PMP Study Notes
PMP Study Notes
Thank you very much for downloading the PMP Study Notes based on PMBOK Guide 5th
Edition by Edward Chung, PMP. Hope the notes will help you preparing for your PMP
Certification Exam.
I originally created the notes for my PMP certification preparation which helped me to pass the
PMP exam with 4 proficient and 1 moderately proficient. These study notes were the fruits of
hours of reading and studying the PMBOK Guide, the PM PrepCast, the Edwel's PMP Book,
Andy Crowe's PMP book and countless practice exams.
After getting my PMP credential, I posted all the PMP study notes as blog posts on my
personal blog at http://www.edward-designer.com/web/pmp. To my surprise, many fellow PMP
aspirants find my notes useful for them and have literally 'printed' all the blog posts for their
PMP preparation.
I constantly ask myself: what I can do more to help PMP aspirants as a way to make some
contribution to the project management profession. The PMP Study Notes you are now
reading is my response to the need of PMP aspirants quality study notes for the PMP
examination. You can use it from the beginning of your PMP preparation so that you can add
any personal notes to it or as a last minute revision notes to check your PMP progress.
The PMP exam is tough, yet with lots of efforts and the right study materials, you can pass too!
A. PMP Formulas
Project Management
Project Manager
Organization Types
Organization Types: Projectized (project manager has the ultimate authority over the
project, team members are often collocated), Matrix (Strong, Balanced, Week),
Functional
Composite - a combination of different types, depending on the actual need
Tight Matrix = co-location, nothing to do with the organization type (not necessarily a
matrix org.)
Functional organizations => the project manager has little authority, often called project
expeditor (no authority) or coordinator (little authority), project coordination among
functional managers
Matrix organization => multiple bosses and more complex
Project Based Organization (PBO) - conduct the majority of their activities as projects
and/or privilege project over functional approaches, they can include: departments with
functional organizations; matrix organizations; projectized organizations and other forms
of organizations that privilege a project approach for conducting their activities, success
is measured by final results rather than position/politics
Project Lifecycle vs Project Management Lifecycle vs Product Lifecycle
Important Terms
Organization Process Assets is a major input in all planning process, which may be
kept at PMO, directly related to project management, including Processess and
Procedures (including templates (e.g. WBS, schedule network diagrams, etc.),
procedures for issuing work authorizations, guidelines, performance measurements)
and Corporate Knowledge Base
The Configuration Management Knowledge Bases contain baselines of all
organization standards
Lessons Learned - focus on the deviances from plan (baseline) to actual results
Enterprise Environment Factors (often are constraints) are influences not in the
immediate control of the project team that affect the project, intra-organization and
extra-organization, e.g. organizational culture, organization structure
(functional/matrix/projectized structure), existing human resources, work authorization
system, PMIS
The work authorization system (WAS) is a system used during project integration
management to ensure that work gets done at the right time and in the right sequence
EEF are inputs for all initiating, most planning process, not much in the
executing/controlling process, none in closing process
Organization culture: process-oriented/results-oriented, job-oriented/employee-oriented,
professional-oriented/parochial-oriented, open system/closed system, tight control/loose
control, pragmatic/normative
Project Governance - for the whole project lifecycle, fits in the organization's
governance model, define responsibilities and accountabilities, controlling the project
and making decisions for success, alignment of project with stakeholders'
needs/objectives, provides a framework for PM and sponsors to make decisions to
satisfy both parties, should be described in the PM plan
Business Case : background, analysis of the business situation, costs and benefits
(cost-benefit analysis), to help in selection of project created by the initiator
Project Statement of Work (SOW) : describes the business need, high level scope of
deliverables and strategic plan of the organization, created by the
sponsor/initiator/buyer
Project Charter : formally authorizes the project, includes all those from above plus
approval criteria, preliminary budget, primary stakeholders, the name of PM,
assumptions and decisions etc., usually created by PM (in develop project charter
process) and signed by the sponsor, remains fairly the same during project lifecycle,
except big changes like sponsor has resigned [the current sponsor should initiate the
change to the charter before he leaves]
Project Charter is not a contract
Project Management Plan : how the project will be performed and managed -
documents assumptions & decisions, helps communication between stakeholders,
goals, costs & time scheduling (milestones), project management system and
subsidiary management plans and documents
Project Management Plan is NOT a project schedule
Project Management System: includes a list of project management processes, level of
implementation (what actions to take in the management processes), description of
tools and techniques, resources, procedures, change control system [forms with
tracking systems, approval levels]
Forecast (future) vs Status Report (current status) vs Progress Report (what have
been done/delivered)
Journey to Abilene (Abilene's Paradox) - committee decisions can have a paradox
outcome, the joint decision is not welcome by either party (because of fear of raising
objections)
when something unusual happens, always refer to the PM Plan/Charter for instruction
on how to proceed; if not found, ask for direction from the management
unresolved issues will lead to conflicts
02 - 03. Project Management Processes and
Knowledge Areas
The Project Management Process Groups (IPECC)
1. Initiating
2. Planning
3. Executing
4. Monitoring and Controlling
5. Closing
Planning and Executing are iterative. Monitoring and Controlling is exercised over Planning
and Executing.
A phase is not a process group. The 5 processes can happen in 1 phase.
The process groups is not in sequence
The PM should tailor the choices of processes to fit in individual processes (tailoring)
deliverables are often incremental in nature
A project/phase begins with the "Initiating" processes, the "Planning", "Executing" and
"Monitoring and Controlling" processes may occur in a repetitive manner while the "Closing"
processes will be carried out to end the project/phase.
Initiating
Planning
create Project Management Plan [why the project? what to deliver? who do what?
when accepted? how executed?], subsidiary documents (schedule baseline, cost
baseline, performance management baseline, scope baseline (scope statement,
WBS, WBS dictionary) and subsidiary management plans (scope, schedule, budget,
quality, human resources [roles & responsibility, organization chart and staffing
management plan include the staff need, rewards, safety and training need] ,
stakeholder, requirements, process improvement, communication, change, risk and
procurement) - all are not finalized until a thorough risk management has been
performed, need to be approved before work begins
all plan and documents can be formal or informal, generalized or detailed, depending
on needs
Project Management Plan maybe continually updated during the project with rolling
wave planning / progressive elaboration
obtain approval of plan from designated stakeholders, changes to the project
management plan and subsidiary documents/plans need formal procedures described
in the change control system
hold kick-off meeting
planning process group is MOST important, with over 1/2 of all the 47 process in this
group
may need re-planning when significant changes to the baseline is observed in the
executing/monitoring processes
Executing
Closing
Product-oriented Processes
initiating
planning and organizing
executing
closing
1. Project Integration Management - assemble and combine all parts into a coherent
whole
2. Project Scope Management
3. Project Time Management
4. Project Cost Management
5. Project Quality Management
6. Project Human Resource Management
7. Project Communications Management
8. Project Risk Management
9. Project Procurement Management
10. Project Stakeholder Management
04. Project Integration Management
integration management is needed when processes interacts
to identify,combine, unify and coordinate various processes/activities and manage the
interdependencies
communication is most important
a PM Plan not meeting requirements is a defect
formally authorize the project and allow the PM to apply organizational resources
well-defined project start and project boundaries
project charter is a several page document including high level information of the
project: project background, business case, goals (S.M.A.R.T. specific, measurable,
attainable, realistic, time-bound), who is and the authority of the project manager,
budget, risk, stakeholders, deliverables, approval criteria, etc.
can link the project to other works in the organization through portfolio/program
management
signed off by the sponsor (the one who supply the money/resources)
agreements: either a contract (for external parties), letter of intent, service level
agreement, etc. (can be legally binding or NOT)
a charter is NOT a contract because there is no consideration
PMO may provide the expert judgement
Facilitation techniques includes brainstorming, conflict resolution, problem solving,
meeting, etc.
the project management plan is a formal written document on how the project is
executed, monitored and closed, including all subsidiary management plans (scope,
requirements, change, configuration, schedule, cost, quality, process improvement,
human resource, communication, risk, procurement) and documents (cost baseline,
schedule baseline, scope baseline, performance measurement baseline, cost
estimate, schedule, responsibility for each deliverable, staff requirements) and some
additional documents/plans (selected PM processes and level of implementation)
the contents to be tailored by the PM (tailoring) to suit each project
created by PM, signed off by destined KEY stakeholders (e.g. project sponsor, project
team, project manager)
may be progressively elaborated in iterative phases (outputs from other processes), this
must be the final process/iteration to consolidate the PM Plan
when the project management plan is baselined (i.e. validated and then signed off by
key stakeholders), it is subject to formal change control and is used as a basis for
comparison to the actual plan
after baselining, the senior management must be consulted if these high level
constraints are to be altered (whether to use the management reserves)
can be re-baselined if significant changes are seen (scope change, internal
changes/variances (for the project execution), external factors) <- needed to be
approved by sponsors/stakeholders/senior management, must understand the
underlying reasons first (built-in costs is not usually a legitimate reason)
cost baseline (specific time-phased budget), schedule baseline (-> knows when to
spend money), scope baseline (includes scope statement, WBS, WBS dictionary):
whether preventive/corrective/defect repair actions are needed
the performance measurement baseline (PMB) is an approved scope-schedule-cost
plan for the project work (to use in earned value management), it includes
contingency reserve but excludes management reserves
configuration management (works with change control management plan), document
all change versions of project deliverables and completed project components, PMIS
includes: Configuration Management System (contains the updated
deliverable/project specifications and processes) and Change Control System
(contains formal documents for tracking changes)
configuration management system contains the most updated version of project
documents
Kick-off Meeting: at beginning of the project/phase, participants including project
team+stakeholders, element including project review, responsibility assignment matrix,
participation of stakeholders, escalation path, frequency of meetings
Microsoft Project is considered by PMI as close to a bar chart, not an PMIS
create project deliverables, acquire/assign/train staff, manage vendors, collect data for
reports, document lessons learned
implement approved process improvement plans and changes, change requests include
corrective actions, preventive actions, defect repair and updates (all considered to
be change requests)
if the PM discovers a defect, he/she should instruct the team to make defect repair
during this process (need change request but may be approved by the PM only (if
stipulated in PM Plan for minor change))
approved change requests - approved in the perform integrated change control, may
include preventive, corrective and defect repair actions
change requests may arise as a result of implementing approved change requests
PM should be of service to the team, not a boss
a work authorization system (part of EEF) defines approval levels needed to issue
work authorization (to allocate the work) and is used to prevent scope creep as formal
approval must be sought before work begins
Stakeholder risk tolerance is part of EEF
Face-to-face meeting is considered to be most effective
The PM Plan can be considered as a deliverable
most of the time of project spends here
validated changes - actions taken as a result of the approved change requests are
validated against the original change requests, to ensure correct implementation
corrective and preventive actions usually don't affect the baseline, only affect the
performance against the baseline
defect repair: considered as rework, deliverable not accepted, either rework or scrap,
strongly advise defect prevention to defect repair
the work performance info is fed from all other control processes (e.g. control schedule,
control stakeholder engagement, control communications, control costs, control quality,
etc.)
variance analysis is NOT a forecast method
ensure all procurements are closed (in the Close Procurements Process) before formal
closure of the project/phase
create the project closure documents
formal sign off by designated stakeholders/customer
obtain formal approval to close out the project/phase (administrative closure)
obtain approval and deliver the deliverables (maybe with training)
finish and archive documentations, lessons learnt and update to organizational process
asset
if the contract comes with a warranty, make sure that changes during the project are
evaluated against the origin clauses, ensure alignment of the warranty and changes
to close a project as neatly and permanently possible
for multi-phase projects, this process will be performed once for every phase end and
once for the whole project (5 times for project with 4 phases)
litigation can be further pursued after the closure
05. Project Scope Management
ensure the inclusion of all and only the work required to complete the project
successfully
Product Scope - requirements needed to be fulfilled to create the product, assessed
against the product requirements and WBS
Project Scope - activities and processes needed to be performed to deliver the
product scope, assessed against the scope baseline (scope statement, WBS and WBS
dictionary), e.g. including testing & quality assurance, assessed against the PM plan
scope management to prevent scope creep (additional requirements added without
any proper control)
The completion of project scope is measured against the project management plan
whereas the completion of product scope is measured against the product
requirements/WBS
gold plating - additional requirements initiated by the team members to exceed
expectation, considered a subset of scope creep
Scope Baseline: scope statement + WBS + WBS dictionary
WBS includes only the deliverables/outcomes/results (not actions)
Scope Management Plan: how the scope will be defined, validated and controlled
including how to prevent scope creep, how to handle change requests, escalation
path for disagreement on scope elements between stakeholders, process for creating
scope statement, WBS, processing CR, how the deliverables will be accepted
Requirements Management Plan: how the requirements will be managed, documented
and analyzed,
including how to process requirements, address missed requirements, configuration
management, prioritize requirements, metrics (and rationale) for defining the product,
define the traceability structure (in RTM), authorization level for approving new
requirements
important: primary means to understand and manage stakeholder expectations
Collect Requirements
Define Scope
project & product scope, outlines what will be and what will NOT be included in the
deliverables, including details of risks, constraints and assumptions
vs project charter which includes high-level descriptions
provides alternatives if the budget and schedule could not meet management's
expectations
value engineering is a part of the product analysis technique (Value Engineering
(value analysis, value management, value methodology) - finding alternatives to
constraints to improve product/reduce cost without sacrificing the scope)
project scope statement includes objectives, (project and product) scope,
requirements, boundaries, deliverables, acceptance criteria, constraints,
assumptions, milestones, cost estimation, specifications, configuration management
requirements, approval requirements, etc.
The scope statement is progressively elaborated
Create WBS
the WBS must be created (if take on a running project without WBS, stop the project
and prepare the WBS first)
WBS is a structured hierarchy created by the organization/stakeholders, can be in an
organization chart or table form, based on the project deliverables (not tasks
needed)
can be a template in OPA
a higher level above a work package is 'control account' (control point where scope,
cost and schedule are compared to earn value for performance measurement), a work
package can have only ONE control account
WBS includes 100% of scope (100% rule)
code of accounts: a numbering system to identify WBS components
chart of accounts: a list of all account names and numbers
1.1 for the 2nd level, 1.1.1 for the 3rd level
WBS is a decomposition tool to break down work into lowest level manageable (time
and cost can be estimated, work package can be assigned to a team member) work
packages, e.g. by phase or major deliverables
different work packages can be at different levels of decompositions
WBS does not show dependencies between work packages, but a WBS dictionary does
(WBS dictionary clarifies WBS by adding additional information)
the major deliverables should always be defined in terms of how the project will actually
be organized, for a project with phases, the decomposition should begin with the phase
first
scope baseline, an output from Create WBS, is created by the project team
the work packages are broken down enough to delegate to a staff, usu. 8 - 80 hours
work
Validate Scope
Control Scope
define policies, procedures and documentation for managing and controlling project
schedule
including scheduling methodology, tools, level of accuracy, control thresholds (limit
beyond which preventive/corrective actions needed), rules of performance
measurement (e.g. earned value)
lead and lags are NOT schedule constraints
Define Activities
the scope baseline is used here as it represents the approved (stable) scope
further decompose work packages into activities for more detailed and accurate
estimations
'activities' is the PMI terminology for 'tasks' and 'work efforts'
activity is more related to the actual work/process to produce the deliverables
activity types: level of efforts (support, measured in time period), discrete efforts or
apportioned effort (in direct proportion to another discrete effort)
activities have durations while milestones do not (zero duration)
Sequence Activities
WBS is no longer needed, so the Project Scope Statement is the input rather than
scope baseline
Precedence Diagramming Method (PDM) to diagram dependencies
Network Diagramming Tools are software tools that graphically represent activity
sequences
network diagrams: shows dependencies, duration, workflow, helps identifying critical
paths
Leads: begin successor activity before end of predecessor, for schedule compression
(fast tracking) (negative lags)
Lags: imposed delay to successor activity, e.g. wait 2 weeks for concrete to cure (FS
+14 days)
Network Diagram Setup : 7-box method, usually using software tools or 5-box method
if the ES and LS are identical, the activity is on the critical path
consults SME (subject matter experts, i.e. the one carrying out the actual work) to come
with with the estimation, not on the PM's own
Analogous Estimating: based on previous activity with similar nature (a form of expert
judgement), used when little is known or very similar scope, works well when project
is small, NOT ACCURATE
Parametric Estimating: based on some parameters, e.g. the time for producing 1000
component based on that for 1 component * 1000, use an algorithm based on historical
data, accuracy depends on the parameters selected, can be used on [a portion of / the
entire] project
One-Point Estimating: based on expert judgement, but highly unreliable
Three-Point Estimating: best (optimistic), most likely (realistic), worst (pessimistic)
cases, Triangular Distribution vs PERT (Project Evaluation and Review Techniques,
Beta Distribution, weighted average using statistical methods [most likely * 4 - 95%
confidence level with 2 sigma]), triangular distribution (non-weighted average of three
data points), uncertainties are accounted for
In real world applications, the PERT estimate is processed using Monte Carlo analysis,
tie specific confidence factors to the PERT estimate
Bottom-Up Estimating: a detailed estimate by decomposing the tasks and derive the
estimates based on reliable historical values, most accurate but time-consuming
Heuristics: use rule of thumb for estimating
standard deviation (sigma value, deviation from mean, to specify the precision of
measurement): 1 sigma: 68%, 2 sigma 95%, 3 sigma 99.7%, 6 sigma 99.99%
accuracy is the conformance to target value
contingency reserve: for known unknowns, owned by PM, may be updated, part of
schedule baseline
management reserve: for unknown unknowns, owned by management, included in
overall schedule requirements
update to documents: basis of estimates, assumptions and contingencies
activity duration estimate may be in a range, don't include lags
Develop Schedule
the schedule baseline is the approved and signed version of project schedule that is
incorporated into the PM plan
the schedule is calendar-based taking into accounts holidays/resource
availability/vacations
vs the time estimate (work effort/level of effort) just describes the man hours / man
days
Slack/Float: activities that can be delayed without impacting the schedule
Free slack/float: time an activity can be delayed without delaying the Early Start of the
successor
Total slack/float: time an activity can be delayed from early start without delaying the
project end date (scheduling flexibility), can be negative, 0 (on the critical path) or
positive
Project Float: without affecting another project
Negative float: problem with schedule, need schedule rework
Project slack/float: time the project can be delayed without delaying another project
Early Start (ES) - earliest time to start the activity
Late Start (LS) - latest time to start without impacting the late finish
Early Finish (EF) - earliest time to end the activity
Late Finish (LF) - latest time to finish without impacting successor activity
Slack/Float = LS - ES or LF - EF
The float is the highest single value along the critical path, NOT the sum of them
Critical Path: the longest path that amount to shortest possible completion time
(usually zero float, activities with mandatory dependency with finish-to-start
relationship), can have more than 1 critical paths (more risks), critical paths may
change (keep an eye on near-critical paths)
activities on the critical path are called critical activities
Path with negative float = behind schedule, need compression to eliminate negative
float
Forward Pass : compute the early start
Backward Pass : compute the late start
Fast Tracking : allow overlapping of activities or activities in parallel, included
risks/resource overloading
Crashing : shorten the activities by adding resources, may result in team burnout
Scheduling Techniques
Critical Path Method (CPM) - compute the forward and backward pass to determine
the critical path and float
Critical Chain Method (CCM) - deal with scarce resources and uncertainties, keep the
resources levelly loaded by chaining all activities and grouping the contingency and put
at the end as project buffer, for activities running in parallel, the contingency is called
feeding buffer (expect 50% of activities to overrun)
Buffer is determined by assessing the amount of uncertainties, human factors, etc.
Parkinson's Law: Work expands so as to fill the time available for its completion.
Modeling Techniques
What if analysis: to address feasibility/possibility of meeting project schedule, useful in
creating contingency plan
Monte Carlo: run thousand of times to obtain the distribution using a set of random
variables (stochastic variables), use a combination of PERT estimate and triangular
distributions as end point estimates to create the model to eliminate schedule risks,
the graph is a 'S' curve
Network Diagram: bar charts with logical connections
Hammock activities: higher-level summary activities between milestones
Milestone Charts: show only major deliverables/events on the timeline
data date (status date, as-of date): the date on which the data is recorded
the Schedule Data includes schedule milestones, schedule activities, activities
attributes, and documentation of all assumptions and constraints, alternative schedules
and scheduling of contingency reserves
the Project Calendars identify working days
Control Schedule
The Cost Management Plan establishes: i) level of accuracy and level of precision, ii)
unit of measurement, iii) WBS procedure links (to control account (CA)), iv) control
threshold, v) earned value rules of performance, reporting, funding and processes
Life cycle costing = total cost of ownership : production cost, running and
maintenance cost, etc.
Estimate Costs
Cost Types
Variable costs - costs change with the amount of work, e.g. hourly consultants
Fixed costs - costs that are constant, e.g. equipment leases
Direct costs - directly attributed to the project
Indirect costs - shared costs like AC, lighting, etc.
Determine Budget
Control Costs
quality policy (either organizational or just for the project), methods and procedures to
meet the objectives and satisfy customer's needs
identify the quality requirements and document how to achieve
Cost-benefit Analysis: cost of implementing quality requirements against benefits
Cost of Quality: lowest quality cost is prevention, highest quality cost (poor quality) is
rework and defect repair (as high as 5000 times the cost for carrying out unit testing),
lost reputation and sales, failure cost may be internal/external (found by customer)
Warranty claims are external cost of quality
Cost of Quality is the total cost of quality efforts throughout the product's lifecycle
cost of conformance (prevention cost, appraisal cost) vs cost of non-conformance
(failure cost [internal/external])
internal/external is reference to the project (not the organization)
Poka Yoke (mistake proofing), Zero Quality Control (100% source inspection), Voice of
Customer and FEMA (Failure Modes of Effects Analysis) are planning tools for quality
management
Quality Metrics: function points, MTBF (mean time between failure), MTTR (mean time
to repair)
Marginal Analysis: ROI of quality measures
Control Quality
Motivational Theories
Maslow's Hierarchy of Needs - personal needs (Physiological > Security > Social >
Esteem > Self Actualization)
Herzberg's Hygiene Theory - satisfaction (motivators) vs dissatisfaction (hygiene
factors to avoid dissatisfaction but do not provide satisfaction, also called KITA factors
e.g. incentives/punishments), hygiene factors include good working conditions, a
satisfying personal life, and good relations with the boss and coworkers
Expectancy Theory - Expectancy (extra work will be rewarded) Instrumentality (good
results will be rewarded) Valence (the individual's expected reward), for a person to be
motivated, efforts/performance/outcome must be matched - will only work hard for
achievable goals
Achievement Theory - three motivation needs: achievement (nAch), power (nPow),
affiliation (nAff), best is a balanced style for the PM
Contingency Theory - task-oriented/relationship-oriented with stress level (high stress
-> task-oriented better)
Leadership Theory
including: analytical (with expertise), autocratic (with power), bureaucratic, charismatic,
consultative, driver (micromanagement), influencing, laissez-faire (stay out)
Theory X - assumes employees are lazy and avoid work, need incentive/threats/close
supervising
Theory Y - assumes employees may be ambitious and self-motivated, will perform
given the right conditions
Theory Z - (japanese) increasing loyalty by providing job for life with focus on well-being
of employee (on and off job), produces high productivity and morale
Situational Continuum Leadership - directing/telling > coaching/selling (manager
define the work) > supporting/participating (subordinate define the work) > delegating
according to maturity/capability of the subordinate
Manage Communications
create, collect, distribute, store, retrieve and dispose project information according to
the Communication Management Plan
ensures good communications, noises managed, stakeholders may feedback on how to
improve
Communication Barriers vs Communication Enhancers
55% message thru body language, 38% thru paralingual, 7% thru words used
Types of Communications: Formal Written, Formal Verbal, Information Written, Informal
Verbal
Formal Written: plans, project charter, meeting minutes
Formal Verbal: presentations, public speeches, keynote addresses
Informal Written: memos, emails
Informal Verbal: meetings, ad hoc conversations
Performance Reporting: status, progress, variance, trend, earned value reports and
forecasts, summary of changes, risks and issues
PM Plan Update to show the latest performance (against Performance Measurement
Baseline)
Feedback from stakeholders are to be stored in OPA
Control Communications
define and provide resources and time to perform risk management, including:
methodology, roles and responsibilities, budget, timing (when and how often), risk
categories (e.g. RBS), definitions, stakeholder tolerances (a EEF), reporting and
tracking
performed at project initiation and early in the Planning process
failure to address risks early on can ultimately be more costly
analytical techniques include stakeholder risk profile analysis, strategic risk scoring
sheets
Identify Risks
prioritizing risks for further analysis/action and identify high priority risks
need to identify bias and correct it (e.g. risk attitude of the stakeholders)
qualitative risk assessment matrix (format described in the Risk Management Plan)
which includes the risk, the impact (high, medium, low) and the likelihood (low, medium,
high)
update to risk register and other related documents
risk register update are output of Perform Qualitative Risk Analysis, Perform
Quantitative Analysis, Plan Risk Responses and Monitor & Control Risks
the scope baseline is used to understand whether the project is a recurrent type or a
state-of-the-art type (more risks)
risks requiring near-term responses are more urgent to address
the cost, schedule and risk management plan contains guidelines on establishing and
managing risks
involves mathematical modeling for forecasts and trend analysis
data gathering and representation techniques: interviewing, probability distributions
[normal distribution (bell shaped curve)],
sensitivity analysis (using the tornado diagram as presentation) for determining the
risks that have the most impact on the project
Failure Modes Effects Analysis (FMEA) which documents the "severity", "occurrence"
and "detection" of risks
FMEA for manufactured product or where risk may be undetectable, Risk Priority
Number (RPN) = severity (1-10) x occurrence ([0.07%] 1-10 [20%]) X detectability (1-10
[undetectable]), also a non-proprietary approach for risk management
Expected Value / Expected Monetary Value (EMV), probability x impact (cost/effort
lost), opportunities (+ve values), threats (-ve values)
Monte Carlo Analysis - by running simulations many times over in order to calculate
those same probabilities heuristically just like actually playing and recording your results
in a real casino situation, 'S' curve (cumulative distribution) will result, may use
PERT/triangular distribution to model data, may use thousands of data points (a random
variable), for budget/schedule analysis
Decision Tree Analysis - another form of EMV, branching: decision squares (decision
branch - options), circles (uncertainty branch - possible outcomes)
Control Risks
when the above risk planning processes have been performed with due diligence, the
project is said to have a low risk profile
to check if assumptions are still valid, procedures are being followed and any deviance
to identify new risks and evaluate effectiveness of risk response plan
any need to adjust contingency and management reserves
to re-assess the individual risk response strategies to see if they are effective
risk audits deal with effectiveness of risk response and the risk management process
risk audits are usually performed by experts outside project team for the whole risk
management process
reserve analysis and fund for contingencies apply only to the specific risks on the
project for which they were set aside
workaround: when no contingency plan exists, executed on-the-fly to address
unplanned events - still need to pass through normal change control if change requests
are needed
determine the workaround is performed in control risks
12. Project Procurement Management
Procurement Statement of Work (SOW) is a legal document subject to legal reviews,
legal advise should be sought throughout the whole procurement process
sellers are external to the project team
need to go through all 4 processes for each and every procurement
contract elements: offer (seller offer buyer), acceptance (buyer criteria), capacity
(physical/financial capabilities), consideration (seller receive), legal purpose (must be
legal under law)
best if contract is signed after PM is assigned
PM needs to understand terms and conditions, identify risks, include procurement time
in schedule and involve in negotiations
Centralized contracting vs decentralized contracting
sole source, single source (preferred), oligopoly (very few sellers)
procurement categories: major complexity (high risk), minor complexity (low risk,
expensive), routine purchase (Commercial Off the Shelf Products COTS), goods and
services (to perform part of our product)
a contract is not required to be written, it can be verbal or handshake, for internal
projects, formal contract is best
procurement applies to actors (as a service)
immaterial breach is minor breach
point of total assumption (PTA) = Target Cost + (Ceiling Price - Target Price) / % Share
of Cost Overrun
contract change control system is defined in the procurement management plan but
not in the contract
Contract Types:
Firm Fixed Price (FFP) - the price is fixed, specifications are well known, risk on the
seller
Fixed Price Incentive Fee (FPIF) - incentives for faster/better than contracted
Fixed Price with Economic Adjustment / Economic Price Adjustment (FPEA / FP-EPA) -
inflation are taken into account
Purchase Order (PO) - for off-the-shelf goods/services with published rates
Cost Reimbursable (CR) / Cost Plus - buying the expertise (not the products), outcome
is not clear, risk on the buyer, little incentive to control costs on buyer, need invoice
audits
Cost Plus Fixed Fee (CPFF)
Cost Plus Incentive Fee (CPIF) - incentive for performance, sharing of unused money if
under/over contracted amount
Cost Plus Award Fee (CPAF) - award to be given based on agreed criteria, solely
decided by the customer on the degree of satisfaction
Cost Plus Percentage of Costs (CPPC) - illegal for contracts with US Government
Cost Contract - not profit, for NGO
Best Efforts - obligates the seller to utilize best attempts, high uncertainty in meeting the
goal
Time and Materials (T&M) - (hybrid type) when scope is not known, need constant
monitoring to control schedule and cost, simple, for short duration, good for proof-of-
concept type projects
Conduct Procurements
Agreement is legally binding and should include (PM should NOT attempt to write the
agreement): statement of work, schedule baseline, performance reporting, period of
performance, roles and responsibilities, warranty, payment terms, fees and retainers,
incentives, liability, penalties, etc.
Control Procurements
Close Procurements
all work are completed, deliverables accepted, claims settled OR terminated by either
party
at completion / termination of contract
prior to administrative closure of Close Project or Phase
unresolved claims may be left for litigation after closure
settlement of claims/invoices, audit, archive, lessons learned
the contract is complete when all the specifications are satisfied, no matter the customer
is satisfied with the product or not
Procurement Audit is the structured review of the procurement process from Plan
Procurement Management through Control Procurements, is used to capture lessons
learned from the procurement exercise
once a procurement is cancelled, the next process will be the close procurements
13. Project Stakeholder Management
stakeholders are groups/individuals who may affect / be affected by the project
identify stakeholders is a continually process throughout the project lifecycle
identify stakeholders, communicate and engage them, manage expectations and focus
on satisfaction
stakeholder satisfaction is a key project objective
the Project Manager is responsible for the engaging and managing the various
stakeholders in a project
Identify Stakeholders
Engagement Level
Unaware
Resistant: resistant to change
Neutral
Supportive: supportive of change
Leading: actively engaged for project success
Stakeholder Engagement Assessment Matrix documents the current level and
desired level of engagement of stakeholders
Respect
Fairness
Honesty
Name
Formula Interpretation
(Abbreviation)
No. of n should include
Communication
Channels
n (n-1)/2 the project
manager
5(5-1)/2 – 4(4-1)/2
=4
PV = Planned Value
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance
Index
(BAC – AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI =
Remaining
Work
/Remaining
Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
Estimate to
Completion
ETC = EAC -
AC
EAC = Estimate at Completion
AC = Actual Cost
PERT
Estimation
(O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
O= Optimistic estimate
P= Pessimistic estimate
Float/Slack = 0 On critical
LS – ES path
< 0 Behind
schedule
LS = Late start
ES = Early start
LF – EF
LF = Late finish
EF = Early finish
B. Last Minutes Revision Notes
1. The contract between the organization and the vendor supercedes all other work
related documents
2. Document analysis (collect requirements) vs Document review (identify risks)
3. Customers, internal or external, are the most important stakeholders in a project,
decisions are made in favor of the customers
4. Project managers manage things, but lead people.
5. Each resource in the project must be accounted for and assigned to a cost category.
Categories include the following: Labor costs, Material costs, Travel costs, Supplies,
Hardware costs, Software costs, Special categories (inflation, cost reserve, and so on)
6. Five different approaches to conflict resolution:
* Withdrawing/Avoiding - Retreating
* Smoothing/Accommodating - Emphasizing on agreements than disagreements
* Compromising
* Forcing – Pushing one’s viewpoint
* Collaborating – Incorporating multiple view points and driving consensus
* Confronting/Problem Solving – Head on with give-and-take policy and open dialogue
7. Confronting (Problem Solving) is the best problem-solving technique since it meets the
problem directly
8. Conflict should be addressed early and usually in private, using a direct, collaborative
approach
9. When a project is performed under contract, the contract can serve as the project
charter
10. Philip Crosby devised the zero defects theory, meaning do it right the first time. Proper
Quality Planning leads to less rework and higher productivity
11. Joseph M. Juran is noted for his fitness for use premise. Simply put, this means the
stakeholders’ and customers’ expectations are met or exceeded.
12. W. Edwards Deming suggested that as much as 85 percent of the cost of quality is a
management problem
13. Shewhart = Plan-Do-Check-Act cycle.
14. Organization, Environmental & external assumptions should be addressed by the
Project Charter
15. Project Manager must consider “cultural differences” while deciding upon
recongnization and rewards during team development.
16. Technical inability and poor risk management by the contractor is mostly the reason for
the project not to meet the customer expectations
17. Cost Of Quality (COQ) are the cost types in modern quality management: “Prevention
Costs”, “appraisal costs” & “failure costs”, Internal failure costs – Failures found by the
project team, External failure costs – Failures found by the customer (including
warranty)
18. Face-to-face meetings are the most effective means for communicating and resolving
issues with stakeholders.
19. Detailed Tasks are detailed in “Project Schedule”, which is part of Project Plan and note
its NOT WBS. WBS is a “deliverable oriented document”
20. A ‘Planning Package” is a WBS component below the control account but above the
work package. It is used for planning unknown work content that does not have detailed
schedule activities
21. Control account Plan (CAP) is a management control point where the integration of
scope, budget and schedule take place and where the measurement of performance
takes place. These CAPS are placed at the selected management points in the WBS.
22. In decision tree, a circle is a chance, a square is a decision
23. Reporting formats: - Forecast Report (what is expected to happen on a project),-
Progress Report (what happened since the last report),- Status Report (state of the
project at the current time),- Earned Value Report (focuses on Earned Value
Management),- Variance Report (what happened vs. what should have happened).
24. The Project Manager ultimately has the responsibility for the Product of the Project and
Senior Management is responsible for the Quality of entire Organization
25. Product analysis includes techniques such as value engineering, value analysis,
systems analysis, systems engineering, product breakdown, and functional analysis
26. The introduction of a new team member will start the formation and development of the
team all over again with the forming stage
27. Fait accompli is a tactic used during contract negotiations where one party convinces
the other that the particular issue is no longer relevant or cannot be changed
28. Understand for the exam that configuration management involves - identifying the
physical characteristics of the product, service, or result of the project (or its individual
components); - controlling changes to those characteristics; and - Documenting
changes to verify that requirements are met.
29. Control process - Configuration identification, - Configuration status accounting and -
Configuration verification and auditing
30. Integrated Change Control, Schedule Control, and Cost Control are all concerned with
three issues: - influencing the things that cause change, - determining that change is
needed or has happened, - and managing the change
31. Change control systems are documented procedures that describe - How to submit
change requests. - They track the status of the change requests, - document the
management impacts of change, - track the change approval status, and - define the
level of authority needed to approve changes.
32. Workarounds are unplanned responses. Workarounds deal with negative risk events as
they occur.
33. Close Project - Collecting project documents, - Disseminating final acceptance notice, -
Documenting lessons learned, - Archiving project records, - Release resources, -
Formal closure
34. Hammocks are summary-level activities or aggregate activities shown as a summary
activity on a project schedule network diagram.
35. “Quality Function Deployment Process” identifies what the customer’s needs are
(Spoken/unspoken words) and translates those needs into technical requirements.
Appropriate for each stage of the product development life cycle
36. When distributing information, the total message impact from the sender is 7% words,
38% vocal tones and 55% body language
37. Decision Trees are considered Quantitative while Influence diagram are considered
Qualitative.
38. Influence diagram shows the dependencies among the variables more clearly than the
decision tree
39. A “Bill of Material” (BOM) describes the product in terms of its assemblies, sub-
assemblies and basic parts
40. Project manager must possess following interpersonal skills
1. Leadership
2. Team building
3. Motivation
4. Communication
5. Influencing
6. Decision making
7. Political and cultural awareness and
8. Negotiation
Ten most important skills and competencies for Project Managers
1. People skills
2. Leadership
3. Listening
4. Integrity, ethical behavior, consistent
5. Strong at building trust
6. Verbal communication
7. Strong at building teams
8. Conflict resolution, conflict management
9. Critical thinking, problem solving
10. Understands, balances priorities
41. Workarounds are unplanned responses. Workarounds deal with negative risk events
as they occur. As the name implies, workarounds were not previously known to the
project team. The risk event was unplanned, so no contingency plan existed to deal with
the risk event.
42. Risk Response
Threats
- Avoid – remove the cause of the risk so that it never materializes
- Mitigate – reduce the probability and or impact of the risk
- Transfer – transfer the risk to another party; usually done with insurance and
warranties, etc.
Opportunities
- Exploit – make sure the opportunity occurs, you can add work or make a change to
the project
- Enhance – increase the probability and or positive impact of the risk
- Share – share the opportunity with a third party to be able to take advantage of the
opportunity