Estimate of Toilet by SAM

The document is a bill of quantities for construction materials and labor for building bathroom facilities and a septic tank. It includes 7 line items for materials and labor needed for 5'x6' bathrooms, including excavation, concrete, brickwork, plastering and filling. It also includes 6 line items for a 4'x4'x4' septic tank, providing quantities of excavation, concrete, brick masonry, plaster and a precast slab. A summary of total materials is provided, requiring 1330 bricks, 9 bags of cement, 41 cubic feet of sand, 17 cubic feet of crush and 30 cubic feet of earth filling for the bathrooms. Labor requirements are estimated at 2 man-days

Uploaded by

Ghiyas Uddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
5K views4 pages

Estimate of Toilet by SAM

The document is a bill of quantities for construction materials and labor for building bathroom facilities and a septic tank. It includes 7 line items for materials and labor needed for 5'x6' bathrooms, including excavation, concrete, brickwork, plastering and filling. It also includes 6 line items for a 4'x4'x4' septic tank, providing quantities of excavation, concrete, brick masonry, plaster and a precast slab. A summary of total materials is provided, requiring 1330 bricks, 9 bags of cement, 41 cubic feet of sand, 17 cubic feet of crush and 30 cubic feet of earth filling for the bathrooms. Labor requirements are estimated at 2 man-days

Uploaded by

Ghiyas Uddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

BILL OF QUANTITIES

Measurement (ft)
Sr. #. Description Quantity
No. Length Breadth Height

A - Bath Rooms (5'x6')ft


1- Excavation of Foundation in Ordinary Soil

Bath Room 1 23.5 1.833 1 43.08 Cft

Total: 43.08 Cft

2- PCC 1:4:8

Bath Room 1 23.5 1.833 0.25 10.77 Cft

Total: 10.77 Cft

3- 2" Thick P.C.C. (1:2:4) in Floors

Bath Rooms 1 5 6 0.166 4.98 Cft

Total: 4.98 Cft

4- Pacca brick work in 1:4 C/S mortor in foundation & plinth


1st step

Bath Room 1 23.5 1.5 0.25 8.81 Cft

2nd step

Bath Room 1 23.5 1.125 0.5 13.22 Cft

3rd step G.L to P.L

Bath Room 1 23.5 0.75 1 17.63 Cft

Total: 39.66 Cft

5- Pacca brick work in 1:4 C/S mortor in S/S

Bath Room 1 23.5 0.375 7.5 66.09 Cft


Sub Total: 66.09 Cft

Reduction of Door and ventilater

Door 1 2.5 0.375 6.5 6.09 Cft

Ventilator 1 2 0.375 1.5 1.13 Cft

Sub-Total: 7.22 Cft

G. Total: 58.88 Cft

6- 2" Thick D.P.C in cement concrete in 1:2:4

Bath Room 1 23.5 0.75 0.166 2.93 Cft

Sub Total: 2.93 Cft

7- 1/2" thick cement sand plaster in 1:4


Inside of Bath's 1 22 - 7.5 165.00 Sft

Door Horizontal Side 1 2.5 0.375 - 0.94 Sft

Door Vertical Side 1 - 0.375 6.5 2.44 Sft

Ventilaotor Horizontal Side 1 2 0.375 - 0.75 Sft

Ventilator Vertical Side 1 - 0.375 1.5 0.56 Sft

Sub-Total: 169.69 Sft

Reduction of Door and ventilater


BILL OF QUANTITIES

Measurement (ft)
Sr. #. Description Quantity
No. Length Breadth Height

Door 1 2.5 - 6.5 16.25 Sft

Ventilator 1 2 - 1.5 3.00 Sft

Sub-Total: 19.25 Sft

Total: 150.44 Sft

8- Earth filling inFloor

Bath Room floor 1 5 6 1 30.00 Cft

Total: 30.00 Cft

B- Septic Tank (4'x4'x4')

Measurement (ft)
Sr. #. Description Quantity
No. Length Breadth Height

1- Excavation For Septic Tank 1 5.5 5.5 4.25 128.56 Cft

Total 128.56 Cft

2- Concrete 1:4:8 In bed of Septic Tank 1 5.5 5.5 0.25 7.56 Cft
Total 7.56 Cft

3- Concrete 1:2:4 In bed of Septic Tank 1 4 3.625 0.167 2.42 Cft

Total 2.42 Cft

4- Brick Masonary in 1:3 CSM 1 19 0.75 5 71.25 Cft

Total 71.25 Cft

5- 1/2" Thick Plaster in 1:3 CSM 1 19 4 76.00 Sft

Total 76.00 Sft

6- Pre Cast Slab 1 4.5 4.5 1 20.25 Sft

Total 20.25 Sft


Quantities of Labour and Material Required
Deformed Skilled Unskilled
Sr. Bricks Cement Sand Crush Earth Tough
Description Quantity Unit Brick ballast Steel Labour Labour
No. (Nos.) (Bags) (Cft) (Cft) (Cft) Paver
(Kg.) (M.Days) (M.Days)

A - Bath Rooms (5'x6')ft

1 Excavation of Foundation in Ordinary Soil 43.08 Cft 0.3

2 PCC 1:4:8 10.77 Cft 1.0 5.1 10.2 0.1 0.5

2 2" Thick P.C.C. (1:2:4) in Floors 4.98 Cft 0.9 2.2 4.4 0.0 0.2
Pacca brick work in 1:4 C/S mortor in
3 39.66 Cft 535 1.9 9.5 0.5 1.0
foundation & plinth
4 Pacca brick work in 1:4 C/S mortor in S/S 58.88 Cft 795 2.8 14.1 0.7 1.3

5 2" Thick D.P.C in cement concrete in 1:2:4 2.93 Cft 0.5 1.3 2.6 0.0 0.1

6 1/2" thick cement sand plaster in 1:4 150.44 Sft 1.7 8.4 1.1 1.9

7 Earth filling inFloor 30.00 Cft 30.0 0.3

Total: 1330 - 9 41 17 30 - - 2 6

Total (Say): 1330.00 - 9.00 41.00 17.00 30.00 - - 2.00 6.00

B- Septic Tank (4'x4'x4')

Deformed Skilled Unskilled


Sr. Bricks Cement Sand Crush Earth Tough
Description Quantity Unit Brick ballast Steel Labour Labour
No. (Nos.) (Bags) (Cft) (Cft) (Cft) Paver
(Kg.) (M.Days) (M.Days)

1 Excavation of Septic Tank In Ordinary Soil 129 Cft 1.03

2 P.C.C (1:4:8) in Bed 7.56 Cft 0.72 3.6 7.2 0.06 0.38

3 P.C.C (1:2:4) in Bed 2.42 Cft 0.43 1.1 2.1 0.02 0.12

4 Brick Masonary in 1:3 CSM 71.25 Cft 961.875 3.38 17.10 0.8 1.6

5 1/2" Thick Plaster in 1:3 CSM 76.00 Sft 0.84 4.26 0.5 0.95

6 Pre Cast Slabs 20.25 Sft

Total: 961.88 - 5.36 26.01 9.32 - - - 1.46 4.06

Total (Say) 962.00 - 5.36 26.01 9.32 - - - 1.00 4.00


CAPITAL COST OF MATERIAL AND LABOUR

Sr. Cost per unit Total Cost


Description Quantity Unit
No. (Rs.) (Rs.)

A - Bath Rooms (5'x6')ft

1 Bricks 1330 No. 7 9,310

2 Cement 9 Bags 470 4,230

3 Sand 41 Cft 35 1,435

4 Crush 17 Cft 45 765

6 Doors 1 No. 2000 2,000

7 Ventilator 1 No. 200 200

8 W.C P trape Elbow Bib cock 1 No. 1300 1,300

9 PVC pipe 4" Dia 6' for each Toilet 6 Rft 30 180

10 PVC Vent pipe 2" Dia with cap 8 Rft 20 160

11 Transportation Charges 1 Job 400 400

Total Material Cost: 19,980

Labour

1 Skilled 2 M.Day 700 1,400

2 Un-Skilled 6 M.Day 350 2,100

Total Labour Cost: 3,500

Total Cost: 23,480

B-Septic Tank (4'x4'x4)

1 Bricks 962 No. 7 6,734

2 Cement 5.36 Bags 470 2,522

3 Sand 26.01 Cft 35 910

4 Crush 9.32 Cft 45 419

5 Pre Cast Slab 20.25 Sft 70 1,418

Total Material Cost: 12,003

Labour

1 Skilled 1.00 M.Day 700 700

2 Un-Skilled 4.00 M.Day 350 1,400

Total Labour Cost: 2,100

Total Cost: 14,103

Total Cost: 37,583