Project Closure Report
Project Closure Report
System Name
Release: Status
Date: DD MMM YYY
Authors: XXXXX
System Name
Project Closure Report Date: 17 October 2019
1 Report History
1.1 Document Location
This document is only valid on the day it was printed.
The source of the document will be found at XX
1.3 Approvals
This document requires the following approvals:
1.4 Distribution
This document has additionally been distributed to:
Document1 Page 2 of 12
System Name
Project Closure Report Date: 17 October 2019
Document1 Page 3 of 12
System Name
Project Closure Report Date: 17 October 2019
5.2 Issue Management ________________________________________________________ 9
5.3 Risk Management _________________________________________________________ 9
5.4 Communication Management _______________________________________________ 9
5.5 Lessons Learned __________________________________________________________ 9
5.5.1 What Went Well ______________________________________________________ 9
5.5.2 What Did Not Go Well__________________________________________________ 9
5.6 Post Project Tasks ________________________________________________________ 10
5.7 Project Closure Recommendations___________________________________________ 10
5.8 Post Implementation Reviews ______________________________________________ 10
6 Project Closure Report Approvals ________________________________________________ 10
Appendix A : Closure Check List _____________________________________________________ 12
Document1 Page 4 of 12
System Name
Project Closure Report Date: 17 October 2019
Project Start
4 Project Performance
4.1 Project Achievements
The primary objectives in the PID were to:
PID objective 1.
PID objective 2.
The project has achieved some/all of these objectives.
The project has also delivered:
Objective 1.
Objective 2.
Document1 Page 6 of 12
System Name
Project Closure Report Date: 17 October 2019
Measurement/
Observation
Method
Baseline
measurement
(pre project)
To be
measured by
(who?)
Frequency
Proposed date
of next
measurement/
observation
To be reported
to
Notes:
1. The project is over/under budget for the following reasons:
Reason 1.
Reason 2.
Document1 Page 7 of 12
System Name
Project Closure Report Date: 17 October 2019
4.7.1 Project Assurance
A project assurance role was implemented as a function within the Project Board to
independently assure the quality of the project process and deliverables.
If not elsewhere specified please provide a summary of how Privacy and Information Security
implications of the project were considered and what (if any) necessary actions were subsequently
taken to address these considerations
Document1 Page 8 of 12
System Name
Project Closure Report Date: 17 October 2019
If not elsewhere specified please provide a summary of how Sustainability implications of the project
were considered and what (if any) necessary actions were subsequently taken to address these
considerations
Open risk 1.
Open risk 2.
Document1 Page 9 of 12
System Name
Project Closure Report Date: 17 October 2019
Lesson Lesson Suggested future action Project Impact
No Description (High, Medium,
Low)
There will be a post implementation review on DD MMM YYY OR post implementation review(s)
have taken place on DD MMM YYYY.
Approval Date
Document1 Page 10 of 12
System Name
Project Closure Report Date: 17 October 2019
Prepared By (Project Manager)
Document1 Page 11 of 12
System Name
Project Closure Report Date: 17 October 2019
Document1 Page 12 of 12