Project Management Professional PMP Formulas
Project Management Professional PMP Formulas
com
PROJECT
MANAGEMENT
PROFESSIONAL (PMP)
Related Formulas
Formulas Snapshot
Hard Values Arithmetic Calculations Network Diagram
Activity Duration = EF – ES +1
1 sigma = 68.26% Average(Mean) = OR
2 sigma = 95.46% Activity Duration = LF – LS +1
3 sigma = 99.73% 𝑆𝑢𝑚 𝑜𝑓 𝑡𝑒 𝑁𝑢𝑚𝑏𝑒𝑟𝑠
6 sigma = 99.99% 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐼𝑡𝑒𝑚𝑠 Total Float = LS – ES EF – Early Finish
OR ES – Early Start
Median = Arrange all the LF – Late Finish
Control Limits = 3 sigma from mean Total Float = LF – EF LS – Late Start
Control Specifications = Defined by customer
values in order and pick the
middle number. In case of
Rough Order of Magnitude(ROM) estimate = Free Float(FF) =
two middle number, take
-25% to +75% mean of two numbers. ES of following – ES of Present – DUR of
Preliminary estimate = -15% to + 50% Present
Budget estimate = -10% to +25% Mode = Most occurring
Definitive estimate = -5% to +10% number in dataset EF = ES + Duration -1
Final estimate = 0% LF = LS + Duration -1
THANK YOU!