Given the following table:
PERT
Task ImmediatePredecessors Optimistic Most Likely Pessimistic
(Expected time)
A None 5 7 12 (5+4*7+12)/6=7.5
B None 8 8 8 (8+4*8+8)/6=8
C A 2 6 10 (2+4*6+10)/6=6
D A,B 12 14 19 (12+4*14+19)/6=14.5
E C,D 6 6 12 (6+4*6+12)/6=7
F B,E 3 12 18 (3+4*12+18)/6=11.5
G F 6 8 10 (6+4*8+10)/6=8
Question 2:
Consider the following table which is Network Diagram Data for a
project. All durations are in Days; and the network proceeds from Node
1 to Node 9.
a. Draw an AOA network Diagram representing the project. Put the node
numbers in circles and draw arrows from node to node, labeling each
arrow with the activity letter and estimated time.
b. Identify of all paths on the network diagram and note how long they
are.
Kingdom of Saudi Arabia
المملكة العربية السعودية
Ministry of Higher Education
وزارة التعليم العالي
Princess Noura bint Abdulrahman University جامعة االميرة نورة بنت عبد الرحمن
College of Computer & Information Sciences كلية علوم الحاسب والمعلومات
c. What is the critical path for this project and how long is it.
Critical path is the longest path through the network diagram,
path3: A,D,G,J,K, length is 20 days that is critical path .