Clean Agent System Test Report-1
Clean Agent System Test Report-1
Fire Department
196 Clear Creek Street | PO Box 68
Black Hawk, CO 80422-068
Office 303-582-0426 | Fax 303-582-2229
www.cityofblackhawk.org
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature:
CLEAN AGENT SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code and
NFPA 2001 Standard, and the manufacturer’s instructions for weekly, monthly, and quarterly
requirements for inspection and testing. System test results must be submitted to the Black Hawk
Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
General
5. All signs, placards, and labels are provided on doors,
system controls, and electrical circuits. □ YES □ NO
6. No significant changes or unrepaired penetrations were
found in the enclosure protected by the system. □ YES □ NO
Recalls
7. The inspector did not find recalled devices during the visual
inspection. □ YES □ NO
Note: the Inspector’s inspection is a visual cursory inspection from the floor level in accessible areas.
Nozzles, Piping, and Hose
8. All nozzles, piping, and brackets are properly placed and
are secured. □ YES □ NO
Release Devices
21. The automatic release device(s) work properly, including
pre-discharge time delays. (Note: Confidence testing of the
release device does not require release of the clean agent
after the initial full discharge acceptance test. However, full □ YES □ NO
discharge tests may be required after changes to the
protected area or system.)
22. All manual stations used to release agents work properly
and require two separate and distinct actions for operation. □ YES □ NO
Abort Devices
23. The manual abort switch is a dead-man type switch and
functions properly. □ YES □ NO
Auxiliary Functions
24. All auxiliary functions such as alarm-sounding or displaying
devices, remote annunciators, air-handling shutdown,
damper operation, and power shutdown operate properly in □ YES □ NO
accordance with system requirements and design
specifications.
25. The alarms can be silenced, when allowed, without
affecting other system functions. □ YES □ NO
System Monitoring
26. The control panel sends the proper signals to the remote
FAP. □ YES □ NO
27. The fire protection system, including the alarm system,
works correctly on standby power during a simulated power □ YES □ NO
failure.
28. A signal was received at the Central Station monitoring
company. □ YES □ NO
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature:
EMERGENCY GENERATOR SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code and
NFPA 2001 Standard, and the manufacturer’s instructions for weekly, monthly, and quarterly
requirements for inspection and testing. System test results must be submitted to the Black Hawk
Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
5. All signs, labels, and placards are in place and visible. □ YES □ NO
Load Test
Amps Volts Hertz
Generator Load Rating
Test Results (full load)
This generator supplies power for Over Current Capacity (Amps)
Required Emergency Equipment
Legally required Equipment
Optional loads
6. The EG was operated for the annual test according to Fire
Code Section 604, the manufacturer’s recommendations, □ YES □ NO
and NFPA 110 Section 8.4.
7. All of the fire and life safety equipment requiring EG power
was checked and operated properly. □ YES □ NO
8. The test results indicate that this generator provides
adequate power to support all loads connected to it and/or
sheds the Optional loads (Emergency, Legally Required, □ YES □ NO
Optional).
Final Checks
Put the Fire Alarm back into service and/or other precautionary measures that were made to restore fire
alarm system to normal operation (includes removal of protective coverings). If the system was taken
offline, the TFWP Log Sheet must be submitted to the City of Black Hawk Fire Department after the
system is restored.
16. The system was left in service. □ YES □ NO
17. A printed or electronic copy of the test report was provided
to the owner/manager to maintain on the premises for a □ YES □ NO
minimum of three (3) years.
18. Temporary Fire Watch Permit Log Sheet submitted. □ YES □ NO
By accepting this statement I, the certified technician shown on this form, certify that this fire protection
system(s) has been properly inspected for functional operation in accordance with the current Fire Code
(FC) used by the department that has jurisdiction and NFPA Standards adopted by the FC for this
system. Any deficiencies found are noted in the report and have been reported to the building
Owner/Manager for corrective action. I am authorized to submit this report for the certified technician who
has accepted this statement.
Printed Name of Technician: Signature:
System Make:
System Model:
Control Panel Location:
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature: Name:
FIRE ALARM SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code,
referenced NFPA 72 Standard, and the manufacturer’s instructions for weekly, monthly, and quarterly
requirements for inspection and testing. System test results must be submitted to the Black Hawk
Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
General
5. The key to the panel is available at the Fire Alarm Control
Panel (FACP). □ YES □ NO □ N/A
6. The operating instructions are available at the FACP. □ YES □ NO
7. Materials and equipment needed to restore pull stations are
available at the main panel, e.g. glass rods, and plates; □ YES □ NO □ N/A
keys and allen wrenches, etc.
Alarm Panel
8. The FACP operates on AC power □ YES □ NO
9. The FACP operates on Battery power. □ YES □ NO
10. The FACP operates on emergency generator/standby
power. □ YES □ NO □ N/A
11. The trouble indicators function properly and a trouble signal
comes on with AC power off. □ YES □ NO
Batteries
21. The batteries are rated for: (hours & minutes) Hours: Minutes:
22. Battery voltage (no load) Volts:
23. Battery voltage (full load) Volts:
24. Charge circuit voltage Volts:
Interface Devices
25. The FACP received signals from the following Interface
devices: Tested by: □ Simulation □ Operation
System Make:
System Model:
Control Panel Location:
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature:
FIRE PUMP SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code,
referenced NFPA 20 and 25 Standards, and the manufacturer’s instructions for weekly, monthly, and
quarterly requirements for inspection and testing. System test results must be submitted to the Black
Hawk Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
5. Routine maintenance is being performed (including weekly
pump tests w/0 flow) and records are being kept in □ YES □ NO
accordance with NFPA 20 and NFPA 25
6. The suction screens were inspected and cleared. □ YES □ NO
7. All signs, placards, and labels are provided on doors and
system controls. □ YES □ NO
Electric Pump
8. Electric Pump Wiring Phase □ Single □ Double □ Triple
0 gpm (churn) Amperage __________ Voltage __________
100% gpm Amperage __________ Voltage __________
150% gpm Amperage __________ Voltage __________
9. The electric pump ran properly for a minimum 10 minutes. □ YES □ NO
Diesel Pump
10. Oil level is OK. □ YES □ NO
11. Coolant level is full. □ YES □ NO
12. The hydrometer reading indicates that the antifreeze
protection is adequate. □ YES □ NO
Pump Test
18. When the Pump starts from pressure drop the start
pressure is 5 psi below the start point of the jockey pump. □ YES □ NO
19. The pump runs smoothly without unusual noise or vibration.
(For standards regarding pump vibration see Hydraulics
Institute Standards for Centrifugal, Rotary and □ YES □ NO
Reciprocating Pumps – Ref. NFPA 20)
20. If due, the gauges passed a 5-year pressure gauge
comparison test with a calibrated gauge and were □ YES □ NO
recalibrated or replaced if necessary.
21. The pump performs at its rated capacity (RC) and at 150%
of its RC (or the capacity that the supply will accommodate □ YES □ NO
above the RC if it is less than 150%).
Actual Test RPM Churn ______ 100%RC ______ 150%RC ______
Pitot or Flowmeter Reading (gpm) Test Capacity 100% _______ Test Peak Flow (150%) _______
PSI Reading on Discharge Gauge Pre-test ______ Churn ______ 100%RC ______ 150%RC ______
PSI Reading on Suction Gauge Pre-test ______ Churn ______ 100%RC ______ 150%RC ______
22. Hose Size Hose Size ______in. Tip Size ______in. Hose length ______ft.
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature: Name:
HOOD SUPPRESSION SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code used by
the AHJ, NFPA 17, NFPA 17A, and NFPA 96 and the manufacturer’s recommendations for inspecting
and testing requirements. System test results must be submitted to the Black Hawk Fire Department
during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The suppression system meets the UL300 standard. (Note
to System Owners: Non UL300 systems are no longer UL
listed for commercial range hood fire suppression. All non □ YES □ NO
UL300 systems must be upgraded or replaced to meet the
UL300 standard.)
Appliance Coverage, Nozzles, and Piping
3. All cooking appliances that can produce grease laden
vapors are completely under the range hood. □ YES □ NO
4. All cooking appliances have the required number and type
of nozzles to provide adequate fire protection. □ YES □ NO
System Controls
7. All system controls and components are accessible and
free from obstructions. □ YES □ NO
8. The system is operational from the terminal link (last fusible
link). □ YES □ NO
13. The gas shuts down upon system activation. □ YES □ NO □ N/A
14. The appliance electrical shutdown device functions
properly. □ YES □ NO □ N/A
24. The alarm monitoring company received the alarm signal. □ YES □ NO □ N/A
Cleaning
25. The surfaced around the cooking surfaces, range hood,
and ducting from hood to termination □ YES □ NO
26. The system is on a cleaning schedule in accordance with
IFC 609.3.3. □ YES □ NO
Final Checks
Put the Fire Alarm back into service and/or other precautionary measures that were made to restore fire
alarm system to normal operation (includes removal of protective coverings). If the system was taken
offline, the TFWP Log Sheet must be submitted to the City of Black Hawk Fire Department after the
system is restored.
27. A printed or electronic copy of the test report was provided
to the owner/manager to maintain on the premises for a □ YES □ NO
minimum of three (3) years.
28. Temporary Fire Watch Permit Log Sheet submitted. □ YES □ NO
By accepting this statement I, the certified technician shown on this form, certify that this fire protection
system(s) has been properly inspected for functional operation in accordance with the current Fire Code
(FC) used by the department that has jurisdiction and NFPA Standards adopted by the FC for this
system. Any deficiencies found are noted in the report and have been reported to the building
Owner/Manager for corrective action. I am authorized to submit this report for the certified technician who
has accepted this statement.
Printed Name of Technician: Signature:
System Make:
System Model:
Control Panel Location:
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Name: Phone:
Signature:
SMOKE CONTROL SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code,
referenced NFPA 92 and 204 Standards, and the manufacturer’s instructions for weekly, monthly, and
quarterly requirements for inspection and testing. System test results must be submitted to the Black
Hawk Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
5. All signs, placards, and labels are provided on doors and
system controls. □ YES □ NO
17. List the measurement method and equipment used to test air flow: □ N/A
28. Gaskets are in good condition on stair and elevator doors. □ YES □ NO
Final Checks
Put the Fire Alarm back into service and/or other precautionary measures that were made to restore fire
alarm system to normal operation (includes removal of protective coverings). If the system was taken
offline, the TFWP Log Sheet must be submitted to the City of Black Hawk Fire Department after the
system is restored.
29. A printed or electronic copy of the test report was provided
to the owner/manager to maintain on the premises for a □ YES □ NO
minimum of three (3) years.
30. Report of all measurements taken attached. □ YES □ NO
31. Temporary Fire Watch Permit Log Sheet submitted. □ YES □ NO
By accepting this statement I, the certified technician shown on this form, certify that this fire protection
system(s) has been properly inspected for functional operation in accordance with the current Fire Code
(FC) used by the department that has jurisdiction and NFPA Standards adopted by the FC for this
system. Any deficiencies found are noted in the report and have been reported to the building
Owner/Manager for corrective action. I am authorized to submit this report for the certified technician who
has accepted this statement.
Printed Name of Technician: Signature:
Sprinkler Inventory
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Signature: Date:
SPRINKLER SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code,
referenced NFPA 25 Standard, and the manufacturer’s instructions for weekly, monthly, and quarterly
requirements for inspection and testing. System test results must be submitted to the Black Hawk
Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. All signs, placards, and labels are provided on doors and
system controls. □ YES □ NO □ N/A
3. There is an up-to-date log of any weekly, monthly, and
quarterly inspections and testing of the system(s) covered □ YES □ NO □ N/A
by this report.
Pre-Test Checks
4. All accessible sprinkler heads have been visually inspected
and are free of corrosion, paint, obstructions and/or □ YES □ NO □ N/A
physical damage.
5. The sprinkler coverage is OK. (Note: If the coverage has
not been altered after the last acceptance/reacceptance □ YES □ NO □ N/A
test it is OK.)
6. The standard sprinkler heads are less than 50 years old or
within a prescribed testing period. If “No” have the heads
sample tested or replaced per NFPA 25 and at the □ YES □ NO □ N/A
prescribed intervals thereafter.
7. The Quick Response sprinkler heads are less than 20
years old or within a prescribed testing period. If “No” have
the heads sample tested or replaced per NFPA 25 and at □ YES □ NO □ N/A
the prescribed intervals thereafter.
8. The dry type sprinkler heads are less than 10 years old or
within a prescribed testing period. If “No” have the heads
sample tested or replaced per NFPA 25 and at the □ YES □ NO □ N/A
prescribed intervals thereafter.
9. The proper number and type of spare sprinkler heads is
available, with the proper wrenches for each, at the riser or □ YES □ NO □ N/A
another designated location.
Heat Activated Devices
10. Heat actuation devices function on pre-action and deluge
systems. □ YES □ NO □ N/A
Valves
15. Pressure regulating valves (PRV) are set properly. □ YES □ NO □ N/A
16. All supply valves are secured or supervised. □ YES □ NO
17. All supply valves have been lubricated (where required) □ YES □ NO
18. The maintenance on the system gauges is up-to-date. □ YES □ NO
Note: The system gauges are to be compared with a calibrated gauge every five (5) years. If a gauge is
not within +/- 3% of the calibrated gauge it must be replaced or recalibrated. This check should be done
for multiple floors at static pressure using one calibrated gauge and hydraulic.
Obstruction Investigation
19. The 5-year obstruction investigation of Fire Department
Connection (FDC) piping is up-to-date in accordance with □ YES □ NO
NFPA 25 Chap. 14. (eff. 10/21/2012).
20. The 5-year obstruction exam for the FDC(s) included
testing and operation of the check valve. □ YES □ NO
21. The 5-year Obstruction Examination of the sprinkler piping
is up-to-date in accordance with NFPA 25 Chap. 14. □ YES □ NO
Note: The technician’s inspection is visual and from the floor level in accessible areas.
Alarm Monitoring
29. A signal was received at the Central Station monitoring
company. □ YES □ NO □ N/A
Final Checks
Put the Fire Alarm back into service and/or other precautionary measures that were made to restore fire
alarm system to normal operation (includes removal of protective coverings). If the system was taken
offline, the TFWP Log Sheet must be submitted to the City of Black Hawk Fire Department after the
system is restored.
43. The system was left in service. □ YES □ NO
44. A printed or electronic copy of the test report was provided
to the owner/manager to maintain on the premises for a □ YES □ NO
minimum of three (3) years.
45. Temporary Fire Watch Permit Log Sheet submitted. □ YES □ NO
By accepting this statement I, the certified technician shown on this form, certify that this fire protection
system(s) has been properly inspected for functional operation in accordance with the current Fire Code
(FC) used by the department that has jurisdiction and NFPA Standards adopted by the FC for this
system. Any deficiencies found are noted in the report and have been reported to the building
Owner/Manager for corrective action. I am authorized to submit this report for the certified technician who
has accepted this statement.
Printed Name of Technician: Signature:
Name: Phone:
Address: Emergency Phone:
Email:
Inspector/Tester Information
Signature: Date:
STANDPIPE SYSTEM
Date Tested:
The items in the checklists below shall be inspected and tested. This list does not constitute all of the
required inspecting and testing of the fire and life safety system(s). Refer to the current Fire Code,
referenced NFPA 25 Standard, and the manufacturer’s instructions for weekly, monthly, and quarterly
requirements for inspection and testing. System test results must be submitted to the Black Hawk
Fire Department during annual inspection.
Pre-Test Checks
A Temporary Fire Watch Permit (TFWP) is required when a system is taken offline. Only the
owner/operator is authorized to request and receive a TFWP. Avoid unnecessary alarms by putting the
Fire Alarm System in test mode. Failure to place the Fire Alarm System (FAS) into test mode and/or
taking other precautions to may cause preventable alarms.
1. If system is taken offline, Temporary Fire Watch Permit
(TFWP) has been submitted and approved. □ YES □ NO
2. The building occupants were notified. □ YES □ NO □ N/A
3. The onsite supervisory station was notified. □ YES □ NO □ N/A
4. The Central Station Monitoring Service was notified to
place FAS in test mode. □ YES □ NO □ N/A
5. All signs, placards, and labels are provided on doors and
system controls. □ YES □ NO
Monitoring
25. A signal was received at the Central Station monitoring
company. □ YES □ NO
Recalls
26. The inspector did not find recalled devices during the visual
inspection. □ YES □ NO
Note: the inspector’s inspection is a visual cursory inspection from the floor level in accessible areas.
Alarm Monitoring
27. A signal was received at the Central Station monitoring
company. □ YES □ NO □ N/A
Type II Standpipes
28. The hose cabinet(s) is in acceptable condition in
accordance with NFPA 25. □ YES □ NO □ N/A
29. The hose storage device(s) is in acceptable condition in
accordance with NFPA 25. □ YES □ NO □ N/A
30. The hose is in acceptable condition in accordance with
NFPA 25. □ YES □ NO □ N/A
31. The nozzle is in acceptable condition in accordance with
NFPA 25. □ YES □ NO □ N/A
ABSTRACT
Despite the long held agreement that a knowledge of enclosure integrity is an essential element
in the design of fire protection systems, relatively little information is available concerning the
development of enclosure pressure during the discharge of gaseous agents.
Room pressure development during clean agent discharges is dependent upon several system-
and enclosure-related factors. A major factor influencing the development of room pressure is
the nature of the clean agent. The discharge of inert gas agents is characterized by a rapid
buildup of pressure to a maximum, followed by a relatively slow decay in pressure with time.
The discharge of halocarbon-based agents on the other hand, is characterized by an initial,
relatively rapid negative pressure pulse, due to initial cooling of the enclosure and its contents,
followed by a relatively rapid positive pressure pulse. Additional factors influencing the
development of room pressure during a clean agent discharge include the enclosure construction,
the enclosure integrity (leakage area, hold time), the fire size per enclosure volume ratio, and the
agent flow rate.
Details of the effects of the above factors on room pressure development for both inert gas and
halocarbon-based systems will be reviewed, along with data relating enclosure pressurization to
enclosure integrity. Approaches to the evaluation of enclosure strengths for various construction
types will be discussed, and recently developed methodologies for the prediction of the pressure
dynamics of clean agent discharges will also be reviewed.
Room pressure development during clean agent discharges is dependent upon several system-
and enclosure-related factors. A major factor influencing the development of room pressure is
the nature of the clean agent. Figure 1 shows the variation of the room pressure with time for the
discharge of Inergen®, an inert gas type clean agent. The discharge of an inert gas agent is
characterized by a rapid buildup of pressure to a maximum, followed by a relatively slow decay
in pressure with time. Figure 2 shows the variation of the room pressure with time for the
discharge of FM-200®, a halocarbon type clean agent. For halocarbon-based clean agents, an
initial negative pressure event occurs: the agent undergoes a phase change from liquid to vapor
2.5
1.5
0.5
0
200 220 240 260 280 300
Time (seconds)
0.4
0.2
Room Pressure (iwc)
-0.2
-0.4
-0.6
-0.8
-1
-1.2
60 70 80 90 100 110
Time (seconds)
2
at the nozzle, which results in the absorption of heat from enclosure air and a decrease in the
room pressure to below the ambient pressure. The negative pressure event is followed by a
positive pressure event during which heat transfer occurs from the enclosure and its contents to
the cooled air and expansion of the agent results in an increase in room pressure to above the
ambient pressure. Hence, the discharge of halocarbon-based clean agents is characterized by an
initial, relatively rapid negative pressure pulse, due to initial cooling of the enclosure and its
contents, followed by a relatively rapid positive pressure pulse.
Previous studies [1-3] of the pressure dynamics of halocarbon agent discharges have shown that
the magnitude of the enclosure pressures developed is dependent upon several factors, including:
• Agent properties
• Agent concentration
• Discharge time
• Enclosure leakage area
• Enclosure construction
• Fire size
As discussed above, the pressure dynamics of inert gas agent discharges differ significantly from
the pressure dynamics of halocarbon-based agent discharges. The thermodynamic properties of
a halocarbon-based agent will determine the extent of heat transfer occurring during agent
discharge, and hence the pressure dynamics of different halocarbon-based agents will be
different. Testing with FM-200® indicated a dependence of the enclosure pressure on the agent
concentration. Figure 3 shows the maximum and minimum enclosure pressures measured during
the cold discharge of FM-200® in an 85 m3 enclosure constructed from 2x4 wood studs and
gypsum wallboard. As can be seen from Figure 3, as the agent concentration increases, the
magnitude of the positive and negative pressure pulses also increases.
1.5
1
Enclosure Pressure (iwc)
0.5
0
6.5 7 7.5 8 8.5 9 9.5
-0.5
-1
-1.5
-2
FM-200 Concentration (% v/v)
3
The discharge time was found to have little effect on the enclosure pressure [1], for discharge
times ranging between 6 and 10 seconds. For example, Figure 4 shows the effect of the
discharge time on the enclosure pressure for the discharge of 8% v/v FM-200® on a 445 mm
heptane pan fire. The effect of the leakage area on the enclosure pressure is as expected: as the
leakage area is increased, the magnitude of the enclosure pressures decreases, as seen in Figure
5.
4
3
Enclosure Pressure, iwc
2
Max. Positive Pressure
1 Max. Negative Pressure
0
-1
-2
-3
4 6 8 10 12
Discharge Time, seconds
1.6
Max. Enclosure Pressure, iwc
1.4
1.2
1
0.8
0.6
20 25 30 35 40 45
Leakage area, sq. in.
4
The construction of the enclosure has been observed to affect the magnitude of the enclosure
pressures developed, as seen in Figures 6 and 7. The magnitude of enclosure pressure was
observed to be larger in an enclosure constructed of cinder block compared to a similar structure
constructed from gypsum wallboard and 2x4 studs. This was attributed to the greater flexibility
of the wallboard construction, which afforded a dampening of the pressure pulses.
1.2
0.8
0.6
0.4
0.2
0
25 35 45
1.2
0.8
0.6
0.4
0.2
0
25 35 45
5
The fire size has been observed to have a large influence on the enclosure pressure as shown in
Figures 8 and 9. An increase in fire size results in an increase in the magnitude of both the
positive and negative pressure pulses associated with the discharge of a halocarbon-based agent.
5
Maximum Positive Pressure, iwc
4
3
2
1
No Fire PVC cable 300 mm Pan 445 mm Pan
0
Maximum Negative Pressure, iwc
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
No Fire PVC Cable 300 mm Pan 445 mm Pan
6
PRESSURE DYNAMICS: MODELING
The inert gas-type clean agents are all based on ideal gases. Calculation of enclosure pressures
can be accomplished by assuming ideal gas behavior, and venting information is available from
the agent manufacturers to allow for the calculation of the vent sizes required to ensure enclosure
pressurization does not occur. The halocarbon-based clean agents, however, do not behave as
ideal gases, and the prediction of enclosure pressures developed upon their discharge is a much
more difficult challenge than in the case of the inert gas clean agents.
A model for use in predicting the enclosure pressures developed during the discharge of a clean
fire suppression agent, either inert gas or halocarbon-type, into an enclosed space had been
previously developed by Hughes Associates, Inc. [4]. The model utilizes a mass balance, an
energy balance and the Soave modification of the Redlich- Kwong equation of state. This model
also utilizes the Hughes Associates, Inc (HAI) Clean Agent flow model to provide the required
flow rate and thermodynamic state of the agent and super-pressurizing nitrogen as they enter the
enclosure. The model assumes instantaneous mixing throughout the enclosure and complete
vaporization of the agent.
In comparison with experimental data, this early model has a tendency to accurately predict
pressures for small enclosures (on the order of 400 ft3), but over-predicts the negative pressure
pulse and under-predicts the positive pressure pulse in larger enclosures (on the order of 3,500
ft3). This was believed to be due to the neglecting of heat transfer to the vaporizing liquid agent
as it comes into contact with the ceiling near the nozzle location.
In order to account for this heat uptake, a sub-model was added to the program. The portion of
the ceiling and the amount of the agent liquid that was involved in this heat transfer was
estimated based upon the liquid flow rate and pressure at the nozzle. A lumped heat capacity-
based energy balance was applied to the involved section of the ceiling to account for the
reduction in heat transfer over time due to the temperature reduction of the ceiling section. With
the addition of the sub-model, pressures in the larger enclosures were accurately predicted.
However, for the smaller enclosures, the sub-model had to be defeated/removed to regain
accurate predictions.
In order to obtain accurate predictions for a wide range of enclosure sizes, a set of experiments
involving the discharge of FM-200® were designed to allow for the development of an improved
correlation for the portion of the ceiling and the amount of agent liquid involved in this enhanced
heat transfer process. The experimental program examined the effect of the following variables
on the enclosure pressure dynamics:
7
Based upon the experimental results, a correlation was developed relating the portion of the
ceiling and the amount of the agent liquid involved in heat transfer to the liquid flow rate and
pressure at the nozzle, and the distance between the nozzle and the walls of the enclosure.
Table 1 compares the peak pressure values predicted by the enhanced model with experimentally
measured values. For fill densities above approximately 35 lb/ft3, the enhanced model predicts
the maximum and minimum enclosure pressures to within approximately 0.5 iwc of the
experimentally observed values. Figure 10 compares the predicted enclosure pressure with the
experimentally observed enclosure pressure for the discharge of 8% v/v FM-200® in a 3355 ft3
(95 m3) enclosure employing gypsum wallboard and 2x4 stud construction, and characterized by
a leakage area of 43 in2.
1.50
1.00
0.50
Enclosure Pressure (iwc)
Predicted
0.00
Experimental
-0.50
-1.00
-1.50
0.00 5.00 10.00 15.00 20.00 25.00
Time (sec)
8
Table 1. Prediction of Enclosure Pressures. FM-200®
GS50 UL2166 pl. sheets in 8'x8'x10' 517 9.8 0.10 4.9 0.20 0.55 -0.35 -0.61 -1.15 0.54
GS55 UL2166 pl. sheets in 8'x8'x10' 517 9.8 0.10 5.4 0.16 0.46 -0.30 -0.66 -1.18 0.52
GS58 UL2166 pl. sheets in 8'x8'x10' 517 9.8 0.10 5.7 0.15 0.32 -0.17 -0.72 -0.95 0.23
GS65 UL2166 pl. sheets in 8'x8'x10' 517 9.8 0.10 6.4 0.18 0.48 -0.30 -0.84 -1.01 0.17
GS70 UL2166 pl. sheets in 8'x8'x10' 517 9.8 0.10 6.9 0.20 0.51 -0.32 -0.88 -1.04 0.16
GLEP7-35 ElDO Pressure Tests 3011 9.8 0.24 7.0 1.42 1.00 0.42 -1.26 -1.00 -0.26
GLEP7-43 ElDO Pressure Tests 3011 9.8 0.30 7.0 1.13 0.80 0.33 -0.97 -1.00 0.03
GLEP8-35 ElDO Pressure Tests 3011 9.8 0.24 8.1 1.72 1.30 0.42 -1.26 -1.10 -0.16
GLEP8-43 ElDO Pressure Tests 3011 9.8 0.30 8.1 1.38 1.20 0.18 -0.98 -0.90 -0.08
GLEP9-35 ElDO Pressure Tests 3011 9.8 0.24 9.2 1.80 1.60 0.20 -1.23 -1.40 0.17
GLEP9-43 ElDO Pressure Tests 3011 9.8 0.30 9.2 1.43 1.30 0.13 -0.97 -1.20 0.23
Hygood-3 IMO telltales 17640 16.4 1.80 7.4 1.21 1.21 0.00 -0.61 -0.60 -0.01
KF-180 IMO telltales 17640 16.4 1.80 6.9 0.46 0.80 -0.35 -0.24 -0.40 0.17
G12EP6 HAI Fall 2004 3591 12.0 0.31 5.9 0.40 0.21 0.19 -0.94 -1.23 0.29
G12EP8 HAI Fall 2004 3591 12.0 0.31 5.9 0.40 0.24 0.16 -0.94 -1.14 0.20
G12EP10 HAI Fall 2004 3591 12.0 0.31 5.9 0.40 0.19 0.21 -0.94 -1.07 0.13
GP16F9 HAI Fall 2004 3505 16.0 0.32 6.0 0.34 0.29 0.05 -0.90 -0.60 -0.30
GP16F10 HAI Fall 2004 3505 16.0 0.32 6.0 0.34 0.27 0.07 -0.90 -0.65 -0.25
GP16F11 HAI Fall 2004 3505 16.0 0.32 6.0 0.34 0.31 0.03 -0.90 -0.60 -0.30
G12EP11 HAI Fall 2004 1344 12.0 0.22 7.0 0.34 0.30 0.04 -1.03 -0.73 -0.30
G12EP12 HAI Fall 2004 1344 12.0 0.22 7.0 0.34 0.29 0.05 -1.03 -0.87 -0.16
G12EP13 HAI Fall 2004 1344 12.0 0.22 7.0 0.34 0.29 0.05 -1.03 -0.83 -0.20
concrete block
9
ENCLOSURE STRENGTHS
The ability to accurately predict enclosure pressures resulting from clean agent discharges is of
practical use only if the strength of the enclosure with respect to the maximum pressure it can
accommodate is known. NFPA 12 (Carbon Dioxide) indicates, without explanation, that “light”
construction can tolerate 25 psf of pressure and that “normal” construction can tolerate 50 psf.
These values are apparently based on resistance to wind, and no definition of “light” or “normal”
construction is provided in NFPA 12. A “rule of thumb” currently encountered in the field is a
maximum pressure of 5 psf. This figure is apparently based on building code requirements for
interior wall partitions subject to normal use.
A previous analysis by Harry, et. al. [2] of various structural elements indicated that the
pressures developed during discharge of FM-200® are less than the yield strengths of structural
members generally used in applications protected by FM-200® systems (interior, no-load bearing
framing or partition studs).
Strength comparisons of concrete, masonry, and wood construction are available from
construction material suppliers. Table 2, for example, shows the pressure limitations (based on
wind loading) for several structural components [5]. In general, it can be observed that typical
construction can tolerate at least 10 psf pressure. This is in agreement with observations made at
Hughes Associates, Inc. during the discharge of clean agents in test enclosures employing 2x4
wood studs or steel studs and wallboard construction in enclosure of up to 16 feet in height:
minor enclosure damage (i.e., the development of small cracks in the structure) do not occur until
enclosure pressures exceed approximately 10 psf.
CONCLUSION
By accounting for the heat transfer to the vaporizing liquid agent as it comes into contact with
the ceiling near the nozzle location, we have been able to refine our enclosure pressure model to
allow for the accurate prediction of enclosure pressures developed during the discharge of the
clean agent FM-200®. Maximum positive and negative enclosure pressures have been predicted
to within 0.5 iwc for structures of various configuration. Combined with a knowledge of the
strength of an enclosure with regard to pressurization, the use of the pressure model ensures the
proper and safe design of FM-200® suppression systems.
10
Table 2. Strength of Walls. Exterior Wall, 10 Feet Tall [5]
Maximum Allowable
Wall Type Pressure
(psf)
2x4 stud @ 16” OC 13
2x6 stud @ 16” OC 32
2x8 stud @ 16” OC 56
2x10 stud @ 16” OC 90
6” masonry reinforced 41
8” masonry reinforced 57
10” masonry reinforced 74
12’ masonry reinforced 91
4” concrete reinforced 59
6” concrete reinforced 89
8” concrete reinforced 120
4” concrete unreinforced 29
6” concrete unreinforced 66
8” concrete unreinforced 117
REFERENCES
2. Harry, L.D., Meltzer, J.S., and Robin, M.L., “Development of Room Pressure in the
Discharge of FM-200 Compared to the Strength of Various Structural Elements,”
Proceedings of the 1997 Halon Options Technical Working Conference, May 6-8, 1997,
Albuquerque, NM.
4. DiNenno, P.J. and Forssell, E.W., “Evaluation of Alternative Agents for Use in Total
Flooding Fire Protection Systems,” NASA SBIR Phase II Final Report, NASA, Kennedy
Space Center, FL, 1994.
5. Technical Bulletin ICF No. 7004, “Concrete, Masonry, Wood Wall Strength
Comparisons, Feb. 1995 (revised March 1999), AFM Corporation.
11
second edition
PIPE DESIGN HANDBOOK
Special Hazard
Fire Suppression
Systems
FSSA PDH-01
SPECIAL HAZARD
Second Edition
August 2003
© 2003 by the Fire Suppression Systems Association. All Rights Reserved. No part of this
book may be reproduced or transmitted in any form or by any electronic or mechanical
means, including photocopy, xerography, recording, or by use of any information or storage
and retrieval system, without prior written permission of the publisher.
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE OF CONTENTS
SECTION
Design Criteria 2
APPENDIX C: References 9
Page 1 of 1
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
FORWARD
The Fire Suppression Systems Association (FSSA) has developed this handbook to provide
guidance to system designers on how to apply the ASME B31.1 Power Piping Code in a uniform
and consistent manner, in order to determine the maximum allowable internal working pressure
for piping used in special hazard fire suppression systems.
The FSSA Technical Committee was assigned the task to address this issue. The resulting
document provides the necessary guidelines, along with supplemental information, to assist the
system designer in complying with the requirements specified in the applicable NFPA Standards
related to the Power Piping Code. This handbook is currently referenced in several of the NFPA
standards.
The second edition of the handbook was published in August 2003, and includes revisions to
Section 3, Appendix A, and Appendix C; along with the addition of new Section 6 and new
Appendix B.
CAUTION
This document provides general guidelines and is not intended to provide all information
necessary to determine equipment and material requirements for specific installations or
applications. Always refer to the equipment manufacturer’s instructions and recommendations,
along with other regulations and NFPA Standards that may apply.
Some limitations and restrictions apply. Please refer to the text and notes, which follow.
This document is subject to modifications. Users should obtain the latest version. The
Association, its members, and those participating in its activities accept no responsibility or
liability to any one for the completeness or use of, or reliance on this document, or for
compliance with the provisions herein.
Section 1 / Page 1 of 3
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
1.0 INTRODUCTION
This document provides general information and guidelines on the design of piping and tubing
systems for use with all types of special hazard fire suppression systems, where the ASME
B31.1 Power Piping Code is specified. This Guide follows the general design parameters of the
Power Piping Code, but has been modified similar to the accepted formats found in NFPA-12A
and NFPA-2001.
An expanded list of pressure Tables are found in Section 3. These Tables provide the system
designer with maximum allowable internal working pressures that have been pre-calculated for
various types of pipe and tubing materials and end connections.
In all cases, the pipe and fittings shall have a minimum rated working pressure equal to or
greater than the minimum piping design working pressure specified in Appendix A of this
document, for the agent being used.
1.1 DEFINITIONS
Some terms used in this document, related to pipe and tubing and supports / hangers are
defined below.
Brazing:
A metal joining process where fusion is produced by use of a nonferrous filler metal having a
melting point above 800oF (425oC) but lower than that of the base metals used. The filler metal
is distributed between the closely fitted surfaces of the joint by capillary action.
Butt Joint:
A joint between two members lying approximately in the same plane.
Filler Metal:
Metal that is added during welding, soldering, or brazing.
Section 1 / Page 2 of 3
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Nominal Thickness:
The thickness given in the product material specification or standard, exclusive of
manufacturing tolerances.
A pipe is a tube of round cross section conforming to the dimensional requirements for
nominal pipe size as tabulated in ANSI B36.10.
A tube is a hollow product of round cross section that may be specified with respect to
any two, but not all three of the following: outside diameter, inside diameter, and wall
thickness. (Types K, L, and M copper tube may also be specified by nominal size and
type only).
Seamless Pipe:
Pipe produced by several methods that result in a round pipe that does not have a longitudinal
seam.
Soldering:
A metal joining process where fusion is produced by heating to a suitable temperature and by
using a nonferrous alloy that melts at temperatures below 800oF (425oC) and having a melting
point below that of the base metals being used.
Rigid Support:
The method of securing pipe or tubing to walls, ceiling structures or columns to prevent
movement in any direction.
Intermediate Support:
The method of supporting piping or tubing to counter the force of gravity. The supports are
normally located between rigid supports, but are not intended to counter longitudinal or lateral
sway, or as bracing against thrusts associated with changes in direction.
Section 1 / Page 3 of 3
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
The criteria specified follows the basic format found in NFPA-12A and NFPA-2001, and covers
pressure-temperature ratings for allowable stress, longitudinal joint efficiencies, end connection
factors, and other allowances and limitations used in the design of actuation and distribution
system piping.
2.1 Limitations established for pipe and tubing, used in special hazard fire suppression
systems, are set by:
(Note: Where the word “pipe” is used it is understood to also mean “tubing”).
(a) Maximum pressure expected in the pipe, or as specified in the applicable NFPA
Standard.
(b) Materials of construction of the pipe, tensile strength, yield strength, and temperature
limitations of the material.
(c) End connection joining methods, (e.g. threaded, welded, grooved, etc.).
(d) Pipe construction method, (e.g. seamless, ERW, furnace welded, etc.).
(e) Pipe diameter.
(f) Pipe wall thickness.
(g) Cast iron pipe, steel pipe conforming to ASTM A-120, aluminum pipe, or non-metallic
pipe, shall not be used.
(c) For piping, the calculations cover threaded, welded, brazed, rolled and cut groove,
end connections.
(d) For tubing, the calculations cover using compression or flare fittings; or welded,
brazed, or soldered end connections.
(e) Materials covered in the calculations include steel pipe and tubing, stainless steel
pipe and tubing, and copper tubing.
(f) Other metallic pipe and tubing can be used, provided that the appropriate SE values,
wall thickness, and end connection factors are substituted.
Section 2 / Page 1 of 5
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
The basic equation to be used to calculate the maximum allowable working pressure for
piping/tubing subject to internal pressure is:
P = 2SE (t-A)/D EQ #1
Where:
The term SE is generally defined as 1/4 of the tensile strength of the piping material or 2/3
of the yield strength (whichever is lower) multiplied by a longitudinal seam joint efficiency
factor, as noted below.
P = (2tSE)/D EQ #2
Section 2 / Page 2 of 5
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
The majority of special hazard fire suppression systems have piping systems that are not
normally pressurized. In addition, most of these systems have discharge times that are
considerably less than 60 minutes in duration, and therefore satisfy the criteria where the
SE values can be increased by 20% when calculating the maximum allowable working
pressures.
To directly address the most common type of systems, the maximum allowable working
pressures shown in the pipe pressure Tables in Section 3, use SE values that have been
increased by 20% for use with piping not normally pressurized. The 20% increase is
only valid where the duration of system discharge is limited to 60 minutes at any one time.
Reference Information
Paragraph 102.2.4 of the ASME B31.1b-2000 Addenda to the Power Piping Code,
recognizes that the piping system shall be considered safe under conditions where
the piping may be subjected to short periods of higher design pressure or
temperature. For this situation the ASME B31.1 Power Piping Code allows the
maximum allowable stress to be exceeded by:
(a) 15% increase in allowable stress, if the event duration occurs for no more
than eight hours (480 minutes) at any one time, and no more than 800
hours/year, or
(b) 20% increase in allowable stress, if the event duration occurs for no more
than 1 hour (60 minutes) at any one time, and no more than 80 hours/year.
Table 2-1 gives values for SE as taken from Appendix A of the ASME B31.1, Power Piping
Code, along with SE values increased by 20% for use in the calculations.
CAUTION
The SE values used in the calculations are also limited to the maximum temperatures
shown in Table 2-1. If higher temperatures are anticipated, then the SE values must
be reduced to agree with the values shown in Appendix A of the Power Piping Code at
the higher temperature for the piping materials being used.
Section 2 / Page 3 of 5
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 2-1
SE Value
Pipe or ASTM Spec (psi) (oF) SE Value
Tube Material Taken From Temperature Increased 20%
Appendix A Range (psi)
ASME B31.1
Steel Pipe
Seamless A 106 Gr. C 17500 -20 to +650 21000
Seamless A 53 Gr. B 15000 -20 to +650 18000
Seamless A 106 Gr. B 15000 -20 to +650 18000
Seamless A 53 Gr. A 12000 -20 to +650 14400
Seamless A 106 Gr. A 12000 -20 to +650 14400
ERW A 53 Gr. B 12800 -20 to +650 15360
ERW A 53 Gr. A 10200 -20 to +650 12240
Furnace Welded A 53 Gr. F 7200 -20 to +650 8640
Stainless Steel Pipe
Type 304 Seamless A 312 15700 -20 to +200 18840
Type 304 Welded A 312 13300 -20 to +200 15960
Type 304L Seamless A 312 13400 -20 to +200 16080
Type 304L Welded A 312 11400 -20 to +200 13680
Type 316 Seamless A 312 16200 -20 to +200 19440
Type 316 Welded A 312 13800 -20 to +200 16560
Type 316L Seamless A 312 13300 -20 to +200 15960
Type 316L Welded A 312 11300 -20 to +200 13560
Steel Tubing
Seamless A 179 11800 -20 to +650 14160
ERW A 178 Gr. A 10000 -20 to +650 12000
ERW A 178 Gr. C 12800 -20 to +650 15360
Stainless Steel Tubing
Type 304 Seamless A 213, A 269 15700 -20 to +200 18840
Type 304 ERW A 249, A 269 13300 -20 to +200 15960
Type 304L Seamless A 213, A 269 13400 -20 to +200 16080
Type 304L ERW A 249, A 269 11400 -20 to +200 13680
Type 316 Seamless A 213, A 269 16200 -20 to +200 19440
Type 316 ERW A 249, A 269 13800 -20 to +200 16560
Type 316L Seamless A 213, A 269 13300 -20 to +200 15960
Type 316L ERW A 249, A 269 11300 -20 to +200 13560
Copper Tubing
Seamless, Annealed B 88, B 280 5100 -20 to +150 6120
Seamless, Drawn B 88, B 280 9000 -20 to +250 10800
Section 2 / Page 4 of 5
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
To determine the maximum allowable working pressure for other type of systems (such as
where the piping is under continuous pressure, or for systems having longer discharge
times), the values of maximum allowable working pressure, shown in the Tables of Section
3, shall be reduced using the applicable multiplication factor shown below.
Section 2 / Page 5 of 5
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
CAUTIONS
a. The values of maximum allowable working pressure, shown in Tables 3-1 to 3-9, have
been calculated subject to the following limitations:
• The pipe/tubing system is not normally pressurized.
• System discharge time does not exceed 60 minutes in duration.
• The pipe/tubing is not normally exposed to ambient temperatures that exceed the
temperature limitations shown in Table 2-1, for the material being used.
b. If the pipe/tubing system is subjected to higher ambient temperatures for a specific
application, then the SE values and the resultant maximum allowable working pressures,
must be reduced to agree with the lower SE values coincident with the higher
temperatures for the material being used. The SE values and temperature data are
found in Appendix A of the Power Piping Code.
c. For pipe/tubing normally under continuous pressure, or for systems having longer
discharge times, the values of maximum allowable working pressure shown in Tables 3-1
to 3-9, shall be reduced using the following multiplication factors:
Multiply By
Section 3 / Page 1 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
The following examples provide typical procedures that can be used to select the proper pipe/tubing
for use in a specific application, where the ASME B31.1 Power Piping Code is specified.
3.1.1
Example #1: High Pressure CO2 System, using stainless steel tubing for the distribution
piping. (Note: NFPA-12, 2000 Edition, section 1-10.1.4 specifies that the minimum pipe design
pressure shall be 2,800 psi when using this material)
Given:
• The pipe/tubing is not normally pressurized.
• There are no stop valves between the agent containers and the nozzles.
• The discharge time is less than 60 minutes.
• The application requires that Type 304 seamless or welded (ERW) stainless steel tubing be
used.
• Tubing Size = 1” OD
• Minimum design pressure specified: 2,800 psi
• Use either flare or compression type tubing fittings (A=0).
• Maximum ambient temperature that the tubing will normally be exposed to: +120oF.
Find:
• Minimum wall thickness capable of withstanding a minimum allowable working pressure of
2,800 psi.
Procedure:
a. Check Table 2-1 for Type 304 stainless steel tubing. Note that the SE values are
acceptable for temperatures up to +200oF. This satisfies the requirement of +120oF.
b. Go to Table 3-7, titled “Stainless Steel Tubing with Welded, Brazed, Flared or Compression
Fitting Ends (A=0)”.
c. For 1” tube size, look under the Type 304 seamless and welded columns for wall thickness’
where the calculated working pressure is 2,800 psi or greater.
d. Inspection of Table 3-7 shows that the following sizes are acceptable:
• 1’” OD x 0.083” wall thickness (or greater) Type 304 seamless tubing is acceptable.
or:
• 1” OD x 0.095” wall thickness (or greater) Type 304 welded (ERW) tubing is acceptable.
e. Check with tubing supplier(s) for commercially available sizes and wall thickness.
f. Check with tubing fitting manufacturer(s) for pressure ratings of fittings.
Section 3 / Page 2 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
3.1.2
Example #2: 360 psi HFC-227ea Clean Agent System using threaded steel pipe.
Given:
• The piping is not normally pressurized.
• There are no stop valves between the agent containers and the nozzles.
• The discharge time is less than 60 minutes.
• The application allows the use of seamless, welded, or furnace welded steel pipe with
threaded end connections.
• Pipe sizes: 2” and 3” schedule 40.
• Minimum pipe design pressure: 416 psi. [This value obtained from NFPA-2001, 2000
edition, Table 2-2.1.1(b) for HFC-227ea at 72 Lb/Ft3 fill density].
• Use threaded fittings.
• Maximum ambient temperature that the pipe will normally be exposed to: +130oF.
Find:
• The types and grades of sch.40 steel pipe that can be used in both 2” and 3” sizes.
Procedure:
a. Check Table 2-1 for steel pipe. Note that the SE values are acceptable for temperatures
up to +650oF. This satisfies the requirement of +130oF.
b. Go to Table 3-1, titled “Steel Pipe with Threaded End Connections (A = thread depth)”.
Look in the sch. 40 section.
c. Look across the rows for 2” and 3” sizes, for the grades and types of steel pipe where
the calculated maximum allowable working pressures are equal to or greater than 416
psi.
d. Inspection shows that, for the 2” and 3” pipe sizes, all grades and types of sch. 40 steel
pipe are acceptable. (Note: Further inspection shows for this example, that all grades
and types of sch. 40 steel pipe can be used in all sizes up to 8” NPS).
e. Check pipe suppliers for commercial availability.
f. Check pressure rating of the threaded fittings to be used.
3.1.3
General Notes:
Note 1: When using copper tubing with brazed or soldered connections, the maximum
allowable stress (SE) must be based on the annealed value.
Note 2: Pipe supplied as dual stenciled A120/A53 Class F, meets the requirements of
Class F furnace welded ASTM A 53 as listed in Table 2-1.
Section 3 / Page 3 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-1
Maximum Allowable Working Pressure (psig)
Steel Pipe with Threaded End Connections (A = thread depth)
A-53B A-53A
NPS Wall “A” Grade: A-106C A-106B A-53B A-106A A-53A A-53F
Pipe Thick. Dim. Type: Smls. Smls. ERW Smls. ERW Furnace
Size (t) SE: 21000 18000 15360 14400 12240 8640
1/4 0.088 0.044 3422 2933 2503 2347 1995 1408
3/8 0.091 0.044 2924 2507 2139 2005 1704 1202
1/2 0.109 0.057 2593 2222 1896 1778 1511 1067
3/4 0.113 0.057 2234 1915 1634 1532 1302 919
1 0.133 0.070 2026 1736 1482 1390 1181 833
1-1/4 0.140 0.070 1782 1528 1304 1222 1038 732
Sch. 1-1/2 0.145 0.070 1667 1429 1220 1144 972 686
40 2 0.154 0.070 1494 1280 1093 1025 871 615
2-1/2 0.203 0.100 1505 1290 1100 1032 877 618
3 0.216 0.100 1392 1193 1018 954 811 572
4 0.237 0.100 1278 1096 935 876 745 526
5 0.258 0.100 1193 1022 872 818 693 490
6 0.280 0.100 1141 978 834 782 664 469
8 0.322 0.100 1081 926 790 740 630 444
1/4 0.119 0.044 5833 5000 4267 4000 3400 2400
3/8 0.126 0.044 5102 4373 3732 3499 2974 2099
1/2 0.147 0.057 4493 3851 3286 3080 2618 1848
3/4 0.154 0.057 3874 3320 2833 2657 2258 1593
1 0.179 0.070 3495 2996 2556 2397 2037 1437
1-1/4 0.191 0.070 3073 2634 2248 2107 1792 1264
1-1/2 0.200 0.070 2883 2472 2110 1978 1681 1186
Sch. 2 0.218 0.070 2625 2250 1920 1800 1530 1080
80 2-1/2 0.276 0.100 2571 2204 1882 1764 1499 1058
3 0.300 0.100 2400 2057 1756 1645 1399 986
4 0.337 0.100 2212 1896 1618 1517 1289 909
5 0.375 0.100 2076 1780 1518 1423 1210 853
6 0.432 0.100 2105 1804 1540 1442 1226 865
8 0.500 0.100 1948 1669 1424 1336 1135 801
4 0.437 0.100 3145 2696 2301 2157 1833 1293
Sch. 5 0.500 0.100 3020 2589 2209 2071 1760 1242
120 6 0.562 0.100 2929 2510 2142 2008 1707 1204
8 0.718 0.100 3009 2579 2201 2064 1754 1237
1/2 0.187 0.057 6500 5571 4754 4457 3789 2674
3/4 0.218 0.057 6440 5520 4710 4416 3754 2649
1 0.250 0.070 5749 4928 4205 3942 3351 2365
1-1/4 0.250 0.070 4554 3904 3331 3123 2654 1874
1-1/2 0.281 0.070 4664 3998 3412 3198 2719 1918
Sch. 2 0.343 0.070 4828 4138 3531 3310 2814 1986
160 2-1/2 0.375 0.100 4017 3443 2938 2755 2342 1652
3 0.437 0.100 4044 3466 2958 2773 2357 1663
4 0.531 0.100 4023 3448 2942 2758 2345 1654
5 0.625 0.100 3964 3397 2899 2718 2310 1630
6 0.718 0.100 3918 3358 2866 2687 2284 1611
8 0.906 0.100 3925 3364 2871 2691 2288 1614
Section 3 / Page 4 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
A-53B
NPS Wall “A” Grade: A-106B
Pipe Thick. Dim. Type: Smls.
Size (t) SE: 18000
1/2 0.294 .057 10157
3/4 0.308 .057 8606
1 0.358 .070 7884
1-1/4 0.382 .070 6766
1-1/2 0.400 .070 6253
XXS 2 0.436 .070 5548
2-1/2 0.552 .100 5660
3 0.600 .100 5143
4 0.674 .100 4592
5 0.750 .100 4206
6 0.864 .100 4152
8 0.875 .100 3235
Section 3 / Page 5 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-2
Maximum Allowable Working Pressure (psig)
Steel Pipe with Rolled Groove or Welded End Connections (A = 0)
A-53B A-53A
NPS Wall Grade: A-106C A-106B A-53B A-106A A-53A A-53F
Pipe Thick. Type: Smls. Smls. ERW Smls. ERW Furnace
Size (t) SE: 21000 18000 15360 14400 12240 8640
1/4 0.088 6844 5866 5006 4693 3989 2816
3/8 0.091 5662 4853 4145 3883 3300 2329
1/2 0.109 5450 4672 3986 3737 3176 2242
3/4 0.113 4520 3875 3306 3100 2634 1860
1 0.133 4248 3641 3107 2912 2475 1747
1-1/4 0.140 3542 3036 2591 2429 2064 1457
1-1/2 0.145 3205 2747 2344 2197 1868 1319
Sch. 2 0.154 2723 2334 1992 1867 1588 1120
40 2-1/2 0.203 2965 2542 2168 2033 1728 1220
3 0.216 2592 2221 1896 1777 1511 1066
4 0.237 2212 1896 1618 1516 1289 909
5 0.258 1948 1669 1424 1336 1135 801
6 0.280 1775 1522 1298 1217 1034 730
8 0.322 1568 1344 1147 1075 914 644
1/4 0.119 9256 7933 6770 6347 5395 3807
3/8 0.126 7840 6720 5734 5376 4570 3225
1/2 0.147 7350 6300 5376 5040 4284 3024
3/4 0.154 6160 5280 4506 4224 3590 2534
1 0.179 5717 4900 4182 3920 3332 2351
1-1/4 0.191 4833 4142 3535 3314 2816 1988
1-1/2 0.200 4421 3789 3234 3032 2576 1819
Sch. 2 0.218 3855 3304 2820 2644 2248 1586
80 2-1/2 0.276 4032 3456 2949 2765 2350 1659
3 0.300 3600 3086 2633 2469 2098 1417
4 0.337 3145 2696 2301 2157 1834 1295
5 0.375 3831 2427 2071 1941 1650 1164
6 0.432 2739 2347 2003 1878 1596 1126
8 0.500 2435 2087 1781 1670 1420 1001
4 0.437 4079 3496 2983 2797 2377 1678
Sch. 5 0.500 3775 3236 2761 2589 2200 1553
120 6 0.562 3563 3054 2606 2443 2077 1465
8 0.718 3496 2997 2557 2397 2038 1438
1/2 0.187 9350 8014 6839 6411 5450 3846
3/4 0.218 8720 7474 6378 5979 5083 3587
1 0.250 7985 6844 5840 5475 4654 3285
1-1/4 0.250 6325 5422 4627 4337 3687 2602
1-1/2 0.281 6212 5324 4543 4259 3620 2556
Sch. 2 0.343 6066 5199 4437 4159 3535 2496
160 2-1/2 0.375 5478 4696 4007 3757 3193 2254
3 0.437 5244 4495 3836 3596 3057 2157
4 0.531 4956 4248 3625 3398 2889 2039
5 0.625 4719 4045 3451 3236 2750 1941
6 0.718 4552 3902 3329 3121 2653 1873
8 0.906 4412 3782 3227 3025 2571 1814
Section 3 / Page 6 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
A-53B
NPS Wall Grade: A-106B
Pipe Thick. Type: Smls.
Size (t) SE: 18000
1/2 0.294 12600
3/4 0.308 10560
1 0.358 9801
1-1/4 0.382 8284
1-1/2 0.400 7579
XXS 2 0.436 6609
2-1/2 0.552 6912
3 0.600 6171
4 0.674 5392
5 0.750 4853
6 0.864 4695
8 0.875 3652
Section 3 / Page 7 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-3
Maximum Allowable Working Pressure (psig)
Steel Pipe with Cut Groove End Connections (A = Groove Depth)
A-53B A-53A
NPS Wall "A" Grade: A-106C A-106B A-53B A-106A A-53A A-53F
Pipe OD Thick. Dim. Type: Smls. Smls. ERW Smls. ERW Furnace
Size (t) SE: 21000 18000 15360 14400 12240 8640
1/2 0.840 0.109 0.056 2650 2271 1938 1817 1545 1090
3/4 1.050 0.113 0.056 2280 1954 1668 1563 1329 938
1 1.315 0.133 0.063 2236 1916 1635 1533 1303 920
1 1/4 1.660 0.140 0.063 1948 1670 1425 1336 1136 802
Sch. 1 1/2 1.900 0.145 0.063 1813 1554 1326 1243 1057 746
40 2 2.375 0.154 0.063 1609 1379 1177 1103 938 662
2 1/2 2.875 0.203 0.078 1826 1565 1336 1252 1064 751
3 3.500 0.216 0.078 1656 1419 1211 1136 965 681
4 4.500 0.237 0.083 1437 1232 1051 986 838 591
5 5.563 0.258 0.084 1314 1126 961 901 766 540
6 6.625 0.280 0.085 1236 1060 904 848 721 509
8 8.625 0.322 0.092 1120 960 819 768 653 461
1/2 0.840 0.147 0.056 4550 3900 3328 3120 2652 1872
3/4 1.050 0.154 0.056 3920 3360 2867 2688 2285 1613
1 1.315 0.179 0.063 3705 3176 2710 2541 2159 1524
1 1/4 1.660 0.191 0.063 3239 2776 2369 2221 1888 1332
1 1/2 1.900 0.200 0.063 3028 2596 2215 2077 1765 1246
Sch. 2 2.375 0.218 0.063 2741 2349 2005 1880 1598 1128
80 2 1/2 2.875 0.276 0.078 2893 2479 2116 1983 1686 1190
3 3.500 0.300 0.078 2664 2283 1949 1827 1553 1096
4 4.500 0.337 0.083 2371 2032 1734 1626 1382 975
5 5.563 0.375 0.084 2197 1883 1607 1507 1281 904
6 6.625 0.432 0.085 2200 1886 1609 1508 1282 905
8 8.625 0.500 0.092 1987 1703 1453 1362 1158 817
4 4.500 0.437 0.083 3304 2832 2417 2266 1926 1359
Sch. 5 5.563 0.500 0.084 3141 2692 2297 2154 1831 1292
120 6 6.625 0.562 0.085 3024 2592 2212 2074 1763 1244
8 8.625 0.718 0.092 3048 2613 2230 2090 1777 1254
1/2 0.840 0.187 0.056 6550 5614 4791 4491 3818 2695
3/4 1.050 0.218 0.056 6480 5554 4740 4443 3777 2666
1 1.315 0.250 0.063 5973 5119 4369 4096 3481 2457
1 1/4 1.660 0.250 0.063 4731 4055 3461 3244 2758 1947
1 1/2 1.900 0.281 0.063 4819 4131 3525 3304 2809 1983
Sch. 2 2.375 0.343 0.063 4952 4244 3622 3395 2886 2037
160 2 1/2 2.875 0.375 0.078 4339 3719 3174 2975 2529 1785
3 3.500 0.437 0.078 4308 3693 3151 2954 2511 1772
4 4.500 0.531 0.083 4181 3584 3058 2867 2437 1720
5 5.563 0.625 0.084 4084 3501 2988 2801 2381 1680
6 6.625 0.718 0.085 4013 3440 2935 2752 2339 1651
8 8.625 0.906 0.092 3964 3398 2899 2718 2310 1631
TABLE 3-4
Maximum Allowable Working Pressure (psig)
Stainless Steel Pipe with Threaded End Connections (A = Thread Depth)
Note: Some sizes, grades and schedule combinations may not be commercially available.
All dimensions are in inches.
Section 3 / Page 9 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-5
Maximum Allowable Working Pressure (psig)
Stainless Steel Pipe with Welded End Connections (A = 0)
Note: Some sizes, grades and schedule combinations may not be commercially available.
All dimensions are in inches.
Section 3 / Page 10 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-6
Maximum Allowable Working Pressure (psig)
Steel Tubing with Welded, Brazed, Flared or Compression Fitting Ends (A = 0)
A-178 A-178 A-178 A-178
Nom. Wall Grade: A-179 Gr. C Gr. A Nom. Wall Grade: A-179 Gr. C Gr. A
Tube OD Thick. Type: Smls. ERW ERW Tube OD Thick. Type: Smls. ERW ERW
Size (t) SE: 14160 15360 12000 Size (t) SE: 14160 15360 12000
0.250 0.022 2492 2703 2112 1.000 0.028 793 860 672
0.250 0.028 3172 3441 2688 1.000 0.035 991 1075 840
0.250 0.032 3625 3932 3072 1.000 0.049 1388 1505 1176
0.250 0.035 3965 4301 3360 1.000 0.058 1643 1782 1392
1/4 0.250 0.042 4758 5161 4032 1.000 0.065 1841 1997 1560
0.250 0.049 5551 6021 4704 1.000 0.072 2039 2212 1728
0.250 0.065 7363 7987 6240 1.000 0.083 2351 2550 1992
0.250 0.083 9402 10199 7968 1.000 0.095 2690 2918 2280
0.250 0.095 10762 11674 9120 1 1.000 0.109 3087 3348 2616
0.375 0.022 1661 1802 1408 1.000 0.120 3398 3686 2880
0.375 0.028 2115 2294 1792 1.000 0.134 3795 4116 3216
0.375 0.032 2417 2621 2048 1.000 0.156 4418 4792 3744
0.375 0.035 2643 2867 2240 1.000 0.172 4871 5284 4128
0.375 0.049 3700 4014 3136 1.000 0.188 5324 5775 4512
3/8 0.375 0.058 4380 4751 3712 1.000 0.219 6202 6728 5256
0.375 0.065 4909 5325 4160 1.000 0.250 7080 7680 6000
0.375 0.083 6268 6799 5312 1.000 0.281 7958 8632 6744
0.375 0.095 7174 7782 6080 1.000 0.313 8864 9615 7512
0.375 0.120 9062 9830 7680 1.000 0.375 10620 11520 9000
0.500 0.035 1982 2150 1680 1.250 0.035 793 860 672
0.500 0.049 2775 3011 2352 1.250 0.049 1110 1204 941
0.500 0.058 3285 3564 2784 1.250 0.065 1473 1597 1248
0.500 0.065 3682 3994 3120 1.250 0.083 1880 2040 1594
0.500 0.072 4078 4424 3456 1.250 0.095 2152 2335 1824
1/2 0.500 0.083 4701 5100 3984 1.250 0.109 2470 2679 2093
0.500 0.095 5381 5837 4560 1.250 0.120 2719 2949 2304
0.500 0.109 6174 6697 5232 1.250 0.125 2832 3072 2400
0.500 0.120 6797 7373 5760 1 1/4 1.250 0.134 3036 3293 2573
0.500 0.134 7590 8233 6432 1.250 0.156 3534 3834 2995
0.500 0.156 8836 9585 7488 1.250 0.188 4259 4620 3610
0.500 0.188 10648 11551 9024 1.250 0.219 4962 5382 4205
5/8 0.625 0.065 2945 3195 2496 1.250 0.250 5664 6144 4800
0.750 0.035 1322 1434 1120 1.250 0.281 6366 6906 5395
0.750 0.049 1850 2007 1568 1.250 0.313 7091 7692 6010
0.750 0.058 2190 2376 1856 1.250 0.344 7794 8454 6605
0.750 0.065 2454 2662 2080 1.250 0.375 8496 9216 7200
0.750 0.072 2719 2949 2304 1.250 0.438 9923 10764 8410
0.750 0.083 3134 3400 2656
0.750 0.095 3587 3891 3040
3/4 0.750 0.109 4116 4465 3488
0.750 0.120 4531 4915 3840
0.750 0.134 5060 5489 4288
0.750 0.156 5891 6390 4992
0.750 0.172 6495 7045 5504
0.750 0.188 7099 7700 6016
0.750 0.219 8269 8970 7008
0.750 0.250 9440 10240 8000
Section 3 / Page 11 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 3 / Page 12 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
A-178 A-178
Nom. Wall Grade: A-179 Gr. C Gr. A
Tube OD Thick. Type: Smls. ERW ERW
Size (t) SE: 14160 15360 12000
3.000 0.313 2955 3205 2504
3.000 0.344 3247 3523 2752
3.000 0.375 3540 3840 3000
3.000 0.437 4125 4475 3496
3.000 0.500 4720 5120 4000
3 3.000 0.563 5315 5765 4504
3.000 0.625 5900 6400 5000
3.000 0.688 6495 7045 5504
3.000 0.750 7080 7680 6000
3.000 0.875 8260 8960 7000
3.000 1.000 9440 10240 8000
3.250 0.120 1046 1134 886
3 1/4 3.250 0.134 1168 1267 990
3.250 0.148 1290 1399 1093
3.250 0.180 1568 1701 1329
3 1/2 3.500 0.120 971 1053 823
3.500 0.134 1084 1176 919
4 4.000 0.134 949 1029 804
4.000 0.148 1048 1137 888
4 1/2 4.500 0.134 843 915 715
4.500 0.148 931 1010 789
Section 3 / Page 13 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-7
Maximum Allowable Working Pressure (psig)
Stainless Steel Tubing with Welded, Brazed, Flared or Compression Fitting Ends (A = 0)
Section 3 / Page 14 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Note: Some sizes, grades and schedule combinations may not be commercially available.
Maximum allowable pressure may be limited by the fitting used.
All dimensions are in inches.
Section 3 / Page 15 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-8
Maximum Allowable Working Pressure (psig)
ASTM B-88 Seamless Copper Water Tubing with Brazed, Flared
or Compression Fitting Ends (A = 0)
Nom. Tube Wall Grade: B-88 B-88
Tube OD Type Thick. Type: Drawn Annealed
Size (t) SE: 10800 6120
0.375 K 0.035 2016 1142
1/4 0.375 L 0.030 1728 979
0.375 M 0.025 1440 816
0.500 K 0.049 2117 1200
3/8 0.500 L 0.035 1512 857
0.500 M 0.025 1080 612
0.625 K 0.049 1693 960
1/2 0.625 L 0.040 1382 783
0.625 M 0.028 968 548
0.750 K 0.049 1411 800
5/8 0.750 L 0.042 1210 685
0.750 M 0.032 922 522
0.875 K 0.065 1605 909
3/4 0.875 L 0.045 1111 629
0.875 M 0.032 790 448
1.125 K 0.065 1248 707
1 1.125 L 0.050 960 544
1.125 M 0.035 672 381
1.375 K 0.065 1021 579
1 1/4 1.375 L 0.055 864 490
1.375 M 0.042 660 374
1.625 K 0.072 957 542
1 1/2 1.625 L 0.060 798 452
1.625 M 0.049 651 369
2.125 K 0.083 844 478
2 2.125 L 0.070 712 403
2.125 M 0.058 590 334
2.625 K 0.095 782 443
2 1/2 2.625 L 0.080 658 373
2.625 M 0.065 535 303
3.125 K 0.109 753 427
3 3.125 L 0.090 622 353
3.125 M 0.072 498 282
3.625 K 0.120 715 405
3 1/2 3.625 L 0.100 596 338
3.625 M 0.083 495 280
4.125 K 0.134 702 398
4 4.125 L 0.110 576 326
4.125 M 0.095 497 282
5.125 K 0.160 674 382
5 5.125 L 0.125 527 299
5.125 M 0.109 459 260
6.125 K 0.192 677 384
6 6.125 L 0.140 494 280
6.125 M 0.122 430 244
8.125 K 0.271 720 408
8 8.125 L 0.200 532 301
8.125 M 0.170 452 256
Note: If soldering or brazing drawn (straight) tubing use annealed allowable pressure.
Maximum allowable pressure may be limited by the fitting used. All dimensions are in inches.
Section 3 / Page 16 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 3-9
Maximum Allowable Working Pressure (psig)
ASTM B-280 Seamless Copper Refrigeration Tubing with Brazed, Flared
or Compression Fitting Ends (A = 0)
Note: If soldering or brazing drawn (straight) tubing use annealed allowable pressure.
Maximum allowable pressure may be limited by the fitting used.
All dimensions are in inches.
Section 3 / Page 17 of 17
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
These tables provide guidance to assist the system designer in selection of pipe fittings used in
a particular application. It is recommended that the maximum allowable pressure ratings be
verified with the fitting manufacturer for the type of fittings being used. In addition, the pipe
fitting requirements specified in the suppression system equipment manufacturer's listed design
manual, and in the applicable NFPA Standards, should also be consulted.
If there are differences between the rated working pressure values shown in the tables of this
section, and the fittings specified in the equipment manufacturer’s listed manual or in the
applicable NFPA Standards, then the fitting requirements shown in the equipment
manufacturer’s manual and/or the applicable NFPA Standard shall take precedent.
Fittings shall have a minimum rated working pressure equal to or greater than the minimum
piping design working pressure specified in Appendix A of this document, for the agent being
used.
The following tables provide values of maximum allowable working pressure for various types of
fittings.
TABLE 4-1
MALLEABLE IRON THREADED FITTINGS
Reference: ANSI B16.3
MAXIMUM RATED
SERVICE PRESSURE
TEMPERATURE FITTING NPS FITTING SIZE
DEGREES F. CLASS 1/4" to 1" 1 1/4" to 2" 2 1/2" to 4" 5" to 8"
-20 TO 150 150 lb. Class (PSIG) 300 300 300 300
-20 TO 150 300 lb. Class (PSIG) 2000 1500 1000 800
Note: 300 lb. Class street elbows are not recommended for pressures above 600 psi.
Section 4 / Page 1 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 4-2
GROOVED FITTINGS AND COUPLINGS
Gruvlok
Grooved Fittings 1" - 8" 500
Fig. 7000 Coupling 1" - 4" 500
Fig. 7000 Coupling 6" - 8" 500
Fig. 7001 Standard Coupling 1" - 8" 500
Fig. 7013 Flange 2" - 8" 500
Fig. 7401 Rigidlok 1 1/2" - 2 1/2" 750
3” - 4” 600
5” - 6” 500
8” 450
Note: Underwriters Laboratories has indicated that listed rubber gasketed fittings (couplings
and fittings rated to 500 PSI minimum) that are not under continuous exposure to HFC-
227ea, and are downstream of the pressure reducing device, can be utilized in 360 psi
HFC-227ea fixed extinguishing systems.
Section 4 / Page 2 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 4-3
FORGED STEEL THREADED FITTINGS
Reference: ANSI B16.11
TABLE 4-4
FORGED STEEL FLANGES
WITH STANDARD FACINGS (OTHER THAN RING JOINTS)
Reference: ANSI B16.5 Material ASTM A-105
Note: The pressure ratings of forged steel flanges are dependent on the type of gasket facing
and the ASTM Grade of material used.
TABLE 4-5
DUCTILE IRON PIPE FITTINGS
Section 4 / Page 3 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 4-6
STAINLESS STEEL THREADED FITTINGS
Reference: ASTM A-16.2, ANSI B16.11
TABLE 4-7a
STANDARD WEIGHT – CARBON STEEL BUTTWELD FITTINGS
Reference: ANSI B16.9
**WORKING
PRESSURE -
PSIG AT THE
SIZE OF *WALL FAHRENHEIT
FITTING THICKNESS TEMPERATURES
INCHES INCHES INDICATED)
-20 to 650 ºF
1/2" 0.109 1695
3/4" 0.113 1455
1" 0.133 1575
1 - 1/4" 0.140 1065
1 - 1/2" 0.145 1005
2" 0.154 900
2 - 1/2" 0.203 1215
3" 0.216 1095
3 - 1/2" 0.226 1020
4" 0.237 975
5" 0.258 885
6" 0.280 840
8" 0.322 765
Section 4 / Page 4 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 4-7b
EXTRA STRONG – CARBON STEEL BUTTWELD FITTINGS
Reference: ANSI B16.9
**WORKING
PRESSURE -
SIZE OF *WALL (PSIG AT THE
FITTING THICKNESS FAHRENHEIT
INCHES INCHES TEMPERATURES
INDICATED)
-20 to 650 ºF.
1/2" 0.147 3030
3/4" 0.154 2595
1" 0.179 2610
1 - 1/4" 0.191 1935
1 - 1/2" 0.200 1815
2" 0.218 1665
2 - 1/2" 0.276 1935
3" 0.300 1770
3 - 1/2" 0.318 1665
4" 0.337 1590
5" 0.375 1470
6" 0.432 1470
8" 0.500 1350
TABLE 4-7c
FORGED STEEL SOCKET-WELD FITTINGS
Reference: ANSI B16.11
Section 4 / Page 5 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Tube fittings are rated to the maximum working pressure of tubing as shown in tables 3-6, 3-7,
3-8 and 3-9 of this document. Compression fittings that have NPT (female or male) pipe
threads are an exception and the fitting manufacturer shall be consulted.
The manufacturer of compression fittings being considered for use, should be consulted prior to
the use of the fittings with hard drawn copper tubing. Most manufacturers require the tubing be
“soft annealed” copper to ensure safe, reliable, leak-free connections. In addition, the metal
tubing material should be softer than the fitting material. (For example: stainless steel tubing
should not be used with brass fittings)
Section 4 / Page 6 of 6
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
These “closed sections of pipe” historically have been located between the agent containers
and stop valves. In this scenario the possibility exists that extinguishing agent may be trapped
in this section from actuation of the system agent containers. Because of this possibility,
pressure relief devices are required to be installed in these pipe sections, in order to prevent
over pressurization, in the event of high temperature exposure, and/or liquid full conditions that
may occur when liquefied extinguishing agents are used.
The pressure relief devices are designed to operate at higher than normal pressure. The
operating range of these relief devices may be specified in the applicable NFPA Standard, or
the equipment Manufacturer’s Listed Design Manual.
5.2.1
Select the proper pressure relief device as specified in the applicable NFPA Standard, the
manufacturer’s design manual, and/or other applicable standards.
5.2.1.1
The minimum allowable working pressure of the pipe must be equal to or greater than the
maximum operating pressure of the pressure relief device.
5.2.1.2
From the pipe tables in Section 3 select the desired type pipe that has a maximum allowable
working pressure equal to or greater than the maximum operating pressure of the pressure
relief device.
Section 5 / Page 1 of 1
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
These general guidelines are not intended to provide all information necessary to determine
equipment and material requirements for specific installations or applications.
Specific installation guidelines, as provided by the manufacturer of pipe supports and/or pipe
support systems, shall be followed.
The design examples provided in this section are typical of installations in the industry. Load
calculations have not been performed for any examples shown.
6.1.1 Conventional hanger design which is generally accepted as good practice, using standard
stock or production units, as manufactured by recognized manufacturers, shall be utilized
whenever possible.
6.1.2 All piping must be solidly anchored to walls, ceiling structure, floors, or columns by angle
iron brackets, channels / struts or equivalent brackets where longitudinal or lateral sway may
occur. Particular attention must be paid to the bracing of all changes in piping direction, nozzle
piping and header piping. As a minimum, rigid pipe supports shall be provided at all locations
where piping changes direction (See Figure 6-1).
FIGURE 6-1
Notes:
1. Actual number of braces will depend upon piping and nozzle arrangement.
2. Nozzles with different orifice orientation may require different types of bracing to counter
thrusts due to direction of agent discharge (Example: 360o, 180o, and orifices angled off the
horizontal).
Section 6 / Page 1 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
6.1.3 Pipe support components shall be steel and adequate to support the pipe in response to
movements created by changing thermal conditions, and to allow for free and ample movement
for contraction except where anchored, thereby preventing excessive stress. Consideration
should be given to avoidance of rigidly restraining both ends of long pipe runs subject to
expansion or contraction. Either one or the other end of the pipe run should be supported with
an intermediate type hanger which will allow free movement of the piping and to avoid buckling
or separation due to expansion or contraction.
6.1.4 Where rod type hangers are permitted for intermediate support between rigid supports,
they shall be steel clevis or steel band hangers of the proper size for the supported pipe and
with solid bar-type hanger rod. Hanger rods shall not be subjected to stresses due to bending.
6.1.5 Grooved pipe, fittings, and couplings must be supported and anchored exactly per the
manufacturer’s specification. Installation shall be such as to allow for contraction over the
anticipated temperature range and pressure thrusts. Consideration should be given to provide
a minimum of two hangers per length of grooved pipe to avoid injury or accident during
installation or maintenance of piping. No grooved pipe length should be left unsupported
between any two couplings.
6.1.6 Cast iron supports, conduit clamps or “C” clamps shall not be used to support piping. All
parts of the supporting equipment shall be fabricated, assembled and installed so that they will
not be disengaged by movement of the supported pipe. Drilling of, welding or the use of beam
clamps are acceptable means of attaching hangers to the building structure. A pipeline is not to
be supported from another pipeline.
6.1.7 All pipe supports shall be installed to avoid interference with other piping, hangers,
electrical conduit, and supports or building structure and equipment.
6.1.8 Supports shall be sufficiently close together to avoid excessive bending stresses from
concentrated loads between supports. (Refer to Table 6-1, Maximum Horizontal Spacing
Between Pipe Supports for Screwed, Welded, Or Grooved Pipe with Rod Diameters and Table
6-2, Maximum Horizontal Spacing Between Tubing Supports with Rod Diameters.)
6.1.9 When using concrete inserts or power driven studs, the manufacturer’s specifications
must be followed. Consideration should be given to minimum and maximum engagement
depths, edge distances, minimum spacing of anchors in the concrete and the quality of the
concrete.
6.1.10 When using channel / strut refer to manufacturer information for limitations.
6.1.11 Consideration shall be given to providing ring inserts to resist galvanic corrosion when
piping and hanger rings or U-bolts are of dissimilar metals.
6.1.12 For guidelines on the application of seismic bracing and supports refer to the following
documents:
9 MSS SP-127-2001 Bracing for Piping Systems Seismic – Wind – Dynamic Design,
Selection, Application – Latest Edition
Section 6 / Page 2 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
6.2 Following are eighteen (18) examples of rigid pipe hangers. Specific installation guidelines,
as provided by the manufacturer of pipe supports and/or pipe support systems, shall be
followed.
Section 6 / Page 3 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 4 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 5 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 6 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 7 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 8 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
6.3 Following are eleven (11) examples of intermediate pipe hangers. Specific installation
guidelines, as provided by the manufacturer of pipe supports and/or pipe support systems,
shall be followed.
Section 6 / Page 9 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 10 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 11 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 6 / Page 12 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
TABLE 6-1
MAXIMUM HORIZONTAL SPACING BETWEEN PIPE SUPPORTS
FOR SCREWED, WELDED, OR GROOVED PIPE WITH ROD DIAMETERS
Reference: MSS SP-69-1996
Distance
Pipe Between Rod
Size Supports Diameter
(inches) (feet) (inches)
¼” 7 3/8
½” 7 3/8
¾” 7 3/8
1” 7 3/8
1 ¼” 7 3/8
1 ½” 9 3/8
2” 10 3/8
2 ½” 11 1/2
3” 12 1/2
4” 14 5/8
5” 16 5/8
6” 17 3/4
8” 19 3/4
TABLE 6-2
MAXIMUM HORIZONTAL SPACING BETWEEN TUBING SUPPORTS
WITH ROD DIAMETERS
Reference: MSS SP-69-1996
Distance
Tubing Between Rod
Size Supports Diameter
(inches) (feet) (inches)
¼” 5 3/8
½” 5 3/8
¾” 5 3/8
1” 6 3/8
1 ¼” 7 3/8
1 ½” 8 3/8
2” 8 3/8
2 ½” 9 1/2
3” 10 1/2
4” 12 1/2
5” 13 1/2
6” 14 5/8
8” 16 3/4
Section 6 / Page 13 of 13
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
APPENDIX A
A.0 PIPE REQUIREMENTS FOR FSSA EQUIPMENT MANUFACTURER’S
ENGINEERED SYSTEMS
Section 7 / Page 1 of 2
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Section 7 / Page 2 of 2
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
APPENDIX B
B.1 PIPE FITTINGS FOR USE IN CLEAN AGENT SYSTEM PIPING
Fittings that are acceptable for use in clean agent systems are found in Table B.1 and Table
B.2. The fittings shown in these tables are based on use in open ended piping systems.
For fittings used in closed sections of pipe, Section 5 of this Handbook should be consulted.
TABLE B.1 Pipe Fittings for Use in Clean Agent Systems (Note 1)
Pressure in Fitting
Agent Container Minimum Design
o
Clean Agent at 70 F Pressure Minimum Maximum
o
(up to and At 70 F Acceptable Fittings Pipe Size
including) (Note 2)
(psig) (psig) (NPS)
All Halocarbon 360 416 Class 300-lb. thrd. malleable iron. 6”
Agents 500 for HFC-125 Class 300-lb. thrd. ductile iron. 6”
(Except HFC-23) Groove type fittings (Note 3). 6”
Class 300-lb. flanged joints. All
600 820 Class 300-lb. thrd. malleable iron 4”
Class 2,000-lb. thrd./weld F.S. All
Class 400-lb. flanged joint All
HFC-23 609 1,371 Class 300-lb. thrd. malleable iron 2”
(Note 4) Class 2,000-lb. thrd./weld F.S. All
Class 600-lb. flanged joint All
IG-541 2,175 2,175 Class 2,000-lb. thrd. forged steel 2-1/2”
Upstream of the Class 3,000-lb. thrd/weld F.S All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
2,900 2,900 Class 2,000-lb. thrd. forged steel 1”
Upstream of the Class 3,000-lb. thrd./weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
IG-01 2,370 2,370 Class 2,000-lb. thrd forged steel 1-1/2”
Upstream of the Class 3,000-lb. thrd/weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
2,964 2,964 Class 2,000-lb. thrd forged steel 1”
Upstream of the Class 3,000-lb. thrd/weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
Section 8 / 1 of 4
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Pressure in Fitting
Agent Container Minimum Design
o
Clean Agent at 70 F Pressure Minimum Maximum
o o
(up to and At 70 F (21 C) Acceptable Fittings Pipe Size
including) (Note 2)
(psig) (psig) (NPS)
IG-55 2,175 2,175 Class 2,000-lb. thrd forged steel 2-1/2”
Upstream of the Class 3,000-lb. thrd/weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
2,900 2,900 Class 2,000-lb. thrd forged steel 1”
Upstream of the Class 3,000-lb. thrd/weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
4,350 4,350 Class 3,000-lb. thrd/weld F.S. 1”
Upstream of the Class 6,000-lb. thrd/weld F.S. All
pressure reducer Class 2,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
Section 8 / Page 2 of 4
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Pressure in Fitting
Agent Container Minimum Design
o
Clean Agent at 70 F Pressure Minimum Maximum
o
(up to and At 70 F Acceptable Fittings Pipe Size
including) (Note 2)
(psig) (psig) (NPS)
IG-100 2,404 2,404 Class 2,000-lb. thrd forged steel 1-1/2”
Upstream of the Class 3,000-lb. thrd/weld F.S. All
pressure reducer Class 1,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) Note 5)
(Note 5)
3,236 3,236 Class 2,000-lb. thrd forged steel 3/4”
Upstream of the Class 3,000-lb. thrd/weld F.S All
pressure reducer Class 1,500-lb.flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
4,061 4,061 Class 3,000-lb. thrd/weld F.S. 1”
Upstream of the Class 6,000-lb. thrd/weld F.S. All
pressure reducer Class 2,500-lb. flanged joint All
Downstream of the
pressure reducer (Note 5) (Note 5)
(Note 5)
Notes:
1. All fitting ratings shown are based on open ended piping systems.
2. Minimum design pressures are taken from Table 2-2.1.1(a) and Table 2-2.1.1(b) of NFPA-
2001.
3. Check with grooved fitting manufacturers for pressure ratings.
4. This value good for all fill densities up to 48 lb/ft3.
5. The minimum design pressure, for fittings downstream of the pressure reducer, should be
determined by system flow calculations. Acceptable pipe fittings for several values of
pressures downstream of the pressure reducer can be found in Table B.2.
6. The materials shown in Tables B.1 and B.2 do not preclude the use of other materials and
other types and style of fittings that satisfy the pressure requirements.
7. The pressure ratings of the forged steel threaded or welded fittings are based on the
pressure equivalent of the numerical class of the fitting or on the pressure rating of ASTM
A-106, Grade B seamless steel pipe, whichever is higher.
Section 8 / Page 3 of 4
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
Maximum Pressure
Downstream of the
Pressure Reducer
o
At 70 F Minimum Maximum
(up to and Acceptable Fittings Pipe Size
including) (NPS)
(psig)
Class 300-lb. thrd. malleable iron 4”
1,000 Class 2,000-lb. thrd/welded forged steel All
Class 3,000-lb. thrd/welded forged steel All
Class 600-lb. flanged joint All
Class 300-lb. thrd. malleable iron 2”
1,350 Class 2,000-lb. thrd/welded forged steel All
Class 3,000-lb. thrd/welded forged steel All
Class 600-lb. flanged joint All
Class 300-lb. thrd. malleable iron 2”
1,500 Class 2,000-lb. thrd/welded forged steel All
Class 3,000-lb. thrd/welded forged steel All
Class 900-lb. flanged joint All
Class 300-lb. thrd. malleable iron 1”
2,000 Class 2,000-lb. thrd/welded forged steel All
Class 3,000-lb. thrd/welded forged steel All
Class 900-lb. flanged joint All
Section 8 / Page 4 of 4
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
APPENDIX C
C.0 REFERENCES
C.1 PUBLICATIONS
♦ ASTM A53 – Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and
Seamless
♦ ASTM A106 – Seamless Carbon Steel Pipe for High-Temperature Service
♦ ASTM A178 – Electric-Resistance-Welded Carbon Steel Tubes
♦ ASTM A179 – Seamless Cold Drawn Low-Carbon Steel Heat Exchanger and
Condenser Tubes
♦ ASTM A213 – Seamless Ferritic and Austenitic Alloy – Steel Boiler, Superheater,
and Heat Exchanger Tubes
♦ ASTM A249 – Welded Austenitic Steel Boiler, Superheater, Heat Exchanger, and
Condenser Tubes
♦ ASTM A269 – Seamless and Welded Austenitic Stainless Steel Tubing for
General Service
♦ ASTM A312 – Seamless and Welded Austenitic Stainless Steel Pipe
♦ ASTM B88 – Seamless Copper Water Tube
♦ ASTM B280 – Seamless Copper Tube for Air Conditioning and Refrigeration
Service
Section 9 / Page 1 of 2
FSSA PDH-01 FSSA Pipe Design Handbook
August 2003
a. ASME International
22 Law Drive
P.O. Box 2900
Fairfield, NJ 07007-2900
Phone: 800-843-2763
973-882-1167
Fax: 973-882-1717
Website: asme.org
b. NFPA Standards
National Fire Protection Association
11 Tracy Drive
Avon, MA 02322-9908
Phone: 800-344-3555
Fax: 800-593-6372
Website: www.nfpa.org
c. ASTM Standards
American Society for Testing and Materials
100 Bar Harbor Drive
West Conshohocken, PA 19428-2959
Phone: 610-832-9585
Website: astm.org
Section 9 / Page 2 of 2