Bill of Materials and Cost Estimate: A. Labor
Bill of Materials and Cost Estimate: A. Labor
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman 1 5 500.00 2,500.00
Skilled 1 5 400.00 2,000.00
Laborer 2 5 300.00 3,000.00
7,000.00
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman 1 10 500 4,500.00
Skilled 1 10 400 4,000.00
Laborer 2 10 300 6,000.00
14,000.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV
Republic of the Philippines
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 500.00 500.00
Laborer 1 1 300.00 300.00
800.00
b.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 500 500.00
Laborer 1 1 300 300.00
800.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV
Republic of the Philippines
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400.00 400.00
Laborer 1 1 300.00 300.00
700.00
B.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400 400.00
Laborer 1 1 300 300.00
700.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV
Republic of the Philippines
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled
Laborer
3,410.00
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 4 4 400 6,400.00
Laborer
6,400.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV
Republic of the Philippines
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled
Laborer
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled
Laborer
Approved:
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400.00 400.00
Laborer 1 1 300.00 300.00
700.00
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 2 400.00 800.00
Laborer 1 2 300.00 600.00
1,400.00
Approved:
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400.00 400.00
Laborer 1 1 300.00 300.00
700.00
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400.00 400.00
Laborer 1 1 300.00 300.00
700.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV
Republic of the Philippines
Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela
I. Demolition/Excavation
a.Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled
Laborer
8,180.00
b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman
Skilled 1 1 400.00 400.00
Laborer 1 1 300.00 300.00
700.00
Approved:
EVELYN A. BUMANGLAG,PhD
Principal IV