0% found this document useful (0 votes)
41 views27 pages

Line Balancing: An Overview of

The document discusses line balancing in manufacturing. It defines line balancing as assigning tasks to workstations to equalize workloads. The objectives are to identify bottlenecks, set production speed, determine needed workstations, and reduce costs. Common methods include precedence diagrams and algorithms to assign tasks in a way that minimizes idle time. The example shows balancing a line from 6 to 5 workstations to increase efficiency from 79% to 84%. Parallel workstations can also help eliminate bottlenecks.

Uploaded by

DileepSingh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views27 pages

Line Balancing: An Overview of

The document discusses line balancing in manufacturing. It defines line balancing as assigning tasks to workstations to equalize workloads. The objectives are to identify bottlenecks, set production speed, determine needed workstations, and reduce costs. Common methods include precedence diagrams and algorithms to assign tasks in a way that minimizes idle time. The example shows balancing a line from 6 to 5 workstations to increase efficiency from 79% to 84%. Parallel workstations can also help eliminate bottlenecks.

Uploaded by

DileepSingh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

An overview of

LINE BALANCING
By: Hiwa Ghaffari
A SIMPLE LINE FOR PRODUCTION OR ASSEMBLY

Workstatio Workstatio Workstatio Workstatio


n1 n2 n3 n4

Input Out
put
ACTIVITY CLASSIFICATION
Value Adding:
Any process that changes the
nature, shape or characteristics
of the product, in line with
customer requirements e.g.
machining, assembly

Non-Value Adding, but


unavoidable with current technology or
methods:
Any work carried out that does not increase
product value e.g. inspection, part movement,
tool changing, maintenance

Waste:
All other meaningless, non-essential
activities that do not add value to the
product you can eliminate immediately
e.g. looking for tools, waiting time
WASTES
Wastes are caused from:
 Transportation
 Inventory
 Motion
 Waiting
 Overproduction
 Over-processing
 Defects
(The 7 Wastes: T.I.M.W.O.O.D)
UNBALANCED LINE : SIMPLE EXAMPLE
Over-processing
defects
Overproduction which Inventory Waiting
causes the other 6 wastes Transportation Motion

5 mins 25 mins 15 mins 10 mins

1 2 3 4

Constraint This operator This operator


Overburden must WAIT for must WAIT for
operator 2 operator 3
25

20

mins 15
10

1 2 3 4
LINE BALANCING: DEFINITION

Line Balancing is the process of assigning tasks to


workstations in such a way that the workstations have
approximately equal time requirements.
LINE BALANCING: OBJECTIVES

Main Objectives:
to equalize the work load among the operators
to identify the bottleneck operation
to establish the speed of the production line
to determine the number of workstations
to determine the labor cost of production and pack out
to establish the percentage workload of each operator
to assist in plant layout
to reduce production cost
LINE BALANCING: METHODS

•There are many ways or methods for balancing the lines.


•The common thing for all this methods is:
using both the operator and the machine in the most
efficient way, at the same time providing flexibility in
production.
BALANCED LINE: SIMPLE EXAMPLE
Promotes one- Avoids Minimises the 7 Reduces
piece FLOW overburden wastes Variation

15 mins 15 mins 15 mins 10 mins

1 2 3 4

Redistribute the work


25

20

15
10

5
CONCEPTS
Bottleneck: The work station taking the longest time.

Required Cycle Time: Takt Time

Current Cycle Time: The same as Bottleneck Time.

Flow Time (Total Work Content): Time to complete all


stations.

1 2 3 Flow time= 2+5+3=10min


2min 5min 3min Current cycle time = 5min
Bottleneck
CONCEPTS
Precedence diagram: Network showing order of tasks
and restrictions on their performance.
B
F
A D

E
G H

Total work content: Sum of the task times for all the
production tasks for the product.
Minimum number of work stations=
The quotient should be rounded to the next highest
integer.
LINE BALANCING: PREREQUISITES

 Determine minimum rational work elements.


(Smallest feasible division of work)

 Determine cycle time.

 Calculate the theoretical minimum number of


work stations.

 Draw Precedence Diagram

9-12
LINE BALANCING: A SIMPLE ALGORITHM

1. Identify tasks whose predecessors have been assigned to a


workstation (available tasks).

2. Determine from available tasks, those that fit, i.e., those whose
tasks times time remaining to be filled at this work station.

3. Choose a task that fits by some decision rule


 task with largest time
 task with most successors
 task with greatest sum of task times of its predecessors.
4. Continue steps 1 to 3 until no task fits, then go on to next
workstation.

5. Continue steps 1 to 4 until all tasks are assigned


LINE BALANCING: EXAMPLE
Task Task Time (sec) predecessors
A 70 -
B 80 A
C 40 A
D 20 A
E 40 A
F 30 B,C
G 50 C
H 50 D,E,F,G
Total: 380

Wanted Total Product is 320 Units Per Day

A B C,D E,F G H

50 min
70 min 80 min 60 min 70 min 50 min
LINE BALANCING: EXAMPLE
Current Conditions:
 Current Cycle Time= Bottleneck Time = 80 sec

 Current No. of Workstations: 6

 Total Product Per Day = (total time available per day)/(cycle time)
= (8×3600)/(80) = 360 units
LINE BALANCING: EXAMPLE
According To The Problem:
 Cycle Time = (8×3600)/320 = 90 sec

 Total Work Content = 380 sec

 No. of Workstations = 380/90 = 4.22 5


LINE BALANCING: EXAMPLE
 Precedence Diagram:

B
80 sec

F
30 sec
C
40 sec

A G
H
50 sec
70 sec
D 50 sec

20 sec

E
40 sec
LINE BALANCING: EXAMPLE
B Task Task Task time +
Time
80 sec
follower
F
task times
30 sec

C A 70 380
A 40 sec G C 80 170
70 sec
50 sec
H B 40 160
D
20 sec
50 sec
G 20 100
E 40 90
E F 30 80
40 sec
D 50 70
Workstation Workstation Workstation Workstation Workstation

1 2 3 4 5 H 50 50

A C B E H
D G F
90 sec 90 sec 80 sec 70 sec 50 sec
LINE BALANCING: EXAMPLE

Comparing Line Efficiency:


Line Efficiency =(Total Work Content)/(No. of Workstations ×Cycle Time)

Case 1: Line Efficiency = (380)/(6×80) = 79%

84%
Case 1: Line Efficiency = (380)/(5×90) = 84%
PARALLEL WORKSTATIONS

30/hr. 30/hr. 30/hr. 30/hr.


1 min. 1 min. 2 min. 1 min.

Bottleneck

30/hr. 1 min. 30/hr.

60/hr. 60/hr.
1 min. 1 min. 1 min.
30/hr.
1 min. 30/hr.

Parallel Workstations
ELIMINATE WASTE : EXAMPLE
30
30

Cycle Time (25 hrs)


25

20
17
15
15

10

1 2 3
total work content = 15 + 30 + 17 = 62 hrs

62 hrs
Line Efficiency = = 69%
(3 x 30)
ELIMINATE WASTE : EXAMPLE
30 30
30
Takt (25 hrs) 25 25
25 25 Cycle time(25 hrs)
17
20 15
20
15
12
10
15
5
10
1 2 3
5

No. of workstations = Total Work Content 1 2 3


cycle time
62 hrs
62 hrs Line Efficiency = = 83%
= 2.48 (3 x 25 hrs)
25 hrs
→ 3 workstations
Traditional Focus
Lean Manufacturing
• Work Longer-Harder-Faster
• Improve the Value
• Add People or Equipment Stream to Eliminate
Waste

Value
Waste
Added

LEAD TIME
ELIMINATE WASTE : EXAMPLE
The operators cycle is broken down into elements.
These elements are put into three main categories, these being :

1. Working (man or machine)


2. Walking
3. Waiting
30
Cycle time (25 hrs)
25

20

15

Non value added activity


10

Value added activity


5

1 2 3
ELIMINATE WASTE : EXAMPLE

30

25

20

15 Operator other
freed up for
10 process or
improvement
5 team

1 2 3
‫‪REFRENCES‬‬
‫سید مهدی الوانی‪ ،‬نصرهللا میر شفیعی ؛ مدیریت تولید ؛ انتشارات آستان قدس رضوی‬ ‫‪‬‬

‫علیرضا علی احمدی؛ ارزیابی کار و زمان؛ انتشارات دانشگاه علم و صنعت ایران‬ ‫‪‬‬

You might also like