Faqonescalation PDF
Faqonescalation PDF
Condition No. 63 of I.A.F.W 2249 is applicable only for all Term Contracts
and contracts having a period of less than or equal to 2 years. It is felt that
where the Special condition prescribed by E-in-C has not been incorporated in
the Contract, by default, Condition No. 63 of I.A.F.W 2249 would stand
applicable. In the case of work for Electrical Installation for lifts, the Special
condition prescribed in Annexure XII of compendium of E-in-C Contracts
should be included in the contract and as would be included in the said Special
condition, the provisions contained in this Special condition would supersede
the provisions of Condition 63 of IAFW-2249 and the provisions of Condition
No. 63 of IAFW 2249 shall not be applicable in such cases.
Page 1 of 7
COMPILED BY CDA CHENNAI
2. What are the salient features of the special condition formulated by E-IN-
C for escalation?
Page 2 of 7
COMPILED BY CDA CHENNAI
ensure that the Value of work claimed as done in the calculation sheet
before the actual date of commencement of work as per Work Order is
Nil.
(6) RARs must be timed in such a manner that the gross value of work
done up to the corresponding date is readily available.
(7) The payment will not cover period beyond the contract date or
extended date of completion of the work.
Page 3 of 7
COMPILED BY CDA CHENNAI
ROAD WORKS NOT INVOLVING
9 SUBSTANTIAL EARTH WORK 57.00 21 2 5.00
CENTRAL SEWAGE DISPOSAL
PLANTS WATER PURIFICATION
10 PLANTS ETC 65.00 18 0.5 1.50
Page 4 of 7
COMPILED BY CDA CHENNAI
EP is arrived by applying a percentage (calculated by dividing (a) the
difference between the Fuel index for the relevant quarter and (b) the Fuel
Index at the beginning as on the last date of opening of the tender by (b) the
Fuel Index at the beginning as on the last date of opening of the tender i.e.,
(a-b) / b ) on the weighted value of work done [value of workdone
(difference between the value of workdone during the current and previous
quarter) multiplied by the applicable percentage for Fuel depending on the
Type of contract as per table given under Answer to Question No. 4) during the
period reckoning]. It is important to note that the E-in-C Instructions clearly
stipulate that the VG1 on which the differential Index percentage is to be
applied, should be the gross value of work done during the period of reckoning
using values of Vg for calculation of VM1 and VM2 during calculation of
escalation of material. This means that the Star rates should not be deducted
from the value of vg).
EP = (KP x VG1 /100) x (F1-FO) / FO
Page 5 of 7
COMPILED BY CDA CHENNAI
9. How should the value of escalation for a quarter be reckoned when the
value arrived at for a quarter is a minus figure?
Sometimes in the Escalation claims when the figure worked out for a
quarter is a minus figure it is remarked that the minus figure is on account of
excess issue of Schedule B Stores and hence the minus figure is ignored and
accepting zero as the figure. Doubt arises as to whether this is tenable.
Audit has to examine the case of excess of issue of Schedule B stores
with reference to Condition No. 10(B) of I.A.F.W 2249. As per this condition, for
the supply of materials listed in Schedule “B” the Contractor shall give a
reasonable notice in writing of his requirements to the Engineer-in-Charge in
accordance with the agreed phased programme. Therefore if the Contractor is
issued with Excess Stores it is clearly a violation of the aforesaid condition and
over and above the advantages obtained for this violation, the contractor
cannot be further given a favour by ignoring the minus figure in the escalation
claim.
In the absence of sanction of Govt. of India Ministry of Defence (duly
concurred by MOD (Fin) the minus figure in any particular quarter has to be
reckoned as such in the overall summary and adjusted alongside plus figures in
other quarters and cannot be substituted with zero.
10. Can Escalation value be calculated and paid along with the RAR Or Should
it necessarily be paid with Final Bill only?
As per E-in-C Instructions once the amount adjustable for any quarter is
worked out the same shall be adjusted as and along with the advance on
account payment under Condition 64 of IAFW-2249 in the following RARs. It
must equally be noted with caution that the amount payable relevant to work
done and materials collected in any quarter will be worked out after firm whole
sale price indices( not provisional) for the relevant quarter are available. Hence
subject to the above condition the escalation shall be worked out and paid
along with the RAR. Since it would become a Contractual right to the Contractor
to claim escalation along with RAR as per above procedure, the AAOsGE should
forward such RARs for Pre-Audit by Main Office of CDA, (where escalation
claims are required to be approved by CDA) duly informing the GE in this
regard.
Page 6 of 7
COMPILED BY CDA CHENNAI
11. What is the significance of escalation in reckoning the value of contract
for the purposes of calculating retention money and liquidated damages?
For the purposes of calculating retention money and liquidated damages,
the value of contract as revised by the above price variation will be taken into
account.
13. Whether the escalation amount has to be clubbed with the work done for
comparing the deviation limit?
As per HQrs Office letter No. 18082/AT-X/XV dated 6/10/2005 (CDA
Chennai Part I Office Order No. 91 dated 8/11/05) the “final cost of service” for
the purpose of Para 9(d) of DWP (1986) (now para 2(h) of DWP 2007) would
definitely include the amount of escalation. Therefore if the final cost of a work
service inclusive of escalation exceeds the Administrative Approval amount by
more than the 10% tolerance limit, revised Administrative Approval /Financial
Concurrence would be required.
xxxxxxxxxxxxxxxxxx
Page 7 of 7
COMPILED BY CDA CHENNAI