1SWB-PORT9

Network cables length is 25 meters. The path used for the network cables is described in
drawing # SN1-62-070-002-C.

Segregation between Power cables and Network cable paths is made.

Existing spare MCT are used. As far as existing spare MCT and network cable trays
allow redundant communication cables will be routed by 2 different ways.

Network cables shall be properly stored under the false floor at a suitable location in
order not to bother further supports installations work at SN1-ER-6204 Server cabinet
location.

FTE Network cables are properly laid and connected to their respective Ethernet ports on
OCS workstations. Ref. SN1-62-070-357-C Rev.B.B.

Honeywell Icon HMI consoles SN1-OCS-01 & SN1-OCS-02 are ready for Pre-
commissioning activities. Pre-commissioning and SAT procedures are covered in
separate documents.

5. SERVER CABINET INSTALLATION IN TATUN INSTRUMENT TECHNICAL ROOM

5.1. SUPPORT CHASSIS INSTALLATION

Server Cabinet SN1-ER-6204 is installed in Instrument Technical Room (ITR) as per


TATUN CONTROL ROOM MODIFICATION LAYOUT (SN1-62-070-001-C Rev. B.A).

Server Cabinet Support chassis is built at CEGELEC/ PT INDOKOMAS Balikpapan


workshop as per SN1-62-070-002-C Rev. A.A. EQUIPMENT SUPPORT DETAIL sheet
20 specification drawing.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page15 - 24

Important note:

A smoke detector is placed at the location defined for the Server Cabinet SN1-ER-6204.
Therefore, this one shall be relocated to a position defined by COMPANY. Relocation
activities are under COMPANY responsibility and Scope of Work.

Support chassis for SN1-ER-6204 server cabinet is placed in order to have its front panel
lined up with the existing panel front panels. Rear side of the cabinet is not lined up with
other cabinets as server cabinet is 1000 mm width. Ref. SN1-62-070-002-C Rev. A.A.
TECHNICAL ROOM MODIFICATION LAYOUT sheet 03 drawing.

Chassis is bolted to the ground concrete floor using Dyna Bolt hanging screws in order to
allow level adjustment as per ground/false floors possible variation. Ref. SN1-62-070-
002-C Rev. A.A. EQUIPMENT SUPPORT DETAIL sheet 20 drawing for hanging system
details.

Chassis is connected to the IPE earth loop. Ref. TATUN PCS/SSS CABLE
SCHEDULE/LIST and SN1-62-070-002-C Rev. A.A. TECHNICAL ROOM EARTHING
LAYOUT MODIFICATION sheet 06.

Chassis is ready to receive Server cabinet.

5.2. SN1-ER-6204 SERVER CABINET MECHANICAL INSTALLATION

SN1-ER-6204 server cabinet is unpacked at COMPANY maintenance workshop in order


to minimize control room disruptions.

SN1-ER-6204 server cabinet is shifted from COMPANY maintenance workshop to


TATUN Control Room using a transpallet. ITR rear access Door is used to enter the
equipment in Control Room.

SN1-ER-6204 server cabinet is placed on its support chassis and fixed using 4 hanging
bolts. Ref. SN1-62-070-002-C Rev. A.A. EQUIPMENT SUPPORT DETAIL sheet 20
drawing for hanging system details.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page16 - 24

SN1-ER-6204 server cabinet is connected to the IPE earth loop. Ref. TATUN PCS/SSS
CABLE SCHEDULE/LIST and SN1-62-070-002-C Rev. A.A. TECHNICAL ROOM
EARTHING LAYOUT MODIFICATION sheet 06.

SN1-ER-6204 server cabinet is ready for power supply connection.

5.3. SN1-ER-6204 SERVER CABINET POWER SUPPLY CONNECTION

Only 6A spare feeder breakers are available in existing UPS-10-DB. Then three
temporary solutions are conceivable and considered to power supply the server cabinet
SN1-ER-6204.

1. Replace 2 x 6A spare feeders by 25 or 32A feeder breakers. This work shall be done
“On-Line” to keep the Control Room existing equipment’s up and running.
2. Use 2 (two) 6A feeders is parallel to avoid “On-Line” electrical work.
3. Use a stand-alone 5KVA UPS (e.g. office UPS), connected to emergency lighting
panel Distribution Board (LP-E-01).

CPY shall define the solution to be implemented.

For these 3 options, power cable laid by TCSS is long enough to be re-routed to the
definitive connection located in the “New” UPS DB.

Proposal No 3 is the preferred one to be implemented with regards to the safety and
because it is not as difficult as the 2 others in term of technical implementation, moreover
it does not affect the load of the existing UPS.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page17 - 24

Consequently, the present procedure considers the power supply option #3.

Prerequisite:
2x 25A (or 32A) rated MCB and associated Distribution board (DB) shall be available
from temporary UPS.

UPS-xx-01 power supply cable is laid from DB-UPS-xx distribution board panel
(temporary) to Server Cabinet. Continuity and megger checks are performed.
UPS-xx-02 power supply cable is laid from DB-UPS-xx distribution board panel
(temporary) to Server Cabinet. Continuity and megger checks are performed.

UPS-xx-01 power supply cable is wired to SN1-ER-6204 Power Incomer 1 terminal


block. Ref. TATUN – SERVER CABINET GENERAL ARRANGEMENT DRAWING.
UPS-xx-02 power supply cable is wired to SN1-ER-6204 Power Incomer 2 terminal
block. Ref. TATUN – SERVER CABINET GENERAL ARRANGEMENT DRAWING.

DB-UPS-xx, MCB 01 and MCB 02 shall remain Off until SAT procedure is performed.
The SAT procedure is covered in a separate document.

5.4. SN1-ER-6204 SERVER CABINET FTE NETWORK CABLES CONNECTION

The following network cables are raised from the false floor. The network cables are
properly laid inside cabinet using the dedicated cable duct:
• SN1SWA-PORT8/SN1ESF1-LINKA
• SN1SWB-PORT8/SN1ESF1-LINKB
• SN1SWA-PORT9/SN1ESF2-LINKA
• SN1SWB-PORT9/SN1ESF2-LINKB

FTE Network cables are connected to their respective Ethernet ports on FTE switch A
and B. Ref. SN1-62-070-357-C Rev.B.B.

SN1-ER-6204 Server Cabinet is ready for Pre-commissioning activities. Pre-


commissioning and SAT procedures are covered in separate documents.

6. ALARM PRINTER SN1-P-2180 INSTALLATION IN TATUN PRINTER ROOM

6.1. INSTALLATION IN PRINTER ROOM

SN1-P-2180 alarm printer is installed on double deck printer table formally used by 69-
PRT-01 and 69-PRT-02 (Yokogawa). The double deck printer table is shared with TMB2
alarm printer.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page18 - 24

6.2. ALARM PRINTER SN1-P-2180 POWER SUPPLY CONNECTION

SN1-P-2180 Alarm printer power cord is plug on UPS-10-45-2 wall socket.

6.3. ALARM PRINTER SN1-P-2180 FTE NETWORK CABLES CONNECTION

The following network cable is laid from SN1-ER-6204 Server cabinet location in
Instrument Technical Room to SN1-P-2180 printer located in Control Room Ref TATUN
PCS/SSS CABLE SCHEDULE/LIST:
• SN1P2180-COM1/SN1SWA-PORT11

Network cables length is 25 meters. The path used for the network cables is described in
drawing # SN1-62-070-002-C.

Segregation between Power cables and Network cable paths is made.

Existing spare MCT are used.

The following network cable is raised from the false floor. The network cable is properly
laid inside cabinet using the dedicated cable duct:
• SN1SWA-PORT11/SN1P2180-COM1

FTE Network cable is connected to its respective Ethernet port on FTE switch A. Ref.
SN1-62-070-357-C Rev.B.B.

7. SCREEN COPY PRINTER SN1-P-4700 INSTALLATION IN TATUN PRINTER ROOM

7.1. INSTALLATION IN PRINTER ROOM

69-PRT-03 and 69-PRT-04 (Yokogawa) alarm printers are shifted on double deck printer
table delivered by TMB2 project.
Sisi Nubi and TMB2 laser jet printers arte placed on the table previously used by 69-
PRT-03 and 69-PRT-04 (Yokogawa) alarm printers.

7.2. SCREEN COPY PRINTER SN1-P-4700 POWER SUPPLY CONNECTION

SN1-P-4700 screen copy printer power cord is plug on UPS-10-46-1 wall socket.

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page19 - 24

7.3. SCREEN COPY PRINTER SN1-P-4700 FTE NETWORK CABLES CONNECTION

The following network cable is laid from SN1-ER-6204 Server cabinet location in
Instrument Technical Room to SN1-P-4700 printer located in Control Room Ref TATUN
PCS/SSS CABLE SCHEDULE/LIST:
• SN1P4700-COM1/SN1SWB-PORT11

Network cables length is 25 meters. The path used for the network cables is described in
drawing # SN1-62-070-002-C.

Segregation between Power cables and Network cable paths is made.

Existing spare MCT are used.

The following network cable is raised from the false floor. The network cable is properly
laid inside cabinet using the dedicated cable duct:
• SN1SWB-PORT11/SN1P4700-COM1

FTE Network cable is connected to its respective Ethernet port on FTE switch B. Ref.
SN1-62-070-357-C Rev.B.B.

8. ENG. WORK STATION SN1-EWS INSTALLATION IN TATUN CONTROL ROOM

8.1. INSTALLATION IN ENGINEERING OFFICE

Engineering Work Station is installed in Engineers Office. Desk is shared with Yokogawa
system EWS. Ref. SN1-62-070-002-C Rev. A.A. TECHNICAL ROOM EARTHING
LAYOUT MODIFICATION sheet 04.

8.2. ENG. WORK STATION SN1-EWS POWER SUPPLY CONNECTION

SN1-EWS workstation and monitor power cords are plugged on UPS-10-xx-y wall
socket.

8.3. ENG. WORK STATION SN1-EWS FTE NETWORK CABLES CONNECTION

The following network cables are laid from SN1-ER-6204 Server cabinet location in
Instrument Technical Room to SN1-EWS workstation located in Engineers Office Ref
TATUN PCS/SSS CABLE SCHEDULE/LIST:
• SN1-EWS-LINKA/SN1SWA-PORT10
• SN1-EWS-LINKB/SN1SWB-PORT10

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page20 - 24

Network cables length is 35 meters. The path used for the network cables is described in
drawing # SN1-62-070-002-C.

Segregation between Power cables and Network cable paths is made.

Existing spare MCT are used. As far as existing spare MCT and network cable trays
allow redundant communication cables will be routed by 2 different ways.

The following network cable is raised from the false floor. The network cable is properly
laid inside cabinet using the dedicated cable duct:
• SN1SWA-PORT10/SN1-EWS-LINKA
• SN1SWB-PORT10/SN1-EWS-LINKB

FTE Network cables are connected to their respective Ethernet ports on FTE switch A
and B. Ref. SN1-62-070-357-C Rev.B.B.

9. SCHEDULE/PLANNING

Ref. Appendix D

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page21 - 24

Appendix A
CPU1/2 UPS POWER SUPPLY PANEL SCHEDULE UPS-10 / DB-UPS-10

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
MCB #33 used to power supply EWS.

MCB #36 used to power supply SN1-OCS-01.


MCB #37 used to power supply SN1-OCS-02.

MCB #41 used to power supply CCTV Control equipment.

MCB #45 used to power supply SN1-P-2180.


MCB #46 used to power supply SN1-P-4700.
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page22 - 24

Appendix B
TATUN CONTROL ROOM MODIFICATION LAYOUT

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page23 - 24

Appendix C
TATUN CONTROL ROOM EQUIPMENTS LAYOUT, CABLES ROUTING &
SUPPORT DETAILS

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
PT NISCONI

Doc. Title : TATUN INSTALLATION PROCEDURE Page24 - 24

Appendix D
SCHEDULE/PLANNING

SISI NUBI FIELD DEVELOPMENT PROJECT -Phase 1 Doc. No : SN1-62-022-302-P


SN1/EPSC 3 Rev. : B Status: C
Date : 24 Nov 06
ID Task Name Duration Start Finish 13 Nov '06 20 Nov '06 27 Nov '06 04 Dec '06 11 Dec '06 18 Dec '06
S T T S M W F S T T S M W F S T T S M W F
54 Construction TATUN 49 days Thu 02/11/06 Wed 20/12/06
55 Preparation 28 days Thu 02/11/06 Wed 29/11/06
56 Survey 0 days Thu 02/11/06 Thu 02/11/06
57 Presentation meeting 0 days Thu 16/11/06 Thu 16/11/06 16/11
58 Dwg issued for approval 0 days Thu 16/11/06 Thu 16/11/06 16/11
59 Dwg approved for constructions 0 days Wed 29/11/06 Wed 29/11/06 29/11
60 Logistic 18 days Mon 20/11/06 Thu 07/12/06
61 CCTV panel integration/modification (remote Wks) 0 days Mon 27/11/06 Mon 27/11/06 27/11
62 Mux panel completion 0 days Wed 22/11/06 Wed 22/11/06 22/11
63 Server panel - PSU installation 0 days Wed 22/11/06 Wed 22/11/06 22/11
64 Frame CPU - Radio integration 0 days Mon 20/11/06 Mon 20/11/06 20/11
65 Packing Icon/Stations/Panels 2 days Mon 27/11/06 Tue 28/11/06
66 Delivery BKP 6 days Wed 29/11/06 Mon 04/12/06
67 LCT delivery to TATUN 2 days Tue 05/12/06 Wed 06/12/06
68 Equipments offloading to KZMX wkshp 1 day Thu 07/12/06 Thu 07/12/06
69 Manufacturing 14 days Mon 13/11/06 Sun 26/11/06
70 Support dwg first draft 0 days Mon 13/11/06 Mon 13/11/06 13/11
71 Support check on Site 1 day Wed 22/11/06 Wed 22/11/06
72 Support manufacturing 4 days Thu 23/11/06 Sun 26/11/06
73 Construction ITR 16 days Mon 27/11/06 Tue 12/12/06
74 Support installation ITR 3 days Mon 27/11/06 Wed 29/11/06
75 Software decommissioning Yoko - OCS CPU 2 days Mon 04/12/06 Tue 05/12/06
76 Software decommissioning Yoko - Other OCS 1 day Wed 06/12/06 Thu 07/12/06
77 OCS & ESD decommissioning incl. cable 1 day Wed 06/12/06 Wed 06/12/06
78 Support OCS removal 1 day Thu 07/12/06 Thu 07/12/06
79 Support installation CR incl. false floor 2 days Fri 08/12/06 Sat 09/12/06
80 Panel Install ITR 2 days Fri 08/12/06 Sat 09/12/06
81 Stations Install CR 1 day Sun 10/12/06 Sun 10/12/06
82 Cable laying & connections ITR 2 days Sun 10/12/06 Mon 11/12/06
83 Cable laying & connections CR 1 day Mon 11/12/06 Mon 11/12/06
84 PreCom Panel & Cable 1 day Tue 12/12/06 Tue 12/12/06
85 Construction Radio Shack 4 days Fri 08/12/06 Mon 11/12/06
86 Panel Install 1 day Fri 08/12/06 Fri 08/12/06
87 Cable laying & connections 2 days Sat 09/12/06 Sun 10/12/06
88 PreCom Panel & Cable 1 day Mon 11/12/06 Mon 11/12/06
89 Start Up 9 days Mon 11/12/06 Wed 20/12/06
90 CPY radio (antenna/cable) ready & connected 0 days Mon 11/12/06 Mon 11/12/06 11/12
91 Vendor Assistance - Cpy Commissioning Primary MUX & NMS 3 days Wed 13/12/06 Fri 15/12/06
92 OSAT PCS system 5 days Sat 16/12/06 Wed 20/12/06
93 Vendor Assistance - Cpy Commissioning CCTV inc. SNPS CCTV 5 days Sat 16/12/06 Wed 20/12/06
94 As Built & PL 5 days Wed 13/12/06 Sun 17/12/06
95 As built dwg (Mark Up) 3 days Wed 13/12/06 Fri 15/12/06
96 PL clearance Hardware/Install 5 days Wed 13/12/06 Sun 17/12/06
97 Handover Commissioning 0 days Wed 20/12/06 Wed 20/12/06 20/12
98 Completion Date Target 0 days Fri 22/12/06 Fri 22/12/06 22/12

Task Progress Summary External Tasks Deadline


Project: SNPS and TATUN r1.1 14-11-
Date: Fri 17/11/06
Split Milestone Project Summary External Milestone

Page 2