0% found this document useful (0 votes)
116 views

Project Management Professional PMP Formulas

This document provides an overview of key formulas used in project management. It includes formulas for project selection, time value of money, earned value management, risk management, communications planning, procurement, estimates, control limits, network diagrams, PERT charts, and crashing a project. Over 30 different formulas are defined across these core project management topics in a high-level "formulas snapshot" format.

Uploaded by

sachingandhi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views

Project Management Professional PMP Formulas

This document provides an overview of key formulas used in project management. It includes formulas for project selection, time value of money, earned value management, risk management, communications planning, procurement, estimates, control limits, network diagrams, PERT charts, and crashing a project. Over 30 different formulas are defined across these core project management topics in a high-level "formulas snapshot" format.

Uploaded by

sachingandhi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

www.ArmadilloConsultants.

com

PROJECT
MANAGEMENT
PROFESSIONAL (PMP)
Related Formulas

Project Management - Subject Matter Experts


www.ArmadilloConsultants.com

Formulas Snapshot Risk P – Probability


I – Impact
 Expected Monetary Value(EMV) = 𝑃 ∗ 𝐼
Project Selection PV – Present Value
𝐹𝑉 FV- Future Value
 PV = r – Interest rate Earned Value Management (EVM)
(1+𝑟)𝑛 n – time period 𝑃𝑉
 FV = PV * (1 + 𝑟)𝑛 NPV – Net Present Value  EV =
𝐴𝐶
ROI – Rate of Interest CV – Cost Variance
 NPV = Pick the biggest number. IRR – Internal Rate of  CV = EV – AC
SV – Schedule Variance
 ROI = Pick the biggest number. Return  SV = EV – PV AC – Actual Cost
BCR – Benefit Cost Ratio 𝐸𝑉 PV – Present Value
 IRR = Pick the biggest number.  CPI =
CBR – Cost Benefit Ratio 𝐴𝐶 CPI – Cost Performance Index
𝐸𝑉 SPI – Schedule Performance Index
 SPI = EAC – Estimate at Completion
 Payback Period = 𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑒𝑑 𝐶𝑎𝑠𝑕 𝐼𝑛𝑓𝑙𝑜𝑤 − 𝑖=0 𝐸𝑥𝑝𝑒𝑛𝑠𝑒𝑠 𝑃𝑉
BAC – Budget at Completion
𝐵𝐴𝐶 TCPI – To Complete Performance Index
𝐸𝑉
𝐵𝑒𝑛𝑒𝑓𝑖𝑡  TCPI = 𝐵𝐴𝐶
 𝐵𝐶𝑅 =
𝐶𝑜𝑠𝑡 𝐴𝐶
𝐵𝐴𝐶
 EAC (no variances) =
𝐶𝑜𝑠𝑡 𝐶𝑃𝐼
 C𝐵𝑅 =
𝐵𝑒𝑛𝑒𝑓𝑖𝑡  EAC (with variances) = AC + ETC
 EAC (typical) = AC + ( BAC – EV )
 Opportunity Cost = Value of project not being chosen 𝐵𝐴𝐶 −𝐸𝑉
 EAC (atypical) = AC +
𝐶𝑃𝐼

ETC – Estimate to Complete


Communications  ETC = EAC – AC EV – Earned Value
𝑛 ∗ (𝑛−1) VAC – Variance at Completion
 Communication Channels =  VAC = BAC – EAC
2
 Number of conversations each person can have at any given
point in time = n -1 𝐸𝑉 𝐶
 𝐶𝑃𝐼 𝐶 =
𝐴𝐶 𝐶
Procurement 𝐹𝑉
C – Cumulative
 Point of Total Assumption(PTA) =  PV =
(1+𝑟)𝑛
𝐶𝑒𝑖𝑙𝑖𝑛𝑔 𝑃𝑟𝑖𝑐𝑒 −𝑇𝑎𝑟𝑔𝑒𝑡 𝑃𝑟𝑖𝑐𝑒 𝐸𝑉
+ 𝑇𝑎𝑟𝑔𝑒𝑡 𝐶𝑜𝑠𝑡  Percent Complete = * 100
𝐵𝑢𝑦𝑒𝑟𝑠 𝑆𝑕𝑎𝑟𝑒 𝑅𝑎𝑡𝑖𝑜 𝐵𝐴𝐶
www.ArmadilloConsultants.com

Formulas Snapshot
Hard Values Arithmetic Calculations Network Diagram
 Activity Duration = EF – ES +1
 1 sigma = 68.26%  Average(Mean) = OR
 2 sigma = 95.46%  Activity Duration = LF – LS +1
 3 sigma = 99.73% 𝑆𝑢𝑚 𝑜𝑓 𝑡𝑕𝑒 𝑁𝑢𝑚𝑏𝑒𝑟𝑠
 6 sigma = 99.99% 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐼𝑡𝑒𝑚𝑠  Total Float = LS – ES EF – Early Finish
OR ES – Early Start
 Median = Arrange all the LF – Late Finish
 Control Limits = 3 sigma from mean  Total Float = LF – EF LS – Late Start
 Control Specifications = Defined by customer
values in order and pick the
middle number. In case of
 Rough Order of Magnitude(ROM) estimate =  Free Float(FF) =
two middle number, take
-25% to +75% mean of two numbers. ES of following – ES of Present – DUR of
 Preliminary estimate = -15% to + 50% Present
 Budget estimate = -10% to +25%  Mode = Most occurring
 Definitive estimate = -5% to +10% number in dataset  EF = ES + Duration -1
 Final estimate = 0%  LF = LS + Duration -1

 Float on the critical path = 0 days  ES = EF of Predecessor + 1


 Pareto Diagram = 80/20  LS = LF – Duration + 1

 Crashing a project = Crash least expensive


tasks on critical path PERT(Program Evaluation and Review Technique)
𝑃 + 4𝑀+ 𝑂
 Time a Project Manager spends  Expected Activity Duration(EAD) =
6 P – Pessimistic Value
communicating = 90% 𝑃 −𝑂 M – Most Optimistic Value
 Standard Deviation =
6 O – Optimistic Value
𝑃 −𝑂
 Variance of an activity = * +2
6
www.ArmadilloConsultants.com

THANK YOU!

PMI, PMBOK, PMP, CAPM, PgMP,


PMI-ACP, PMI-RMP, PMI-SP are
registered marks of Project
Management Institute, Inc.

All registered trademarks, symbols,


Project Management - Subject Matter Experts names are marks of their respective
owners and acknowledged.

You might also like