c4-20 Driven Piling
c4-20 Driven Piling
1
Version 1.0
NPQS
C4-20 Driven Piling
CONTENTS
Page
1. GENERAL 3
1.1 Scope 3
1.2 Related Sections 3
1.3 Standard and Regulations 3
1.4 Trade Preambles 4
1.5 Definitions 7
2. PERFORMANCE REQUIREMENTS 8
2.1 Requirements for Design Verification 8
2.2 Performance Criteria for Piles Under Test 8
2.3 Driving Requirement 9
2.4 Permissible Damage Criteria for Existing Critical Structures or Services 9
2.5 Noise Nuisance 10
3. MATERIALS 11
3.1 Pile Sections and Pile Dimensions 11
3.2 Precast Reinforced Concrete Piles Including Spun Piles 11
3.3 Steel Piles 12
3.4 Treated Timber Piles 13
3.5 Proprietary Micropiles 15
3.6 Pile Shoes and Toes 15
4. WORKMANSHIP 16
4.1 Fabrication of Piles: Concrete Piles 16
4.2 Fabrication of Piles: Steel Piles 16
4.3 Handling and Pitching of Driven Piles 17
4.4 Installation and Driving 18
4.5 Welding 20
4.6 Damaged Piles 21
4.7 Tolerances 21
4.8 Pile Heads 21
4.9 Non-Performance of Working Piles 22
4.10 Noise and Disturbance 22
2
Version 1.0
NPQS
C4-20 Driven Piling
1. GENERAL
Read with the General Requirements section, and all other contract documents.
1.1 Scope
This section covers the requirements for the construction of driven piles, including the
use of the following pile types:
a. Precast Concrete piles including Spun Piles
b. Steel Piles
c. Treated Timber Piles
d. Composite Micro-piles
This document specifies project specific data to be read in conjunction with section
C4-20 of NPQS. All modification and additions noted in this documents take
precedence over clauses noted in NPQS.
1.3.1 Standards
Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant
requirements of the Standards and Codes listed below or referenced in the body of
the Specification. Alternative Standards and Codes may be proposed for approval by
the SO, provided it can be demonstrated that the alternative Standards and Codes
comply with the requirements of the standards specified. All Standards and Codes
quoted are the current version, unless specific year references are noted.
Singapore Standards
SS 72 Treatment of timber and plywood with copper/chrome/arsenic
wood preservatives
SS 187 Qualification test for manual metal-arc welders
3
Version 1.0
NPQS
C4-20 Driven Piling
4
Version 1.0
NPQS
C4-20 Driven Piling
5
Version 1.0
NPQS
C4-20 Driven Piling
1.4.11 Obstructions
If any obstructions such as existing fences, structures, footings, boulders, concrete
blocks, pipes, drains, driveways or ramp are encountered during excavation, submit
proposals for their removal for the SO's acceptance.
6
Version 1.0
NPQS
C4-20 Driven Piling
1.4.15 Safety
Provide safety precautions to comply with all current legislation and regulations,
notably:
a. Building Control Regulations
b. Code of Practice for Traffic Control at Work Zone
c. Factories (Building Operations and Works of Engineering Construction)
Regulations
d. Factories Act
e. SS CP 79 Safety management system for construction worksites
f. For works within LTA Railway Protection Zone, ensure the works comply fully with
Code of Practice for Railway Protection.
Additionally, comply also with the following:
a. BRE Digest 251 (1995) Assessment of damage in low rise building
b. BS 8008: Guide to safety precautions and procedures for the construction and
descent of machine-bored shaft for piling and other purposes
1.5 Definitions
a. Pile The term ‘coating’ includes the primer and the number of other
Coating coats specified.
7
Version 1.0
NPQS
C4-20 Driven Piling
2. PERFORMANCE REQUIREMENTS
8
Version 1.0
NPQS
C4-20 Driven Piling
9
Version 1.0
NPQS
C4-20 Driven Piling
2001). Notwithstanding the above, ensure that the ground movements and vibrations
generated by the works comply with the following if more stringent:
a. Generally comply with the requirements of BS 5228 Part 1.
b. The vibration generated by the works in MRT structures not to exceed a peak
particle velocity of 15mm/s.
c. Unless otherwise directed, refer to Section C2-50, Clause 4.2.2 for general
restrictions on ground movements and vibration limits for adjacent structures
where relevant.
10
Version 1.0
NPQS
C4-20 Driven Piling
3. MATERIALS
3.2.1 Concrete
Refer to Section C3-10, clause 3.0 for general requirement of concrete.
3.2.2 Reinforcement
3.2.2.1 General
Refer to section C3-20, clause 3.0 for general requirement of reinforcement and
section C3-70, clause 3.0 for requirement of prestress elements.
Ensure all precast concrete piles supplied are reinforced in accordance to the design.
The minimum number of longitudinal bars provided is to be four in rectangular piles
and six in circular or hexagonal piles. Minimum bar size is to be 12 mm.
Total cross sectional area of reinforcement is not to be less than 1% of the cross
section of the pile. Incorporate adequate reinforcement for lifting and handling
purposes.
3.2.3 Spacers
Check that spacers are designed and manufactured using materials, which will not
lead to reinforcement corrosion or spalling of the concrete cover.
3.2.4 Formwork
3.2.4.1 General
Refer to Section C3-60, clause 3.1 for general requirement of precast
mould/formwork.
Ensure formwork is clean, robust and constructed such as to prevent grout loss or
loss of aggregate during casting and to ensure the production of uniform sections.
When the sides of adjacent piles are used as formwork, use an accepted method to
prevent adhesion between concrete surfaces.
11
Version 1.0
NPQS
C4-20 Driven Piling
12
Version 1.0
NPQS
C4-20 Driven Piling
3.3.2 Welding
All welding for fabrication of steel piles and accessories are to be in accordance with
section C5-10 “ Structural Steelwork”, clause 4.5.
3.4.1 General
Timber piles are to comply with SS CP 1 and SS CP 7 in terms of classification and
strength, and are to be pressure treated with approved chemical preservative in
accordance with SS 72.
The piles are to be free from defects which may affect their strength and durability.
3.4.2 Species
All square sawn timber piles are to be Kempas or Keruing unless otherwise specified
or agreed.
3.4.3 Grading
Grading is to be in accordance with Malaysian Grading Rules by qualified timber
grading agents registered with Malaysian Timber Industry Board. Comply with the
following grading limits:
3.4.3.1 Knots
The size of knots is not to exceed one-quarter the width of the face or edge on which
they appear, and not be grouped closer than one knot per 1 metre of the length of the
pile. Unsound knots are not permitted.
13
Version 1.0
NPQS
C4-20 Driven Piling
3.4.3.2 Wane
Wane is to be allowed on one edge only and the total width of wane on its adjacent
faces is not to exceed:
a. 65 mm for 125 mm square piles
b. 75 mm for 150 mm square piles
c. 90 mm for 175 mm square piles
3.4.3.3 Curvature
In piles up to 6 metres in length, maximum deviation is not to exceed 25 mm, ie the
longitudinal curvature is to fall within 25 mm of the centre line of the pile. In piles over
6 metres long, maximum deviation is not to exceed 35 mm.
14
Version 1.0
NPQS
C4-20 Driven Piling
pressure of not less than 15.5 kg/cm2 and with an average dry salt retention of 24
kg/m3 in the treatable volume: and secondly with creosote/fuel oil solution all in
accordance with manufacturer's recommendation.
A sample boring taken from any part of any treated pile is to demonstrate evidence of
continuous and substantially even penetration of the preservation for the full depth of
the treated zone.
Submit a treatment certificate for every consignment of piles delivered. Provide
details of charge number, average dry salt retention, and the number and sizes of
piles supplied.
All timber piles delivered to site are to bear marks from approved labs certifying the
standard attained for treatment or otherwise tested at random at SO’s direction.
15
Version 1.0
NPQS
C4-20 Driven Piling
4. WORKMANSHIP
4.1.1.1 Curing
Unless otherwise agreed, the piles are to be cured for the period as below.
Type of Cement Minimum Period from Time of Casting
Strike Side End of Wet Lift from Drive
Shutters Curing Casting Bed
Sulphate 12 hours 4 days 10 days 28 days
Resisting
Portland Cement
Rapid-Hardening 12 hours 3 days 7 days 10 days
Portland Cement
Do not lift piles from the casting bed until sufficient concrete strength has developed
to allow handling to take place without causing damage. Assess this on the basis of
the results of the concrete cube tests and the type of cement and admixtures used,
and provide a proposed level for acceptance.
When accelerated curing is used, the curing procedure is to SO’s acceptance and
must not cause deleterious effects to the pile. Allow not less than four hours from the
completion of casting before raising the temperature. Control rates of heating and
cooling in accordance with section C3-60, clause 4.1.5.
16
Version 1.0
NPQS
C4-20 Driven Piling
4.3.1 Handling
Do not lift piles by slinging from other than accepted lifting holes or points. For each
section, clearly mark the lifting points.
Ensure that all piles within a stack are in groups of the same length and placed on
accepted supports.
Carry out handling, transporting and pitching of piles in a manner that avoid damage
to piles and their coatings.
4.3.2 Pitching
Before the commencement of driving, check each pile and the leaders or guides of
the pile frame for correct rake or plumb and maintain the rake or plumb during driving.
During the driving operation ensure the centre of the monkey or hydraulic ram does
not deviate more than 40 mm off the centre of the pile being driven.
17
Version 1.0
NPQS
C4-20 Driven Piling
4.4.1 General
Install each pile to a penetration as indicated in the drawings or as adjusted as a
result of the design verification check supported by accepted set records.
Ensure the equipment set up and installation procedures are in conformance with SS
CP 4.
4.4.3.2 Depth
Drive each pile continuously until the specified depth or accepted set has been
reached. Acceptable set is indicated in the PSD. Do not suspend driving without
approval. Demonstrate that the rate of penetration prior to the cessation of driving will
be substantially re-established on its resumption.
Drive each pile continuously until the specified depth or a set of not more than
mm per last 10 hammer blows has been achieved. Set to be confirmed during
preliminary pile tests.
18
Version 1.0
NPQS
C4-20 Driven Piling
4.4.3.8 Obstruction
In the event of encountering obstructions below ground level during piling operations,
inform the SO immediately for further directions.
19
Version 1.0
NPQS
C4-20 Driven Piling
b. The dolly and packing, if any, is to be in sound condition. Set taken by dolly is to
be correlated with load test results.
c. The hammer blow is to be in line with the pile axis and the impact surfaces are to
be flat and at right angles to the pile and hammer axis.
d. The hammer is to be in good condition and operating correctly.
e. The temporary compression of the pile is to be recorded as directed.
4.4.6 Preboring
Adopt pre-boring to assist pile installation only with permission.
Pitch the pile into a hole pre-bored to the depth and diameter as agreed with the SO.
Record the details of the pre-boring depth and diameter.
4.4.7 Jetting
Adopt jetting to assist pile installation only with permission. Propose details for the
jetting operations to SO’s acceptance before commencing. Do not carry out jetting
over the last 3m of penetration.
4.5 Welding
All welding are to conform to the requirement in section C5-10 “Structural Steelwork”,
clause 4.5. Ensure that all welding are carried out by a certified welder.
20
Version 1.0
NPQS
C4-20 Driven Piling
When welding the splice joints during driving, allow a minimum cooling time of 30
minutes for welds before continuing any driving work.
4.7 Tolerances
4.7.3 Verticality
For vertical piles, the maximum permitted deviation of the finished pile from the
vertical is 1 in 75.
4.7.4 Rake
For raked piles, set and maintain the piling rig to attain the required rake. The
maximum permitted deviation of the finished pile from the specified rake is 1 in 25.
21
Version 1.0
NPQS
C4-20 Driven Piling
In stripping pile heads, strip the concrete to a level such that the remaining concrete
will project 75 mm into the pile cap.
Where a pile has been formed below the required cut-off level, build it up with
concrete of at least the same grade and ensure that the reinforcement projects for
such length as above.
Provide details of the proposed method of cutting the pile heads.
Take care to avoid shattering or damaging the rest of the pile. Cut away any cracked
or defective concrete and made good with new concrete properly bonded to the old to
provide a full and sound section to the cut-off level.
22
Version 1.0
NPQS
C4-20 Driven Piling
5.1 Submissions
23
Version 1.0
NPQS
C4-20 Driven Piling
5.2.1 General
Provide the SO with test certificates, analysis and mill certificates. Ensure that
adequate notice is given to the SO to inspect the process or test.
24
Version 1.0
NPQS
C4-20 Driven Piling
5.3 Tests
25
Version 1.0
NPQS
C4-20 Driven Piling
5.5 Records
Keep piling records with the following information and submit copies as directed in
good time to the SO. Note any unexpected boring conditions in the record.
a. Contract and site information
b. Pile reference number (location)
c. Pile type
d. Nominal cross-sectional dimensions or diameter
e. Hammer weight
f. Hammer drop height
g. Temporary Compression
h. Re-drives Achieved
i. Final Set Achieved
j. Length of preformed pile
26
Version 1.0
NPQS
C4-20 Driven Piling
27
Version 1.0