FACULTY OF CIVIL ENGINEERING
UNIVERSITI TEKNOLOGI MARA
UiTM CAWANGAN PAHANG
PROJECT : SCHEME OF WORKS (FINAL EXAMINATION JUNE 2016 : QUESTION 2)
ELEMENT/ TASK : REINFORCEMENT AND STIRRUPS (BEAM 3)
BEAM 3 (250 X 450) Total:
2/(0.200+0.400) 1.200
4T12 (Top & Bottom)
Add (+) 2 anchorage
Length 3.000 2/12/0.008 0.192
Less (-) 2 cover Total Length
2/0.025 0.050 of stirrups 1.392
Add (+) 2 Bend
1/ 2/5.5/0.012 0.132 Nos. of Stirrups
4/ Total Length 3.082
3.082 Length 3.000
12.328 12.328 m Less (-) 2 cover
2/0.025 0.050
STIRRUPS (R8-200) Total Length 2.950
(Span 3000mm)
Length of Stirrups: 1/ 2.950 + 1 = 15.75 = 16
16/ 0.200
250 1.392
22.272 22.272 m
450
Length -1 0.250
Less (-) 2 cover 0.050
Total Length -1 0.200
Length -2 0.450
Less (-) 2 cover 0.050
Total Length -2 0.400