BOQ - Civil, Structural and Architectural
BOQ - Civil, Structural and Architectural
SUMMARY / PAGE 1 OF 1
BILL OF SUMMARY
SUMMARY / PAGE 1 OF 1
SUMMARY / PAGE 1 OF 1
SPECTRA BPO BUILDING
BILLS OF QUANTITIES FOR GENERAL CONSTRUCTION WORKS
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
EARTHWORKS
EARTH MOVING
Trimming:
D Vertical m2 - - - - - N/A
E Horizontal m2 - - - - - N/A
Soil Treatment
Soil Treatment
Page 1 of 2 9,634,525.07
Page 2 of 2 554,123.69
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
CONCRETE
Concrete Forming
C Concrete beams and girders m2 26,860.00 240.65 525.88 121.26 887.79 23,846,039.40
Others
Formworks to produce fair or smooth surface
(details to be ascertained) to:
K Curbs, gutter / side walk m2 239.00 240.65 433.08 121.26 794.99 190,002.61
Concrete Reinforcing
Reinforcing Steel
Slab on Grade
AA 10mm diamater Grade 40 (NOSING BAR) kg 5,083.00 34.61 6.07 - 40.68 206,776.44
Trench
C 12mm diameter Grade 60 kg 46.00 35.21 6.07 - 41.28 1,898.88
Equipment Pads
D 10mm diameter Grade 40 kg - - - - - N/A
Plant Box
F 12mm diameter Grade 60 kg 362.00 35.21 6.07 - 41.28 14,943.36
Countertop
G 10mm diameter Grade 40 kg 734.00 34.61 6.07 - 40.68 29,859.12
Mechanical Coupler
H 32mm diameter kg - - - - - N/A
Drilled Bars
P 16mm diameter kg - - - - - N/A
Tank Walls
A 12mm diameter Grade 60 kg 684.00 35.21 6.07 - 41.28 28,235.52
Sump Tank
B 12mm diameter Grade 60 kg 1,054.00 35.21 6.07 - 41.28 43,509.12
Grease Interceptor
C 12mm diameter Grade 60 kg 360.00 35.21 6.07 - 41.28 14,860.80
Oil Interceptor
D 12mm diameter Grade 60 kg 516.00 35.21 6.07 - 41.28 21,300.48
Water Meter
E 12mm diameter Grade 60 kg 19.00 35.21 6.07 - 41.28 784.32
Catch Basin
F 12mm diameter Grade 60 kg 166.00 35.21 6.07 - 41.28 6,852.48
Drainage Manhole
G 12mm diameter Grade 60 kg 310.00 35.21 6.07 - 41.28 12,796.80
Encasement
H 12mm diameter Grade 60 kg 150.00 35.21 6.07 - 41.28 6,192.00
Steel Decks
Cast-in-Place Concrete
Structural Concrete
Columns:
Shear Walls:
Retaining Walls:
Slabs:
Stairs:
RC Walls:
Ramps:
SOG
Lean Concrete:
A 2500 PSI m3 296.00 4,205.85 433.08 181.08 4,820.01 1,426,722.96
Wheel Stopper
D 3000 PSI m3 12.00 4,205.85 494.95 181.08 4,881.88 58,582.56
Concrete countertop
E 3000 PSI m3 7.00 4,205.85 494.95 181.08 4,881.88 34,173.16
Underground Tanks:
F 5000 PSI m3 - - - - - N/A
Equipment Pads:
G 3000 PSI m3 - - - - - N/A
Plant Box:
I 3000 PSI m3 7.00 4,205.85 433.08 181.08 4,820.01 33,740.07
Concrete Block:
J 2500 PSI m3 - - - - - N/A
Trench
K 3000 PSI m3 6.00 4,205.85 494.95 181.08 4,881.88 29,291.28
Sump Tank
L 3000 PSI m3 11.00 4,205.85 433.08 181.08 4,820.01 53,020.11
Grease Interceptor
M 3000 PSI m3 4.00 4,205.85 433.08 181.08 4,820.01 19,280.04
Oil Interceptor
N 3000psi m3 6.00 4,205.85 433.08 181.08 4,820.01 28,920.06
Water Meter
O 3000psi m3 1.00 4,205.85 433.08 181.08 4,820.01 4,820.01
Catch Basin
P 3000psi m3 3.00 4,205.85 433.08 181.08 4,820.01 14,460.03
Drainage Manhole
Q 3000psi m3 3.00 4,205.85 433.08 181.08 4,820.01 14,460.03
Steel Decks
T 5000psi m3 326.00 4,968.15 525.88 188.63 5,682.66 1,852,547.16
Concrete Topping
A FF-4, To areas to receive tiles m2 1,548.00 289.80 309.35 7.55 606.70 939,171.60
D FF-11, To areas to receive natural finish (honed) m2 480.00 289.80 309.35 7.55 606.70 291,216.00
Concrete Finishing
To Floor:
D Plain cement finish (FF-1 ) m2 88.00 203.91 309.35 7.55 520.81 45,831.28
I Plain cement plaster finish ready to accept wall tiles, m2 3,115.00 82.43 320.66 7.55 410.64 1,279,143.60
To ceiling:
Demolition
Restoration
Concrete Reinforcing
Reinforcing Steel
RC Walls
Concrete Saddle
Tank Walls
A 3000 psi m3 249.00 4,205.85 433.08 181.08 4,820.01 1,200,182.49
Concrete Saddle
A 3000 psi m3 71.00 4,205.85 433.08 181.08 4,820.01 342,220.71
Steel Decks
Retrofitting Works
Demolition Works
A Drilling and Filling of Holes no. 2,316.00 1,641.37 0.63 105.52 1,747.52 4,047,256.32
A to new mat footing with contact to existing struct. m2 224.00 655.94 281.12 - 937.06 209,901.44
Page 1 of 10 71,948,389.01
Page 2 of 10 628,042.10
Page 3 of 10 123,084,411.84
Page 4 of 10 9,336,793.08
Page 5 of 10 1,368,294.12
Page 6 of 10 79,399,839.39
Page 7 of 10 4,722,185.47
Page 8 of 10 15,448,170.44
Page 9 of 10 4,824,423.89
Page 10 of 10 6,636,037.49
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
Unit Masonry
A 150mm thk. CHB Wall m2 8,921 1,008.47 493.59 8.32 1,510.38 13,474,099.98
B 100mm thk. CHB Wall m2 1,041 903.22 486.12 8.30 1,397.64 1,454,943.24
Zocalo
A ________________________________________ item
B ________________________________________ item
C ________________________________________ item
To Collection Php -
TO COLLECTION
Page 1 of 3 19,568,476.88
Page 2 of 3 -
Bill. No. 2.3 - MASONRY TOTAL AMOUNT (INCLUSIVE VAT) TO BILLS OF SUMMARY 19,568,476.88
SPECTRA BPO BUILDING
BILLS OF QUANTITIES FOR GENERAL CONSTRUCTION WORKS
Unit Rate
Item Description Unit Amount
Quantity Materials Labor Others Total
METALS
Steel Beams:
A W21x44 kg - - - - - Deleted
B W21x62 kg - - - - - Deleted
C W21x57 kg - - - - - Deleted
D W21x50 kg - - - - - Deleted
E W18x55 kg - - - - - Deleted
F W18x50 kg - - - - - Deleted
G W18x46 kg - - - - - Deleted
H W18x40 kg - - - - - Deleted
I W18x35 kg - - - - - Deleted
Canopies
Steel Framing
Connection:
To Collection Php -
Transformer Hoisting Beam
X 4-20mm dia x 400 LG. Anchor Bolts no. 2,120 307.54 135.76 - 443.30 939,796.00
Ladder rung
M 16mm dia. Stainless Steel Ladder Rung no. 18 1,995.00 855.00 - 2,850.00 51,300.00
spaced @ 300mm O.C. (Grease Interceptor)
16mm dia. Stainless Steel Ladder Rung no. 60 1,995.00 855.00 - 2,850.00 171,000.00
spaced @ 300mm O.C. (Domestic Water Tank)
16mm dia. Stainless Steel Ladder Rung no. 30 1,995.00 855.00 - 2,850.00 85,500.00
spaced @ 300mm O.C. (Fire Reserve Tank)
Ladder rung for Floor Control Valve no. 25 1,995.00 855.00 - 2,850.00 71,250.00
Railings
Perimeter Fence
Metal Gratings
Steel stair
Helipad
J 50mm Wide Brass Strip Nosing (Main Entrance) l.m 109 2,793.00 1,197.00 - 3,990.00 434,910.00
K 50mm Wide x 25mm Deep Tile Nosing l.m 1,519 3,192.00 1,368.00 - 4,560.00 6,926,640.00
(6th Basement Flr. To 18th Flr.)
25mm dia. X 450mm long A-325 Anchor Bolts pcs 16.00 1,659.84 732.71 - 2,392.55 38,280.80
Stair Railings
50mm dia. B.I. Pipe Railing l.m 125 638.40 273.60 - 912.00 114,000.00
(Basement)
Metal Gratings
Trench Drain
1-1/2' Trench Grating Cover (Cast Iron) lm 21 1,851.36 793.44 - 2,644.80 55,540.80
L 75 x 75 x 10 x 900 LG. (Bot. 300 fr. Driveway lvl.) no. 570 399.00 171.00 - 570.00 324,900.00
painted black and yellow 100 wide strips, 45 deg.
diagonal alternately
10mm dia.x 600 LG. Anchor Bars Welded to no. 2,850 447.72 181.21 - 628.93 1,792,450.50
L@300 O.C.
Page 1 of 6 -
Page 2 of 6 5,435,829.14
Page 3 of 6 10,221,120.16
Page 4 of 6 925,408.08
Page 5 of 6 6,456,044.86
Page 6 of 6
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
ROOFING
WATERPROOFING
Sealant
Polyurethane Sealant:
Elastic Sealant:
F. Waterproofing Compound for interior face m2 351 359.10 153.90 - 513.00 180,063.00
of Parapet Walls
Isulation
A To walls & floor Joints @ basement m 2,232 446.30 128.27 7.55 582.12 1,299,291.84
2,261,120.45
Others (Pls specify)
Polyurethane Sealant:
Waterstop
Vapor Barrier
Elastomeric Waterproofing
Dense Concrete
to Slab on Grade m3 279 5,072.70 433.08 188.63 5,694.41 1,588,740.39
Isulation
Polynum Ultra Thermal Reflective Insulation m2 1,983 720.60 308.83 - 1,029.43 2,041,359.69
Page 1 of 2 6,689,231.85
Page 2 of 2 2,261,120.45
Page 3 of 3 9,262,088.10
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
FINISHES
Plaster
Tiling
Homogeneous tiles
To floor:
200mm x 200mm x 50mm thk. Concrete Ramp m² 1,548 299.08 961.98 83.71 1,344.77 2,081,703.96
Tiles
To wall:
To floor:
To wall:
Ceilings
Gypsum Board
E 25mm Shadow Gap for Ordinary Gypsum Board lm 1,029 310.48 254.03 - 564.51 580,880.79
Acoustic Board
Painting
To Floor:
A Epoxy porcelain paint lining finish (FF-1) m2 88 424.54 181.95 - 606.49 53,371.12
To wall:
C Flat Latex painted finish (F-1 & F-3) m2 26,579 235.96 101.13 - 337.09 8,959,515.11
D Elastomeric painted finish, 5 coats - (F-2) m2 319 812.88 348.38 - 1,161.26 370,441.94
D Epoxy porcelain lining painted finish (F-4) m2 1,286 402.20 172.37 - 574.57 738,897.02
To Ceiling:
H Painting on Gysum surfaces finish (CF-2 & CF-3) m2 4,199 235.96 101.13 - 337.09 1,415,440.91
Other painting:
K Epoxy Paint Finish to Steel Louver Door m2 701 603.29 258.56 - 861.85 604,156.85
M Thermoplastic Luminus Paint for Directional Arrow m2 84 491.57 210.68 - 702.25 58,989.00
Floor Hardener
Concrete Floor Hardener (FF-2, FF-3, FF-8) m² 14,655 369.29 163.03 - 532.32 7,801,149.60
Page 1 of 5 56,198,313.28
Page 2 of 5 11,797,615.06
Page 3 of 5 14,881,610.45
Page 4 of 5 13,110,208.20
Page 5 of 5
Bill. No. 2.6 - FINISHES TOTAL AMOUNT (INCLUSIVE VAT) TO BILLS OF SUMMARY 95,987,746.99
SPECTRA BPO BUILDING
BILLS OF QUANTITIES FOR GENERAL CONSTRUCTION WORKS
Unit Rate
Item Description Unit Quantity Amount
Materials Labor Others Total
Aluminum Window
Steel Door
A SD-1 1000mmW x 2100mmH set 51.00 15,338.20 2,529.35 3.02 17,870.57 911,399.07
Finishes: 4mm thk. Flush Type Door w/ GA. 18 Face Plate
on GA. 16 Steel Bended Frames/Jambs w. Steel Stiffeners
for all hardwares and accesories
Locations: Fire Exit
A SLD - 1 1000mmW x 2100mmH set 55.00 13,202.23 2,529.35 3.02 15,734.60 865,403.00
Finishes: 4mm thk. Louver Steel Door w/ GA. 18 face
plate bended louvers on GA. 16 Steel bended jambs/frames
w/ steel stiffenerfor all hardware & accessories
(epoxy paint finish)
Locations: Telco, E.E. Rm., MDF, Carrier
B SLD - 2 2000mmW x 2100mmH set 2.00 19,580.15 4,081.33 3.02 23,664.50 47,329.00
Finishes: 4mm thk. Louver Steel Door w/ GA. 18 face
plate bended louvers on GA. 16 Steel bended jambs/frames
w/ steel stiffenerfor all hardware & accessories
(epoxy paint finish)
Locations: Pump Rm.
C SLD - 3 1100mmW x 2100mmH set 2.00 13,530.86 2,684.55 3.02 16,218.43 32,436.86
Finishes: 4mm thk. Louver Steel Door w/ GA. 18 face
plate bended louvers on GA. 16 Steel bended jambs/frames
w/ steel stiffenerfor all hardware & accessories
(epoxy paint finish)
Locations: Main E.E. Rm.
D SLD - 800mmW x 2100mmH set 15.00 12,544.98 2,218.95 3.02 14,766.95 221,504.25
Finishes: 4mm thk. Louver Steel Door w/ GA. 18 face
plate bended louvers on GA. 16 Steel bended jambs/frames
w/ steel stiffenerfor all hardware & accessories
(epoxy paint finish)
Locations: S/S
E SLD - 900mmW x 2100mmH set 30.00 5,733.24 2,374.15 3.02 8,110.41 243,312.30
Finishes: 4mm thk. Louver Steel Door w/ GA. 18 face
plate bended louvers on GA. 16 Steel bended jambs/frames
w/ steel stiffenerfor all hardware & accessories
(epoxy paint finish)
Locations: Mechanical Rm.
DOOR HARDWARE
Hinges
A Dorma BA 2F, Hager BB1279 or Stanley (4 pcs.) - no. 392.00 646.71 128.27 - 774.98 303,792.16
127mm x 101mm Stainless Steel hinges
B Dorma BTS84 EN 3 w/ complete accessories no. 3.00 11,775.41 128.27 - 11,903.68 35,711.04
C 4 pcs. Dorma BA 2F, or Hager BB1279 or Stanley - 127mm x no. 348.00 646.71 128.27 - 774.98 269,693.04
101mm Stainless Steel Hinges (Full Mortise Ball Bearing)
D 8 pcs. Dorma BA 2F, or Hager BB1279 or Stanley - 127mm x no. 128.00 646.71 128.27 - 774.98 99,197.44
101mm Stainless Steel Hinges (Full Mortise Ball Bearing)
Lockset
E Dorma PHB - 300 (Panic Device) no. 51.00 16,517.90 320.66 - 16,838.56 858,766.56
F Dorma Lever Set ANSI Grade 1 UL3HRFR no. 134.00 5,510.46 256.53 - 5,766.99 772,776.66
G Dorma Lever Set ANSI Grade 1 UL3HRFR w/ Dummy Trim no. 16.00 11,031.70 256.53 - 11,288.23 180,611.68
Patch Lock
H Dorma Universal Patch Lock: US10 no. 3.00 11,452.05 256.53 - 11,708.58 35,125.74
Patch Fitting
I Dorma Universal PT Patch: PT10, PT20, PT30 no. 3.00 11,452.05 256.53 - 11,708.58 35,125.74
Door Accessories
Door Closer
J LCN 1460 Series or Dorma TS - 91 Sliding Track and Paralle no. 170.00 13,129.44 320.66 - 13,450.10 2,286,517.00
K LCN 1460 Series or Dorma TS - 91 Sliding Track and Paralle no. - - - - - N/A
Door Pull
Overhead Bolt & Footbolt no. 102.00 505.24 384.79 - 890.03 90,783.06
Page 1 of 10 7,229,161.90
Page 2 of 10 45,817,551.62
Page 3 of 10 127,009,580.04
Page 4 of 10 2,963,776.96
Page 5 of 10 1,840,078.09
Page 6 of 10 1,707,262.38
Page 7 of 10 1,498,495.03
Page 8 of 10 4,968,100.12
Page 9 of 10 20,395.44
Page 10 of 10
Bill. No. 2.8 - DOORS, WINDOWS & GLAZING TOTAL AMOUNT (INCLUSIVE VAT) TO BILLS OF SUMMARY 193,054,401.58