Bidding
Bidding
Design phase
In this phase the owner retains an architect (or consulting engineer for infrastructure works) to
design and produce bid documents, including construction drawings and technical
specifications, on which various general contractors will in turn bid to construct the project.
For building projects, the architect will work with the owner to identify the owner's needs,
develop a written program documenting those needs and then produce a conceptual and/or
schematic design. This early design is then developed, and the architect will usually bring in
other design professionals including a structural engineer, sometimes a civil
engineer, mechanical, electrical, and plumbing engineers (MEP engineers), a fire protection
engineer and often a landscape architect to help complete the construction drawings and
technical specifications. The finished bid documents are coordinated by the architect and
owner for issuance to general contractors during the bid phase.
Design fees are typically between 5-10% of the total project cost.[1]
Re-bid (or re-tender) the construction of the project on a future date when the owner's
needs are met, such as when money becomes available and/or construction costs go down.
Abandon the project entirely.
Issue a work order to have the architect revise the design (sometimes at no cost to the
Owner, if previously negotiated), so as to make the project smaller or more efficient, or
reduce features or elements of the project to bring the cost down. The revised bid
documents can then be issued again for bid (or re-tendered).
Select a general contractor, such as the lowest bidder, or an experienced cost estimator to
assist the architect with design changes aimed at cost reduction. This process is often
referred to as value engineering. The revised bid documents can then be issued again for
bid (or re-tendered).
Construction phase
Once the construction of the project has been awarded to the contractor, the bid documents
(e.g., approved construction drawings and technical specifications) may not be altered. The
necessary permits (for example, a building permit) must be achieved from all jurisdictional
authorities in order for the construction process to begin. Should design changes be necessary
during construction, whether initiated by the contractor, owner, or as discovered by the
architect, the architect may issue sketches or written clarifications. The contractor may be
required to document "as built" conditions to the owner.
In most instances, nearly every component of a project is supplied and installed by sub-
contractors. The general contractor may provide work with its own forces, but it is common
for a general contractor to limit its role primarily to managing the construction process and
daily activity on a construction site (see also construction management).
During the construction phase the architect also acts as the owner's agent to review the progress
of the work as it relates to pay requests from the Contractor, and to issue site instructions,
change orders (or field orders), or other documentation necessary to facilitate the construction
process and certify that the project is built to the approved construction drawings.
Potential problems of design–bid–build
Failure of the design team to be current with construction costs, and any potential cost
increases during the design phase could cause project delays if the construction documents
must be redone to reduce costs.
Redesign expense can be disputed should the architect's contract not specifically address
the issue of revisions required to reduce costs.
Development of a "cheaper is better" mentality amongst the general contractors bidding
the project so there is the tendency to seek out the lowest cost sub-contractors in a given
market. In strong markets, general contractors will be able to be selective about which
projects to bid, but in lean times, the desire for work usually forces the low bidder of each
trade to be selected. This usually results in increased risk (for the general contractor) but
can also compromise the quality of construction. In the extreme, it can lead to serious
disputes involving quality of the final product, or bankruptcy of a sub-contractor who was
on the brink of insolvency desperate for work.
As the general contractor is brought to the team post design, there is little opportunity for
input on effective alternates being presented.
Pressures may be exerted on the design and construction teams due to competing interests
(e.g., economy versus acceptable quality), which may lead to disputes between the
architect and the general contractor, and associated delays in construction.
Benefits of design–bid–build
The design team looks out for the interests of the owner.
The design team prepares documents on which all general contractors place bids. With this
in mind, the "cheaper is better" argument is rendered invalid since the bids are based on
complete documents. Incomplete, incorrect or missed items are usually discovered and
addressed during the bid process in the form of addenda.
Ensures fairness to potential bidders and improves decision making by the owner by
providing a range of potential options. It also identifies new potential contractors.
Assists the owner in establishing reasonable prices for the project.
Uses competition both in the selection of the architect and the contractor to improve the
efficiency and quality for owners.