Project Schedule - Rev B (Phase I) : LEVEL 4 (220 m2)

The document is a project schedule for Phase I of the Mowilex Office Renovation project. It outlines 16 tasks across 4 categories (Design & Project Management, Preparation Works, Interior Works, Wall Partition Works) to be completed over 4 months. Interior works make up the largest portion at 45.93% and include flooring, wall partition, wall treatment, and ceiling works. Preparation works will take place in the first month, with interior works continuing through months 2-4.

Uploaded by

Refina Azanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views

Project Schedule - Rev B (Phase I) : LEVEL 4 (220 m2)

The document is a project schedule for Phase I of the Mowilex Office Renovation project. It outlines 16 tasks across 4 categories (Design & Project Management, Preparation Works, Interior Works, Wall Partition Works) to be completed over 4 months. Interior works make up the largest portion at 45.93% and include flooring, wall partition, wall treatment, and ceiling works. Preparation works will take place in the first month, with interior works continuing through months 2-4.

Uploaded by

Refina Azanna
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT SCHEDULE - REV B (PHASE I)

LEVEL 4 (220 m2)


CLIENT: PT MOWILEX INDONESIA At Site
PROJECT: MOWILEX OFFICE RENOVATION At Workshop / Office
LOCATION: LEVEL 4, at Daan Mogot
UPDATE: 24-Oct-19

Weight Duration MONTH 1 MONTH 2 MONTH 4 MONTH 3


NO Description Qty UoM
(%) Installation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Design & Project Management 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1 Approval Design 1.00 Ls 0.00% 1 0.00%
2 Approval Material Interior & ME 1.00 Ls 0.00% 2 0.00% 0.00%
3 Approval Custom Furniture Drawing 1.00 Ls 0.00% 2 0.00% 0.00%
4 Approval Purchased Item 1.00 Ls 0.00% 3 0.00% 0.00% 0.00%
5 Project Management Services 1.00 Ls 0.00% 8 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Preparation Works 10.70% 0.00% 3.44% 3.44% 0.69% 0.69% 0.69% 0.69% 1.04%
1 General Cleaning & Garbage Disposal 1.00 LS 0.77% 7 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
2 Accomodation 1.00 LS 1.60% 7 0.23% 0.23% 0.23% 0.23% 0.23% 0.23% 0.23%
3 Transportation 1.00 LS 1.00% 7 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
4 Site Protection 1.00 LS 0.75% 7 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
5 Temporary Electrical Power 1.00 LS 0.25% 7 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
6 As Built Drawing Interior & ME 1.00 LS 0.35% 1 0.35%
7 Scaffolding 1.00 LS 0.50% 7 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
8 Floor Demolition at existing office 1.00 LS 2.50% 2 1.25% 1.25%
9 Wall Demolition at existing office 1.00 LS 2.00% 2 1.00% 1.00%
10 Ceiling Demolition at existing office 1.00 LS 1.00% 2 0.50% 0.50%

INTERIOR WORKS 45.93% 0.00% 2.75% 4.89% 7.79% 11.29% 12.85% 5.47% 0.89%
A FLOORING WORKS 10.57% 0.00% 0.55% 0.55% 2.93% 2.93% 1.36% 1.36% 0.89%
1 Floor Screeding for carpet installation 78.33 m2 0.78% 2 0.39% 0.39%
2 Floor Chippint & Screading for cabinet installation 80.00 m' 0.32% 2 0.16% 0.16%
3 Supply & Install Homogenous Tile 77.81 m2 3.73% 2 1.86% 1.86%
at Meeting Room & Staff Area
4 Supply & Install Homogeneous Plank Tile 44.63 m2 2.14% 2 1.07% 1.07%
at Meeting room
5 Supply & Install Carpet Tile 78.33 m2 2.66% 3 0.89% 0.89% 0.89%
at Manager room
6 Supply & Install Raised Floor 12.60 m2 0.94% 2 0.47% 0.47%
at Server room

B WALL PARTITION WORKS 22.26% 0.00% 2.20% 2.76% 2.76% 7.10% 7.10% 0.35% 0.00%
1 Supply & Install of Gypsum Wall Partition 217.85 m2 5.98% 5 1.20% 1.20% 1.20% 1.20% 1.20%
(Two Sided) w/ Sound Insulation
2 Supply & Install of Gypsum Wall Partition 73.50 m2 1.19% 5 0.24% 0.24% 0.24% 0.24% 0.24%
(One Sided) w/o Sound Insulation
at column cover & perimeter
3 Supply & Install of Gypsum Wall Partition 157.40 m2 2.87% 5 0.57% 0.57% 0.57% 0.57% 0.57%
(One Sided) w/ Sound Insulation
at column cover & perimeter
4 Supply & Install of Gypsum Wall Partition 32.63 m2 0.95% 5 0.19% 0.19% 0.19% 0.19% 0.19%
(Two Sided) w/ Sound Insulation
at column cover & perimeter
5 Supply & Install Glass Partition 35.22 m2 2.74% 2 1.37% 1.37%
6 Supply & Install Glass Door 7.00 Set(s) 5.24% 2 2.62% 2.62%
7 Supply & Install Solid Wooden Door 5.00 m2 2.25% 4 0.56% 0.56% 0.56% 0.56%
at Server room,file storage room,cashier room,big safe
8 Supply & Install Skirting (upper & bottom) 231.00 m' 1.04% 3 0.35% 0.35% 0.35%

C WALL TREATMENT WORKS 7.14% 0.00% 0.00% 0.00% 0.00% 0.00% 3.57% 3.57% 0.00%
1 Supply & Install Cement Finished 422.21 m2 3.16% 2 1.58% 1.58%
at General Area
2 Column & Slab Painting 1.00 ls 1.50% 2 0.75% 0.75%
at General Area
3 Supply & Install White Brick Accent 47.04 m2 0.94% 2 0.47% 0.47%
at Meeting room, Pantry & Breakout
4 Supply & Install Red Brick Accent 45.57 m2 1.09% 2 0.55% 0.55%
at Staff Area
5 Supply & Install Laminated Wall Panel 7.56 m2 0.38% 2 0.19% 0.19%
at Meeting Room
6 Supply & Install Glasstone 3.00 m2 0.07% 2 0.04% 0.04%
at Meeting Room & Staff Area
0.00%
D CEILING WORKS 5.96% 0.00% 0.00% 1.58% 2.10% 1.25% 0.82% 0.20% 0.00%
1 Supply & Install of Gypsum Ceiling 224.91 m2 2.68% 2 1.34% 1.34%
at General Area
2 Install Only Ceiling Painting 233.75 m2 0.63% 1 0.63%
3 Supply & Install of Drop Ceiling 44.21 m' 0.48% 2 0.24% 0.24%
at Lounge
4
5
Install HPL of Drop Ceiling at Manager Room
Supply & install Manhole di. 600 x 600mm
24.15
4.00
m2
units
1.57%
0.20%
3
2
0.52% 0.52%
0.10%
0.52%
0.10%
3TH FLOOR (PHASE II)
6 Supply & Install of decorative wiremesh Ceilling 5.04 m2 0.40% 2 0.20% 0.20%

ELECTRICAL WORKS 10.82% 0.00% 0.25% 1.59% 2.21% 2.21% 2.12% 2.43% 0.00%
1 Supply & Install Electrical Panel 1.00 Point(s) 1.50% 6 0.25% 0.25% 0.25% 0.25% 0.25% 0.25%
2 Supply & Install Incoming Cable (assumption 40 m') 1.00 Ls 0.35% 2 0.17% 0.17%
3 Supply & Install Cable Floor Duct 50.00 m' 0.90% 2 0.45% 0.45%
4 Supply & Install Wiring for Power c/w PVC Conduit 28.00 Point(s) 0.67% 3 0.22% 0.22% 0.22%
2 power each desk (assumption)
5 Supply & Install Wiring for Power Jumper 38.00 Point(s) 0.57% 3 0.19% 0.19% 0.19%
6 Supply & Install Wiring for Switch c/w PVC Conduit 16.00 Point(s) 0.38% 3 0.13% 0.13% 0.13%
7 Supply & Install Wiring for Lighting c/w PVC Conduit 100.00 Point(s) 2.40% 3 0.80% 0.80% 0.80%
8 General Power Outlet 66.00 Piece(s) 0.40% 1 0.40%
2 Outlet Power / each table (assumption)
9 General Switches Triple/Double/Single 12.00 Piece(s) 0.07% 1 0.07%

10 Supply & Install Downlight, 15W, Warm White 80.00 Set(s) 2.00% 2 1.00% 1.00%
at Lobby
11 Supply & Install Indirect Lighting LED Strip 14.00 set 0.42% 2 0.21% 0.21%
12 Supply & Install Hanging Lamp Linear Shape 6.00 set 0.51% 1 0.51%
at Staff Area
13 Supply & Install Hanging Lamp X Shape 1.00 set 0.39% 1 0.39%
at Meeting Room
14 Supply & Install Hanging Haning Lamp 1.00 LS 0.07% 1 0.07%
at Collector Lounge
15 Test & Commisioning 1.00 LS 0.20% 1 0.20%

IT WORKS 5.78% 0.00% 0.00% 0.24% 0.24% 2.65% 2.65% 0.00% 0.00%
1 Supply & Install of Control Access, Finger Print 1.00 Unit(s) 0.55% 2 0.27% 0.27%
2 Supply & Install of UTP Data Cabling c/w PVC Conduit 33.00 Unit(s) 4.28% 2 2.14% 2.14%
for access control, telephone IP, data & wifi
1 data each desk
3 General Data Outlet 28.00 Piece(s) 0.20% 4 0.05% 0.05% 0.05% 0.05%
2 Outlet Power / each table (assumption)
4 Supply & Install of Patch Cord, 1 meter length 28.00 Points(s 0.34% 4 0.08% 0.08% 0.08% 0.08%
from Outlet to Laptop )
5 Supply & Install of Patch Cord, 1 meter length 28.00 Points(s 0.34% 4 0.08% 0.08% 0.08% 0.08%
to Patch Panel )
6 Supply & Install of HDMI/VGA Cable 1.00 Unit(s) 0.08% 4 0.02% 0.02% 0.02% 0.02%

FURNITURE WORKS 26.81% 0.00% 2.00% 3.22% 3.22% 5.09% 5.09% 5.09% 3.09%
A WORKSTATION 12.01% 0.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 0.00%
1 Staff Island for 8 pax 2.00 Unit(s) 5.49% 6 0.91% 0.91% 0.91% 0.91% 0.91% 0.91%
2 Staff Island for 4 pax 1.00 Unit(s) 1.36% 6 0.23% 0.23% 0.23% 0.23% 0.23% 0.23%
3 Staff Island for 1 pax 4.00 Unit(s) 2.40% 6 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
4 Head Division Desk 2.00 Unit(s) 1.00% 6 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%
5 Manager Desk - FT 01 2.00 Unit(s) 1.27% 6 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
6 Round Meeting Table for 4 pax - RT 01 2.00 Unit(s) 0.50% 6 0.08% 0.08% 0.08% 0.08% 0.08% 0.08%

B CUSTOM FURNITURE 7.46% 0.00% 0.00% 0.00% 0.00% 1.86% 1.86% 1.86% 1.86%
1 Wall Display at Staff Area 1.00 Unit(s) 0.85% 4 0.21% 0.21% 0.21% 0.21%
2 Wall Display at Audit Dept Head & Accounting Dept Head 2.00 Unit(s) 1.04% 4 0.26% 0.26% 0.26% 0.26%
3 Credenza A at Close Room 7.00 Unit(s) 2.66% 4 0.66% 0.66% 0.66% 0.66%
4 Credenza B at Close Room 1.00 Unit(s) 0.47% 4 0.12% 0.12% 0.12% 0.12%
5 Credenza C at Close Room 3.00 Unit(s) 0.68% 4 0.17% 0.17% 0.17% 0.17%
6 Pantry Cabinet 1.00 Unit(s) 1.06% 4 0.27% 0.27% 0.27% 0.27%
7 Pantry Backplash 2.70 m2 0.20% 4 0.05% 0.05% 0.05% 0.05%
8 Pantry Top Table 2.70 m2 0.49% 4 0.12% 0.12% 0.12% 0.12%

C LOOSE FURNITURE 7.34% 0.00% 0.00% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22%
1 Director Chair CH-01 4.00 Unit(s) 0.76% 6 0.13% 0.13% 0.13% 0.13% 0.13% 0.13%
2 Staff chair CH-02 19.00 Unit(s) 2.18% 6 0.36% 0.36% 0.36% 0.36% 0.36% 0.36%
3 Guest Chair & Meeting chair CH-03 18.00 Unit(s) 2.40% 6 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
4 Discussion Chair 8.00 Unit(s) 2.00% 6 0.33% 0.33% 0.33% 0.33% 0.33% 0.33%

100.04%
100%
Weekly Planned Progress (%) 0.00% 8.44% 13.38% 14.16% 21.94% 23.41% 13.69% 5.02%
Accumulate of Weekly Planned Progress (%) 0.0% 8.4% 21.8% 36.0% 57.9% 81.3% 95.0% 100.0%
PROJECT SCHEDULE - REV B (PHASE II)
LEVEL 3 (74 m2)
CLIENT: PT MOWILEX INDONESIA At Site
PROJECT: MOWILEX OFFICE RENOVATION At Workshop / Office
LOCATION: LEVEL 3, at Daan Mogot
UPDATE: 24-Oct-19

Weight Duration MONTH 3 MONTH 4 MONTH 1 MONTH 2


NO Description Qty UoM
(%) Installation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Design & Project Management 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1 Approval Design 1.00 Ls 0.00% 1 0.00%
2 Approval Material Interior & ME 1.00 Ls 0.00% 2 0.00% 0.00%
3 Approval Custom Furniture Drawing 1.00 Ls 0.00% 2 0.00% 0.00%
4 Approval Purchased Item 1.00 Ls 0.00% 3 0.00% 0.00% 0.00%
5 Project Management Services 1.00 Ls 0.00% 8 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Preparation Works 16.08% 0.00% 3.91% 3.91% 1.48% 1.48% 1.48% 1.48% 2.33%
1 General Cleaning & Garbage Disposal 1.00 LS 0.45% 7 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
2 Accomodation 1.00 LS 3.88% 7 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55%
3 Transportation 1.00 LS 2.42% 7 0.35% 0.35% 0.35% 0.35% 0.35% 0.35% 0.35%
4 Site Protection 1.00 LS 1.82% 7 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26%
5 Temporary Electrical Power 1.00 LS 0.61% 7 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
6 As Built Drawing Interior & ME 1.00 LS 0.85% 1 0.85%
7 Scaffolding 1.00 LS 1.21% 7 0.17% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%
8 Floor Demolition at existing office 1.00 LS 2.06% 2 1.03% 1.03%
9 Wall Demolition at existing office 1.00 LS 1.21% 2 0.61% 0.61%
10 Ceiling Demolition at existing office 1.00 LS 1.58% 2 0.79% 0.79%

INTERIOR WORKS 37.75% 0.00% 1.28% 1.93% 5.01% 11.76% 12.18% 4.79% 0.80%
A FLOORING WORKS 10.67% 0.00% 0.52% 0.52% 3.60% 3.60% 0.80% 0.80% 0.80%
1 Floor Screeding for carpet installation 31.13 m2 0.75% 2 0.38% 0.38%
2 Floor Chipping & Screeding for Cabling installation 30.00 m' 0.29% 2 0.15% 0.15%
Supply & Install Homogenous Tile 49.35 m2 5.74% 2 2.87% 2.87%
3
at Meeting Room & Staff Area
Supply & Install Homogeneous Plank Tile 12.60 m2 1.47% 2 0.73% 0.73%
4 at Meeting room

Supply & Install Carpet Tile 31.13 m2 2.41% 3 0.80% 0.80% 0.80%
5
at Manager room

B WALL PARTITION WORKS 16.41% 0.00% 0.76% 0.76% 0.76% 6.91% 6.91% 0.32% 0.00%
1 Supply & Install of Gypsum Wall Partition 49.29 m2 3.01% 5 0.60% 0.60% 0.60% 0.60% 0.60%
(Two Sided) w/ Sound Insulation
2 Supply & Install of Gypsum Wall Partition 21.77 m2 0.77% 5 0.15% 0.15% 0.15% 0.15% 0.15%
(One Sided) w/o Sound Insulation
at column cover & perimeter
3 Supply & Install Glass Partition 23.48 m2 4.41% 2 2.21% 2.21%
4 Supply & Install Glass Door 4.00 Set(s) 7.27% 2 3.64% 3.64%
5 Supply & Install Skirting (upper & bottom) 78.02 m' 0.95% 3 0.32% 0.32% 0.32%

C WALL TREATMENT WORKS 7.26% 0.00% 0.00% 0.00% 0.00% 0.29% 3.49% 3.49% 0.00%
1 Supply & Install Cement Finished 116.29 m2 1.83% 2 0.92% 0.92%
at General Area
2 Column & Slab Painting 1.00 ls 3.64% 2 1.82% 1.82%
at General Area
3 Supply & Install Red Brick Accent m2 0.00% 0
at Staff Area -
4 Supply & Install White Brick Accent 17.64 m2 0.86% 3 0.29% 0.29% 0.29%
at Meeting room, Pantry & Breakout
5 Supply & Install Laminated Wall Panel 6.30 m2 0.76% 2 0.38% 0.38%
at Meeting room
6 Supply & Install Glasstone 3.00 m2 0.17% 2 0.09% 0.09%
at Meeting Room & Staff Area

D CEILING WORKS 3.41% 0.00% 0.00% 0.65% 0.65% 0.96% 0.97% 0.18% 0.00%
1 Supply & Install of Gypsum Ceiling 23.21 m2 0.62% 2 0.31% 0.31%
at Lounge& Meeting Room w/ Folding Partition
2 Install Only Ceiling Painting 28.82 m2 0.17% 1 0.17%

3 Supply & Install of Drop Ceiling 28.05 m' 0.68% 2 0.34% 0.34% 4TH FLOOR (PHASE I)
at Lounge
4 Install HPL of Drop Ceiling at Manager Room m2 0.00% 0
5 Re-touch existing acoustic ceiling 1.00 m' 1.58% 2 0.79% 0.79%
6 Supply & install Manhole dim. 600 x 600mm 3.00 units 0.36% 2 0.18% 0.18%

ELECTRICAL WORKS 10.85% 0.00% 0.00% 1.43% 2.51% 2.51% 2.68% 1.72% 0.00%
1 Supply & Install Electrical Panel - Point(s) 0.00% 0
2 Supply & Install Incoming Cable (assumption 40 m') 1.00 Ls 0.85% 2 0.42% 0.42%
3 Supply & Install Cable Floor Duct 30.00 m' 1.31% 2 0.65% 0.65%
4 Supply & Install Wiring for Power c/w PVC Conduit 28.00 Point(s) 1.63% 3 0.54% 0.54% 0.54%
2 power each desk (assumption)
5 Supply & Install Wiring for Power Jumper 11.00 Point(s) 0.40% 3 0.13% 0.13% 0.13%
6 Supply & Install Wiring for Switch c/w PVC Conduit 5.00 Point(s) 0.29% 3 0.10% 0.10% 0.10%
7 Supply & Install Wiring for Lighting c/w PVC Conduit 34.00 Point(s) 1.98% 3 0.66% 0.66% 0.66%
8 General Power Outlet 39.00 Piece(s) 0.57% 1 0.57%
2 Outlet Power / each table (assumption)
9 General Switches Triple/Double/Single 5.00 Piece(s) 0.07% 1 0.07%

10 Supply & Install Hanging Lamp #4 6.00 set 1.24% 1 1.24%


at Staff Area
11 Supply & Install Indirect Lighting LED Strip 5.00 set 0.36% 1 0.36%
12 Supply & Install Downlight, 15W, Warm White 23.00 Set(s) 1.67% 1 1.67%
at Lobby
13 Test & Commisioning 1.00 LS 0.48% 1 0.48%

IT WORKS 4.48% 0.00% 0.14% 1.36% 1.36% 1.36% 0.14% 0.14% 0.00%

1 Supply & Install of UTP Data Cabling c/w PVC Conduit 11.00 Unit(s) 3.47% 3 1.16% 1.16% 1.16%
for access control, telephone IP, data & wifi
1 data each desk
2 Supply & Install of General Data Outlet 11.00 Unit(s) 0.19% 3 0.06% 0.06% 0.06%

3 Supply & Install of Patch Cord, 1 meter length 11.00 Unit(s) 0.32% 6 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%
from Outlet to Laptop
4 Supply & Install of Patch Cord, 1 meter length 11.00 Unit(s) 0.32% 6 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%
to Patch Panel
5 Supply & Install of HDMI/VGA Cable 1.00 Unit(s) 0.19% 6 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%

FURNITURE WORKS 30.89% 0.00% 2.62% 3.69% 3.69% 3.69% 6.61% 6.61% 3.99%
A WORKSTATION 15.73% 0.00% 2.62% 2.62% 2.62% 2.62% 2.62% 2.62% 0.00%
1 Staff Island for 4 pax _ DK 02 1.00 Unit(s) 5.09% 6 0.85% 0.85% 0.85% 0.85% 0.85% 0.85%
2 Staff Island for 1 pax 4.00 Unit(s) 5.82% 6 0.97% 0.97% 0.97% 0.97% 0.97% 0.97%
3 Manager Desk - FT 01 2.00 Unit(s) 3.08% 6 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%
4 Meeting Table for 6 pax - MT 01 1.00 Unit(s) 1.75% 6 0.29% 0.29% 0.29% 0.29% 0.29% 0.29%

B CUSTOM FURNITURE 8.77% 0.00% 0.00% 0.00% 0.00% 0.00% 2.92% 2.92% 2.92%
1 Credenza A 2.00 Unit(s) 2.58% 3 0.86% 0.86% 0.86%
at Close Room
2 Filling Cabinet 1.00 Unit(s) 6.19% 3 2.06% 2.06% 2.06%
at Staff Room

C LOOSE FURNITURE 6.39% 0.00% 0.00% 1.06% 1.06% 1.06% 1.06% 1.06% 1.06%
1 Director Chair CH-01 2.00 Unit(s) 0.92% 6 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
2 Staff chair CH-02 8.00 Unit(s) 2.23% 6 0.37% 0.37% 0.37% 0.37% 0.37% 0.37%
3 Meeting chair & Guest Chair CH-04 10.00 Unit(s) 3.24% 6 0.54% 0.54% 0.54% 0.54% 0.54% 0.54%

100.06%
100%
Weekly Planned Progress (%) 0.00% 7.95% 12.31% 14.05% 20.80% 23.08% 14.74% 7.13%
Accumulate of Weekly Planned Progress (%) 0.00% 7.9% 20.3% 34.2% 55.0% 78.1% 92.8% 100.0%