0% found this document useful (0 votes)
591 views4 pages

Bill of Materials and Cost Estimate: Column Footing/Wall Footing

This document provides a bill of materials and cost estimate for a two-story residential building project. It includes estimated quantities, unit costs, and total costs for various construction materials grouped into categories like concreting works, masonry works, carpentry works, plumbing works, and electrical works. The total estimated cost for all materials is over 1.8 million pesos.

Uploaded by

Gelli Quidoles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
591 views4 pages

Bill of Materials and Cost Estimate: Column Footing/Wall Footing

This document provides a bill of materials and cost estimate for a two-story residential building project. It includes estimated quantities, unit costs, and total costs for various construction materials grouped into categories like concreting works, masonry works, carpentry works, plumbing works, and electrical works. The total estimated cost for all materials is over 1.8 million pesos.

Uploaded by

Gelli Quidoles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

BILL OF MATERIALS AND COST ESTIMATE

TOTAL
DESCRIPTION QTY UNIT U/COST AMOUNT COST

I. CONCRETING WORKS
Column Footing/Wall Footing
Cement 79 bag/s 218 17222
Sand 5 cu.m. 430 2150
G1 Gravel 9 cu.m. 800 7200
20mm Ø Deformed Steel Bar 35 pc/s 550 19250
16mm Ø Deformed Steel Bar 3 pc/s 357 1071
12mm Ø Deformed Steel Bar 1 pc/s 200 200
Boulders 3 cu.m. 450 1350
Columns
Cement 106 bag/s 218 23108
Sand 6 cu.m. 430 2580
3/4 Gravel 12 cu.m. 820 9840
20mm Ø Deformed Steel Bar 130 pc/s 550 71500
16mm Ø Deformed Steel Bar 132 pc/s 357 47124
12mm Ø Deformed Steel Bar 2 pc/s 200 400
Beams
Cement 183 bags 218 39894
Sand 10 cu.m. 430 4300
3/4 Gravel 20 cu.m. 820 16400
16mm Ø Deformed Steel Bar 236 pc/s 357 84252
10mm Ø Deformed Steel Bar 460 pc/s 142 65320
Slabs
Cement 484 bags 218 105512
Sand 27 cu.m. 430 11610
3/4 Gravel 54 cu.m. 820 44280
12mm Ø Deformed Steel Bar 626 pc/s 200 125200
Sub Total 699763

II. MASONRY WORKS


Exterior Walls
5"CHB 4380 pcs 10.5 45990
Cement 615 bag/s 218 134070
Sand 36 cu.m 430 15480
10mm Ø Deformed Steel Bar 250 pcs 142 35500
Interior Walls
4"CHB 796 pc/s 8.5 6766
Cement 69 bag/s 218 15042
Sand 4 cu.m 430 1720
10mm Ø Deformed Steel Bar 45 pc/s 142 6390
Tile Works
12x12 Floor Tile 86 pc/s 26 2236
12x12 Wall Tile 40 pc/s 32 1280
Sub Total 260958

III. CARPENTRY WORKS


Ceiling works
C-Purlin (200x75x24x2.4) 45 pc/s 520 23400
Chord Angle Bar 6 pc/s 1950 11700
King post 12 pc/s 2100 25200
Rivets 12 kg 98 1176
GI Sheet 32"x12' 22 pc/s 480 10560
GI Sheet 32"x 9' 66 pc/s 430 28380

A TWO-STOREY RESIDENTIAL BUILDING


BILL OF MATERIALS AND COST ESTIMATE

GI Washer 33 kg 98 3234
Lead Washer 27 kg 98 2646
1/4" thk Marine Plywood 38 pc/s 370 14060
Formworks
2x2x12 Coco Lumber 8820 pc/s 60 529200
2x3x12 Coco lumber 3785 pc/s 75 283875
1/4 thk ord. Plywood 240 pc/s 370 88800
Sub Total 901875

IV. PLUMBING WORKS


Water Closet 2 set/s 3500 7000
Lavatory 2 set/s 1800 3600
Stainless kitchen sink w/ faucet 1 set/s 2300 2300
Shower Head 2 set/s 550 1100
Shower Valve 2 set/s 450 900
Shower Faucet 2 set/s 195 390
bidet 2 set/s 450 900
4 x 4 Stainless Floor Drain 8 pc/s 125 1000
Waterline pipe & fittings (wexan) 1 I.s. 13000 13000
4" Ø PVC pipe Sanimond 5 pc/s 435 2175
3" Ø PVC pipe Sanimond 10 pc/s 230 2300
2" Ø PVC pipe Sanimond 11 pc/s 165 1815
4" Ø x 90° PVC Elbow Sanimond 5 pc/s 88 440
3" Ø x 90° PVC Elbow Sanimond 4 pc/s 20 80
2" Ø x 90° PVC Elbow Sanimond 1 pc/s 16 16
4" Ø x 45° PVC Elbow Sanimond 2 pc/s 55 110
2" Ø PVC Tap Tee Sanimond 5 pc/s 20 100
3" Ø PVC Tee Sanimond 3 pc/s 20 60
3" x 2" Ø PVC Wye Sanimond 1 pc/s 85 85
6" CO 1 pc/s 60 60
1/2" Ø Gate Valve 1 pc/s 450 450
3/4" Ø Gate Valve 1 pc/s 450 450
Teflon Tape 10 rolls 16 160
Catch Basin 9 set 600 5400
Septic Tank 1 I.s. 15000 15000
Sub Total 58891

IV. ELECTRICAL WORKS


2.0 mm2 THHW copper wire 351 meter/s 20 7020
3.5 mm THHW copper wire
2 340 meter/s 30 10200
8.0 mm2 THHW copper wire 14 meter/s 60 840
38 mm THHW copper wire
2 18 meter/s 200 3600
20.00 mm dia PVC pipe 280 pc/s 60 16800
25.00 mm dia PVC pipe 8 pc/s 135 1080
50.00 mm dia PVC pipe 6 pc/s 220 1320
20.00 mm dia PVC elbow 10 pc/s 30 300
25.00 mm dia PVC elbow 2 pc/s 50 100
50.00 mm dia PVC elbow 4 pc/s 120 480
20 AT, 2P Molded Case 12 pc/s 300 3600
40 AT, 2P Molded Case 1 pc/s 350 350
125 AT, 2P Molded Case 1 pc/s 2000 2000
Panel Board -14 Branches 1 pc/s 3000 3000
Single pole 7 pc/s 100 700
Duplex 1 pc/s 150 150
Three way 1 pc/s 120 120
Single Pole Switch with Dimmer switch 6 pc/s 250 1500

A TWO-STOREY RESIDENTIAL BUILDING


BILL OF MATERIALS AND COST ESTIMATE

4 pc/s 250 1000


2 gang switch with one 3 way switch
Duplex Convenience 23 pc/s 75 1725
2 gang switch with dimmer switch 1 Pc/s 300 300
Range 1 pc/s 320 320
Air Conditioning 1 pc/s 105 105
Refrigerator 1 pc/s 90 90
Duplex Weatherproof 1 pc/s 120 120
Circular Fluorescent Lamp ( 32W ) 9 pc/s 460 4140
Compact Fluorescent Lamp 11 pc/s 165 1815
Pin Light 28 pc/s 180 5040
Pin Light Receptacle 28 pc/s 120 3360
Utility Box 45 pc/s 40 1800
Junction Box 25 pc/s 60 1500
Electrical Tape 7 pc/s 25 175
Rubber Tape 4 pc/s 85 340
Spool Insulator 2 pc/s 60 120
Metal strap 4 pc/s 310 1240
Kilowatthour Meter CL-200 GE 1 pc/s 3000 3000
Meter Base 1 pc/s 510 510
Service Entrance Cap 1 pc/s 90 90
Sub Total 79950

VI. DOORS AND WINDOWS


2.1mx0.9m Hardwood Panel Door with Jambs 1 set/s 3900 3900
2.1mx0.7m Hardwood Panel door with Jambs 4 set/s 3300 13200
2.1mx0.6m PVC Flush Door with Jambs 2 set/s 2100 4200
2.1mX0.8m Aluminum Sliding Door 1 set/s 500 500
2.60mx1.30m Aluminum Sliding Door 2 set/s 1000 2000
2.1mx3.6m Steel Casement Window 3 set/s 17900 53700
2.8mx1.8m Steel Casement Window 1 set/s 12000 12000
2.1mx2.4m Steel Casement Window 1 set/s 12000 12000
1.0mx2.4m Steel Casement Window 2 set/s 12000 24000
2.1mx3.6m Steel Casement Window 2 set/s 17900 35800
0.4mx1.2m Steel Casement Window 2 set/s 1140 2280
2.6mx2.7m Steel Casement Window 1 set/s 16620 16620
2.1mx2.4m Steel Casement Window 4 set/s 11930 47720
2.4mx1.2m Steel Casement Window 1 set/s 6820 6820
0.4mx2.4m Steel Casement Window 2 set/s 2280 4560
2.6mx0.65m Aluminum Glass Window 4 set/s 510 2040
4.0mx2.4m Aluminum Glass Window 2 set/s 2880 5760
0.3mx0.9m Aluminum Glass Window 1 set/s 90 90
Subtotal 247190

VII. HARDWARE MATERIALS


Door Knob 7 set/s 800 5600
4x4 LP Hinges 15 pair/s 150 2250
3x3 LP Hinges 6 pair/s 100 600
Tie Wire 195 kgs 60 11700
4" CWN 382 kgs 50 19100
1 1/2 " CWN 18 kgs 50 900
Subtotal 40150

A TWO-STOREY RESIDENTIAL BUILDING


BILL OF MATERIALS AND COST ESTIMATE

VII. PAINTING WORKS


Subtotal 106950

Total Material Cost 2288780


Miscellaneous (3%) 68660
Contingencies (2%) 45780
Labor Cost (35%) 801080
Supervision (3% of Labor & malts) 68670

TOTAL PROJECT COST: P 3,272,970.00

A TWO-STOREY RESIDENTIAL BUILDING

You might also like