Saudi Oger Ltd. (Project Name) : Plastering

This document is an inspection and test plan for plastering work on a construction project. It outlines 8 activities to be inspected, including checking materials, surface preparation, installation of embedded items, application of plaster coats, curing times, and ensuring smooth plaster finishes. The acceptance criteria and documentation for each inspection point are defined, such as specifications, standards, or test records. Responsibilities for inspections are assigned to the contractor's engineer, QA/QC engineer, and client engineer.

Uploaded by

Anthony Angeles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
328 views1 page

Saudi Oger Ltd. (Project Name) : Plastering

This document is an inspection and test plan for plastering work on a construction project. It outlines 8 activities to be inspected, including checking materials, surface preparation, installation of embedded items, application of plaster coats, curing times, and ensuring smooth plaster finishes. The acceptance criteria and documentation for each inspection point are defined, such as specifications, standards, or test records. Responsibilities for inspections are assigned to the contractor's engineer, QA/QC engineer, and client engineer.

Uploaded by

Anthony Angeles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SAUDI OGER LTD.

(Project Name)
INSPECTION & TEST PLAN PLASTERING ITP-C-32 Rev. 00
Project No.: Project Title:
Contractor: Contract No: CIVIL
Item No.

Contractor Contractor
Applicable Code or Test Record or (Client) Engr /
Activity Inspection and Test Point Acceptance Criteria Site QA/QC
Standard Document Inspector
Engineer Engrineer

1.0 MATERIAL 1.1 Aggregate: Natural sand of the required gradation. Project specification As per spec. Laboratory records
Visual R R R

1.2 Cement: Portland cement type I. Project specification As per spec. Mill certificate
I/R I/R I/R

2.0 EXECUTION 2.1 Check surface preparation, masonry, concrete. Project specification As per spec. and Code Visual
QR-C-32 I W W

2.2 Check embeded items within wall have been already Project specification As per specification and QR-C-32
installed. approved drawings. I W S

2.3 Electro-Mechanical services have been tested and Project specification As per specification and Electromechanical
approved. approved drawings. RFI's, QR-C-32 I W S

2.4 Check required plaster mix for exterior wall, interior Project specification As per spec. QR-C-32
wall and ceiling. ASTM C-926 I W S

2.5 Application of dash coat, scratch coat, brown coat Project specification As per spec. QR-C-32
and finish coat as per mix design and required ASTM C-926 I S S
thickness.
2.6 Finish coat shall be cured for a minimum of 48 hours. Project specification As per spec. QR-C-32
I S S

2.7 Plaster shall extend 100mm beyond finished ceiling Project specification As per spec. QR-C-32
level for rooms with suspended ceiling. I S S

2.8 Check plaster variation to true finish. Project specification Maximum variation is 3mm QR-C-32
in 3m. I S S

I=Inspect or Perform Work; W=Witness Point; R=Review/ approve Records or Documentation; S=Surveilance or Monitor; H=Hold Point Page 1 of 1