Republic of the Philippines
DEPARTMENT OF ENERGY
(Kagawaran ng Enerhiya)
Department Order No. D02017-04- 0005 |
PRESCRIBING THE NEW GUIDELINES IN THE
PROCESSING OF APPLICATIONS FOR RENEWABLE ENERGY SERVICE /OPERATING.
CONTRACTS
WHEREAS, Republic Act {R.A.) No. 7638, a5 amended, otherwise known as the
“Department of Energy Act of 1992,” mandates the Department of Energy (DOE) to
prepare, integrate, coordinate, supervise and control all plans, programs, projects
and activities of the Government relative to energy exploration, development,
utilization, distribution and conservation, among others;
WHEREAS, R.A. No, 9513, otherwise known as the “Renewable Energy Act of 2008
(RE Act),” declares as a policy of the State to encourage and accelerate the
exploration, development and increase the utilization of Renewable Energy (RE)
resources such as, but not limited to, biomass, solar, wind, hydropower, geothermal,
and ocean energy resources, and including hybrid systems;
WHEREAS, Department Circular No. DC2009-05-0008 which prescribes the
Implementing Rules and Regulations (IRR) of RE Act, also mandates the DOF to
develop the necessary regulatory framework for the RE industry, among others;
WHEREAS, Department Circular No. DC2009-07-0011 created a Review Committee
to evaluate the RE Proposals and Applications of RE Applicants and provide
recommendations to the DOE Secretary for the award of RE Service/Operating
Contracts (RE Contracts);
WHEREAS, Department Order Nos. DO2026-09-0013. and 002016-06-0010
reconstituted the membership of the RE-Review and Evaluation Committee (RE-REC)
and providing for its functions, duties and responsibilities, as well as revised the
existing guidelines for the processing of applications, amendments and terminations
of RE service/operating contracts;
WHEREAS, it is the thrust of the government to further enhance the transparency
and shorten the time frame in the processing and issuance of service contracts and
permit;
NOW, THEREFORE, premises considered, the DOE hereby issues the following
guidelines in the processing of RE Applications for RE Contracts.
Page 1 of 8
seiay Center, Rizal Dive cor 3th Sweet, Bonifacio Global Gy, Taguig City, Philippines 1632
Eneray Cs Tel. No. (Trunkline) (632) 479-2900;
Website: hapa doe gou-Dis Ema fades ay. oh
CoSection 1.
(a)
(a)
ing of Letter of interests ("LOI").
All applicants for the processing and issuance of RE Contracts shall initiate its
RE Application with the filing of an LOI addressed to the RE-REC, through the
Records Division.
Within one (1) working day from receipt of the LOI, the RE-REC shall issue an
acknowledgment letter addressed to the RE Applicant. The said
acknowledgment letter shall also direct the RE Applicant to secure an Area
Clearance from the Information Technology Management Services (ITMS) of
the DOE
{n the same acknowledgment letter, the RE-REC shall inform the RE Applicant
of the schedule of an orientation/briefing on the RE Application requirements
and processes. During the orientation/briefing far the RE Applicant, the
request for area clearance stamped received by the ITMS shall be presented
by the RE Applicant.
Thereafter, the RE Applicant may file his RE Application with the DOE, subject
to the result of the Area Clearance under Section 2 hereof.
Section 2, Area Clearance. The RE Applicant shall file a request for an Area
Clearance from the ITMS within one (1) working day from receipt of the
acknowledgment letter from the RE-REC. The request shall include the exact area of
interest/location as shown by the RE Applicant’s submission of the PRS ‘92
Beographic coordinates, which shall conform to the RE Blocking System, except for
biomass and hydropower which shall provide the exact coordinates of the power
plant, weir and powerhouse, respectively.
‘The ITMS shall complete its evaluation and provide the RE-REC the evaluation result
within a period of three (3) working days from receipt of the request.
a)
»)
\f the proposed area is already covered by an existing RE Contract for the
development of the same RE technology/resource being applied for, the
ITMS shall certify that the proposed area is not open for RE Application
If the proposed area is not open for RE Application and/or if it is covered by
service contract of other energy/RE technologies, or if it is within a protected
area, the ITMS shall inform the RE-REC of such findings and stating the
verification results and other necessary information
In case the proposed area is with a pending RE Application far the same RE
technology/resource, the ITMS shall recommend that the RE Application shall
be placed in @ queue.
Page 2 of &a)
e)
For Solar Energy Service Contract (SESC) application covering rooftop areas
located within an existing SESC, the exact coordinates for the proposed Solar
PV rooftop installation may be carved out in case of the following conditions
2. The existing SESC is already under construction stage or already in
commercial operation and the proposed area of the RE Application does
not cover overlap with development area of the existing SESC; or
2. The RE Developer of the existing SESC has complied with its Milestone
obligations and in its submitted Feasibility Study ("FS”) and the
approved Work Program, there is no showing that it will include in its
development the praposed rooftop areas.
In case of overlap with existing service/operating energy contract other than
that with the same RE technology/resource being applied for, the RE
Applicant may pursue his RE Application by submitting a notarized
acknowledgment and undertaking on the followin
1. The recognition of the existence of the prior right of the existing
contract holder;
2. The RE Applicant shall secure the clearance and/or no opposition
from the existing contract holder.
In cases under Section 2 (a) and {b) hereof, the RE-REC shall formally notify the RE
Applicant. in case the result of the Area Clearance evaluation is covered by Section 2
(0), (d) and (e) hereof, the result shall be presented to the RE Applicant during the
orientation/briefing
Section 3. Receii
‘of RE Application. In case the RE Applicant complies with the
procedures and requirements under Section 1 hereof, it may now submit its RE
Application as follows:
fa}
(b)
The RE Applicant shall prepare and submit five (5) copies of its RE
Application. One (1) copy shall be submitted to the DOE Records Division for
filing and reference. The other four (4) copies shall be stamped-received by
the DOE Records Division.
The RE Applicant shall then proceed to the RE-REC Secretariat for the
issuance of an Order of Payment for its RE Application. The RE-REC
Secretariat shall ensure that prior to the issuance of an Order of Payment, the
RE Applicant shall show the four (4) copies of its RE Applications as stamped-
received by the DOE Records Division.
Page 3 of(o)
After payment of the application fee, the RE Applicant shall then submit the
four (4) copies to the RE-REC Secretariat. The RE-REC Secretariat shail keep
one (1) copy of the RE Application for filing and reference.
‘At this stage, the RE Application is deemed filed and submitted so as to
determine the order of formal filing by the RE Applicant.
Section 4. RE Contract Evaluation Process Flow. The RE-REC Secretariat shall, within
‘one (1) working day from receipt thereof, distribute the three (3) copies of the RE
‘Application to the following units: (1) Legal Services for legal evaluation, (2) REMB
Division for technical evaluation and {3) Financial Services for financial evaluation
Thereafter, all RE-REC Technical Working Group member units shall evaluate the RE
Application at the same time.
@
(b)
)
(d)
The LS shall complete its review and evaluation within five (5) working days
from date of receipt of the RE Application.
In case the RE Applicant is not legally qualified, the Legal Services shall inform
the RE-REC Secretariat within the evaluation period. Otherwise, the RE
Application shall be endorsed to the RE-REC Secretariat for further
processing.
The appropriate division of the Renewable Energy Management Bureau
(REMB) shall complete its technical evaluation within five (5) working days
fcom receipt of the RE Application
In case the RE Applicant is not technically qualified, the REMB Division shall
inform the RE-REC Secretariat within the evaluation period. Otherwise, the
RE Application shall be endorsed to the RE-REC Secretariat for further
processing.
The Financial Services (FS) shall complete its financial evaluation within five
(5) working days from receipt of the RE Application.
\n case the RE Applicant is not financially qualified, the Financial Services shall
inform the RE-REC Secretariat within the evaluation period, Otherwise, the
RE Application shall be endorsed to the RE-REC Secretariat for further
processing.
\¥ the RE Application passed the legal, technical and financial evaluations, the
RE-REC Secretariat shall prepare, within three (3) watking days from receipt
of all the evaluations, an RE-REC Resolution to recommend approval of an RE
Contract by the Secretary.
Page 4 of 8{e)
(
(e)
In case the RE Application is not either \egally, technically or financially
qualified, or not qualified all together, the RE-REC Secretariat shall, within
three (3) working days from receipt of all the evaluations, require the RE
Applicant in writing to submit additional or lacking documents in order for it
to qualify within a period of five (5) working days from receipt of such notice.
Copy of the Memoranda of the legal, technical and financial evaluations shall
be attached.
Failure of the RE Applicant to complete the documentary requirements
within the prescribed period shall mean withdrawal of the RE Application
Thereafter, a notice shall be issued to the RE Applicant by the RE-REC that the
RE Application is deemed withdrawn.
In case the RE Applicant submits additional or lacking documents for it to
qualify with the prescribed period under Section 4 (d) hereof, the RE-REC
shall convene and evaluate the submitted documents. In this regard, the RE-
REC shall then decide whether to qualify or disqualify the RE Application.
In case the RE Applicant is disqualified, the RE-REC shall issue @ formal notice
to the RE Applicant stating the basis of the disqualification and immediately
proceed to the next-in-line RE Application. Otherwise, the RE-REC shalt
recomment the award of an RE Service/Operating Contract.
Section 5. The RE Contract Review and Evaluation Committee, Technical Working
Group and Secretariat. The RE-REC, RE-REC Technical Working Group and RE-REC
Secretariat are hereby constituted as follows
RE-REC
Chairperson Chief of Staff (COs)
Vice-Chairperson : Director, REMB
Members Director, Legal Services (FS)
Director, Financial Services (LS)
Director, ITMS
RE-REC Technical Working Group (TWG)
Chairperson Director Ill, Office of the Secret:
Vice-Chairperson Assistant Director, REMB
Members Chief, concerned REMB Division
Chief, Renewable Energy Legal Service Division- LS
Chief, Renewable Energy Resources Compliance
Division-FS
Chief, information Services Division of ITMS
Page 5 of 8The RE-REC TWG shall be assisted and supported by the Technical Service
Management Division-REMB, acting as Secretariat.
‘The RE-REC, RE-REC TWG and the RE-REC Secretariat shall continue, insofar as they
are consistent with this 00, to discharge the functions, duties and responsibilities
under Department Circular No. DC2009-07-0011, and Department Order Nos.
1D02013-22-0020, DO2014-06-0010 and DO2014-10-0018.
(a)
The RE-REC shall convene at least once a month or in the event an Important
matter arises in the evaluation proceedings that need RE-REC deliberation
and resolution of a particular RE Application.
The simple majority of the RE-REC Members shall constitute a quorum. In
the absence of the Chairperson, the Vice Chairperson shall preside the
meeting,
Section 6. Approval and Signing of the RE Contract.
(a)
()
(d)
(e)
Any RE Application that passed the legal, technical and financial evaluation
under Section 4 (d) and (e) hereof shall be recommended for the award of an
RE service/operating contract.
‘The RE-REC shall issue a Resolution that shall contain the highlights of the
evaluation and a recommendation to the DOE Secretary, through the
Assistant Secretary and Undersecretary, to award the RE Contract, within
three (3) working days from the date of the RE-REC deliberation. The RE-REC
Resolution shall be signed by ali RE-REC Members.
‘The RE-REC Secretariat shall prepare the RE Resolution, including the legal,
technical and financial evaluations, the Certificate of Registration (COR) and
endorsement letters, and coordinate the pre-signing by the RE Applicant
within the same three (3)- working day period.
The RE-REC Resolution, all attachments and the re-signed RE
service/operating contract shall be submitted to the DOE Secretary who shall
act on it within seven (7) working days from receipt.
The RE Contract that will be issued to the RE Applicant shail follow the RE
Contract templates hereto attached as Annexes “A” to “F”,
The notarized copy of the RE Contract and the COR shall be furnished to the
RE Applicant upon submission by the latter of a copy of the official receipt
(“OR”) as proof of payment of the corresponding Signature Bonus.
Page 6 of 8Section 7. Posting and Updating of RE Contract Awarded and Pending Application
in the DOE Website.
(a) The RE-REC Secretariat shall update the RE Contract Awarded and Pending
Application once a month and every time a new RE Application commenced
with the evaluation of was disqualified or was awarded.
(b) The RE-REC Secretariat shall secure the approval of the RE-REC on the new
updates before forwarding the same to ITMS for posting and database
update. Thereafter, all applications in queue as provided under Section 2.
shall be deleted by ITMS and the RE applicant shall be informed by TSMD that
its application is hereby disqualified.
(c)_ The RE-REC Secretariat shall also provide copies for posting in the Energy
Virtual One Shared System (EVOSS) website.
Section 8. Amendment and Termination of RE Service/Operating Contracts.
(a) The concerned REMB Division shall evaluate and recommend amendments of
RE Service/Operating Contracts as prescribed under Department Order No.
102014-10-0018, including other amendments to the RE-REC for approval.
In case the evaluation of the concerned REM Division shows that there are
additional costs to be incurred that should warrant another financial
evaluation, the said Division shall endorse to FS for subsequent financial
evaluation
(b) Based on REMB’s monitoring, the concerned REMB Division shall evaluate
and recommend the termination of RE Service/Operating Contracts to the RE-
REC for approval.
(c)__ In both cases as provided in Sections 8 (a) and 8(b) hereof, the concerned
REMB Division shall provide the RE-REC the complete basis of the
recommendation prior to RE-REC deliberation.
{¢) The RE-REC shall issue a Resolution that shall contain the highlights of the
evaluation and a recommendation to the DOE Secretary for approval. The
RE-REC Resolution shall be signed by all RE-REC Members.
(e) The RE-REC shall immediately provide to ITMS any RE Contract status for
timely update of database.
Page 7 of 8Section 9. Repealing Clause. Department Order Nos, 002016-02-0001, DO2016-06-
0010, DO2016-09-0011, D02013-08-0011 and all other Department Circulars, Orders
and issuances which are inconsistent with any of the provisions of this Department
Order are hereby amended or repealed accordingly.
Section 10. Separability Clause. Should any provision of this Department Order be
declared invalid or unconstitutional, the other provisions, so far as they are
separable, shall remain in force.
Section 11. Effectivity. This Department Order shall take effect immediately.
/
0; i Ww
DOE-AGC. a8
NEN GA
APRO? 2017
Page 8 af &FLOWCHART UNDER THE DEPARTMENT ORDER NO. D02017-.04.- 0005 OR GUIDELINES IN THE
PROCESSING OF APPLICATIONS FOR RENEWABLE ENERGY SERVICE/OPERATING CONTRACTS
RE Applicant Sec. 1. Filing of Letter of interest (LO!)
tt ote
DOE-Records receives from the applicant the 1. Allopplicants shal intote its applications withthe fing
of ano.
LOM addressed to RE-REC. 2 Acknowledgment letter shall also direct the RE Applicant
TL [7 toseeure an Areo Clearance from the DOE-TMS within 1
~~ iay upon receipt ofthe letter and inform of the Schedule
RE-REC issues acknowledgment letter” within | of orentorion/briefing on the requirements and
processes. a stamped receipt of the area clearance shall
1 working day from receipt of the LOI. | be presented during orientation/briefing.
| DOE-ITMS receives the request forarea___| Sec. 2. Area Clearance
verification from the applicant and provides eee (00) & (e) resus shot ae
the evaluation result’ to the RE-REC within 3 cpplican during vention friefings
working days from receipt of the request. (c) For proposed erea with «pending RE
| application forthe sme technology.
tS + TMS recommends oppcation fhe paced in
oqueve
| (0) ForSeSC Rooftop Application within exsting
‘ESC the exact coordinates ofthe former
{s the proposed are}
‘may be cared aut incase the following
RE-REC formally | 6 cyisting SESC i under construction ort
open for RE application notifies applicant commercial operation ond des not cover te
or not within the —\, based on the proposed rooftop area.
contract of other NO) issued ITMs’ ' sting SESC is complione with Milestone
| ebigatin and doesnot include the proposeo
energy / RE technology certification and | | rooftop oreainits 5 and we.
or protected area?
Jor information (e) For RES/OC Application ovrapping with
of such findings. | | evsting RES/OC of other RE technologie, the
= Jormer may pursue by submitting a notarized
| cknewiedgment and undertoking of the folowing
+ The recognition ofthe enstenceof the prior
right ofexsting contract holder.
The coplicant shal secure clearance from the
exsting contract holder.
DOE-Records receives 1 copy of RE
application for filing and reference and
stamped-receipt 4 copies for RE-REC
Secretariat. |
Upon receipt of proof of the 4 stamped |
copies of application from the RE Applicant, Sec. 3. Receipt of RE Application
RE-REC Secretariat issues order of payment Lote:
(application fee) | « atthis stage, the RE opplicotion is deemed filed and
| After payment of application fee, RE-REC
Secretariat receives the 4 copies of
application and keeps 1 copy for filing and
reference’
ABtwo
swo
the 3 copies of RE Application to the following for simultaneous
evaluation:
LS completes review | | REMB concerned FS completes
and legal evaluation division completes financial evaluation
within 5 days from technical evaluation | | within S days from
receipt and endorses | | within 5 days from receipt and endorses
the same to RE-REC receipt and endorses | | the same to RE-REC
Secretariat the same to RE-REC Secretariat
Secretariat
Is the RE application
legally/technically/financially
qualified?
Within 3 days upon receipt, RE-REC Secretariat prepares RE-
REC resolution recommending approval of an RE contract by
the DOE Secretary
RE-REC convenes and evaluates
submitted documents.
Is the RE
application
qualified?
the basis of disqualification and immediately
proceeds to the next in line application.
RE-REC issues formal notice to the applicant stating
Within 3 working days
from receipt of
evaluation result, RE-REC
Secretariat requires
applicant in writing to
submit additional/iacking
documents within 5
working days from
receipt of such notice
Are the lackiny
documents
completed on
EC issues notice
‘to the applicant that
the application is
deemed withdrawn
Sec. 4,
RE Contract
Evaluation Flow5
tt |
RE-REC issues Resolution’ to award the RESC Sec. 6. Approval and
3wo within 3 working days from date of RE-REC signing of RE Contract,
deliberation. RE-REC Secretariat shall prepare | move
the RE Resolution, including the legal, technical 5. This shoil contoin the highlights ofthe
| evaluation ond o recommendation to
and financial evaluations, the COR and
the Secretary through Asec and Use.
endorsement letters, and coordinate the pre- The same shall be signed by a RE-REC
signing by the Applicant within the same 3-day Members.
period 6 Contract remplotes attached as
Annexes “A” to°F
Upon receipt of resolution, al attachments and
7wo re-signed RE service/operating contract®, OO:
Secretary sallact onit within 7 days.
RE-REC Secretariat furnishes the applicant of the |
notarized RE-Contract and COR upon receipt of |
the OR (signature bonus).
Note:
* PROCESSING PERIOD ~ NOT MORE THAN 25 WORKING DAYS. (19 Working Doys is doable as shown
above).