Line Balancing: An Overview of
Line Balancing: An Overview of
LINE BALANCING
By: Hiwa Ghaffari
A SIMPLE LINE FOR PRODUCTION OR ASSEMBLY
Input Out
put
ACTIVITY CLASSIFICATION
Value Adding:
Any process that changes the
nature, shape or characteristics
of the product, in line with
customer requirements e.g.
machining, assembly
Waste:
All other meaningless, non-essential
activities that do not add value to the
product you can eliminate immediately
e.g. looking for tools, waiting time
WASTES
Wastes are caused from:
Transportation
Inventory
Motion
Waiting
Overproduction
Over-processing
Defects
(The 7 Wastes: T.I.M.W.O.O.D)
UNBALANCED LINE : SIMPLE EXAMPLE
Over-processing
defects
Overproduction which Inventory Waiting
causes the other 6 wastes Transportation Motion
1 2 3 4
20
mins 15
10
1 2 3 4
LINE BALANCING: DEFINITION
Main Objectives:
to equalize the work load among the operators
to identify the bottleneck operation
to establish the speed of the production line
to determine the number of workstations
to determine the labor cost of production and pack out
to establish the percentage workload of each operator
to assist in plant layout
to reduce production cost
LINE BALANCING: METHODS
1 2 3 4
20
15
10
5
CONCEPTS
Bottleneck: The work station taking the longest time.
E
G H
Total work content: Sum of the task times for all the
production tasks for the product.
Minimum number of work stations=
The quotient should be rounded to the next highest
integer.
LINE BALANCING: PREREQUISITES
9-12
LINE BALANCING: A SIMPLE ALGORITHM
2. Determine from available tasks, those that fit, i.e., those whose
tasks times time remaining to be filled at this work station.
A B C,D E,F G H
50 min
70 min 80 min 60 min 70 min 50 min
LINE BALANCING: EXAMPLE
Current Conditions:
Current Cycle Time= Bottleneck Time = 80 sec
Total Product Per Day = (total time available per day)/(cycle time)
= (8×3600)/(80) = 360 units
LINE BALANCING: EXAMPLE
According To The Problem:
Cycle Time = (8×3600)/320 = 90 sec
B
80 sec
F
30 sec
C
40 sec
A G
H
50 sec
70 sec
D 50 sec
20 sec
E
40 sec
LINE BALANCING: EXAMPLE
B Task Task Task time +
Time
80 sec
follower
F
task times
30 sec
C A 70 380
A 40 sec G C 80 170
70 sec
50 sec
H B 40 160
D
20 sec
50 sec
G 20 100
E 40 90
E F 30 80
40 sec
D 50 70
Workstation Workstation Workstation Workstation Workstation
1 2 3 4 5 H 50 50
A C B E H
D G F
90 sec 90 sec 80 sec 70 sec 50 sec
LINE BALANCING: EXAMPLE
84%
Case 1: Line Efficiency = (380)/(5×90) = 84%
PARALLEL WORKSTATIONS
Bottleneck
60/hr. 60/hr.
1 min. 1 min. 1 min.
30/hr.
1 min. 30/hr.
Parallel Workstations
ELIMINATE WASTE : EXAMPLE
30
30
20
17
15
15
10
1 2 3
total work content = 15 + 30 + 17 = 62 hrs
62 hrs
Line Efficiency = = 69%
(3 x 30)
ELIMINATE WASTE : EXAMPLE
30 30
30
Takt (25 hrs) 25 25
25 25 Cycle time(25 hrs)
17
20 15
20
15
12
10
15
5
10
1 2 3
5
Value
Waste
Added
LEAD TIME
ELIMINATE WASTE : EXAMPLE
The operators cycle is broken down into elements.
These elements are put into three main categories, these being :
20
15
1 2 3
ELIMINATE WASTE : EXAMPLE
30
25
20
15 Operator other
freed up for
10 process or
improvement
5 team
1 2 3
REFRENCES
سید مهدی الوانی ،نصرهللا میر شفیعی ؛ مدیریت تولید ؛ انتشارات آستان قدس رضوی
علیرضا علی احمدی؛ ارزیابی کار و زمان؛ انتشارات دانشگاه علم و صنعت ایران