Recommendations For Structural Grouting
Recommendations For Structural Grouting
Structural grouting is an integral part of precast concrete, steel, and tilt-up construction.
Currently, there are no requirements in building codes or standards for the installation or special
inspection of grouted joints. The lack of attention to the timeliness of structural grouting has led
to structural failures in both precast concrete and steel-framed structures.
Figure
1. Aerial view of the Miami parking structure collapse. Courtesy of OSHA.
On October 10, 2012, a six-story precast parking structure in Miami, Florida, was under
construction when a portion of the garage collapsed. The collapse killed four and injured three
others. The collapse was caused, as reported by the Occupational Safety and Health
Administration (OSHA) Construction Incidents Investigation Engineering Report, “because
grout was not placed, as required, at the base of an interior column to adequately transfer the
column load to the footing. As loads on the column gradually increased on the day of the
incident, the bearing of the column over the shim plates exceeded its capacity, resulting in
failure. This triggered a cascade of collapse of columns, inverted tee beams, and double tees on
all five floors weighing approximately 3,300 tons over an area of approximately 16,000 square
feet.” (Figure 1)
Figure 2.
Protruding anchor rods after shim stack punched into pilaster below the column
Figure 3. Failure
of pilaster viewed from below.
Figure 4.
Apparatus to lift building frame to the proper position following failure.
Another instance of structural failure due to lack of timely grouting occurred on a precast
concrete structure in Colorado. The precast column had not been grouted when a significant load
was placed on it. The result was the shim stack punching into the precast column and causing a
localized failure of the column (Figure 5).
Water Requirements – Precise measurements are required for drypack, flowable, and
fluid mixtures
Mixing Time – Typically between three and five minutes depending on the manufacturer
Surface Preparation – Substrate temperature must be between 45°F and 90°F prior to
grouting.
Grout Temperature – Some manufacturers recommend that grout should be within 15°F
of substrate temperature. Cure grout between 45°F and 90°F for a minimum of 24 hours.
Supplemental Materials – Must add pea gravel for wider joints (over three inches for
most manufacturers.)
It can also be challenging to install grout properly. Obtaining adequate compaction of drypack
grout is difficult, especially with narrow joints, deep joints, or limited access. Fluid grout can be
equally challenging with required formwork and the difficulty of avoiding trapped air, which
prevents solid contact of grout with the bearing surface.
To address the gap in building codes and standards, the Structural Engineer’s Association of
Colorado (SEAC) Precast Concrete Committee has developed recommended structural grouting
practices. This committee consists of representatives of consulting engineering firms; precasters
(precast manufacturers, precast specialty engineers, and precast erectors) in Colorado; and the
Executive Director of the Precast/Prestressed Concrete Institute (PCI) Mountain States Region.
The committee has developed the following suggested practices for the local market to improve
the construction practices of structural grouting:
Precasters should be responsible for establishing the QA/QC program, including grout design,
installation requirements, and verification procedures. Each of these steps has an important role
in establishing the necessary assurance and documentation as part of a close-out package to the
design team and, ultimately, the building owner.
Colorado precasters and PCI have implemented several strategies to improve the quality of
structural grouting. Colorado precasters have refined their QA/QC programs to ensure grouting
is compliant with erection stability plans. Nationally, the PCI Field Safety Task Group
recommended that all PCI Certified Erectors include, as part of the erector’s daily field reports,
documentation that identifies each grouted joint and grout sleeve, the date it was completed, and
its location in the building. The PCI Erectors committee is also developing grouting
recommendations and is working on language to be included in the next edition of the
PCI Erectors Safety Manual and the PCI Erectors Manual. It is expected that the
recommendations will be similar to those presented above.
Special inspection may be utilized to verify the QA/QC programs are being executed as
submitted and approved; however, the International Building Code (IBC) has no special
inspection requirements for grouting. If the designer or owner request special inspection services,
then the special inspection requirements should be fully defined by the party requiring the special
inspection, including activity, frequency, and location.
The SEAC Precast Concrete Committee recommends additional review and attention be given to
grouting requirements of all structural systems to ensure that a proper load path exists during
construction and at ultimate loading.
To aid in the application of these recommendations, the SEAC Precast Committee has developed
a guide, Structural Grouting Specification, Section 036000. This specification includes
requirements for structural grouting of precast concrete joints, steel bearing assemblies, and tilt-
up concrete joints. The specification is written with two separate paths for approval of the
grouting procedures: performance-based and prescriptive.
The performance-based path is required to be used by PCI certified precast erectors and can also
be used by experienced contractors. When the performance-based path is used, submittal of a
comprehensive Installation and Quality Control Plan is required. This plan should include the
following for each type of grouted joint: preparation and installation procedures, methods of
thermal control and curing, method of verification of the quality of grouting, size of shim stacks,
timing and sequence of grouting, and qualifications of personnel performing grouting operations.
The prescriptive path of the structural grouting specification is required when an Installation and
Quality Control Plan is not submitted. The specification discusses the timing of grout placement
to require grouting before large loads are imposed on the joint, preparation of the joint, required
formwork, grout mixing, grout placement for dry-packed grout, poured grout, and pumped grout,
as well as curing and finishing of grouted joints.
The specification also requires special inspection of grouted structural joints. For structures
erected by PCI certified erectors, special inspections are recommended to inspect the work
procedure for compliance with submitted Installation and Quality Control Plan. For other
systems, special inspections should include a review of the preparation of joints to be grouted,
mixing of grout in conformance with manufacturer instructions, the temperature of the air,
substrate, and grout, placement of grout and grouting method, curing procedures, and test poured
and pumped grout flow rates. Where the placement of concrete slabs, soil, or other construction
may conceal joints, joints should be inspected before concealment. Prior to placement of
concrete slabs supported by a column or wall, inspections should verify that grouting has been
completed below the column or wall.
The specification intentionally does not indicate the use of grout cube testing per ASTM C109,
as the compressive strength of a 2-x2-x2-inch grout cube is not representative of the actual
strength of a grouted joint. Most grouted joints have a dramatically different aspect ratio and
confinement than a 2-inch cube, which significantly increases the grout’s apparent strength.
Also, ASTM C109 does not directly apply to pumped or fluid grouts. As such, while testing does
indicate the performance of the material relative to the manufacturer’s stated test data and
properties, it is not a good representation of in-situ grout strength. Better testing includes
destructive testing to confirm the completeness of grout installation and other verification
procedures during mixing and placing. The sample Structural Grouting Specification can be
reviewed at https://bit.ly/2KymIxK. The SEAC Precast Concrete Committee recommends that
practicing engineers, precasters, and contractors remain attentive to structural grouting and
review and adapt the sample grouting specification as they see fit. Structural grout is an integral
part of the structural system of nearly all structures; improper installation of this material can
lead to failures