Excitation System Commissioning Procedure
Excitation System Commissioning Procedure
PROCEDURE
Approved by:
Performed by: Approved by:
CNEEC RUM
Approved by:
Rev No.
PT RUM’S Heating Power Plant
Checked by:
Solo Indonesia
Prepared by: 0
TTR.COMM/B14.04/WRK-RUM/ELC/005
TEST PROCEDURE CHINAUNITEDENGINEERINGCORPORATION
1. APPENDIX
1.1. Record for Disclosure of Test Technical Meaures (Scheme), Organizaitonal
Measures and Safety Measures
Description:
1. Principle scheme (see Commissioning Scheme for the Plant-wdie Excitation System
for details)
2. Prerequisite before the test (see Commissioning Scheme for the Plant-wdie Excitation
System for details)
3. Scope, Procedure and Steps of Commissioning (see Commissioning Scheme for the
Plant-wdie Excitation System for details)
4. Organization and labor division (see Commissioning Scheme for the Plant-wdie
Excitation System for details)
5. Safety Precautions:
5.1. The checking of temperature channel of motor and signal test has been completed;
5.2. The insulation of motor is qualified;
5.3. The emergency button test of motor is qualified.
5.4. The logic action of interlock protection of air Excitation system;
5.5. The warning line is set for the commissioning are, with specially-assigned person
guarded.
5.6. For the initial starting, there are specially-assigned person arranged for patrolling
TEST PROCEDURE CHINAUNITEDENGINEERINGCORPORATION
and measuring the vibration and temperature, monitoring the lubricating oil flow and
oil pressure and temperature;
5.7. The temporary fire extinguisher or sandbag is placed on the commissioning site.
5.8. Use the interphone (connection between DCS and local place) to ensure the
smooth communication.
5.9. In case there are factors influencing the starting of air compressor, it is only allowed
to start the air compressor after eliminating these factors.
5.10.Record the parameter of commissioning.
Blank below
2. ORGANIZATION CHART:
TEST PROCEDURE CHINAUNITEDENGINEERINGCORPORATION
Mr. Feri
(Project Manager)
Mr. Siswanto
(Safety Officer)
Mr. Rodney
(Commissioning)
3. ATTACHMENT