Gantt Chart

The document outlines a project schedule to upgrade a workshop from November 12th to December 24th. It involves 15 tasks including pre-inspection, ordering parts, installation, testing, and a final project review. The tasks are broken down and scheduled day-by-day over the 6 week period with dependencies shown between each sequential task.

Uploaded by

Prince
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views2 pages

Gantt Chart

The document outlines a project schedule to upgrade a workshop from November 12th to December 24th. It involves 15 tasks including pre-inspection, ordering parts, installation, testing, and a final project review. The tasks are broken down and scheduled day-by-day over the 6 week period with dependencies shown between each sequential task.

Uploaded by

Prince
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Task Name Duration Start November Finish Predecessors

Mode T W T F S S
1 Pre inspection of current workshop layout 1 day Tue 12/4/18 Tue 12/4/18
2 Purchasing and order processing 2 days Wed 12/5/18 Thu 12/6/18 1
3 Order follow up 3 days Fri 12/7/18 Tue 12/11/18 2
4 Shipment receiving 1 day Wed 12/12/18 Wed 12/12/18 3
5 Installation of parts 1 day Thu 12/13/18 Thu 12/13/18 4
6 Trial cut 1 day Fri 12/14/18 Fri 12/14/18 5
7 Setting up DNC 1 day Mon 12/17/18 Mon 12/17/18 6
8 Software Installation 1 day Tue 12/18/18 Tue 12/18/18 7
9 Issuing Proposal 1 day Wed 12/5/18 Wed 12/5/18 1
10 Accepting and Finalizing Proposal 1 day Thu 12/6/18 Thu 12/6/18 9
11 Finalizing contractor 1 day Fri 12/7/18 Fri 12/7/18 10
12 Final quality inspection 1 day Wed 12/19/18 Wed 12/19/18 11,8
13 Testing and performance review 1 day Thu 12/20/18 Thu 12/20/18 12
14 Final testing and Initiation of production 1 day Fri 12/21/18 Fri 12/21/18 13
15 Project Success Meet 1 day Mon 12/24/18 Mon 12/24/18 14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: gantt chart
Summary Manual Summary Rollup Progress
Date: Wed 11/14/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
December
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: gantt chart
Summary Manual Summary Rollup Progress
Date: Wed 11/14/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2