NGCP TDP With Process Flow
NGCP TDP With Process Flow
TRANSMISSION
DEVELOPMENT
PLAN
2014-2015
Final Report
DECEMBER 2016
DISCLAIMER
The Transmission Development Plan (TDP) is prepared and published solely for information purposes. While
NGCP, to the best of its knowledge, has used the most accurate data available, and has used utmost prudence in
the use of those information, nothing in this document can be or should be taken as a recommendation in respect of
any possible investment or business decision. This document does not claim to contain all the information that a
prospective investor or grid user or potential participant to the electricity market, or any other person or interested
parties may require for making decisions. In preparing this document it is not possible nor is it intended for NGCP to
have considered the investment objectives, financial situation and particular needs of each person who uses this
document.
In all cases, anyone proposing to rely on or use the information in this document should independently verify and
check the accuracy, completeness, reliability and suitability of that information and the reports and other information
relied on by NGCP in preparing this document, and should obtain independent and specific advice from appropriate
experts.
In the same manner, NGCP does not make representations or warranty as to the accuracy, reliability,
completeness or suitability for particular purposes of the information in this document. Persons reading or using this
document acknowledge that NGCP and/or its employees shall have no liability (including liability to any person by
reason of negligence or negligent misstatement) for any statements, opinions, information or matter (expressed or
implied) arising out of, contained in or derived from, or for any omissions from, the information in this document,
except insofar as liability under any statute of the Republic of the Philippines cannot be excluded.
FOREWORD
The National Grid Corporation of the Philippines (NGCP) is pleased to present its 2014-2015
Transmission Development Plan (TDP) which strategically lays out, over a 10-year period, the
expansion of the Philippine power grid. This is part of its continuous efforts to provide reliable,
adequate, secure, and stable power transmission to its customers and stakeholders.
Other than the status of the approved projects for the 3rd Regulatory Period, the 2014-2015 TDP
contains the list of proposed transmission projects for the next ten years. The list includes the
crucial projects scheduled for implementation in the 4th Regulatory Period.
In Luzon, the additional major projects already approved by the ERC, with ongoing
implementation already, include the new Calaca-Dasmariñas Transmission Line Project which
aims to accommodate the generation capacity additions in Batangas; the Las Piñas Substation
Expansion Project which involves the installation of an additional transformer to support load
growth in Metro Manila; and the Tuguegarao-Lal-lo 230 kV Transmission Line Project which will
extend the 230 kV transmission backbone to the north-eastern part of Luzon. Positively, the San
Esteban-Laoag 230 kV T/L project was already energized which allows full dispatch of the wind
farms in northernmost part of Luzon.
NGCP is also giving special attention to increase the capacity and improve system reliability of
the transmission facilities in the country’s load center in Metro Manila. New substations in
Navotas/Manila, Pasay, and Taguig and associated transmission lines have been proposed to
support the load growth and to strengthen the Metro Manila grid by forming loop configurations.
In the Visayas, where the Cebu-Negros-Panay 230 kV Backbone Project is already being
implemented, more projects that will support the entry of generators are also in the pipeline.
These projects will ensure the long-term security of power transmission in the Visayas and
strengthen NGCP’s transmission facilities to accommodate incoming generating plants that will
cater to the region’s growing power demand.
Major projects include the Malita-Matanao 230 kV Transmission Line Project and the Balo-i–
Kauswagan 230 kV Transmission Line Project which will support the entry of the new coal-fired
power plants in Mindanao. Another noteworthy undertaking is the Mindanao 230 kV
Transmission Backbone Project which will enable higher transfer capability of the existing
transmission lines and support the impending entry of huge capacity power plants. More
importantly, this project is expected to play a vital role in the exchange of power between
Visayas and Mindanao in consideration of the proposed Visayas-Mindanao Interconnection
Project.
The TDP also includes the transmission planning approach for renewable energy (RE)
particularly, wind and solar. The challenges for integration are discussed in this TDP as well as
corresponding action plan of NGCP to fully support the development of RE.
The TDP is a valuable document for industry stakeholders. As the country’s sole power grid
operator and transmission service provider, it continues to improve the quality of its
transmission planning process through constant collaboration with the Department of Energy,
generation facilities, power customers, distribution utilities, local government units, and the
general public. Their inputs are carefully considered in each year’s comprehensive and
responsive TDP update.
The long-term projects contained in the TDP are expected to improve NGCP’s transmission
services. With the support and engagement of stakeholders in the development of this
document, NGCP is ensured of the smooth implementation of its plan towards a "Stronger
Transmission for a Stronger Nation.”
1.1 Introduction
NGCP’s transmission system network consists of 500 kV, 350 kV HVDC, 230 kV, 138 kV, 115
kV and 69 kV high voltage lines and cables. As the sole transmission service provider, NGCP
plays a vital role in the safe and reliable transmission of electricity in response to system
requirements and market demands. It continues to improve the reliability, adequacy, security
and stability of the grid in the three major regions of the Philippines, namely: Luzon, the Visayas
and Mindanao.
As the System Operator of the Philippine power grid, NGCP balances the supply and demand of
electricity to efficiently serve all of its customers – power generators, private distribution utilities,
electric cooperatives, government-owned utilities, eco-zones, industries, as well as directly-
connected customers. It is responsible in dispatching the power plants and transmitting the
generated power to the various distribution utilities which, in turn, deliver the electricity at a
lower voltage to households and other end-users. NGCP also operates and maintains metering
facilities and provides technical services, particularly system studies, and operation and
maintenance of customer facilities.
This Transmission Development Plan (TDP) outlines the planned projects which are required to
address the system needs for the period 2016 to 2025.
With the enactment of the EPIRA into a law in June 2001, the Philippine Electricity Industry was
subdivided into four sectors: generation, transmission, distribution and supply. Each sector is
distinguished as different business activity. The transmission and distribution sectors exhibit
natural monopoly characteristic; hence these are regulated. Generation and supply or the
aggregators for the sale of electricity, on the other hand, operate under a competitive
environment.
In its continuing effort to provide quality and efficient service, NGCP received its Integrated
Management System (IMS) recertification on May 11, 2015 from TUV Rheinland Philippines, a
third-party auditing firm specializing in international standards accreditation. The country’s sole
transmission service provider and power System Operator was certified in three management
systems: Quality Management System – ISO 9001:2008, Occupational Health and Safety
Management System – OHSAS 18001:2007 and Environmental Management System – ISO
14001:2004 + Cor.1:2009.
The 2014-2015 TDP consists of three volumes. Volume I contains the proposed grid expansion
and upgrades, which generally, are based on the results of system studies. The other volumes
1
outline the capital expenditure programs of Operations and Maintenance (Volume II–Part 1) and
System Operations (Volume III). Those for metering services have been integrated into Volume
II but in a separate report (Volume II-Part 2). Volume I consists of twelve chapters.
Chapter 3 discusses the profile of each grid and the features of the existing transmission
facilities;
Chapter 4 presents the latest demand projection as inputs to the simulation studies to
identify future transmission constraints and transmission expansions in each grid;
Chapter 5 presents the latest generation capacity addition including Renewable Energy
(RE), potential resource areas and ideal locations of power plants as inputs to
the simulation studies to determine the future transmission
reinforcements/expansions in each grid;
Chapter 6 presents the power system reliability/security measures through climate change
adaptation for transmission facilities, including discussion on strategies to meet
the challenges on right-of-way (ROW) acquisition;
Chapter 7 enumerates the ERC-approved projects in Luzon, the Visayas and Mindanao
Grids that are in various stages of implementation;
Chapter 8-10 discusses transmission outlook for 2016-2025 including discussion on project
components and drivers for the proposed transmission projects for Luzon, the
Visayas and Mindanao Grids; including Major Island/Grid Interconnection
projects;
Chapter 12 contains different appendices that include discussions on relevant topics such as
the Prospective Plants, ASEAN Power Grid (APG), other RE potential, and
comparison of transmission projects, i.e., 2013 TDP vs. 2014-2015 TDP.
2
Chapter 2 – TDP Volume 1 Preparation Process
The System Peak Demand Forecast and the Generation Capacity Addition Line-up are the
two major inputs in the TDP which come from the DOE. These inputs are being updated
annually by the DOE. For use in the transmission network analysis, the system peak
demand forecast shall be broken down and forecasted into individual transformer loads. For
determination of load-end substation expansion requirements, on the other hand, NGCP’s
own non-coincident substation peak loading forecast is being used.
One of the requirements of EPIRA as regards the preparation of the TDP is the conduct of
consultation with the electric power industry participants. NGCP regularly conducts
Customers Interface Meetings to gather inputs from the Distribution Development Plans of
Distribution Utilities, expansion programs of Generator Companies and other directly
3
connected customers. In addition, coordination meetings with other stakeholders are also
being conducted.
The identification of system requirements for the next ten years involves the conduct of load
flow, short-circuit, and transient stability studies using special software in power system
simulation. These assessments are made in reference to the planning criteria and limits
prescribed in the Philippine Grid Code (PGC).
The system assessment takes off from the model of the existing transmission network. Then
using the updated system peak load forecast, which is disaggregated into per substation
transformer level and the recent list of generation capacity additions, the network model for
the next ten-year period as covered by the TDP will be developed.
In conducting the simulation studies, different dispatch scenarios are considered. For Luzon
Grid, the bulk generations are located in the northern and southern part of the island. Thus,
the Maximum North, Maximum South, Typical Generation and Other Generation scenarios
are considered. Maximum Leyte and Maximum Panay scenarios for the Visayas, and
Maximum North and Dry Season scenarios for Mindanao.
All generation facility outputs in the southern part of the grid are set to
Maximum South Dry Season
their maximum capacities;
Power generation are based on the typical output levels of power plants
Typical Generation Scenario
during system peak load;
4
plants are assumed to be dispatched to augment the power requirement;
1) Development of thermal generation in Southeastern Mindanao; and
Other Future Scenarios 2) Linking of the Visayas and Mindanao Grids, through the
implementation of the proposed Visayas-Mindanao Interconnection
Project (VMIP).
Resulting transmission line loading, grid transformer loading, fault level at the substations,
voltage profile and system response to disturbance can be evaluated. The next step would
be the assessment of the various solutions to the identified network problem which may be
in the form of a new transmission line, transmission line upgrading, new substation or
substation expansion, PCB replacement, installation of reactive power compensation
equipment, and/or transmission network reconfiguration project. One important
consideration in the identification of projects is the overall long-term transmission backbone
development for each grid. Some projects may have to be implemented by stages or may
be initially energized at lower voltage level but will remain consistent with the target end-
state of the grid. The selected solution from the network analysis will form part of the
documentation of the TDP.
In the case of expansion plans for load-end substations, a direct comparison of the existing
substation capacity and the load forecast would already result in the determination of
capacity addition projects to meet load growth both during normal and single-outage
contingency conditions of the transformers. The transformer addition projects, however,
would also take into account the sizing and age of the existing units, optimization and the
space limitation issues in a substation. Moreover, development of a separate new substation
is also an option in lieu of further expanding the transformer capacity at the existing
locations. Under this case, system simulation studies will be required to fully assess the
need and impact of new substation nodes in the grid.
This step is still part of the consultation process with the stakeholders as required by the
EPIRA. Stakeholders are given the opportunity to raise comments and suggestions on the
proposed transmission network developments as contained in the TDP.
As provided in the EPIRA, the TDP shall be submitted to the DOE for approval and for
integration in the Power Development Program (PDP) and the Philippine Energy Plan
(PEP).
The 2014-2015 TDP will serve as the reference plan in the Fourth Regulatory Period (2016-
2020) reset application of NGCP. While the TDP already provides the long list of projects
needed by the network, project prioritization and project ranking would be another important
process and a separate exercise during the capital expenditure (CAPEX) application. This will
5
involve further assessment on the probability of contingency events, assessment of the impact if
a project is not implemented yet and economic analyses.
The proposed major transmission projects for the period 2016-2025 under the 2014-2015 TDP
Volume 1, with components shown in Chapters 7, 8, 9 and 10, were based on the selected
implementation scheme after considering all the technically feasible alternatives. The
identification of project components would involve line routes, substation sites evaluation and
selection, and other initial field investigations. A least-cost development approach was also
applied consistent with various NGCP Planning and Design Standards utilizing the cost estimate
database derived from recently completed projects and/or prices of materials and equipment
obtained through canvass from suppliers.
Similar to the 2005 and 2009 TDPs which were used as references in the rate applications for
2nd and 3rd Regulatory Periods, respectively, the capital expenditures of NGCP for Major
Network Development were included in the documentation of the 2014-2015 TDP Volume 1.
However, a more detailed five-year CAPEX Program will be included in the 4th regulatory reset
application together with other relevant information necessary for a more extensive review and
evaluation by the ERC following the transparency provision for a prudent CAPEX in the RTWR.
Project prioritization is generally based on the ranking of the project drivers as follows:
Load Growth – this pertains to ensuring transmission facility adequacy and given
top most priority are projects to address the projected overloading which will occur
even during normal condition or no outage condition.
Power Quality – this involves the installation of equipment that will aid in operating
the grid within the grid code prescribed voltage limit.
System Reliability – this pertains to projects that will provide N-1 contingency and
projects that will upgrade aging facilities or replace defective equipment.
Project drivers are highly interrelated and that addressing load growth, generation entry and
system reliability are same projects that will address system congestions.
6
2.4 Project Impact to Customers
As the transmission projects are aimed at ensuring the adequacy, reliability and security of the
power grid, these will have direct impact to the quality and level of reliability of transmission
service to customers. Projects should be able to support load growth and entry of generation
capacity additions in the long-term while maintaining the reliability criterion prescribed in the
Philippine Grid Code.
The transmission rates increase or decrease is determined by the ERC during the regulatory
reset which is based on the building block approach to derive the revenue path of NGCP for the
regulatory period. The revenue path to be decided by the ERC may be in the form of increasing
or decreasing trend. Thus, the cost of a single transmission project or a group of transmission
projects can only provide an indicative rate impact which does not necessarily be the same with
that of the ERC regulatory reset determination. NGCP’s fourth regulatory period is from 2016 to
2020 and the regulatory reset process to date is yet to be undertaken as of this writing.
7
8
Chapter 3 – Assessment of Transmission System
As of August 2015, a total of 31,038 MVA substation capacities and 20,073 circuit-km are
accounted in NGCP’s asset. Table 3.1 shows the summary of existing facilities.
To ensure that voltages across the network are within the levels prescribed in the Philippine
Grid Code, capacitor banks and shunt reactors have been installed in appropriate locations in
different parts of the grid. The summary is shown below:
9
3.2 Dependable Capacity Mix
The dependable capacity indicated in the following sections is based from the DOE List of
Existing Plants as of December 30, 2015.
Philippines
Wind Solar
Biomass 2.31% 0.76%
0.89%
Geothermal
9.73%
Coal
Coal Hydro
Oil-Based
16.62% 34.24% Natural Gas
Oil-Based
Natural Gas Hydro
18.68% Geothermal
16.77%
Biomass
Wind
Solar
Figure 3.2 and Table 3.3 show the distribution of dependable capacity for Luzon, Visayas and
Mindanao.
10
5,000.00
4,000.00 Coal
Oil-Based
-
Luzon Visayas Mindanao
Figure 3.2: Dependable Capacity Mix for Luzon, the Visayas and Mindanao
11
3.3 Luzon Transmission Network
Legend:
230 kV
350 kV HVDC
500 kV
12
The bulk generation sources in the Luzon Grid are located in the northern and southern parts of
the Luzon Island while the load center is in Metro Manila area. About 53% of the total demand in
Luzon is accounted in Metro Manila. Because of this system configuration, NGCP’s
transmission backbone must have the capability to transfer bulk power from both northern and
southern parts of Luzon to the Metro Manila area.
The transmission corridor consists of several flow paths for transferring power from the
generation sources located in Northern Luzon to Metro Manila. The 500 kV double-circuit Bolo-
Nagsaag-San Jose is rated at 2,850 MVA per circuit and is capable of transferring the more
than 1,800 MW generation from Masinloc and Sual CFPP to Metro Manila. The Bolo and
Nagsaag 500 kV Substations are the receiving ends of generation from the north. The power is
then delivered to Metro Manila mainly via Mexico and San Jose Substations.
Legend:
69 kV
115 kV
230 kV
500 kV
The San Manuel-Concepcion-Mexico 230 kV line is an alternate corridor which also caters the
generation capacity of the HEPP delivering power to San Manuel 230 kV Substation.
Metro Manila
As the center of commerce and trade, it is inevitable that the demand within Metro Manila will
continue to grow, thus requiring the expansion of existing substations and building of new ones.
The National Capital Region (NCR) accounts to more than half of the total load in Luzon but
only relies on the import of power coming from the north and south Luzon.
One unique geographical feature of Metro Manila is its narrow land area between Manila Bay
and Laguna Lake, which is only about 10 km wide.
The New Antipolo 230 kV Substation Project will cater to the demand increase in Metro Manila
and reduce the loads at Doña Imelda and Taytay Substations, which have expansion
constraints.
Presently, there are three main load sectors within Metro Manila:
a. Sector 1 is served through Quezon, Paco and Marilao (Duhat) Substations. Both
Paco and Marilao (Duhat) Substations are MERALCO-owned;
b. Sector 2 is served through Taytay and Doña Imelda 230 kV Substations; and
c. Sector 3 is served through Muntinlupa and Las Piñas 230 kV Substations.
14
The major supply lines for both Quezon and Taytay are the double-circuit 230 kV line from San
Jose as these substations rely heavily on the supply from San Jose 500 kV Substation.
In the south, the power requirements are being drawn from Dasmariñas 500 kV Substation and
from power plants directly connected to the 230 kV system. Las Piñas is connected through a
double circuit 230 kV radial line from Dasmariñas, while Muntinlupa has four-circuit supply line
from Biñan.
The southern portion of the 500 kV transmission backbone stretches from Naga Substation in
Bicol Region to Tayabas, Quezon. Tayabas is also connected to San Jose thereby completing
the link between the north and south 500 kV transmission corridors.
Legend:
69 kV
115 kV
230 kV
350 kV HVDC
500 kV
The 500 kV backbone segment from Tayabas to Naga Substation is currently energized at 230
kV. The Naga Substation is also the termination point for the HVDC Interconnection System that
could allow the exchange of power for up to 440 MW between Luzon and the Visayas Grids.
The 500 kV backbone in the south facilitates the transfer of about 2,400 MW from Ilijan Natural
Gas, Pagbilao and QPPL CFPP. The 230 kV transmission system in Batangas and Laguna area
caters more than 2,500 MW total generation capacity of Calaca CFPP, new coal-fired power
plants and the other Natural Gas Plants (San Lorenzo and Sta. Rita).
From Tayabas Substation, the 500 kV backbone also stretches to Dasmariñas Substation which
serves as a drawdown substation for the loads in the south of Metro Manila.
15
3.4 Visayas Transmission Network
The Visayas transmission system is divided into five different sub-system or sub-grids: Panay,
Negros, Cebu, Bohol and Leyte-Samar. The sub-grids are interconnected by AC submarine
cables as follows with indicated capacity: Leyte-Cebu (2x185 MW), Cebu-Negros (2x90 MW),
Negros-Panay (1x85 MW) and Leyte-Bohol (1x90 MW). These submarine cables provide the
capability of sharing excess generation between islands to accommodate the Visayas’ growing
demand.
Legend:
69 kV
138 kV
230 kV
The transmission backbone of the Visayas Grid extends from Allen Cable Terminal Station in
Samar, all the way to Nabas Substation in Panay. This power delivery system comprises
approximately 895 kilometers of transmission lines.
Eastern Visayas (District 1) is composed of Leyte and Samar Islands. Leyte remains the power
supplier to Samar and Bohol Islands through the single-circuit Ormoc-Babatngon and Ormoc-
Maasin 138 kV lines, respectively. Outage of the said lines will result in power interruption in the
affected island. Thus, projects intended to provide single outage contingency or N-1 for the said
lines are currently ongoing. Also, it has a 230 kV interconnection to Cebu enabling the other
16
islands to source power from cheaper geothermal resources. Leyte is the site of 547 MW
geothermal resources that comprise about 30% of the total dependable capacity in the Visayas.
Legend:
230 kV
138 kV
69 kV
Central Visayas (District 2) is composed of Cebu and Bohol. Cebu can be well considered as
the major load center of the Visayas Grid. In 2015, it has a coincident peak load of 921 MW
which accounted for 52% of the grid’s total demand. Bohol has the lowest peak load among
sub-grids at 70 MW (3.96%) in 2015.
Legend:
230 kV
138 kV
69 kV
17
In the Island of Negros (District 3), the load center is located in Bacolod City in the northern part,
while the bulk of generation is in the southern part. A total of 95.5 MW, generation capacity was
added in the Negros Island with the entry of San Carlos Solar, Nasulo Geothermal, URC
Bagasse Cogeneration and HPCo Bagasse Congeneration Plant from January 2014 to August
2015.
Legend:
138 kV
69 kV
Panay Island (District 4) had been reliant to oil-based plants until the entry of Panay Energy
Development Corporation (PEDC) 164 MW CFPP. Panay became less reliant on power import
from other islands via the 138 kV Negros-Panay Interconnection System and, at certain times,
also exports power to Negros. A total of 82.4 MW generation capacity was added in the Panay
Island with the entry of San Lorenzo Wind and the PetroWind Nabas last December 2014 and
June 2015, respectively.
Legend:
138 kV
69 kV
18
3.5 Mindanao Transmission Network
The Mindanao transmission system is composed of six Districts: North Western Mindanao Area
(District 1 – NWMA) covers Zamboanga area and Misamis Occidental, Lanao Area (District 2 -
LA), North Central Mindanao Area (District 3 - NCMA) includes the provinces of Bukidnon and
Misamis Oriental, North Eastern Mindanao Area (District 4 - NEMA) comprised of Agusan and
Surigao provinces, South Eastern Mindanao Area (District 5 - SEMA) is the Davao Region, and
South Western Mindanao Area (District 6 - SWMA) consists of South Cotabato, Cotabato,
Sultan Kudarat, Saranggani and Gen. Santos (SOCCSKSARGEN) and Maguindanao. While the
bulk of power generation is situated in the northern part of the island, the load centers are
located in southeast (Davao provinces) and southwest (SOCSKSARGEN) regions. Power
demand from these areas accounts to approximately half of Mindanao’s total demand.
Given this power supply-demand characteristics, much of the power flows from north to south
through the Balo-i-Tagoloan-Maramag-Kibawe 138 kV transmission corridor and the Balo-i-
Villanueva-Maramag-Bunawan backbone which is designed at 230 kV but initially energized at
138 kV.
Legend:
138 kV
Aside from the new 230 kV-designed transmission backbone, Mindanao Grid comprises mostly
of 138 kV transmission corridors, with 69 kV radial lines that traverse from the main substations
to load-end substations. Three 138 kV transmission corridors emanate from the Lanao Area,
where the biggest chunk of power supply for Mindanao is generated.
19
20
Chapter 4 – Demand Projections
The two important input parameters in the preparation of the TDP are the updated annual peak
demand forecast and generation capacity addition listed in the DOE List of Private Sector
Initiated Power Projects (PSIPP).
The demand forecast for the 2014-2015 TDP used the electricity sales and peak demand
projections of the Department of Energy (DOE) based on the aggregated forecasts of the
Distribution Utilities from the Distribution Development Plans (DDP).
Total peak demand (in MW, non-coincident sum) of the Philippines shows consistent
upward trend from 2006 to 2015 with an Average Annual Compounded Growth Rate
(AACGR) of 3.58%. Total demand growth was at its highest in 2010 (at 9.53%) while it was
at its most sluggish in 2011 (at 0.04%).
21
4.1.2.1 Luzon
MW
Luzon Grid except for the
7,500
decrease in demand observed in
2006 and 2011. This was due to 7,000
the reduction in the power 6,500
consumption of MERALCO for the
two periods brought about by the 6,000
effect of the global financial crisis
in 2006 and the effect of La Niña
phenomenon experienced in
2011. MERALCO’s demand accounts for at least 70% of the total system peak demand
(SPD) in Luzon. Further, demand growth in 2010 has been unprecedented (10.51%) –
similar double-digit growth was also observed in MERALCO’s franchise area. This was
attributed to increased economic activity brought about by election spending and the higher-
than-average growth in GDP for the year. Also, the prolonged hot temperature experienced
during the summer months brought about by El Niño have contributed to the unusual
upsurge in the Luzon SPD. Note however that this demand growth has not been sustained
in 2011. In fact, SPD has fallen by 1.36%. Demand was quick to recover though, registering
a 4.46% growth in 2012, 5.27% in 2013 and 4.96% in 2014.
4.1.2.2 Visayas
22
because the peak demand in Visayas normally occurs during the last quarter of the year
specifically between November and December. However, due to the onslaught of typhoons
during the second half of the year, majority of the electrical systems was destroyed resulting
in reduction in power demand. Typhoons Glenda, Mario, Ruby and Seniang hit Visayas in
July, September and December, respectively.
4.1.2.3 Mindanao
MW
demand growth has been sluggish 1,300
from 2005 to 2010 due to the 1,200
overall reduced power requirement
from large non-utility customers. 1,100
From 2005 onwards, the historical 1,000
growth in the Mindanao Grid has
been volatile with alternating
periods of rise and decline.
Drop in demand occurred in 2005, 2008, 2010 and 2012. 2005 was characterized by
reduced demand from distribution utilities while 2008 was characterized by the large
decrease in the demand of non-utility customers, possibly a direct effect of the global
financial crisis which adversely affected exporting industries. On the other hand, suppressed
generation impeded demand growth in 2010 and 2012. This is due to the El Niño
phenomenon that hampered hydropower generation, which comprises about half of the
Grid’s installed capacity. Mindanao power demand recovered in the recent years and grew
by 8.1% in 2013 and 2.9% in 2014.
Power demand for the country is expected to grow at an AACGR of 4.35% for the period
2016-2020 and 4.05% for 2021-2025. It is projected that Mindanao will have the highest
AACGR compared with the other Grids. Mindanao is forecasted to reach an AACGR of 5.9%
for 2016-2025 while the Luzon and Visayas Grids at 3.99% and 3.61%, respectively. The
peak demand used for Luzon in 2015 is the actual year-to-date peak demand of 8,928 MW
which occurred in May. The table below shows the projected demand disaggregated per
district based on the transformer peak demand coincident with the System Peak. It was
derived from the DOE Forecast as of 11 September 2015 based on the generation level.
23
3
Table 4.2: Summary of Projected Demand per District (MW)
District Area 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Luzon 9,127 9,474 9,934 10,368 10,821 11,249 11,694 12,164 12,657 13,161
MERALCO 6,764 7,047 7,294 7,561 7,822 8,107 8,404 8,716 9,029 9,356
1 NCR 4,745 4,943 5,117 5,304 5,486 5,686 5,894 6,114 6,333 6,563
2 North 294 307 317 329 340 352 365 378 392 406
3 South 1,725 1,797 1,860 1,928 1,995 2,068 2,144 2,224 2,304 2,387
North Luzon 1,824 1,876 2,063 2,204 2,361 2,474 2,588 2,710 2,850 2,987
1 Ilocos 160 162 173 181 191 199 208 217 228 238
2 Mt. Province 151 155 165 172 183 191 200 209 220 231
3 North Central 197 200 237 249 264 276 290 303 319 334
4 Cagayan Valley 206 214 229 240 255 267 281 295 311 327
5 West Central 322 332 359 381 409 431 455 488 524 560
6 South Central 716 739 821 897 971 1,018 1,056 1,094 1,138 1,181
7 North Tagalog 72 74 79 83 88 93 98 103 110 116
South Luzon 539 552 577 603 638 667 702 737 778 818
1 Batangas/Cavite 250 254 264 274 288 298 311 325 340 355
2 Laguna /Quezon 86 88 92 96 102 106 112 118 124 131
3 Bicol 204 210 222 234 249 263 279 295 314 332
Visayas 1,699 1,762 1,823 1,885 1,945 2,011 2,079 2,150 2,223 2,320
1 Panay 279 290 300 310 320 330 341 353 365 380
2a Cebu 879 912 943 975 1,006 1,040 1,075 1,112 1,150 1,200
2b Bohol 68 71 73 76 78 81 83 86 89 93
3 Leyte-Samar 196 203 211 218 225 232 240 249 257 269
4 Negros 276 287 297 307 316 327 338 350 362 378
Mindanao 1,669 1,803 1,927 2,044 2,141 2,229 2,320 2,415 2,512 2,658
1 North Western 211 217 235 255 270 282 295 308 324 343
2 Lanao Area 162 176 192 203 212 223 231 239 249 264
3 North Central 278 364 379 394 407 418 430 441 454 473
4 North Eastern 156 161 183 198 209 224 243 262 274 292
5 South Eastern 591 605 643 682 717 744 771 800 833 886
6 South Western 272 278 296 313 326 338 350 363 378 400
Philippines 12,494 13,038 13,684 14,296 14,906 15,487 16,092 16,727 17,392 18,138
3
Based on the transformer peak demand coincident with the System Peak.
Based on NGCP System Peak Forecast as derived from DOE Forecast Levels, excluding applicable losses
The demand projections for substation expansion take off from the per meter forecast
undertaken by NGCP. Forecast energy deliveries per metering point are derived from
historical trends and/or information as to the potential expansion or contraction of demand
of Grid-connected customers. Inputs are sought from customers in this bottom-up process
to incorporate their expansion plans.
Projected monthly energy deliveries (in MWh) to metering points connected to a given
transformer are then summed up. Accounting adjustments for technical losses and
substation use to this sum, the monthly per transformer energy delivery forecast (in MWh)
is derived. The forecast transformer peak (in MW) is then calculated by applying the
appropriate load factor to these energy delivery projections. This transformer peak
becomes the basis for adding transformer capacities at the substations.
24
4.2.2 Demand Projections for Transmission Expansions
The SPD projections for each Grid are used in determining the necessary transmission
expansion projects. However, for these figures to be usable in the power system analysis
software, it has to be broken down into individual transformer loads. First, the embedded
generation during system peak is subtracted from the SPD to come up with the non-
embedded peak. Then the individual transformer maximum demand projections during the
month when the system peak usually occurs (as determined in the previous section) are
used to establish the percent share to arrive at the non-embedded peak that will be
assumed for a specific transformer.
Visayas Panay Island (130 MW), Negros Island (225 MW), Cebu Island
(85 MW), Leyte (150 MW)
Mindanao Zamboanga del Sur (170 MW), Zamboanga del Norte (25 MW),
Lanao del Norte (8 MW), Misamis Oriental (60 MW), Bukidnon (8
MW), Surigao del Norte (60MW), Surigao del Sur (2 MW),
Agusan del Sur (30 MW), Agusan del Norte (55 MW), Davao del
Sur (20 MW), Compostela Valley (50 MW), Cotabato (40 MW),
South Cotabato (65 MW), Sultan Kudarat (75 MW)
25
26
Chapter 5 – Generation Capacity Addition
This section shows the additional capacities and proposed generating plants in Luzon, the
Visayas and Mindanao Grids based on DOE Power Outlook 2015-2020 as of August 2015.
The DOE has also provided the list of generating plants that already have clearance to
undertake System Impact Study (SIS) but are not included yet in the said DOE Power Outlook
since the reports on the status of their development are not yet submitted. This list will fall under
the new classification named as the Prospective Projects. Thus, there will be three generation
project classifications, as follows:
a. Committed – These are projects that have service contracts in place, are in the
development/commercial stage and have reached financial closure already and have
been declared as “committed” by the DOE.
b. Indicative – Projects with service contracts, in the development/ commercial stage but
with no financing yet.
c. Prospective – Projects with DOE clearance to undertake SIS and service contracts and
on the predevelopment stage. These projects are not included in the official list of
DOE’s Private Sector Initiated Power Projects. (Refer to Appendix 1 for the generation
list).
It is worth noting that the proponents should regularly update the DOE on their plans and
updates regarding the status of their projects for monitoring and inclusion in the official list of
DOE’s PDP Generation Projects. Proponents are advised to regularly coordinate with the DOE’s
Electric Power Industry Management Bureau (EPIMB).
Table 5.1 shows the additional capacities from 01 January 2014 to 15 August 2015.
27
Table 5.1: List of Additional Capacities from 01 Jan 2014 to 15 Aug 2015
Installed Dependable
Commercial
Power Plant Location Capacity Capacity
Operation
(MW) (MW)
LUZON
Maibarara Geothermal Power Sto. Tomas, Batangas 20 18.6 Feb 2014
Lafarge DPP Taysan, Batangas 12.7 12 July 2014
Bangui Bay Wind Phase 3 Bangui, Ilocos Norte 18.9 12.6 Oct 2014
Burgos Wind Burgos, Ilocos Norte 150 45 Nov 2014
SJCiPower Biomass San Jose, Nueva Ecija 12 10 Oct 2014
Caparispisan Wind Pagudpud, Ilocos Norte 81 28 Nov 2014
Raslag Solar^ Pampanga 10 8.5 Feb 2015
Majestic CEZ Solar Cavite 41.3 20 Mar 2015
Burgos Solar^ Burgos, Ilocos Norte 4.1 4 Mar 2015
SLTEC Puting Bato Coal Unit 1 Calaca, Batangas 135 123 Apr 2015
Sinoma Waste Heat Recovery
San Jose, Antipolo 6 5.7 Apr 2015
Facility*
SPCRPI SM North* Quezon City 1.5 1.5 Apr 2015
Millennium Gas** Navotas, Metro Manila 100 80 May 2015
Sabangan HEPP Sabangan, Mt. Province 14 4 Jun 2015
Pililia Wind^ Pililia, Rizal 54 48.6 Jul 2015
Sub-total (Luzon) 660.5 421.5
VISAYAS
San Carlos City, Negros
San Carlos Solar Phase 1 13 9 May 2014
Occidental
San Carlos City, Negros
San Carlos Solar Phase 2 9 7.5 Aug 2014
Occidental
Nasulo Geothermal Valencia, Negros Oriental 49.37 40 Sep 2014
San Lorenzo Wind San Lorenzo, Guimaras 54 50 Dec 2014
URC Bagasse Cogeneration Facility Kabankalan, Negros
40 36 Jan 2015
Phase 1 Occidental
HPCo Bagasse Cogeneration Silay City, Negros Occidental 12 3 Feb 2015
PSFLI (SOLEQ) Solar Ormoc, Leyte 30 24 Apr 2015
PetroWind Nabas Wind Nabas, Aklan 36 32.4 Jun 2015
TPC – 1A Coal Toledo City, Cebu 82 75.9
Sub-total (Visayas) 325.37 277.8
MINDANAO
Brgy. Apopong, Gen. Santos
SoEnergy DPP^ 19 18.05 Mar 2014
City, South Cotabato
MPC-Digos DPP^ Digos, Davao del Sur 15 14.25 Mar 2014
Panaon, Ozamis City, Misamis
KEGI-Panaon DPP^ 15 13.6 May 2014
Occ.
Tudaya 1 Hydro^ Sta. Cruz, Davao del Sur 6.6 6.53 May 2014
Tudaya 2 Hydro^ Sta. Cruz, Davao del Sur 7 6.93 May 2014
KEGI Tandag^ Tandag, Surigao 7.5 6 Oct 2014
Mapalad Energy DPP^ Iligan City 15 14.25 Dec 2014
Brgy. Apopong, Gen. Santos
Peak Power (PSI) DPP^ 20.9 19.6 Jan 2015
City
Peak Power (PSFI) DPP^ San Francisco, Agusan del Sur 5.9 5 Feb 2015
Sub-Total (Mindanao) 111.9 104.21
It can be noted that the list includes small capacity plants which may not actually connect
directly to NGCP. For relatively small capacity power plants connecting to the distribution
system, the main impact is a slight reduction in the power being drawn by the Distribution Utility
from NGCP substations and would not generally require reinforcement in the transmission
network.
Also, there are power plant projects in the DOE list with no connection application yet to NGCP
or with no System Impact Study (SIS) yet.
Table 5.3(a): List of Luzon Generation Capacity Addition
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
COMMITTED POWER PLANTS
COAL
SLPGC Coal Phase 1* 300 Brgy. San Rafael, Calaca, Batangas 2016
Anda Power Coal* 82 Brgy. Bundagul, Mabalacat, Pampanga 2016
Limay Coal Phase 1 Unit 1* 150 Brgy. Lamao, Limay, Bataan 2016
Limay Coal Phase 1 Unit 2* 150 Brgy. Lamao, Limay, Bataan 2017
Pagbilao Power Station, Brgy. Ibabang Polo,
Pagbilao 3 Coal* 420 2017
Pagbilao, Quezon
GN Power Dinginin Expansion Unit 1* 600 Mariveles, Bataan 2018
San Buenaventura (SBPL) Coal* 460 Mauban, Quezon 2019
GN Power Dinginin Expansion Unit 2* 600 Mariveles, Bataan 2020
Sub-Total Coal 2,762
BIOMASS
ACNPC WTE Biomass 1.5 Tarlac City, Tarlac 2016
GIFTC Biomass* 10.8 Muñoz, Nueva Ecija 2016
Bicol Biomass Energy Corp* 4.5 Pili, Camarines Sur 2016
Biogas Power Plant 6.1 Batangas 2016
SJCiPower Rice Husk-Fired Phase 2 10.8 Brgy. Tulat, San Jose, Nueva Ecija 2017
Sub-Total Biomass 33.7
NATURAL GAS
Pagbilao Combined Cycle 600 Brgy. Ibabang Polo, Pagbilao, Quezon 2016
San Gabriel Avion Project* 100 Brgy. Bolbok, Batangas 2016
San Gabriel Project* 450 San Gabriel, Batangas 2016
Sub-Total Natural Gas 1,150
HYDRO
Kapangan HEPP* 60 Kapangan and Kibungan, Benguet 2019
Bulanao HEPP 1 Tabuk, Kalinga 2019
Prismc HEPP 1 Rizal, Nueva Ecija 2019
Magat A 1.4 Ramon, Isabela 2020
Magat B 1 Ramon, Isabela 2020
Tubao Mini Hydro 1.5 Tubao, La Union 2020
Sub-Total Hydro 65.9
SOLAR
29
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
Currimao Solar* 20 Currimao, Ilocos Norte 2016
Macabud Solar* 30 Brgy. Macabud, Rodriguez, Rizal 2016
San Rafael Solar 3.82 San Rafael, Bulacan 2016
Morong Solar 5.02 Morong, Bataan 2016
Cabanatuan Solar 10.06 Cabanatuan City, Nueva Ecija 2016
Palauig Solar 5.02 Morong, Bataan 2016
Sta. Rita Solar 100.44 Morong and Hermosa, Bataan 2016
YH Green 14.5 Hermosa, Bataan 2016
Tarlac Solar 50 Tarlac City, Tarlac 2016
Calatagan Solar 46.78 Calatagan and Balayan, Batangas 2016
Sub-Total Solar 285.64
GEOTHERMAL
Bacman 3 (Tanawon) 31 Guinlajon, Sorsogon 2017
Maibarara 2 Geothermal 12 Batangas 2017
Sub-Total Geothermal 43
31
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
Brgy. Balaoi and Caunayan, Pagudpud, Ilocos
Pagudpud Wind 84 2018
Norte
Sub-Total Wind 249
BIOMASS
GGREC Rice Husk-Fired Biomass 10.8 Nueva Ecija 2018
Sub-Total Biomass 10.8
BATTERY
AES Battery 10 Masinloc, Zambales 2016
AES Battery 40 Laoag, Ilocos Norte TBD
AES Battery 40 Bantay, Ilocos Norte TBD
Sub-Total Battery 90
32
Figure 5.1(b): Luzon Generation Capacity Addition (Renewable Energy Plants)
33
Figure 5.1(c): Luzon Generation Capacity Addition (Hydroelectric Power Plants)
34
Table 5.3(b): List of Visayas Generation Capacity Addition
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
COMMITTED POWER PLANTS
COAL
PEDC Expansion 150 Brgy. Ingore, La Paz, Iloilo 2016
Concepcion Coal Unit 1* 135 Brgy. Nipa, Concepcion, Iloilo 2016
Concepcion Coal Unit 2* 135 Brgy. Nipa, Concepcion, Iloilo 2018
Sub-Total Coal 420
OIL-BASED
Brgy. Calumangan,Bago City, Negros
Calumangan Diesel* 18.9 2016
Occidental
Sub-Total Oil-Based 18.9
HYDRO
Villasiga HEPP* 8 Brgy. Igsoro, Bugasong, Antique 2016
Igbulo (Bais) Hydro* 5.1 Igbaras, Iloilo 2018
Cantakoy HEP* 8 Danao, Bohol 2018
Amlan 0.8 Amlan, Negros Oriental 2019
Sub-Total Hydro 21.9
WIND
Nabas Wind* 14 Brgy. Pawa, Nabas Aklan 2017
Sub-Total Wind 14
GEOTHERMAL
2016
Biliran Geothermal* 50 Biliran, Biliran
2017
Sub-Total Geothermal 50
SOLAR
La Carlota Solar Phase A*
18 La Carlota City, Negros Occidental 2016
(SACASOL II-A)
Brgy. Tinampa-an, Cadiz City, Negros
Cadiz Solar* 132.5 2016
Occidental
Miag-ao Solar* 5.67 Miag-ao, Iloilo 2016
Manapla Solar (SACASOL III) 48 Manapla, Negros Occidental 2016
Bais Solar (SACASOL IV) 25 Bais City, Negros Occidental 2016
La Carlota Solar Phase A
14 La Carlota City, Negros Occidental 2016
(SACASOL II-B)
SACASUN Solar 58.98 San Carlos City, Negros Occidental 2016
Sub-Total Solar 302.15
35
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
SOLAR
Tigbauan Solar 30.2 Tigbauan, Iloilo 2016
Biliran Solar 48 Biliran, Biliran 2016
E&P Green Energy Solar 25 Biliran, Biliran 2016
Ceko Solar 100 Brgy. Tominjao, Daan Bantayan, Cebu TBD
First Toledo Solar 60 Toledo City, Cebu TBD
Sub-Total Solar 263.2
WIND
Pulupandan Wind 50 Pulupandan, Negros Occidental 2016
Sub-Total Wind 50
HYDRO
Timbaban Hydro* 18 Madalag, Aklan 2018
Loboc Hydro 1.2 Loboc, Bohol 2018
Hilabangan (Upper Cascade) 4.8 Kabankalan, Negros Occidental 2018
Hilabangan (Lower Cascade) 3 Kabankalan, Negros Occidental 2018
Main Aklan River Hydro 15 Libacao, Aklan 2018
Maninila (Lower Cascade) 4.5 San Remigio, Antique 2018
Maninila (Upper Cascade) 3.1 San Remigio, Antique 2018
Sibalom (Upper Cascade) 4.2 San Remigio, Antique 2018
Sibalom (Middle Cascade) 4 San Remigio, Antique 2018
Sibalom (Lower Cascade) 4 San Remigio, Antique 2018
Basak II 0.5 Badian, Cebu 2019
Amlan* 5.5 Amlan, Negros Oriental 2019
Malugo 6 Silay City. Negros 2019
Lower Himogaan 4 Sagay, Negros Occidental 2020
Caroan 0.84 Sebaste, Antique 2020
Ipayo 0.84 Sebaste, Antique 2020
Ilaguen 4 10 Echague 2020
Bansud 1.5 Bansud & Gloria, Oriental Mindoro 2020
Sub-Total Hydro 90.98
BIOMASS
Mina Multi-Fuel Biomass Phase 1* 16.5 Iloilo 2017
Mina Multi-Fuel Biomass Phase 2* 16.5 Iloilo 2018
MCEI Multi-Feedstock Biomass 12 Negros Occidental 2018
MCEI Risk Husk-Fired Biomass 2.25 Leyte 2018
Sub-total Biomass 47.25
BATTERY
AES Battery Storage* 40 Kabankalan, Negros Occidental 2016
Sub-Total Battery 40
36
Figure 5.2(a): Visayas Generation Capacity Addition (Conventional Power Plants)
37
Figure 5.2(b): Visayas Generation Capacity Addition (Renewable Energy Plants)
38
Figure 5.2(c): Visayas Generation Capacity Addition (Hydroelectric Power Plants)
39
Table 5.3(c): List of Mindanao Generation Capacity Addition
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
COMMITTED POWER PLANTS
COAL
Southern Mindanao Phase 1* 100 Brgy. Kamanga, Maasim, Sarangani 2016
SMC Davao Phase 1* 300 Brgy. Culaman, Malita, Davao del Sur 2016
Phividec Industrial Estate, Villanueva, Misamis
FDC-Misamis Coal* 405 2016
Oriental
Brgy. Mandangoa, Balingasag, Misamis
Balingasag Thermal Power Plant* 165 2017
Oriental
GNPower Kauswagan Ltd.* 540 Kauswagan, Lanao del Norte 2018
Southerm Mindanao Phase 2* 100 Brgy. Kamanga, Maasim, Sarangani TBD
Sub-Total Coal 1,610
DIESEL / OIL
Purok Garfin, Brgy. Paraiso, Koronadal, South
SPC Koronadal Diesel* 11.9 2016
Cotabato
PSFI Bunker Fired 2.5 San Francisco, Agusan del Sur 2016
PSI Bunker Fired 13.94 General Santos City, South Cotabato 2016
PBI Bunker Fired 10.4 Manolo Fortich, Bukidnon 2017
Sub-Total Diesel / Oil 38.74
BIOMASS
PTCI Rice Husk-Fired Biomass 1.6 Maguindanao 2016
GEEC Biomass Cogeneration System 2.6 Maguindanao 2016
LPC Rice Husk-Fired Biomass* 10 Maguindanao 2016
Sub-Total Biomass 14.2
HYDRO
Lake Mainit* 25 Jabonga, Agusan del Norte 2016
Puyo Hydro 30 Jabonga, Agusan del Norte 2018
Asiga HEPP 8 Santiago, Agusan del Norte 2019
Manolo Fortich 1* 43.4 Santiago, Bukidnon 2019
Manolo Fortich 2* 25.4 Santiago, Bukidnon 2019
Sub-Total Hydro 131.8
SOLAR
Kibawe Solar 10.49 Brgy. Labuagon, Kibawe, Bukidnon 2016
Digos Solar Phase I 10 Brgy. San Roque, Digos City, Davao del Sur 2016
Digos Solar Phase II 19.58 Brgy. San Roque, Digos City, Davao del Sur 2016
Sub-Total Solar 40.07
TOTAL COMMITTED 1,834.81
40
Proposed Generation Facility / Capacity Comm.
Location
Name of the Project (MW) Year
Sub-Total Solar 166
HYDRO
Bubunawan Hydro 23 Baungon and Libona, Bukidnon 2016
Limbatangon Hydro 9 Cagayan de Oro, Misamis Oriental 2018
Tagoloan 39 Impasugong & Sumilao, Bukidnon 2018
Culaman Hydro* 10 Manolo Fortich, Bukidnon 2018
Cabadbaran Hydro* 9.8 Cabadbaran, Agusan del Norte 2018
Tumalaong Hydro 9 Baungon, Bukidnon 2018
Cabulig-2 Hydro 10 Jasaan, Misamis Oriental 2019
Pasonanca 0.5 Zamboanga City 2019
Clarin* 5 Clarin, Misamis Occidental 2019
Mat-i-1* 2 Claveria, Cagayan de Oro 2019
Mat-i-2* 1.6 Cagayan de Oro, Misamis Oriental 2019
Mat-i-3* 3.25 Cagayan de Oro, Misamis Oriental 2019
New Bataan 2.4 New Bataan, Compostela Valley 2019
Mangima Hydro 10 Manolo Fortich, Bukidnon 2019
Maladugao River (Upper Cascade) 5.5 Wao, Bukidnon 2020
Maladugao River (Lower Cascade) 10 Kalilangan & Wao, Bukidnon 2020
Lanon (Lam-alu) 9.5 Lake Sebu, South Cotabato 2020
Silo-o* 3.29 Malitbog, Bukidnon 2020
Pantar & Balo-I, Lanao del Sur & Lanao del
Agus III 225 2020
Norte
Malitbog 17.85 Malitbog, Bukidnon 2020
Maramag 1.4 Maramag, Bukidnon 2020
Manupali 9 Valencia, Bukidnon 2020
Pulanai 9 Valencia, Bukidnon 2020
Kitaotao1 150 Bukidnon 2021
Sub-Total Hydro 575.09
BIOMASS
Kalilangan Bio-Energy 9 Bukidnon 2016
Don Carlos Bio-Energy 9 Bukidnon 2016
EPC Woody Biomass* 21 Agusan del Norte 2017
Malay-balay Bio-Energy 9 Bukidnon 2017
Biomass Power Plant 10.8 Misamis Oriental 2017
Napier Grass-Fired Biomass 10.8 Bukidnon 2018
Sub-Total Biomass 69.6
OXYFUEL GAS
Bislig 1 Oxyfuel-Gas 1 Brgy. Kahayag, Bislig City, Surigao del Sur 2016
Bislig 2 Oxyfuel-Gas 4 Brgy. Kahayag, Bislig City, Surigao del Sur 2016
Sub-Total Oxyfuel 5
41
Figure 5.3(a): Mindanao Generation Capacity Addition (Conventional Power Plants)
42
Figure 5.3(b): Mindanao Generation Capacity Addition (Renewable Energy Plants)
43
Figure 5.3(c): Mindanao Generation Capacity Addition (Hydroelectric Power Plants)
44
5.2 Renewable Energy
NGCP allocates this section for the development and plans associated with the entry of
Renewable Energy (RE). Discussed here are the transmission planning approach with RE,
present concerns and the activities of NGCP in support to RE.
In developing transmission expansion plans for the grid, every project included in the TDP is
evaluated to meet the following objectives:
a. Ensure the reliability and stability of the grid
b. Grid demand requirements are met by available supply
c. Minimize the cost of transmission investments passed-through to end-consumers
d. Minimize the cost of energy by providing more opportunities for competition and
mitigating market congestions
The same objectives are given with the addition of RE. The RE Act of 2008 mandates NGCP to
include the required connection facilities for RE-based power facilities in the TDP. The Feed-in
Tariff (FIT) rules strengthens this mandate by giving eligible RE plants priority connection to the
transmission or distribution system, subject to their compliance to the pertinent standards and
ERC rules governing such connection. This, however, provides further challenges in
transmission planning faced by NGCP.
First challenge is the proximity of transmission facilities and its available transfer capacity to
Variable Renewable Energy (VRE) potential areas. These are applicable to site-specific VREs
located far from load centers. Although there are some areas that are near transmission
facilities, these are not designed to accommodate the potential capacity of VRE. As a result,
long transmission lines were needed to be built.
Second is the shorter timeline of VRE projects compared to transmission expansion projects.
Actual construction timeline of VRE projects has proven that it can be completed faster
compared to transmission projects. Aggravated by the “first come first serve” policy of the FIT
scheme, VRE proponents are somewhat in a race to secure an allocation to the installation
targets. Consequently, the transmission expansion projects need to catch-up with the
completion VRE projects.
Though recognized, NGCP cannot simply advance the implementation of transmission facilities
without the confirmation of VRE proponent. Transmission investments shall still conform to the
Rules for Setting Transmission Wheeling Rates (RTWR) and the principles contained therein,
the optimization principle among one of them. At this regulation, NGCP transmission facility
could be exposed to the risk of being optimized down if the VRE proponent decided not to
pursue with their project. As a result in some cases, the VRE proponent had to advance the
transmission investment and later to be transferred to NGCP subject to reimbursement upon
ERC approval.
Third challenge is the grid connection and operational requirements for VRE. The latest
Philippine Grid Code after the approval of the RE Act of 2008 only covers the rules and
requirements for conventional generators. With the limited experience on VRE, creating and
setting the proper requirements for VRE was a big challenge. The goal was to set the necessary
requirements to make VRE behave like a conventional power plant. Positively, the Addendum to
45
the Amendment no.1 of the Grid Code was approved in 2013, containing the requirements for
VRE, particularly wind and solar.
In the RE Act of 2008, NGCP is required to determine a maximum penetration limit to the grid of
intermittent or variable RE. NGCP and PEMC are also tasked to implement technical mitigation
and improvements in the system in order to ensure safety and reliability of electricity
transmission.
Starting with the limited knowledge on grid integration of VRE, NGCP was in an interesting
position. With continuous research and workshops, NGCP has determined how to analyze the
effect of VRE to the grid in its study called the Renewable Energy Integration Study. Here, the
variability of the net load or residual load (load minus VRE) was analyzed and compared to the
availability of regulating reserves.
However, the availability of accurate data to come up with a credible study gave further
challenge to NGCP. NGCP initially requested the resource assessment data of VRE proponents
and used it as substitute to actual data. NGCP had reservations on whether the results of the
study would actually provide the safe level of VRE penetration. With this uncertainty, NGCP will
update the study using actual VRE data.
With the given challenges in transmission planning, there are already present concerns
experienced by NGCP with the fast phase development of VRE.
The present situation in the Visayas Grid provides a good example. As of April 2016, a total of
455 MW capacity of VREs is already installed where 90 MW capacity is from wind and 370 MW
capacity is from solar PVs. At certain periods, VREs supply about 13% of the load which leads
to the increase of net-load variability. With no providers of frequency regulation, only the HVDC
link to Luzon delivers the needed flexibility but also has operating limitations particularly the
minimum stable loading and the standby time to reverse the direction of power flow. In some
instances, the scheduled HVDC power flow from the market is already near its minimum stable
loading that further response due to the variability could not anymore be accommodated, i.e.,
HVDC cannot further be used as frequency control. The next option of the System Operator is
to adjust the scheduled generation from the merit order dispatch. But there are also instances
that the HVDC is needed to reverse the direction of power flow. Given the 10-minute standby
time, the Visayas Grid is left without any flexible support, which makes the task of the System
Operator even more challenging.
Further in the Visayas Grid, most of the solar PVs are located in Negros Island. The
concentration of Solar PV in Negros Island led to transmission congestion at certain dispatch
schedules due to the limited capacities of existing submarine cable interconnections. This
signifies the need to properly integrate generation and transmission planning to avoid or at least
mitigate the likelihood of such situations.
There are also some issues with VRE in Luzon Grid but are only local issues. Voltage
fluctuations are experienced at the wind farm side in North Luzon when there are prolonged
outages of one circuit of adjacent parallel lines. This is caused by the reduction of the short-
circuit level or the strength of the grid at the connection point which makes the voltage sensitive
to generation variability. To mitigate the issue, the System Operator had developed an
46
operational guideline to limit the total output of the wind farms during prolonged outages of one
circuit of adjacent parallel lines.
Based on other jurisdictions, there are no studies involving the determination of such maximum
penetration limit but rather on the optimistic side; what are the needed changes to the grid to
integrate a certain target of VRE. With this, NGCP will conduct a new integration study based on
the experience and challenges. NGCP has conceptualized an approach that will not only
analyze the variability of VRE but also geographic grid adequacy involving these potential areas
of VRE and the system inertia and frequency response. These three areas will provide a clearer
integration study to the grid.
The geographic grid adequacy study intends to determine the maximum amount of VRE in
potential areas that can be connected without violating static thermal, voltage limits and stability
limits. The study will also include the required transmission expansion projects to increase the
capacity. The results of this study are intended to be part of the next TDP update. Furthermore,
the results of this study will provide a guide to the most plausible areas to connect to the grid.
The inertia and frequency response study intends to determine a limit on the penetration of
“inertia-less” generation in each of the regional grid. This study will assess the frequency
response of the grid on a certain amount of VRE penetration. The result of the study will provide
a basis on when to require operating restrictions on VRE, particularly on the amount and
delivery of power sourced from VREs during contingencies.
Lastly, the reserve adequacy study that is previously known as the Renewable Energy
Integration Study intends to analyze of VRE variability and review the existing reserve
requirements under the Ancillary Services Procurement Plan (ASPP). It is needed to revisit
ASPP given that the conventional generator would not follow only the load but rather the
residual or net load (load minus VRE). As previously mentioned on the availability of accurate
data, NGCP is closely monitoring and recording all the data from the recently installed VRE
generators for this study. The result of the study would provide how much VRE capacity can be
accommodated using the existing requirements for reserves and how much additional reserves
should be scheduled to accomodate more VREs.
Coincidently, a new initiative called “Greening the Grid Project” by the United States Agency for
International Development (USAID) and National Renewable Energy Laboratory (NREL) have
been conducting an RE Integration Study for the DOE. The project involves the concerned
agencies, i.e., DOE, NGCP, GMC and PEMC to work together for a collaborative study. The
study will develop a production cost model which is needed to conduct a system-wide
economic analysis. The investments needed for flexible generation and transmission
infrastructure are among the outputs of the study, which is targeted to be completed in 2017.
NGCP sees that this initiative will complement its proposed studies, particularly the geographic
grid adequacy and reserve study with the help of the experts from NREL. After the completion
of the project, NGCP can use the results of this study to know what aspects it can focus on in
its planned studies discussed above.
47
5.2.4 Renewable Energy Developments with Certificate of Confirmation of Commerciality
Among the concerns for the renewable energy development, especially the large capacity
plants, is the adequacy of the transmission line capacity especially for cases where several
renewable energy plant projects are concentrated in one area only. While transmission projects
are already being proposed, the completion of transmission projects would take longer time,
about 3 to 5 years, compared with the duration of power plant construction.
In the table below, the major RE projects with Certificate of Confirmation of Commerciality1 are
summarized together with the required grid reinforcement and its timing.
Target Date
Declared
Of Required Grid
Region Location Project Name Capacity ETC
Commercial Reinforcement
(MW)
Operation
1
From DOE: List of Major RE Projects with Certificate of Confirmation of Commerciality
48
Target Date
Declared
Of Required Grid
Region Location Project Name Capacity ETC
Commercial Reinforcement
(MW)
Operation
Table 5.4b Major RE projects with Certificate of Confirmation of Commerciality in the Visayas
Target Date
Declared
Of Required Grid
Region Location Project Name Capacity ETC
Commercial Reinforcement
(MW)
Operation
Victorias
City, Victorias Solar Power
VI 2018 30.63 CNP Stage 3 2020
Negros Project
Occidental
Pulupanda
Pulupandan Wind
VI n, Negros 2018 50 CNP Stage 3 2020
Power Project
Occidental
Nabas,
Aklan I Wind Power CNP Stage 3 / 2020/
VI Malay, 2018 24.75
Project Phase I Panitan-Nabas Line 2 2018
Aklan
49
Target Date
Declared
Of Required Grid
Region Location Project Name Capacity ETC
Commercial Reinforcement
(MW)
Operation
Main Aklan River
Libacao , September
VI Hydroelectric Power 15 CNP Stage 3 2020
Aklan 2018
Project
Madalag , Timbaban Hydroelectric
VI May 2018 18 CNP Stage 3 2020
Aklan Power Project
50
Target Date
Declared
Of Required Grid
Region Location Project Name Capacity ETC
Commercial Reinforcement
(MW)
Operation
Manolo Fortich 2
Santiago, October
X Hydroelectric Power 25.4 Manolo Fortich S/Y 2017
Bukidnon 2019
Project
Iligan City,
Bayug Hydroelectric
X Lanao del 2022 17.81 None
Power Project
Norte
Jabonga,
XIII Agusan del Lake Mainit March 2016 25 None
Norte
Jabonga ,
Puyo Hydroelectric
XIII Agusan del July 2018 30 None
Power Project
Norte
5.3.1 Coal
The Philippines is largely a coal consuming country with coal having the highest contribution to
the power generation mix at 44.5% in 2015. The Philippines has a vast potential for coal
resources just awaiting full exploration and development to contribute to the attainment of the
country's energy self-sufficiency program. As of 31 December 2015, our in-situ coal reserves
amount to 470 million metric tons or 19.7% of the country's total coal resource potential of 2.39
billion metric tons2.
AREA MUNICIPALITIES
1 Cagayan Valley Benito Soliven Cauyan Gattaran
Iguig
2 Cebu Asturias Catmon Naga
Balamban Compostela Oslob
Boljoon Dalaguete Pinamungahan
Carmen Danao Toledo City
3 Davao Manay Tarragona
4 Masbate Cataingan Palanas
5 Mindoro Bulalacao San Jose
6 Negros Bayawan City Calatrava
7 Bicol Bacon Gubat Rapu-Rapu
8 Catanduanes Bagamanoc Caramoran Panganiban
2
As discussed in the DOE website. Data in Tables 5.5 and 5.6 are provided by DOE.
51
AREA MUNICIPALITIES
9 Quezon Bordeos Polillo
10 Antique Caluya
11 Surigao Alegria Guigaquit San Miguel
Bacuag Kicharao Tago
Bislig City Lingig Tandag
Cagwait Marihatag
12 Zamboanga Buug Ipil Payao
Diplahan Kabasalan Siay
Godod Malangas
Imelda Naga
13 Sarangani Maitum
14 South Cotabato Lake Sebu
15 Sultan Kudarat Palimbang Senator Ninoy
Bagumabayan Aquino
16 Agusan Bunawan Butuan City Trento
5.3.2 Oil
Oil-based power generation contributed to 7.1% of the power generation mix in 2015. The
Philippines has 2.8 to 3.9 trillion cubic feet of proven natural gas reserves. The largest natural
gas development project in the country, Malampaya, fires three power plants with a combined
2,700 megawatts (MW) capacity with remaining reserves for an additional 300MW of power.
Other than the Malampaya gas discovery, there are still no new significant discoveries that have
been found in the country.
TOTAL RESOURCES
AREA (sq
BASIN
km)
OIL CONDENSATE GAS
(million bbl) (million bbl) (billion cubic ft)
North West Palawan 36,000 547.5 156.1 14,285
52
TOTAL RESOURCES
AREA (sq
BASIN OIL CONDENSATE GAS
km)
(million bbl) (million bbl) (billion cubic ft)
Cotabato 14,000 84 0 418
Agusan-Davao 33,000 59 1 768
Sulu Sea 115,000 130 0 405
West Luzon 16,000 0 0 129
Ilocos 19,500 0 0 106
Bicol Shelf 32,500 0 0 247
Iloilo-West Masbate 25,000 1 0 21
TOTAL 3684 173.85 33,547
Out of the total resources, 93.96% of oil resources remain undiscovered. 31.72% of condensate
and 73.61% of gas resources have yet to be discovered as well.
53
5.4 Ideal Locations of Power Plants
To serve as a guide for generation investors, this section identifies the substations where new
power plants may connect without the need for any significant transmission reinforcement.
These recommended connection points, however, should be viewed from a transmission
planning perspective and are based on the capability of the existing grid and already
considering the completion of ERC-approved projects for the 3rd Regulatory Period and without
consideration on the following other requirements in generation location siting, particularly for
the non-site specific plants: (a) fuel supply/transport; (b) topology/geology of site; (c)
accessibility; (d) availability of area; (e) availability of cooling water; (f) fresh water supply; (g)
security; and (h) environmental/social concerns.
It can be noted, however, that the existing transmission facilities in some generation potential
areas have no much room particularly in accommodating bulk generation addition. Thus, new
transmission backbone developments are usually required first for the entry of new large
capacity plants.
55
Figure 5.6: Ideal Location of Power Plants (Mindanao)
56
Chapter 6 – Power System Reliability/Security Measures and ROW Challenges
In order to improve the ability of the power system to withstand the effects of adverse
environmental conditions, natural or man-made power interruptions and other disturbances,
there is a need to further reduce the technical and human risks to minimize disruption of power
delivery service to the electricity end users. A high degree of system reliability is equivalent to a
high availability of the electricity supply service, while system security refers to the robustness of
a power system to withstand unexpected events having severe consequences3.
NGCP supports the seven Strategic Action Plans under the National Climate Change Action
Plan (NCCAP) formulated by the Climate Change Commission (CCC). Specifically, NCCAP
“Strategic Actions on Sustainable Energy for 2011 to 2028”, highlights the following facts:
b) The country continues to rely on importation to meet energy demand. Based on the 2010
DOE data, the country imports an average of 300,000 barrels per day of crude oil and
petroleum products and more than three quarters of its coal consumption;
c) The country’s total energy sufficiency, however, has been increasing from 48 % in 2001 to
59% in 2009 due to the increase in renewable energy production; and
d) Environmental sustainability and energy security are the twin energy challenges caused by
the country’s economic growth and rapid urbanization. The energy sector is a major
source of greenhouse gas emissions, whereas the transport and electricity generation are
the biggest Green House Gas (GHG) emitters.
The NCCAP further emphasized that “the energy sector has to respond to significant changes in
demand due to fluctuation in temperature and weather condition to ensure that energy systems
are able to adapt to the impacts of climate change”. Climate-proofing and rehabilitation of
energy systems infrastructures is one of the four priorities identified to address the climate
change issues of the energy sector.
a) The maximum wind velocity design of overhead transmission lines’ (OHTL) support
structures is based on three wind zones: Zone 1 (270 kph), Zone 2 (240 kph) and Zone 3
3
CIGREE-IEEE joint task force on stability terms and definitions
4
Under the Performance-Based Regulation (PBR), the economic lives of transmission assets ranges from 15 to
50 years (depending on the type of assets, e.g., transmission lines, substations, protection and
communication facilities, etc.)
57
(160 kph). In view of the increasing frequency of super typhoons that hit various areas in
the country in the past decade, NGCP will be increasing the maximum velocity design of
support structures for all OHTL including substation take-off towers and other support
structures;
b) In the transmission line route selection process, careful evaluation are undertaken to avoid
areas prone to flood, with steep slopes prone to soil erosions, and with sufficient distance
from fishponds, rivers, lakes, swamps and seashores;
c) For substation sites, the risk of flood or flash flood are carefully assessed, while avoiding
areas that are considered possible sources of pollutions, e.g., industrial plant/buildings that
generate polluted gases, storage areas for explosive or inflammable materials, bulk oil
storage tanks and oil/gas pipelines. If necessary, close proximity to seashores are also
avoided to prevent or minimize corrosions and depletion or failure of insulations of
substation equipment; and
d) For existing overhead transmission lines critical function to the grid and are located in
areas vulnerable to typhoon, the use of HV underground cables will be thoroughly
considered.
Furthermore, NGCP selects overhead transmission line routes and substation sites that have
minimal effect on human settlement or as much as possible, minimize the removal of vegetation
or cutting of trees.
Among the challenges is to keep the transmission lines free from any obstruction from
vegetation and structures that may breach safety clearance and may damage towers and lines.
Damaged towers and downed lines pose danger and can result in service interruption.
Vegetation, i.e., trees that grow too close to the electric lines can cause power outage. Effective
vegetation management has become a very essential part not only of constructing new
transmission facilities, but also of operating and maintaining a safe and reliable transmission
system.
58
6.2.2 Right-of-Way of New Transmission Projects
In some cases, the aggressive timeline of new power plants that are not part of previous
generator list as committed or indicative project resulted in shorter lead time for NGCP to secure
regulatory approval and to put up the necessary facilities to support their connection to the grid.
Having the adequate lead time is particularly crucial for right-of-way acquisition for new
transmission line developments. The deployment of more right-of-way teams may not
necessarily work unless adequate lead time is observed, specifically for the resolution of
expropriation cases. The locations of generating facilities are also determined by the
proponents, in many cases in critical parts of the network resulting in more congested
transmission corridors.
The incoming large capacity coal-fired power plants as well as natural gas-fired power plants in
Luzon are mainly concentrated in four (4) provinces namely: Batangas, Quezon, Bataan and
Zambales. The existing capacity of transmission corridors in those areas will not be adequate to
reliably integrate these new capacities into the Luzon Grid. Thus, the network expansion will be
geared towards 500 kV transmission facilities which will require building new transmission lines
with broader right-of-way requirements.
Acquiring lands for future substation sites and transmission lines in urban center has become
inevitable as the available lot size diminishes and land prices go up with the rapid urbanization
growth. Land banking would be more economical compared to acquiring land on a per project
approach or as the need arises. Strategic locations of these future substations and transmission
lines can be readily identified in the Transmission Master Plan.
The Energy Policy Act of 2005 (2005 EPACT) in the United States gave the US Department of
Energy (DOE) the power to identify areas of the national electric grid with problematic reliability
and designate such areas as National Interest Electric Transmission Corridors (“NIETCs” or
“National Corridors”). This allows the DOE to consider the long-term requirements for
transmission corridors.
In the Philippines, the DOE is advocating for energy projects to be declared as Projects of
National Significance. This will be particularly helpful given the conflicting interests of
stakeholders in provinces and regions being traversed by NGCP’s transmission line. As building
transmission lines is imbued with national interest, a law that ensures that these infrastructures
are considered in the medium- to long-term development plan of the country may also be
necessary. More importantly, the assistance from the national government and its agencies
would be very important in ensuring that the common good takes precedence over parochial
interests.
59
some jurisdictions abroad through a well thought legislation. NGCP will support this initiative if
this will be the approach that the government will implement in the future. In the meantime,
NGCP is already considering in the transmission line route selection the sharing of right-of-way
with national highways or expressways. This approach though may result in a longer
transmission line length.
For the associated transmission line of the proposed Taguig 500 kV Substation, NGCP has
coordinated with designer of the Southeast Metro Manila Expressway (SEMME) Project for
possible alignment of the line with the C-6 highway. Aligning the transmission line route with the
highway will avoid populated areas and will minimize right-of-way cost.
Parcellary survey poses a number of problems, chief of which is the unavailability of cadastral
survey – an indication that the government has not yet undertaken survey of the affected lots.
Without such records, there will be no technical descriptions as basis to draw the plans of the
affected lots. In some cases, the available records are only for the individual surveys initiated by
the landowners.
Records from concerned government agencies (DENR, LMB, RoD and Assessors Office) are
most often incomplete or inconsistent from one another and therefore not always reliable. In
addition, most lot records are not updated particularly those sold to new owners and the sale not
registered. The absence of records of affected lots would entail the conduct of NGCP’s own
survey, verification and data gathering from concerned landowners. There is also limited
number of dependable service providers to conduct the survey works.
Upon completion of engineering surveys, NGCP’s main source of information to establish the
ownership of affected lands will be the LRA. In some areas, it is not uncommon to encounter
LRA personnel who refuse to release copy of Original Certificate of Title (OCT) or Transfer
Certificate of Title (TCT). It usually takes 15 to 30 days to secure from the concerned Register of
Deeds certified true copy of land titles. Proof of ownership of properties covered by the
Comprehensive Agrarian Reform Program is usually not available as these properties are not
subdivided individually to the beneficiaries and the corresponding TCT are not available. The
mother TCT is usually in the possession of a government bank pending full payment of the
beneficiaries.
Identification and verification of land ownership also pose problem to researchers due to the
following reasons: (a) owner is residing abroad and contact cannot be established; (b) living
heirs cannot be located and difficulty in establishing extrajudicial partition of estate; (c) property
is mortgaged; and, in some cases (d) subdivided lots are not registered.
Aesthetics and potential impact on environment, human health and safety are the common
concerns raised by communities where the transmission facilities will be installed. Among the
usual questions in consultation meetings are: (a) whether or not the transmission line could be
relocated somewhere else; (b) if it would be possible to re-route the line; (c) the safety of people
living near the power lines; and (d) environmental impact during and after construction.
60
The final approved route for a new transmission line would be based on the result of thorough
investigation of alternative routes, with due consideration to environmental, cultural, social,
engineering, construction, maintenance factors and economic factors. Among the important
considerations is to select, as much as possible, a route or location with the least affected
communities.
Generally, it is safe to live near a transmission line as long as precautionary measures are
taken, primarily the observance of safe distance from the power conductors. NGCP’s facilities
and operation are in accordance with the Philippine Electrical Code (PEC) and International
Commission on Non-Ionizing Radiation Protection (ICNIRP) guidelines. ICNIRP is an
independent scientific organization responsible for providing guidance and advice on the health
hazards of non-ionizing radiation exposure. The PEC prescribes the required clearances for
transmission lines while ICNIRP guidelines sets the EMF exposure limits. NGCP is addressing
this issue by ensuring it has the most up-to-date and relevant information on EMF. It has been
following reviews and developments on EMF studies. It likewise conducts information
campaigns on EMF for its employees and the general public.
Construction activities at the tower and substation sites would have potential effects on the
environment such as temporary soil disturbance, cutting of affected trees, generation of solid
wastes and in few cases, temporary disturbance of nearby bodies of water. The mitigating
measures are contained in the Terms of Reference (TOR) for the contractor who will implement
the project as provided under the Initial Environmental Examination (IEE), a pre-requisite for the
issuance of Environmental Compliance Certificate (ECC). In addition, NGCP also secures the
following permits from DENR: Special Tree Cutting permit and Special Land Use Permit or
Special use Agreement of Protected Area. Zoning/locational clearance is also secured from the
concerned local government unit.
For the affected landowners, the compensation package for the affected properties, including
the payment of taxes, is of utmost concern. Voluntary grant of land rights does not come easy
even with the appropriateness of market value being offered. In the end, it would depend on the
landowners – if they would be reasonable to accept the market value of their properties or aim
for a financial windfall by demanding for higher amount.
It should be pointed out that anything less than 100% availability of workable sites might cause
delays in the completion of the project. Partial availability of land rights does not mean that
partial capacity of the line would be available and that electricity would already be transmitted
over the line. For this reason, every landowner matters, regardless of the size of the affected lot.
There would be situations when voluntary agreement from the affected landowners would not
come easy, in particular to those who refuse to accept the project without citing any reason at
all. When faced with this situation, there is no recourse for NGCP but to exercise its right to
eminent domain in order to deliver its obligations and serve the common good.
The expropriation cases will be filed in the local courts and challenges will be faced particularly
if the landowners are known to be influential in the community. It takes time for the courts to
61
resolve the cases and issue the Writ of Possession for the affected lots. One factor is the limited
number of courts to handle the cases and the multiple cases they handle.
Abaga-Kirahon Transmission Project (Mindanao) has the longest expropriation case which took
49 months to resolve, followed by Santiago-Alicia line (Luzon) at 40 months, Colon-Cebu
Transmission Project and Lumban-Bay, both at 25 months. Completing the top 5 is Bauang-San
Esteban (21 months) transmission project.
This development initiative comes in the form of financial assistance provided by NGCP to fund
the barangays’ priority projects. Usually supported by a Barangay Council Resolution and
implemented through a Memorandum of Agreement, these small projects include logistical
support to the needs of the affected villages such as two-way radio and uniform for barangay
tanod (village guards), improvement of barangay hall, repair of water distribution system and
construction of solar dryer (a small concreted pavement where farmers could dry their palay
harvest). The projects go a long way in building a good relationship between NGCP and host
communities.
For Ancestral Domain and Indigenous People, NGCP has to go through the processes provided
under the law5 to secure necessary clearance for proposed transmission facilities that will
traverse ancestral domain. Firstly, the prior certification from the National Commission on
Indigenous Peoples (NCIP) must be secured certifying that the areas affected do not overlap
with or affect any ancestral domain. The certification will only be issued after a field–based
investigation (FBI) is conducted by the concerned ancestral Domains Office. The conduct of FBI
and the issuance of Free and Prior Informed Consent (FPIC) from the concerned indigenous
cultural communities and indigenous people (ICC/IP) are required prior to issuance of Certificate
Precondition (CP). After a favorable decision from the concerned ICC/IPs has been secured, the
negotiation process on the benefits for the ICC/IP will begin. The negotiation takes time as
ICC/IP would usually demand for more benefits. The results of the negotiation will be contained
in a Memorandum of Agreement among ICCs/IPs, NGCP and NCIP. The report on the whole
process of FBI and FPIC including the MOA shall be subject to the deliberation and approval of
the NCIP Commissioners meeting En Banc. Upon the approval of the MOA, the CP will be
issued.
The law empowered the ICC/IP on their rights to benefit from the utilization, extraction, use and
development of lands and natural resources within their ancestral lands/domains and to be
compensated for any social and/or environmental costs of such activities. It must be
emphasized that transmission line projects, which involve only the use of land to build the
pylons or towers, should be differentiated from other projects, e.g., mining and hydro power,
which entail utilization and even extraction of natural resources. NGCP, in building the
5
Republic Act No. 8371, the Indigenous Peoples’ Rights Act of 1997
62
structures within the ancestral lands, does not extract mineral from the land or make use of
resources such as water or geothermal to generate electricity.
Aside from the actual landowners, cases of informal settlers are also among the major concerns
during project implementation. This can result in delays in projects as well as operational issues
during the conduct of transmission line maintenance activities for existing transmission lines. To
address this, NGCP needs the coordination and support of the local government units.
In areas with security issues, each proposed transmission project is subjected to security
assessment as part of transmission line route or substation site selection process. All security
threats are thoroughly identified to determine the necessary mitigation measures that will be
implemented during construction and its eventual operation.
63
64
Chapter 7 – ERC Approved Projects
The major network developments are triggered by the entry of new power plants to the grid. For
major power outages previously experienced, like the incident in Calaca 230 kV Substation in
May 2013, the major system requirements to address the criticality of the configuration of the
transmission network in Batangas area have been already identified prior to the incident. These
include the recently completed Lumban-Bay 230 kV Line Project and the implementation of the
new Calaca-Dasmarinas Transmission Line Project which is actually driven by the new power
plants in Batangas.
The projects already approved by the ERC are in various stages of implementation. The
approval, as contained in the Final Determination (FD), was obtained in 2010 during the
regulatory reset process for the Third Regulatory Period. In addition, there are other projects
provisionally approved by the ERC as of December 31, 2015 which will form part of the
application for the Fourth Regulatory Period to obtain the final approval.
Summarized below are the projects completed or energized from 01 January 2014 to 31
December 2015. In this period, NGCP completed a total of 1,175 circuit-km of overhead
transmission lines and installed 4,325 MVA additional substation capacities and 707.5 MVAR of
reactive power support.
LUZON
To address the old age
condition of the line and
Binga-San Manuel 230 kV T/L,
provide N-1 contingency
Stage 1 50 Dec 2015
during maximum dispatch of
-Binga S/S Upgrade
the generating power plants
in North Luzon.
To maintain the provision for
Dasmariñas EHV S/S Expansion N-1 contingency for the
900 Oct 2014
Project transformers at Dasmariñas
drawdown substation.
To maintain the N-1
Mariveles Coal Transmission contingency provision of the
Reinforcement Project line during maximum dispatch Dec 2014
-BCCPP S/S Expansion of both Mariveles CFPP and
Limay B-CCPP units.
Lumban-Bay 230 kV T/L Project To increase the capacity of
-Lumban-Kalayaan Line 1 this corridor in order to Jan 2015
-Lumban-Bay Line 2 accommodate any generation Mar 2015
-Lumban-Calauan Line 2 dispatch scenarios Mar 2015
80
-Lumban-Bay Line 1 Mar 2015
-Lumban-Malaya Line 1 May 2015
65
Date of
CKT-
Project Name / Components Purpose MVA MVAR Completion /
KM
Energization
66
Date of
CKT-
Project Name / Components Purpose MVA MVAR Completion /
KM
Energization
In addition to the above list, there are transmission projects that are not part of the Final
Determination for the Third Regulatory Period but have been reclassified from connection asset
to transmission asset. It also includes ERC approved projects implemented in advance by the
concerned power plant proponents. The facilities in this table are either for acquisition or for
reimbursement to the power plant proponent.
Date of
Project Name Purpose MVA MVAR CKT-KM Completion /
Energization
LUZON
This is an existing substation
constructed to accommodate
the connection of Hanjin Heavy
Industries and Construction
Philippines, Inc. (HHIC-PHIL
Inc.) in Subic. Because of its
cut-in configuration to the
Botolan-Olongapo 230 kV Line,
2007
the Hanjin Substation itself is
(Reclassified
Hanjin 230 kV Substation part of the transmission corridor, 34
in October
thus, reclassified by the ERC to
2011)
transmission asset. The main
components reclassified are the
cut-in lines and the 230 kV
switchyard excluding the
existing 2x83 MVA transformers
which are dedicated facilities to
HHIC-PHIL Inc.
67
Date of
Project Name Purpose MVA MVAR CKT-KM Completion /
Energization
This substation is presently
serving the Mariveles Coal-Fired
Power Plant and load customers
namely PENELCO and AFAB
through a 100 MVA 230/69 kV
2013
transformer and new 69 kV 36
Mariveles 230 kV Substation 100 (Reclassified
lines. The ERC has reclassified
in June 2014)
the substation including the
Mariveles-BCCPP A 230 kV
Transmission Line from
connection asset to
transmission asset.
MINDANAO
This project was implemented in
advance by Therma South Inc.
(TSI) to accommodate the
connection of the 2x150 MW
TSI CFPP. It involves a new
Toril 138 kV Substation substation connected as bus-in
2015
(Stage 1) to the Matanao-Davao 138 kV
Transmission Line. Due to
limited line capacity, the
implemented project also
included the reconductoring of
the Toril-Davao Line segment.
TOTAL 100 70
The list below summarized the updates on other ERC approved projects and with the indicated
expected time of completion or ETC. This includes the previously completed projects but still
with some remaining components yet for completion.
68
Project Name /
Driver Purpose & Remaining Major Components ETC
Components
To improve the reliability of the Bauang-Bacnotan-San
Esteban Line by replacing the wood pole structures
Bacnotan Tap-Bacnotan
SR with steel tower structures in the segment immediate Mar 2016
230 kV T/L*
to Bacnotan Substation. This is an ERC approved
project originally under O&M capex.
Luzon Substation
To add substation capacity to provide N-1 contingency
Reliability I
Botolan: 1-50 MVA 230/69 kV transformer
-San Esteban S/S* SR May 2016
Labo: 1-50 MVA 230/69 kV transformer
-Botoloan
San Esteban: 1-50 MVA 115/69 kV transformer
-Labo S/S
To provide a new substation to adequately and reliably
Balingueo (Sta.
LG serve the load centers in the province of Pangasinan Jun 2016
Barbara) 230 kV S/S*
Balingueo: 1-100 MVA 230/69 kV transformer
The installation of new 1-600 MVA 500/230 kV
transformer has been completed already. The
Dasmariñas EHV
SR remaining project component is the replacement of Jul 2016
Substation
some 230 kV PCBs to increase the fault interrupting
capability of the substation.
Installation of the 4th transformer unit for N-1
contingency for the 230/115 kV transformers. This will
Las Piñas (Zapote) S/S address the ex-ante pricing errors in the WESM
LG,SR Sep 2016
Expansion Market Operation brought about by the contingency
constraint violations in Las Piñas Substation.
Las Piñas: 1-300 MVA 230/115 kV transformer
To provide reliable power service delivery in eastern
Albay by developing new 69 kV supply line and a new
Eastern Albay 69 kV T/L
LG,SR 69 kV substation in Sto. Domingo. Dec 2016
Stage 1
Daraga-Sto. Domingo: 1-336.4 MCM ACSR, SP-SC,
20 km
To add substation capacity to accommodate load
growth.
Daraga: 1-100 MVA 230/69 kV transformer
Luzon Substation
LG Gumaca: 1-50 MVA 230/69 kV transformer Dec 2016
Expansion IV
Santiago: 2-100 MVA 230/69 kV transformer
Tuguegarao: 1-100 MVA 230/69 kV transformer
Nagsaag EHV: 1-100 MVA 230/69 kV transformer
Luzon PCB To replace old PCBs to improve substation reliability
SR Dec 2016
Replacement at San Jose, Labo, Malaya and Gumaca.
To provide N-1 contingency for the existing
Santiago-Tuguegarao
SR transmission corridor serving Isabela and Cagayan Dec 2016
230 kV Line 2
Santiago-Tuguegarao: 1-795 MCM ACSR, 118 km
VISAYAS
To accommodate the grid connection of PCPC’s
Eastern Panay
GE 300 MW CFPP implemented by the power plant Jun 2016
Transmission Project
proponent
To make Quinapundan Substation closer to its power
Sta.Rita-Quinapundan
SR source and thus, provide a more reliable power Jun 2016
69 kV T/L
delivery system.
To accommodate load growth in Southern Panay by
extending the 138 kV backbone.
Southern Panay
LG San Jose: 1-50 MVA 138/69 kV transformer Jun 2016
Backbone
69
Project Name /
Driver Purpose & Remaining Major Components ETC
Components
To provide additional capacity to meet load growth
and to accommodate the full dispatch of coal plants
Colon-Cebu T/L CA Jul 2016
Colon-Cebu: 138 kV 1-795 MCM ACSR, ST-DC, 25
km
Culasi-San Jose 69 kV To provide N-1 contingency for the existing corridor
SR Jul 2016
T/L Culasi-San Jose: 1-336.4 MCM ACSR, ST-SC, 86 km
To accommodate the full generation capacity of the
Calong-Calong-Toledo- 246 MW CEDC Coal and the 82 MW TPC Coal
GE Aug 2016
Colon 138 kV T/L Calong-calong-Colon: 1-795 MCM ACSR, ST-DC, 28
km
To provide N-1 contingency for the existing corridor
Ormoc-Maasin 138kV
SR Ormoc-Maasin: 138 kV 1-795 MCM ACSR, ST-DC2, Aug 2016
T/L
113.97 km
To provide N-1 contingency for the existing corridor
Ormoc-Babatngon 138 by installing the second circuit
SR Oct 2016
kV T/L Ormoc-Babatngon: 1-795 MCM ACSR, ST-DC1,
78.54 km
To add substation capacity to provide N-1
contingency
Ormoc: 1-150 MVA 230/138 kV transformer
Visayas Substation Amlan: 1-50 MVA 138/69 kV transformer
SR Dec 2016
Reliability I Bacolod: 1-100 MVA 138/69 kV transformer
Cadiz: 1-50 MVA 138/69 kV transformer*
Maasin: 1-50 MVA 138/69 kV transformer
Samboan: 1-50 MVA 138/69 kV transformer
To accommodate load growth in Northeastern Negros
and to provide operational flexibility
Negros V T/L LG Dec 2016
San Carlos-Guihulngan: 69 kV 1-336.4 MCM ACSR,
ST-SC, 58 km
MINDANAO
To provide N-1 contingency transformers at various
substations
Mindanao Substation Jasaan: 1-100MVA 138/69 kV transformer
SR Mar 2016
Reliability I Lugait: 1-75MVA 138/69 kV transformer intended for
this substation was installed in Opol Substation
instead.
To accommodate the grid connection of SMCPC’s
CFPP
Malita-Matanao 230 kV
GE Malita-Matanao: 230 kV 2-410mm2 TACSR, ST-DC, Mar 2016
T/L*
67 km transmission line
Malita (New): 1-50 MVA 138/69 kV transformer
To provide N-1 contingency capability to the
Matanao-Gen. Santos transmission corridor
SR Mar 2016
138 kV T/L Matanao-Gen.Santos: 138 kV 1-795 MCM ACSR, ST-
SC, 72.60 km transmission line
To strengthen the existing 138 kV double circuit
Maramag-Kibawe transmission line and to relieve
Maramag-Kibawe 138 kV line from overloading due to
Maramag-Kibawe 138 the frequent outage of the Agus 2- Kibawe 138 kV
Apr 2016
kV T/L Project* line.
70
Project Name /
Driver Purpose & Remaining Major Components ETC
Components
To address the increase in demand and improve
power quality in the area
LG, SR,
Opol 138 kV S/S Opol: 1-75 MVA 138/69 kV transformer. This Jun 2016
PQ
transformer was originally planned for Lugait
Substation.
To add substation capacity to meet load growth
Mindanao Substation Gen. Santos SS: 1-100 MVA 138/69 kV transformer
LG Jun 2016
Expansion Project 2 Kidapawan SS: Transfer of 1-50 MVA 138/69 kV
transformer from General Santos Substation.
Sultan Kudarat (Nuling) To improve the voltage profile in the area
SR, PQ Dec 2016
Capacitor Project Sultan Kudarat SS: 2-7.5 MVAR 69 kV capacitor
Agus 6 Switchyard
To ensure the operational reliability of the plant’s
Upgrading / SR Dec 2016
switchyard
Rehabilitation
GE – Generation Entry; SR – System Reliability; LG – Load Growth; PQ – Power Quality;
*Completed/Energized
71
7.3 Projects for Completion in 2017 onwards
The list below summarized the updates on the remaining ERC approved projects with ETC by
2017 onwards.
72
Project Name Driver Purpose ETC
MINDANAO
Balo-i-Kauswagan-
To accommodate the proposed 4x100MW coal-fired
Aurora 230 kV T/L GE Aug 2017
power plant of GNPower in Kauswagan.
(Phase 1)
Aurora-Polanco 138 kV To serve the growing power demand in Zamboanga
LG Aug 2017
T/L del Norte area
To provide N-1 contingency to the existing line
Butuan-Placer 138 kV
SR Butuan-Placer: 138 kV 1-795MCM ACSR, ST-SC, 96 Dec 2017
T/L
km transmission line
Toril 138 kV S/S, Stage 2 To provide 138/69 kV transformer in order to serve
GE Dec 2017
load customers such as DASURECO and DLPC
Agus 2 Switchyard To address the deteriorating physical and operational
SR Feb 2018
Upgrading Project condition of the switchyard
Tacurong-Kalamansig 69 To provide a grid connection to the off-grid
SR Nov 2019
kV Line municipalities in Sultan Kudarat province
GE – Generation Entry
SR – System Reliability
LG – Load Growth
PQ – Power Quality
73
7.3.1.2 San Jose-Quezon 230 kV Line 3
Major Project Components
San Jose-Quezon 230 kV T/L, ST/SP-SC 2-610 mm2 TACSR, 19 km;
San Jose 230 kV S/S, 5-230 kV PCB and associated equipment;
Quezon 230 kV S/S, Line Protection and Communication System.
projected overloading
problem during an QUEZON
Several power plant projects have been proposed in the Luzon Grid and based on the data from
the DOE, the province of Bataan is one of the areas with expected bulk generation capacity
additions. To transmit this bulk generation to Luzon load center in Metro Manila, transmission
line projects will be required going up to Hermosa then to Metro Manila and submarine cable
link from Bataan to Cavite area. For higher level of grid reliability and to support the bulk
generation development, the establishment of a looped EHV backbone system including the
Bataan – Cavite Transmission Line Project is envisioned for the Luzon Grid. Phase 1 of the
project is the conduct of feasibility study to establish the appropriate project scheme and the
receiving point in Cavite or Metro Manila through the proposed Pasay 230 kV Substation.
74
7.3.1.4 Hermosa-Floridablanca 69 kV Transmission Line
Major Project Components
Hermosa-Floridablanca 69 kV T/L, 1-795 MCM ACSR, SP-SC,
16.86 km;
Basa Air Base-100D 69 kV kV T/L, 1-795 MCM ACSR, SP-SC,
2.86 km.
HERMOSA
75
7.3.1.6 Western 500 kV Backbone (Stage 1)
Major Project Components
Castillejos-Hermosa 500 kV T/L, ST-DC, 4-410mm2 TACSR, 32 km;
New Hermosa 230 kV S/S, 4-230 kV PCB and associated equipment.
76
7.3.1.8 Ambuklao-Binga 230 kV Transmission Line Upgrading
Major Project Components AMBUKLAO
Ambuklao-Binga 230 kV T/L, ST-DC, 2-410mm2 TACSR,
11 km;
Ambuklao 230 kV S/S, 6-230 kV PCB and associated
H
equipment.
3 x 35 MW
SAN MANUEL
77
7.3.1.10 New Antipolo 230 kV Substation
Major Project Components
Bus-in point along San Jose-Taytay 230 kV T/L, ST-DC 4-795 MCM
ACSR, 2 km;
Antipolo 230 kV S/S, 12-230 kV PCB and associated equipment;
2-100 MVAR 230 kV Capacitor.
2 x 300 MVA
Taytay Substations require the
development of a new 230 kV delivery
substation. Initially, Antipolo 230 kV
Substation will have 2-300 MVA
capacity with capacitor banks to be installed for voltage support. To draw supply from Antipolo,
MERALCO will put up line connections to their existing 115 kV network in the area. In the 3rd
Regulatory Period FD, the 2-300 MVA transformers and the 115 kV switchyard components
were reclassified as subtransmission assets, thus, only the 230 kV switchyard, 230 kV
capacitors, and the 230 kV line extension will be covered by NGCP’s project.
78
7.3.1.11 Calaca-Dasmariñas 500 kV Transmission Line
Major Project Components
Calaca – Dasmariñas (500 kV-designed portion), ST-DC, 4-
410 mm2 TACSR, 49.7 km;
Calaca – Dasmariñas (230 kV-designed portion), ST-DC, 4-
410 mm2 TACSR, 8.6 km;
Calaca – Taal 69 kV extension, SP-SC, 1-336.4 MCM ACSR,
1.5 km;
Dasmariñas S/S Expansion, 2-230 kV PCB and associated
equipment;
Sta. Rita Switchyard Expansion, Line Protection and
Communication System.
79
7.3.2 Visayas Grid
80
7.3.2.3 Cebu-Lapu-lapu Transmission Line
Major Project Components
Cebu-Umapad 230 kV T/L, ST/SP-DC, 2-795 MCM ACSR, 9 km;
Umapad-Mandaue CJ 138 kV T/L, SC, 3-1C 1,000mm2 XLPE
underground cable, 0.3 km;
Mandaue-Lapu-lapu CJ 138 kV T/L, SC, 2-3C 500mm2 XLPE
Submarine Cable, 0.5km;
Lapu-lapu CJ-Lapu-lapu 138 kV T/L, SC, 3-1C 1,000mm2 XLPE
underground cable, 0.1km;
Lapu-lapu 138 kV S/S, 1-138 kV GIS Switchbay;
Umapad CTS, Cable Sealing End Structures, 3-138 kV Disconnect
Switches.
was conducted.
The new project configuration now involves 230 kV-designed overhead line from Cebu to
Mandaue and submarine cable from Mandaue to Lapulapu. The overhead line will tap along the
existing Colon-Cebu 138kV line and will bypass Cebu and Mandaue Substations to minimize
unbalanced loading due to difference in impedance between the proposed overhead line and
the existing underground cable. Effectively, the project will connect Lapulapu Substation directly
to Colon Substation.
Moreover, the overhead line will already be designed at 230 kV but initially energized at 138 kV
taking into consideration the demand growth in Metro Cebu and the difficulty of acquiring
available space for future transmission facilities as the area is highly urbanized.
81
7.3.3 Mindanao Grid
Balo-I S/S Expansion, 4-230 kV PCB and associated equipment. KAUSWAGAN 230 kV
equipment;
Polanco LES, 3-69 kV Air Break Switch. POLANCO 138 kV
82
7.3.3.3 Butuan-Placer 138 kV Transmission Line
PLACER 69 kV
Major Project Components
Butuan-Placer 138 kV, ST-SC, 1-795MCM, 100km;
Placer, 2-138 kV PCB and associated equipment; 50 MVA 100 MVA
BUTUAN 69 kV
allow the connection of load customers in the area namely: DLPC TORIL 69 kV
83
7.3.3.6 Tacurong-Kalamansig 69kV Transmission Line
Major Project Components
Tacurong-Kalamansig 69kV T/L, ST-SC, 1-336.4MCM ACSR, 80 km With the limited source of power
transmission line including Communication System System; in the area and to support the
increasing load in the long term,
Tacurong 69kV S/S, 1-69kV PCB and associated equipment; there is a need to provide grid
connection to the off-grid
Kalamansig 69kV SS, 1-7.5MVAR 69kV capacitor. municipalities of Bagumbayan,
Ninoy Aquino, Lebak and
Kalamansig. The project will allow these towns in Sultan Kudarat to have access to secure,
reliable and efficient power delivery services. Thus, it will serve as a catalyst for economic
development and likewise accelerates the total electrification of the province.
84
Chapter 8 – Luzon Transmission Outlook
The DOE list shows that there are many committed and indicative power plant projects in Luzon
Grid which can well support the increasing demand for the next 10 years. The incoming large
capacity coal-fired power plants as well as natural gas-fired power plants are mainly
concentrated in four (4) provinces namely: Batangas, Quezon, Bataan and Zambales, which
would result in huge excess power in these areas. Since the remaining transmission capacity of
the existing facilities is also very limited for the grid integration of new bulk generation additions,
the development of the Luzon Grid is geared towards implementation of new 500 kV
transmission facilities that would allow power export from bulk generation sites going to the load
center.
With the increasing delivery of bulk power to the 500 kV system, however, the two (2) existing
500 kV substations located in San Jose, Bulacan and Dasmariñas, Cavite which serve as the
only EHV drawdown facilities supporting Metro Manila loads would become critical nodes in the
grid. The capacity and expansion limitations in these substations could result in grid congestion
unless new 500 kV drawdown substations are developed. In the TDP, new 500 kV substations
are being proposed with Taguig as the priority site. Being close to the load center, Taguig is a
very strategic location but has the major challenge also in the establishment of its associated
500 kV transmission line traversing portion of the Laguna Lake.
Along with the support given to grid integration of new power plants, NGCP is paying special
attention in strengthening the transmission facilities in Metro Manila which is the country’s load
center. The existing 230 kV transmission line traversing from Quezon City to Muntinlupa City is
a very critical line given its heavy loading condition and single-circuit configuration. Such
conditions also pose great risk both on power quality and supply reliability in the area. In
addition, the existing 230/115 kV substations in Metro Manila are heavily loaded already and
mostly with capacity expansion limitations, thus, the development of new substations is very
important in supporting load growth in the long term.
Being the center of nation’s economy, the grid reinforcement projects to ensure the long term
adequacy, reliability and security of power supply in Metro Manila can be regarded as “projects
of national significance”. As can already be expected in a highly urbanized area, securing right-
of-way for new transmission facilities is increasingly becoming difficult. It is therefore important
to immediately start the implementation to realize the transmission development plans and it
should be coupled with support from the local and national government. Aside from Taguig
EHV, the proposed new facilities include Pasay and Manila/Navotas Substations which would
also involve the implementation of associated 230 kV transmission lines.
After Metro Manila and the already industrialized areas in Cavite and Laguna, the province of
Pampanga is expected as the next major load growth area. In the long-term, new 230 kV
backbone and new 230/69 kV substations would be needed for Porac and Clark in order
support the load increase in the coming years. For other provinces, on the other hand,
supporting load growth generally involves installation of additional transformers at existing
substations or development of new substations and some reinforcements on the 69 kV
transmission lines.
85
To help improve system reliability and to maintain the power quality within the grid code-
prescribed standards, included in the development plans are the implementation of transmission
looping configurations even for the 500 kV system, upgrading of old transmission lines and
substations as well as installation of reactive power compensation equipment at various
substations.
For renewable energy developments particularly in north Luzon, the implementation of the
Northern Luzon 230 kV Loop could provide the needed transmission capacity augmentation. In
the long-term, however, considering the full wind power generation potential in North Luzon as
well as the hydro power generation potential in Cagayan Valley, Abra and Benguet, a new
backbone from San Manuel, Pangasinan going up north would also be needed. Solar and other
new RE-based plants, on the other hand, are well dispersed in the grid and generally not
requiring major grid reinforcements.
Shown in Table 8.1 is the list of transmission projects proposed in the period 2016-2025 in
addition to the ERC approved projects for Luzon Grid as discussed in Chapter 5.
86
Project Name/Driver(s) Province(s) ETC
Malvar 230 kV Substation Batangas Dec 2024
Porac 230 kV Substation Pampanga Dec 2024
Liberty-Baler 230 kV Transmission Line Nueva Ecija, Aurora Apr 2025
Magalang 230 kV Substation Pampanga Jun 2025
System Reliability
Relocation of Steel Poles along Hermosa-Duhat
Pampanga Dec 2018
230 kV Transmission Line
La Trinidad-Calot 69 kV Transmission Line Benguet Jun 2019
Tiwi Substation Upgrading Project Albay Jul 2019
Pinili 115 kV Substation Ilocos Norte Dec 2019
Navotas-Pasay 230 kV Transmission Line Metro Manila Jul 2020
Taguig-Taytay 230 kV Transmission Line Metro Manila Oct 2020
Balayan 69 kV Switching Station Batangas Jun 2021
San Manuel-Nagsaag 230 kV Transmission Line Pangasinan Dec 2021
Dasmariñas-Las Piñas 230 kV Transmission Line Metro Manila Dec 2023
Manila(Navotas)-Dona Imelda 230 kV Transmission
Metro Manila Dec 2023
Line
Mexico-Clark 69 kV Transmission Line Upgrading Pampanga Apr 2024
Minuyan 115 kV Switching Station Bulacan Apr 2024
Western 500 kV Backbone – Stage 2 Pangasinan, Zambales Jun 2024
Baras 500 kV Switching Station Rizal Dec 2024
Alaminos 500 kV Switching Station Laguna Dec 2024
Silang-Taguig 500 kV Transmission Line Cavite, Metro Manila Dec 2024
Calaca-Salong 230 kV Transmission Line 2 Batangas Mar 2025
Santiago-Dinadiawan-Baler 230 kV Transmission
Isabela, Aurora Nov 2025
Line
Liberty – Cabanatuan - San Rafael - Mexico 230 kV
Nueva Ecija, Pampanga Jun 2025
Transmission Line Upgrading
Power Quality
Ilocos Norte, Ilocos Sur, Cagayan,
Luzon Voltage Improvement Project 3 – Stage 1 / Jan 2018 /
Zambales, Pampanga, Bulacan, Nueva
Stage 2 Jun 2022
Ecija, Pangasinan
Luzon Voltage Improvement Project 4 – Stage 1 / Albay, Sorsogon, Rizal, Laguna, Cavite, Dec 2019/
Stage 2 Camarines Sur Jun 2022
87
Figure 8.1: Proposed Projects for Luzon
88
8.1.1 Pagbilao 500 kV Substation
Major Project Components
Pagbilao 500 kV S/S, 3-1,000 MVA, 500/230 kV Power
Transformers and Accessories, 8-500 kV PCBs and
11-230 kV PCBs and associated equipment;
Tayabas 500 kV S/S Expansion, 3-500 kV PCBs and 1-230 kV
PCBs and associated equipment;
Swinging of Naga-Tayabas EHV Line at Tayabas 500 kV S/S,
ST-DC, 4-795 MCM ACSR, 0.5 km;
Naga-Tayabas Line Extension to Pagbilao 500 kV S/S,
500 kV, ST-DC, 4-795 MCM ACSR, 0.5 km;
Pagbilao-Tayabas Line Extension to Pagbilao 500 kV S/S,
230 kV, ST-DC, 4-795 MCM ACSR, 2.75 km;
Pagbilao-Tayabas connection to Naga-Tayabas, 230 kV,
ST-DC, 4-795 MCM ACSR, 2.75 km
new 500 kV
PAGBILAO EWLNG
substation in
Pagbilao is in lieu
of further C C C
expanding the 2 x 367.5 MW 420 MW 3 x 200 MW
existing Tayabas
500/230 kV Substation which has transformer capacity limitations and with high fault level issue
in the 230 kV side of the substation. The project scheme involves the energization to 500 kV of
a segment of the Naga-Tayabas Transmission Line.
89
8.1.2 Hermosa-San Jose 500 kV Transmission Line
Major Project Components
Hermosa-San Jose 500 kV T/L, ST-DC, 4-410 mm2
TACSR/AS, 82.41 km;
New Hermosa-Old Hermosa Tie Line, SP-DC, 4-795 MCM
ACSR, 0.5 km;
New Hermosa 500 kV S/S, 2-1000 MVA, 500/230-13.8 kV
Power Transformer and Accessories, 10-500 kV PCBs and
12-230 kV PCBs and associated equipment;
New Hermosa 500 kV S/S, 2-60 MVAR 500 kV Shunt Reactors
and Accessories, 1-90 MVAR 500 kV Line Reactor and
Accessories; and 2-100 MVAR, 230 kV Capacitor Banks and
Accessories;
Old Hermosa 230 kV S/S, 2-230 kV PCBs and Associated
Equipment and 9-69 kV PCBs and associated equipment.
accommodating the
TIE LINE
generation capacity
additions in Bataan and
Zambales area. Hermosa
SAN JOSE
Substation serves as a
2 x 1000 MVA
4 x 750 MVA
NEW HERMOSA
merging point of bulk HERMOSA
power generation coming
from the existing Limay
CCPP, Petron RSFF,
Subic Enron DPP,
Mariveles CFPP and the
programmed generation TAGUIG/
TAYABAS
capacity additions which
include RP Energy CFPP, SMC CFPP and others. With an aggregate dependable capacity
reaching about 4,000 MW from the existing and incoming power plants, the system study has
determined the need to develop a 500 kV transmission backbone which will serve as the
additional outgoing circuits from Hermosa to San Jose Substation in order to allow simultaneous
maximum dispatch of associated power plants. Because of the expansion limitation of San Jose
500 kV Substation which is a GIS, the scheme would have one 500 kV line that will need to
initially by-pass San Jose Substation. This will be permanently addressed by the Marilao 500 kV
Substation Project.
90
8.1.3 Bataan 230 kV Grid Reinforcement Project
Major Project Components
Limay-Hermosa Reconductoring (single circuit termination),
230 kV, 1-795 MCM ACSR/AS to 1-410 mm2 TACSR/AS,
38.01 km;
Limay-BCCPP Line Extension, 230 kV, SP-SC, 2-410 mm2
TACSR/AS, 1.0 km;
Hermosa-Mexico Reconductoring, 230 kV, 1-795 MCM
ACSR/AS to 1-410 mm2 TACSR/AS, 35.0 km;
Lamao (Limay) bus-in to the existing Mariveles – BCCPP B
230 kV lines, 230 kV, ST – DC, 4-795 MCM ACSR/AS,
2-1.0 km;
Mexico-Cabanatuan 230 kV Line bus-in to San Rafael S/S,
SP-DC, 1-795 MCM ACSR, 1.0 km;
Limay S/S (Replacement), 10-230 kV PCBs and associated
equipment;
BCCPP A and B Switchyard (Replacement/Expansion), 9-
230 kV PCBs and Associated Equipment;
Lamao Switchyard (New), 12-230 kV PCBs and associated
equipment;
San Rafael 230 kV S/S (Expansion), 4-230 kV PCBs and
associated equipment.
MEXICO
This project aims to accommodate the
connection of the 600 MW SMC Consolidated
Power Corporation Coal-Fired Power Plant
(SMC CPC CFPP) Project to the Luzon Grid HERMOSA
91
8.1.4 Bolo 5th Bank
Major Project Components
Bolo 500 kV S/S (Expansion), 1-600 MVA 500/230 kV
Transformer, 3-500 kV PCB and associated equipment.
BOLO
Bolo 500 kV Substation collects the generation from the major coal-
4 x 600 MVA
1 x 600 MVA
fired power plants in the area namely: Sual and Masinloc. The power
flow in the transformers at this substation is also being influenced by
the dispatch of the hydro power plants and other generators in north
Luzon. With the proposed 600 MW expansion of Masinloc CFPP and
the generation developments in North Luzon, the substation capacity
would no longer be adequate to maintain the N-1 contingency provision, thus, a 5th transformer
bank is being proposed. This will provide the required grid augmentation while the Western 500
kV Backbone is not yet in place.
TAYABAS
This involves the establishment of the 500 kV
backbone at Bataan peninsula in order to support the SAN JOSE
is developed. This new backbone will form part of the OLD HERMOSA
92
8.1.6 Northern Luzon 230 kV Loop
Major Project Components
Laoag-Bangui 230 kV T/L, ST-DC, 1-795 MCM ACSR/AS, 50
km;
Bangui – Pamplona – Lal-lo (Magapit), 230 kV, ST-DC, 1-795
MCM, ACSR, 130 km;
Laoag 230 kV S/S (Expansion), 4-230 kV PCBs and associated
equipment;
Bangui 230 kV S/S (New), 2-300 MVA, 230/115-13.8 kV Power
Transformer and Accessories, 10-230 kV PCBs, 11-115 kV
PCBs and associated equipment;
Pamplona 230 kV S/S (New), 2-300 MVA, 230/115-13.8 kV
Power Transformers and Accessories, 10-230 kV PCBs and
associated equipment, 6-115 kV PCBs and associated
equipment;
Lal-lo (Magapit) 230 kV S/S (Expansion), 4-230 kV PCBs and
associated equipment.
It should be noted that due to generation additions also in the Cagayan Valley Area, the
transmission line from Santiago to Ambuklao Substations will also be requiring grid
reinforcement together with the implementation of the Northern Luzon 230 kV Loop.
93
8.1.7 Sta. Maria / Ibaan 500 kV Substation
Major Project Components
Sta. Maria / Ibaan 500 kV S/S, 10-500 kV PCB and associated
equipment;
Sta. Maria 500 kV Cut-in Lines, ST/SP-DC, 4-795 MCM ACSR,
9 km.
94
where the link to the 500 kV backbone and to the high capacity San Manuel-Concepcion-Mexico
230 kV Transmission Line are connected. It can be noted that the Liberty-Nagsaag 230 kV
Transmission Line, will already form part of the upgrading project of the old single circuit
Nagsaag-Pantabangan-Cabanatuan-Mexico 230 kV line. The Liberty 230 kV Substation, on the
other hand, will also be utilized to serve the existing loads connected at the Cabanatuan-
Pantabangan 69 kV line. This new substation will allow the shifting of loads connected at the
far-end of the Cabanatuan-Pantabangan 69 kV Line thereby improving operational flexibility,
supply reliability as well as provision to accommodate future loads in the area.
La Trinidad-Bulalacao 69 kV Line.
95
8.1.10 Pagbilao-Tayabas 500 kV Transmission Line
Major Project Components
Pagbilao-Tayabas 500 kV T/L, ST-DC, 4-795 MCM ACSR/AS,
17 km;
Pagbilao 500 kV S/S, 4-500 kV PCB and associated equipment.
of the system C C
development in Quezon
province associated with QPPL
96
8.1.11 Santiago-Nagsaag 500 kV Transmission Line
Major Project Components
Santiago-Nagsaag 500 kV T/L, ST-DC, 4-795 MCM ACSR/AS,
140.0 km;
Old and new Santiago S/S 230 kV tie-line, ST-DC, 4-795 MCM
ACSR/AS, 1.0 km;
New Santiago 500 kV S/S, 2-750 MVA 500/230-13.8 kV Power
Transformer and Accessories, 6-500 kV PCBs and 6-230 kV
PCBs and associated equipment;
Santiago 230 kV S/S, 4-230 kV PCBs and associated
equipment;
Nagsaag 500 kV S/S, 4-500 kV PCBs and Accessories,
2-60 MVAR 500 kV Line Reactor and Accessories.
STAGE 1
This project will serve as a new
SANTIAGO BAYAOMBONG AMBUKLAO BINGA
transmission backbone to support
the generation developments in
Cagayan Valley area including 500 KV DESIGNED INITIALLY
ENERGIZED AT 230 KV
hydro power plants, wind farms and
other conventional power plants. SAN
Without this project, the double- MANUEL
NAGSAAG
2 x 60 MVAR
BOLO(KADAMPAT)
97
8.1.12 Clark-Mabiga 69 kV Transmission Line
Major Project Components
Clark-Mabiga 69 kV T/L, 1-410mm2 TACSR/AS, SP-DC, 6 km;
Clark 230 kV S/S (Expansion), 1-300 MVA 230/69-13.8 kV
Power Transformer and Accessories, 1-230 kV PCB and
Associated Equipment and 3-69 kV PCB and associated
equipment.
98
8.1.13 North Luzon 230 kV Substation Upgrading Project
Major Project Components
STAGE 1
Bauang 230 kV S/S (Replacement), 1-100 MVA 230/115/69- This project package contains the
13.8 kV Power Transformer and Accessories, 7-230 kV PCB transformer capacity installation
and associated equipment;
components at various substations in
Gamu 230 kV S/S (Expansion), 1-100 MVA 230/69-13.8 kV
Power Transformer and accessories, 10-230 kV PCB and North Luzon which aim to ensure the
associated equipment, 2-69 kV PCB and associated continuous adequacy of substation
equipment; capacity in serving the increasing
Bayombong 230 kV S/S (Replacement), 1-100 MVA 230/69- loads both during normal and N-1
13.8 kV Power Transformer and Accessories, 5-230 kV PCB
and associated equipment, 3-69 kV PCB and associated
contingency conditions. It also
equipment; involves replacement of PCBs at
Hermosa 69 kV S/S, 12-69 kV PCB and associated equipment; Pantabangan switchyard due to
Pantabangan 230 kV S/S, 4-230 kV PCBs and associated historical equipment failure and
equipment;
installation of neutral grounding
Doña Imelda S/S, 1-115 kV PCB and associated equipment and
neutral grounding transformer; transformer at Doña Imelda to
Malaya 230 kV S/S (Expansion), 1-300 MVA, 230/115-13.8 kV energize the spare 4th transformer
Power Transformer and Accessories, 9-230 kV PCB and bank.
associated equipment, 1-115 kV PCB and associated
equipment;
San Jose 230 kV S/S (Expansion), 1-300 MVA, 230/115-13.8
Such developments would allow
kV Power Transformers and Accessories, 1-230 kV PCB and NGCP to meet the grid code standard
associated equipment, 7-115 kV PCB and associated and to have operational flexibility
equipment. especially during the maintenance
STAGE 2
activities for power transformers at
Balingueo 230 kV S/S (Expansion), 1-100 MVA 230/69-13.8 kV the substations, thereby, avoiding
Power Transformer and Accessories, 5-230 kV PCB and supply interruption to the loads.
associated equipment, 4-69 kV PCB and associated
equipment;
Bacnotan 230 kV S/S (Expansion), 1-50 MVA 230/69-13.8 kV
Power Transformer and Accessories, 1-230 kV PCB and
associated equipment, 6-69 kV PCB and associated
equipment;
Labrador 230 kV S/S (Replacement), 1-100 MVA 230/69-13.8
kV Power Transformer and Accessories, 5-230 kV PCB and
associated equipment, 2-69 kV PCB and associated
equipment;
San Rafael 230 kV S/S (Expansion), 1-300 MVA 230/69-13.8 kV
Power Transformer and Accessories, 1-230 kV PCB and
associated equipment.
99
8.1.14 Calamba 230 kV Substation
Major Project Components
Calamba 230 kV S/S, 2-300 MVA, 230/115-13.8 kV Power
Transformers to be implemented by MERALCO, 10-230 kV
PCB and associated equipment;
Bus-in Lines, 230 kV T/L, SP-DC, 2-610 mm2 TACSR/AS,
1.5km.
100
Switchgear (GIS) substation has been considered. This substation can also serve as a
connection point for TMO and Millenium power plants in the area, thus, facilitate direct plant
connection to NGCP.
to accommodate the
SAN SIMON
incoming steel plants and
1 x 300 MVA
load growth in San
Simon, Pampanga. To
serve the immediate
needs of the new steel
plants, additional 69 kV lines for Mexico Substation are required. If more steel plants or other
industrial facilities will be built in San Simon in the future, a new 230 kV drawdown substation,
which is a separate project, will serve as the long term solution.
FITUI
CALAMBA
(PHILTOWN)
101
8.1.18 Pasay 230 kV Substation
Major Project Components
Pasay 230 kV S/S, 5-230 kV PCBs (GIS) and associated
PASAY
equipment;
Las Piñas-Pasay 230 kV T/L, 230 kV, 2-795 MCM ACSR/AS, 2 x 300 MVA
SP-DC, 4.2 km; 230 kV 2-1C-2,000 mm² XLPE, UG-DC,
3.9 km.
the installation of the 4th transformer unit, but these would serve as
3 x 300 MVA
medium-term solution only to address the increasing load and to
provide single outage (N-1) contingency. Ultimately, new drawdown
substation will have to be developed and Pasay was identified as a
strategic site being close to the load growth area in the
Entertainment City in Pasay and can also help support the loads in
Makati City. As its supply line, a new 230 kV transmission highway DASMARIÑAS
102
system and need to reinforce the single-circuit 230 kV transmission line traversing within Metro
Manila. The implementation of the Taguig 500 kV Substation will improve the reliability of the
transmission network by providing direct power injection within Metro Manila through the
Muntinlupa-Paco 230 kV Transmission Line segment and at the same time, this will also
address the power quality issues. It should be noted that Taguig 500 kV has been prioritized
over the previous Baras (Antipolo) 500 kV Substation Project but this could still be implemented
in the far future as part of the 500 kV system development.
103
8.1.21 Daraga-Ligao 69 kV Transmission Line Upgrading
Major Project Components
Daraga-Ligao 69 kV T/L, 1-795 MCM ACSR/AS, ST-SC, 22 km;
Daraga 69 kV S/S Expansion, 1-69 kV PCB and associated
equipment;
Ligao Switching Station, 1-69 kV PCB and associated
equipment.
project will be able to ensure continuous adequate and reliable operation including the benefit of
providing operational flexibility during contingency or maintenance in the 69 kV facility.
104
8.1.23 Marilao 500 kV Substation
Major Project Components
Marilao 500 kV S/S, 2-1,000 MVA, 500/230-13.8 kV Power
Transformers and Accessories, 14-500 kV PCBs, 14-230 kV
PCBs, and associated equipment;
Nagsaag -San Jose 500 kV Line Extension to Marilao 500 kV
S/S, 500 kV, ST-DC, 4-795 MCM ACSR/AS, 8.7 km;
Marilao bus-in to Hermosa-San Jose 500 kV Line, 500 kV,
ST-DC, 4-410mm2 TACSR, 1.5 km;
Marilao- Duhat 230 kV T/L, SP-DC, 2-795 MCM ACSR/AS,
3.2 km;
Marilao-Manila 230 kV T/L, SP-DC, 4-795 MCM ACSR, 3.6 km;
4 x 750 MVA
at San Jose Substation under the project
Hermosa-San Jose 500 kV Transmission DUHAT
105
Albay. The 230 kV backbone is already extended up to Bacman Geothermal Plant in Sorsogon
and may already be used as part of the supply facilities for the proposed Abuyog Substation.
106
8.1.27 Porac 230 kV Substation
Major Project Components
Porac 230 kV S/S, 1-300 MVA 230/69 kV transformer, 5-230 kV
PORAC CLARK
PCB, 9-69 kV PCB and associated equipment;
Hermosa-Porac-Clark, 4-795 MCM ACSR, ST-DC, 54-km.
Hermosa 230 kV S/S (Expansion), 4-230 kV PCB and
associated equipment;
Clark 230 kV S/S (Expansion), 4-230 kV PCB and associated 1 x 300 MVA
equipment.
This project, which will be implemented by stages, has
the primary goal of supporting load growth in Pampanga
and establishing the 230 kV backbone loop from
Hermosa to Clark thereby providing a more direct
HERMOSA
access to the generation hub in Bataan. Among the
expected major load developments include Alviera and
Clark Green City.
1 x 100 MVA
from Cabanatuan Substation. This line will also support
the development of line extension going to Casiguran
ENERGIZED AT
and will serve as a link to connect other loads in Aurora
INITIALLY
69 kV
Province which are not grid-connected yet.
BALER
MAGALANG
107
this new substation project would still serve as future augmentation in adequately and reliably
serving the loads in the area.
AIR BREAK
HEDCOR
SWITCH
ASIN
HEDCOR
H AMPOHAW
108
8.1.32 Tiwi Substation Upgrading
Major Project Components
Tiwi A 230 kV S/S, 4-230 kV PCBs and associated equipment;
Tiwi C 230 kV S/S, 1-50 MVA, 230/69-13.8 kV Power
Transformer and Accessories, 15-230 kV PCBs and
associated equipment and 3-69 kV PCBs and associated
equipment.
NAGA
DARAGA
The project aims to upgrade the old and
deteriorated substation equipment at Tiwi A and
C Substations to improve the reliability of the
system. It will also augment the power
requirement of Malinao/Ligao LES by installation
of additional power transformer at Tiwi C
Substation and will clearly identify asset TIWI C TIWI C
1 x 50 MVA
Plant Complex through construction of NGCP's
G G
own control facilities. It also involves diversion of
the Daraga/Naga 230 kV Lines to Tiwi C
Substation and extension of the Malinao/Ligao 69
kV Line from Tiwi A to Tiwi C Substation.
This new substation will replace the LAOG 1 x 100 MVA BANTAY
Currimao 115 kV Substation to
accommodate the load growth and
provide N-1 contingency for the loads PINILI
109
8.1.34 Navotas-Pasay 230 kV Transmission Line MARILAO
that the new line will traverse along the Roxas Boulevard.
LAS PIÑAS
DASMARIÑAS
4 x 750
MVA
Substation. With the link from Taguig to
Taytay, the decongestion of San Jose EHV MUNTINLUPA PACO
DOÑA
IMELDA
Substation will become more effective, the
ANTIPOLO
utilization of the new substation in Taguig QUEZON
2 x 1000
TAYABAS
surrounding the Laguna Lake.
110
8.1.36 Balayan 69 kV Switching Station
BINGA
BOLO(KADAMPAT)
The existing 230 kV tie-line connecting Nagsaag and San Manuel 230 kV Substations is a
single-circuit facility only. During outage of the existing tie-line, the identified problems include
low voltage issues and overloading of the Pantabangan-Cabanatuan 230 kV Line particularly
during maximum dispatch of the hydro plants in North Luzon. This project will help improve
system security by ensuring continuous connectivity between the concerned substations and
will allow optimal utilization of the high capacity San Manuel-Concepcion-Mexico transmission
corridor.
111
8.1.38 Dasmariñas-Las Piñas 230 kV Transmission Line
Major Project Components
Dasmariñas-Las Piñas 230 kV T/L, 4-795 MCM ACSR SP-DC, This line is interrelated with the
32 km; Navotas-Pasay 230 kV Transmission
Las Piñas 230 kV S/S (Expansion), 4-230 kV PCB GIS and Line Project. Without the looping to
associated equipment. Navotas or any augmentation, the
substation capacity for Las Piñas and Pasay as well the PASAY
allowable loads that can be served by these two
substations will just be constrained by the capacity of the
existing radial Dasmariñas-Las Piñas 230 kV Line. In this
regard and in view of the challenges in the right-of-way for a
new transmission line from Pasay to Navotas, the
development of another circuits from Dasmariñas to Las
LAS PIÑAS
Piñas has been considered. This new line, which may be able
to align with the route of the Cavite-Laguna Expressway or
CALAX, will further improve system reliability by
providing a separate corridor. Moreover, substation
expansion in Las Piñas will also be required.
DASMARIÑAS
MARILAO
This project aims to provide QUEZON
112
8.1.40 Mexico-Clark 69 kV Line
Major Project Components
Mexico-Clark Line 69 kV T/L, ST-DC 2-795 MCM ACSR, 18 km
113
8.1.42 Western 500 kV Backbone – Stage 2
Major Project Components
Castillejos-Bolo 500 kV T/L, 4-410 mm2 TACSR, ST-DC,
Castillejos-Masinloc: 84 km, Masinloc-Bolo: 90 km;
Castillejos 500 kV S/S, 2-1000 MVA, 500/230-13.8 kV Power
Transformer, 1-90 MVAR 500 kV Shunt Reactor, 11-500 kV
PCB, 6-230 kV PCB, and associated equipment.
2 x 1000 MVA
CASTILLEJOS
higher level of reliability up to N-2
contingency for the 500 kV backbone
system of the Luzon grid. It should be noted
that the existing double-circuit 500 kV
transmission line from Bolo to Nagsaag to San Jose is on common tower structures and that
toppling of a tower (e.g. due to typhoon) would result in simultaneous outage of two circuits
which will completely disrupt the power flow in the 500 kV corridor. Such scenario can be
expected to result in grid congestion due to the required curtailment to the base load coal-fired
power plants in the north. The capacity expansion of Masinloc Plant and entry of other new
plants in the area would further highlight the critical role of the existing 500 kV backbone in
ensuring security of supply, thus, the need to reinforce the transmission network by developing
the Western 500 kV backbone corridor. For the case of Castillejos 500 kV Substation, it will
serve as the new connection point for RP Energy CFPP and can also help support any future
bulk generation development in the area. This Stage 2 project involving very long transmission
lines may still be divided into further staging during implementation.
This project aims to address the reliability and SAN JOSE TAYABAS
stability concerns brought about by the initial
cut-in scheme of Taguig 500 kV Substation.
With the increasing bulk power injection to the
500 kV system in the southern part of Luzon
grid particularly in Quezon Province area, the
BARAS
worst contingency event will be the tripping of
the San Jose-Tayabas 500 kV Line which
would result in bulk power swing towards
Taguig and Hermosa then back to San Jose. TAGUIG
This is under the scenario with Marilao 500
kV Substation not yet in place.
114
8.1.44 Alaminos 500 kV Switching Station
Major Project Components
Alaminos 500 kV S/S, 12-500 kV PCB, 2-30 MVAR 500 kV
Shunt Reactor and associated equipment.
115
As conceptualized, the Silang-Taguig Line will be traversing the Laguna Lake near the shoreline
as the solution to right-of-way problems in establishing a 500 kV backbone within Metro Manila.
The Calaca – Salong 230 kV Transmission Line 2 Project will provide SALONG
provision for single outage contingency for the existing Calaca –
Salong 230 kV Transmission Line. Presently, the Salong 230 kV
SLTEC
Switching Station serves the 2-135 MW SLTEC Coal-Fired Power
BACNOTAN
Plant and the Bacnotan Steel Plant. STEEL
C
2 x 135 MW
116
8.1.48 Liberty-Cabanatuan-San Rafael-Mexico 230 kV Transmission Line
Major Project Components
Liberty-Cabanatuan-San Rafael-Mexico 230 kV T/L, ST-DC,
4-795 MCM ACSR, 140 km.
117
8.1.49 Luzon Voltage Improvement Project 3
Major Project Components
STAGE 1 The network analyses conducted
Laoag 230 kV S/S, 1-35 MVAR & 1-25 MVAR 230 kV Shunt have identified power quality issues at
Reactors and Accessories, 2-25 MVAR 230 kV Capacitor various 230 kV, 115 kV substations,
Banks and Accessories;
69 kV load-end substations as well as
Cabanatuan 230 kV S/S, 2-50 MVAR, 230 kV Capacitor Banks
and Accessories; 500 kV substation in north Luzon. In
Nagsaag 500 kV S/S, 1-90 MVAR, 500 kV Shunt Reactor and order to maintain the system voltages
Accessories; within the PGC-prescribed limits both
Tuguegarao 230 kV S/S, 1-25 MVAR Capacitor Bank and during normal and N-1 contingency
Accessories and 1-25 MVAR, 230 kV Shunt Reactor and
Accessories;
conditions, installation of capacitor
Baler Load-End 69 kV S/S, 3-2.5 MVAR, 69 kV Capacitor Bank banks and shunt reactors will be
and Accessories; required.
Pantabangan Load-end 69 kV S/S, 1-5 MVAR, 69 kV Capacitor
Bank and Accessories ;
Umingan Load-end 69 kV S/S, 3-5 MVAR 69 kV Capacitor Bank
and Accessories;
Paniqui Load-end 69 kV S/S, 3-5 MVAR 69 kV Capacitor Bank
STAGE 2
San Esteban 230 kV S/S, 2-25 MVAR, 230 kV Capacitor Banks
and Accessories;
Botolan 230 kV S/S, 1-25 MVAR 230 kV Shunt Reactor and
Accessories;
Mexico 230 kV S/S, 1-100 MVAR 230 kV Capacitor Bank and
Accessories ;
San Jose 230 kV S/S, 1-100 MVAR 230 kV Capacitor Bank and
Accessories;
Itogon Load-end 69 kV S/S, 1-7.5 MVAR, 69 kV Capacitor Bank
and Accessories;
Antipolo 230 kV S/S, 2-100 MVAR, 230 kV Capacitor Banks and
Accessories; and
Bayambang Load-end 69 kV S/S, 3-5 MVAR 69 kV Capacitor
Bank and Accessories.
118
8.1.50 Luzon Voltage Improvement Project 4
Major Project Components
STAGE 1 The conduct of system study has
Ligao Switching Station, 3-5 MVAR, 69 kV Capacitor Banks identified these 230 kV substations
and Accessories; and 69 kV load-end substations that
Iriga Load-end 69 kV S/S, 2-5 MVAR, 69 kV Capacitor Banks
will experience power quality issues.
and Accessories;
In order to maintain the 230 kV and
STAGE 2 69 kV system voltages within the
Biñan 230 kV S/S, 2-100 MVAR, 230 kV Capacitor Banks and PGC-prescribed limits both during
Accessories; normal and N-1 contingency
Dasmariñas 230 kV S/S, 2-100 MVAR, 230kV Capacitor Banks
and Accessories; conditions, installation of capacitor
Mabini Load-end 69 kV S/S, 3-7.5 MVAR, 69 kV Capacitor banks at various substations is
Banks and Accessories; required.
Cuenca Load-end 69 kV S/S, 3-7.5 MVAR, 69 kV Capacitor
Banks and Accessories;
Taysan Load-end 69 kV S/S, 3-7.5 MVAR, 69 kV Capacitor
Banks and Accessories;
San Juan Load-end 69 kV S/S, 3-5 MVAR, 69 kV Capacitor
Banks and Accessories;
Lagonoy Load-end 69 kV S/S, 3-5 MVAR, 69 kV Capacitor
Banks and Accessories.
119
120
Chapter 9 - Visayas Transmission Outlook
In reference to the DOE list, Cebu and Panay are the main sites for large generation capacity
additions specifically for coal-fired power plants. For RE-based plants, on the other hand, it can
be observed that the concentration is in Negros and Panay Islands. Such direction of generation
development would further emphasize the need to reinforce the 138 kV submarine cable
interconnections between Cebu, Negros and Panay.
Presently, the 230 kV facilities are in Leyte and Cebu only but the development of a 230 kV
transmission backbone to reach up to Panay Island has been part of the master plan in order to
support the generation developments and also to avert the criticality of island grid separations
due to the present long radial line configuration of the Visayas Grid. The implementation of this
project, which is called Cebu-Negros-Panay 230 kV Backbone, is divided into three (3) stages.
The first stage is the additional submarine cable between Negros and Panay. As presented in
Chapter 7, this project is already in the construction stage to immediately address the
congestion and market issues being encountered due to the limited capacity of the existing
single-circuit 138 kV link. Also, the existing Negros-Cebu 138 kV can only export a maximum of
180 MW of excess generation capacity. This will be insufficient just with the entry of committed
power plants only. Thus, the second and third stages of the new 230 kV backbone, which will be
discussed in this chapter, are the next major requirements in the Visayas Grid.
The upgrading of the Panitan-Nabas and Ormoc-Tongonan-Isabel 138 kV Lines is also a priority
project of NGCP. While these lines have been restored already after the onslaught of typhoon
Yolanda in 2013, the implemented Emergency Restoration Systems (ERS) or temporary
structures would remain susceptible to line interruption concerns especially during times of
another calamity. The temporary facilities will be replaced with permanent tower structures
which will already adopt new wind design standards to further improve grid security.
Within Cebu Island where the load center is located, the development of new 230 kV load
substations and implementation of new 230 kV transmission line extensions are required to
ensure adequate supply facilities in the long term. Although not yet included in the DOE list as
of August 15, 2015, there are other bulk generation additions such as the proposed coal-fired
power plant of Salcon Power Corporation and Ludo Power Corporation which will also require
grid reinforcements. Similar with other urbanized area, securing right-of-way in Cebu is also a
major challenge in transmission project implementation.
In Panay, the new developments in the tourism industry in Boracay Island would result in an
increase in power supply requirements. It is projected that the existing 69 kV submarine cable
serving the island would not be adequate in supporting load growth in the coming years. Thus,
this is also one of the areas requiring grid reinforcements through the installation of additional
submarine cable under the Nabas-Caticlan-Boracay 138 kV Transmission Project.
121
Another major submarine cable project to be implemented within the next 10 years is the Cebu-
Bohol 138 kV Interconnection Project. Presently, Bohol Island has power deficiency issue due to
limited power sources in the island. In 2014, the maximum demand in Bohol reached 71MW.
Almost 90% of the island’s demand comes from Leyte via the Leyte-Bohol submarine cable
which is already equivalent to 70% of the submarine cable’s capacity. By 2020, it is expected
that the Leyte-Bohol interconnection will be overloaded. The implementation of this Cebu-Bohol
Interconnection Project would significantly boost the supply reliability to support the load growth
in the island as will be brought about by its direct access to the bulk generations located in
Cebu. It can be noted also that during the Typhoon Yolanda incident affecting the transmission
facilities in Ormoc, Leyte area, the supply for Bohol Island was also interrupted because there is
no alternate source for the island. Such concern will also be addressed by the Cebu-Bohol
Interconnection Project.
Shown in Table 9.1 is the list of transmission projects planned for Visayas in the period 2016-
2025 in addition to the projects already approved by the ERC.
STA. BARBARA
The project is intended SUBSTATION
3 X 50
generators in the area. MVA
Interconnection at 138
kV by expanding Zaldivar CTS into a substation and construction of a 2 km overhead line
terminating to PEDC substation.
124
9.1.3 Cebu-Negros-Panay 230 kV Backbone Project - Stage 3
TOLEDO
SWITCHING
STATION
MAGDUGO
SUBSTATION
BACOLOD
SUBSTATION
2 X 300 MVA
TO
CEBU
SUBSTATION
125
9.1.4 Sta. Barbara-Dingle 138 kV Line 3 Project
The project is intended to improve the delivery of power to the loads connected to the Naga-
Sibonga-Dumanjug 69 kV line. It involves the installation of a new transformer at Colon S/S and
the transfer of the Naga-Sibonga-Dumanjug 69 kV Feeder from Naga S/S to Colon S/S, which
were originally part of the formerly known and ERC-approved New Naga (Cebu) Substation
Project, however, were not implemented as proposed during the 3rd Regulatory Period since the
projected load to be catered by the transformer did not materialize.
The implementation of the remaining works under the New Naga (Colon) Substation Project will
be pursued in the 4th Regulatory Period in consideration of the renewed need to address,
among others, the increase in power demand along the Naga-Sibonga-Dumanjug 69 kV Line.
126
9.1.6 Nabas-Caticlan-Boracay Transmission Project
BORACAY
SUBSTATION NABAS
SUBSTATION
1 x 100 2 x 50
MVA AVON-NABAS MVA
2 x 50
MVA 30
ANTECO AKELCO
MVA
Culasi Nabas
AKELCO AKELCO Lezo
Boracay Caticlan Andagao
Altavas
To address the projected load growth and improve the system reliability in Dumaguete City and
vicinity, there is a need to implement another transmission line with bigger capacity and at
higher voltage. The proposed new line will also allow Negros Oriental Electric Cooperative II
(NORECO II) to source its power from the proposed Dumaguete Substation, thereby unloading
Amlan Substation and the Amlan-Siaton 69 kV line. The proposed implementation scheme will
also minimize transmission loss and improve the power quality to the customers served by the
69 kV line.
To meet the projected demand and provide an alternate source of power, a new line with higher
transfer capacity and at higher voltage is required. There is also a need to establish a 138 kV
drawdown substation in the vicinity of Palo to serve Don Orestes Romualdez Electric
Cooperative, Inc. (DORELCO) and LEYECO II and provide alternate power supply source
(during N-1 contingency event) for the load customers in the area.
128
9.1.10 Umapad 230 kV Substation Project
Major Project Components
Umapad 230 kV S/S (New), 2-150 MVA 230/69-13.8 kV Power
Transformer, 7-230 kV PCB (GIS), 5-69 kV PCB (GIS) and
associated equipment.
substation is proposed. To
achieve this, the double
2 X 150 MVA
circuit overhead component
of the Cebu-Lapulapu
Transmission Project will LAPU-LAPU
SUBSTATION
be energized to 230 kV
from 138 kV. This line will connect Umapad 230 kV Substation to the Cebu 230 kV substation
via 2-795 MCM ACSR. This will then be stepped down to 69 kV via 2-150 MVA transformer.
This is intended to relieve the Cebu – Mandaue 138 kV line and Mandaue 138 kV substation by
providing an alternative 230 kV drawdown substation for VECO.
The project is intended to address the system limitation and restore the reliability of the
Ormoc/Tongonan-Isabel 138 kV Transmission Line. It involves the construction of new steel
tower structures and installation of associated overhead line component. It also aims to provide
N-1 contingency for the transmission corridor between the Isabel, Tongonan and Ormoc
Substations.
The upgrading project also involves the use of steel tower structures with higher wind design
capability.
129
9.1.12 Upgrading of Panitan-Nabas 138 kV Transmission Line
Major Project Components
Panitan-Nabas 138 kV T/L, 128 tower structures and associated
In 2013, the super typhoon Yolanda
overhead line component to be replaced. has caused the toppling of 128 steel
tower structures of the Panitan-Nabas
138 kV T/L. The restoration of the transmission line was undertaken through the use of ERS
and steel pole structures, which offer limited capability in terms of reliably transmitting power.
The project is intended to address the system limitation and improve the reliability of the
Panitan-Nabas 138 kV Transmission Line. It involves the construction of new steel tower
structures and installation of associated overhead line component.
The upgrading project also involves the use of steel tower structures with higher wind design
capability.
Panitan-Nabas
Transmission
Corridor which is
composed of a AVON Culasi Nabas CAPELCO ILECO III CAPELCO EDPP
single circuit 138 Caticlan Mambusao PB 103 Roxas City
Boracay Dau
kV line and a
single circuit 69 kV line. However, during the outage of the 138 kV line, the 69 kV line will have
limited transmission capacity to cater the entire load of the area, hence, will result in power
curtailment.
The project is intended to improve the reliability of the power transmission system towards the
northwestern part of Panay by providing N-1 contingency to the existing single circuit Panitan-
Nabas 138 kV Transmission Line.
130
9.1.14 Naga (Visayas) Substation Upgrading Project
Major Project Components
Naga 138 kV S/S, 6-138 kV PCB and associated equipment. The project is being proposed to
improve the operational reliability of
Naga Substation in Cebu by minimizing outages due to equipment failure, maintenance and
repair works which are expected to occur more frequently and at longer duration. The Naga
Substation was commissioned in 1977, hence, most of the equipment are already antiquated
and are difficult to maintain. This project was formerly named as Naga Substation Rehabilitation
Project.
xxxx
Initially, the Leyte-Bohol Line 2 Interconnection Project was proposed to address the projected
increase in Bohol’s power demand. However, additional considerations, which include the need
to establish a more reliable transmission system towards Bohol, triggered the proposed
development of the Cebu-Bohol Interconnection Project. In comparison with the initially
proposed project, the Cebu-Bohol Interconnection will address the increasing demand and at
the same time improve the reliability of power supply in Bohol Island. It will also serve as an
alternative transmission corridor between Cebu and Leyte/Samar Islands.
Nonetheless, the Leyte-Bohol Line 2 Interconnection may still be implemented in the future and
would serve as a feasible interconnection scheme for the long-term system requirement.
131
9.1.16 Calbayog-Allen 69 kV Transmission Line Project
Major Project Components
Calbayog-Allen 69 kV T/L, SP-SC 1-336.4 MCM ACSR, 78 km; In line with the frequent and extended
Calbayog 69 kV S/S, 1-69 kV PCB and associated equipment. outage of the 69 kV lines in the area,
construction of a 69 kV line from
Calbayog to Allen is needed to form a loop and provide CALBAYOG
SUBSTATION
single outage contingency (N-1) capability to the
transmission lines serving Northern Samar.
50 MVA
ALLEN
SUBSTATION
BOBON
LES
BOBOLOSAN
LES
132
9.1.18 Visayas Substation Upgrading Project - 1
Major Project Components
LEYTE To accommodate the projected
demand and avoid overloading of the
Tabango 230 kV S/S, 1-50 MVA 230/69-13.8 kV Power transformer, there is a need to
Transformer, 2-230 kV PCB, 1-69 kV PCB and associated upgrade the substation capacity of
equipment.
Maasin 138 kV S/S, 1-50 MVA 138/69-13.8 kV Power
Tabango Substation.
Transformer, 2-138 kV PCB, 1-69 kV PCB and associated
equipment; To accommodate the proposed
100MW CEKO Solar Power Plant,
SAMAR
there is a need to upgrade the
Calbayog 138 kV S/S, 1-50 MVA 138/69-13.8 kV Power substation capacity in Daanbantayan
Transformer, 1-138 kV PCB, 2-69 kV and associated Substation.
component;
To comply with N-1 contingency
CEBU
criterion of the PGC, an additional 50
Daanbantayan 230 kV S/S, 1-100 MVA 230/69-13.8 kV Power MVA transformer needs to be
Transformer, 1-230 kV PCB, 3-69 kV PCB and associated installed at Maasin Substation.
equipment.
To improve reliability by
DINGLE BAROTAC VIEJO
providing N-1 in Natividad
LES of ILECO III,
Barotac Viejo- Natividad
transmission line is
needed to form a loop
that will enable transfer of
load from Natividad LES
NATIVIDAD
to Barotac Viejo
Substation during outage
of one transformer in Dingle Substation.
133
9.1.20 Kabankalan Substation Reliability Improvement Project
Major Project Components
Substation Reconfiguration (no additional major equipment)
To improve the system reliability of
the 138 kV lines to Bacolod and
Mabinay Substations and prevent partial blackout during double-bus outage in Kabankalan
Substation, the Kabankalan-Bacolod and Kabankalan-Mabinay 138 kV lines should be
connected in the same switchbay. The proposed connection scheme will ensure continuity of
supply in Northern Negros and Panay during the simultaneous outage of the two 138 kV buses
at Kabankalan Substation.
2 X 50 MVA
QUINAPUNDAN
SUBSTATION
2 X 50 MVA
134
9.1.23 Visayas Substation Upgrading Project – 2
PANAY
135
9.1.25 Maasin-Javier 138 kV Transmission Line Project
MAASIN
JAVIER
Major Project Components SUBSTATION
SUBSTATION
Maasin-Javier 138 kV T/L, ST-DC, 1-795 MCM ACSR, 105 km;
Maasin 138 kV S/S, 3-138 kV PCB and associated equipment;
Javier 138 kV S/S (New), 2-50 MVA 138/69-13.8 kV Power
Transformer, 6-138 kV PCB, 5-69kV PCB and associated
equipment.
2 X 50 MVA
To address the low voltage and improve reliability, the system needs another transmission line
with bigger transfer capacity, at higher voltage and a new drawdown substation in the vicinity of
Javier. This proposed Javier Substation could serve the entire SOLECO customers. DORELCO
and LEYECO II Load-end Substations may also be shifted to this proposed substation during
N-1 contingency event.
136
Chapter 10 – Mindanao Transmission Outlook
The recent major transmission development in Mindanao is the completion of a 230 kV-
designed transmission backbone system from Balo-i, Lanao del Sur to Villanueva, Misamiz
Oriental then down to the Bunawan in Davao del Sur. This facility, which is initially energized at
138 kV, facilitates the transfer of bulk power from the hydro power plant complex in the north
going to the load centers in the south of Mindanao.
In its generation capacity mix in the past years, Mindanao is known as a hydro generation
dependent grid, thus, the adequacy of supply has always been a major concern during dry
season. However, the power supply deficiency being experienced in Mindanao is slowly being
averted by the entry of bulk generation capacity additions from a number of coal-fired power
plant projects. To facilitate its integration to the grid, further extensions of the 230 kV system
have been required to reach the bulk generation sites as in the case of GNPower Kauswagan,
TSI, and SMC Malita. It can be noted also that the new power plants have plans for generation
capacity expansions in the future which would reach a total of 600 MW to 1,200 MW capacity in
each site. Such developments would already necessitate the energization of the Mindanao
backbone to 230 kV voltage level to increase its transmission capacity.
Furthermore, because of the aggressive plans for future plant expansion which could be more
than enough for the Mindanao loads particularly during wet season, there is an increasing
clamour to pursue already the Visayas-Mindanao Interconnection Project in order to allow
export of power to the other grids. This major interconnection project, which is the final link to
interconnect the Philippine Grid, is further discussed in Chapter 11.
In other parts of Mindanao, the requirements generally include reinforcements of the existing
138 kV transmission lines and extension also of some 69 kV facilities for system reliability
improvement, and the usual transformer capacity additions in the substations for continuous
adequate supply for the load customers.
Shown in Table 10.1 is the list of transmission projects planned for Mindanao Grid in the period
2016-2025 in addition to the projects already approved by the ERC.
137
Table 10.1: Proposed Transmission Projects for Mindanao
Project Name/Driver(s) Province(s) ETC
Generation Entry
Mindanao 230 kV Transmission Backbone Mindanao Island Dec 2018
Balo-i-Kauswagan-Aurora 230 kV Lanao del Norte, Misamis Occidental,
Dec 2022
Transmission Line (Phase 2) Zamboanga del Sur
Load Growth
Mindanao Substation Upgrading Mindanao Island Dec 2022
System Reliability
Kabacan 138 kV Substation Cotabato Dec 2021
Villanueva-Jasaan-Butuan 138 kV
Misamis Oriental, Agusan del Norte Dec 2021
Transmission Line
Mindanao Substation Rehabilitation Mindanao Island Dec 2022
Balo-i-Tagoloan-Opol 138 kV Transmission
Lanao del Norte and Misamis Oriental Dec 2025
Line
Tacurong-Sultan Kudarat 138 kV Transmission
Maguindanao, Sultan Kudarat Dec 2025
Line
138
10.1.1 Mindanao 230 kV Transmission Backbone
Major Project Components
Matanao-Toril 230 kV T/L, ST-DC, 4-795 MCM ACSR, 34 km;
Toril-Bunawan 230 kV T/L, ST-DC, 4-795 MCM ACSR, 40.2 km;
Malita 230 kV S/S, 1-50 MVA 230/69 kV Power Transformer;
Matanao 230 kV S/S, 2-230 kV PCB and associated equipment;
Toril 230 kV S/S, 2-300 MVA 230/138 kV Power Transformer;
10-230 kV PCB, 6-138 kV PCB and associated equipment;
Bunawan 230 kV S/S, 2-300 MVA 230/138 kV Power
Transformer; 10-230 kV PCB, 1-69 kV PCB and associated
equipment;
Balo-i 230 kV S/S, 10-230 kV PCB and associated equipment;
Villanueva 230 kV S/S, 2-300 MVA 230/138 kV Power
Transformer; 2-35 MVAR Reactor, 12-230 kV PCB, 1-69 kV
PCB and associated equipment;
Maramag 230 kV S/S, 4-230 kV PCB and associated equipment.
BALO-I 230 kV
The project will provide additional high
voltage corridor for the upcoming power
300 MVA 300 MVA
plants in the northern and southern parts 300 MVA 300 MVA
50 MVA
139
10.1.2 Balo-i-Kauswagan-Aurora 230 kV Transmission Line (Phase 2)
Major Project Components AURORA 69 kV
AURORA 138 kV
The project will ensure the reliability of power supply to
the entire Zamboanga Peninsula given that majority of
300 MVA 300 MVA
power is being supplied through the existing Balo-i –
Aurora and Balo-i – Agus 5 – Aurora 138kV
AURORA 230 kV
transmission lines, which are critically loaded during N-
1 contingency condition. Considering the growing
demand and reliability of these existing transmission
lines connecting the Zamboanga Peninsula to the VMIP
KAUSWAGAN 138 kV
140
10.1.3 Mindanao Substation Upgrading
Major Project Components
This project involves the installation of
Polanco 138 kV S/S, 1-75 MVA 138/69 kV Power Transformer, a total of 975 MVA power
3-138 kV PCB, 1-69 kV PCB and associated equipment; transformers, 52.5 MVAR capacitor
Naga 138 kV S/S, 1-100 MVA 138/69 kV Power Transformer, banks, 19 – 138 kV power circuit
2-69 kV PCB and associated equipment; breakers (PCB) and 22 – 69 kV PCB.
Pitogo 138 kV S/S, 1-100 MVA 138/69 kV Power Transformer,
1-138 kV PCB, 1-69 kV PCB and associated equipment; Also included in the project are the
Agus 6, 1-100 MVA 138/69 kV Power Transformer, 2-138 kV replacement of 14 – 138 kV and 28 –
PCB and associated equipment; 69 kV PCB.
Maramag 138 kV S/S, 1-75 MVA 138/69 kV Power Transformer, It will enable various substations in
1-138 kV PCB, 1-69 kV PCB and associated equipment;
Tagoloan 138 kV S/S, 1-100 MVA 138/69 kV Power
Mindanao Grid to accommodate
Transformer, 3-138 kV PCB, 2-69 kV PCB and associated projected load growth and to comply
equipment; with the single-outage (N-1)
Opol 138 kV S/S, 1-75 MVA 138/69 kV Power Transformer, 4- contingency provision prescribed
138 kV PCB, 5-69 kV PCB and associated equipment; under the Philippine Grid Code
Butuan 138 kV S/S, 1-100 MVA 138/69 kV Power Transformer,
2-7.5 MVAR Shunt Capacitor, 5-138 kV PCB, 5-69 kV PCB (PGC). The project also includes the
and associated equipment; installation of capacitor banks that
Placer 138 kV S/S, 1-100 MVA 138/69 kV Power Transformer, can improve the voltage regulation of
1-7.5 MVAR Shunt Capacitor, 3-138 kV PCB, 6-69 kV PCB the network and reduce transmission
and associated equipment;
Bislig 138 kV S/S, 1-50 MVA 138/69 kV Power Transformer, 4-
system losses. Lastly, it will replace
138 kV PCB, 5-69 kV PCB and associated equipment; old, obsolete and underrated PCB to
San Francisco 138 kV S/S, 1-50 MVA 138/69 kV Power avoid frequent breaker failures and
Transformer, 2-7.5 MVAR Shunt Capacitor, 4-138 kV PCB, power interruptions.
3-69 kV PCB and associated equipment; The additional power transformers,
Kidapawan 138 kV S/S, 1-50 MVA 138/69 kV Power
Transformer, 1-138 kV PCB, 2-69 kV PCB and associated installation of capacitor banks and
equipment; replacement of old, obsolete and
Gen. Santos 138 kV S/S, 1-7.5 MVAR Shunt Capacitor, 1-138 underrated PCB, are part of the plan
kV PCB, 8-69 kV PCB and associated equipment; of NGCP to ensure adequate, reliable
Tacurong 138 kV S/S, 1-7.5 MVAR Shunt Capacitor, 1-138 kV
PCB, 10-69 kV PCB and associated equipment
and quality power transmission
system.
km.
50 MVA
The new Kabacan Substation is proposed to be situated in Cotabato which will serve as the
terminal point for the Kibawe – Kabacan double-circuit line and new connection point for Sultan
Kudarat – Kabacan and Tacurong – Kabacan 138 kV lines. The new substation will also cater
load end substations connected at Sultan Kudarat – Midsayap 69 kV line and Kidapawan –
Matalam (Manauban) 69 kV line, further connecting the Kidapawan Substation to the proposed
substation. The Project, likewise, will serve as a loop connection scheme for the 69 kV lines in
the vicinity giving flexibility in transmitting power to Sultan Kudarat Substation during critical
incidents. Sultan Kudarat can then draw its power requirement from adjacent substations
through Kabacan – Sultan Kudarat 138 kV line which offers more secured power transmission
than the existing Tacurong – Cotabato – Sultan Kudarat 69 kV line.
142
10.1.6 Mindanao Substation Rehabilitation
Major Project Components
Aurora 138 kV S/S, 1-138 kV PCB, 3-69 kV PCB and associated Mindanao Substation Rehabilitation
equipment; Project aims to replace defective, old,
Zamboanga 138 kV S/S, 3-138 kV PCB, 2-69 kV PCB and obsolete and low fault level capacity
associated equipment; PCBs in the Mindanao Grid. This
Balo-I 138 kV S/S, 13-138 kV PCB and associated equipment;
Agus 5 S/S, 4-138 kV PCB and associated equipment; involves the replacement of 47 – 138
Lugait 138 kV S/S, 5-138 kV PCB and associated equipment; kV and 25 – 69 kV Power Circuit
Pulangi 4 S/S, 10-138 kV PCB, 3-69 kV PCB and associated Breakers (PCB) in eleven (11) NGCP
equipment; substations. Implementation of project
Nasipit 138 kV S/S, 4-138 kV PCB and associated equipment;
Davao 138 kV S/S, 4-138 kV PCB, 6-69 kV PCB and associated
will increase the reliability of the
equipment; network, reduce/prevent unserved
Maco 69 kV S/S, 2-69 kV PCB and associated equipment; energy, and reduce costly
Nabunturan 138 kV S/S, 3-138 kV PCB, 5-69 kV and associated maintenance expenses. Lastly, the
equipment; implementation of the project can
Sultan Kudarat 69 kV S/S, 4-69 kV PCB and associated
equipment. improve personnel safety and
decrease incidents of breaker
failures.
143
10.1.8 Tacurong-Sultan Kudarat 138 kV Transmission Line
Major Project Components
Tacurong-Sultan Kudarat 138 kV T/L, ST-SC, 1-795 MCM
ACSR, 101 km;
Tacurong 138 kV S/S, 2-138 kV PCB and associated equipment;
Sultan Kudarat 138 kV S/S Expansion, 2-138 kV PCB and
associated equipment.
144
Chapter 11: Major Island/Grid Interconnection
With the archipelagic nature of the Philippines, one of the challenges in improving the system
reliability and reducing the reserve requirements without adding new generation is the
interconnection of two or more islands by the use of an undersea cable. Major considerations in
the implementation of such kind of project are the required investment and the potential
generation resources in the concerned island. The power cable systems have exhibited high
reliability and long life of more than 20-30 years with limited maintenance.
As of December 2015, the Philippines has seven major undersea island interconnection
systems: six High Voltage Alternating Current (HVAC) and one High Voltage Direct Current
(HVDC). These are the Leyte-Luzon ± 350 kV HVDC, Leyte-Cebu 230 kV, Negros-Panay 138
kV, Cebu-Negros 138 kV, Cebu-Lapu-lapu 138 kV HVAC and the Panay-Boracay 69 kV AC
Interconnection facilities. The 432-km Leyte-Luzon ± 350 kV HVDC, with a 23-km connecting
Leyte Island (via Samar Island) to the Luzon Grid has been in operation since 1998. Its
maximum transmission capacity is 440 MW with provision for upgrade to 880 MW.
The Leyte-Cebu interconnection is a 33-km double circuit 230 kV submarine cable, with a
transfer capacity of nearly 400 MW. The first and second circuits were energized in 1997 and
2005, respectively. The double circuit Cebu-Negros Interconnection enables power sharing of
maximum of 180 MW between Cebu and Negros Islands. Its first circuit of 18-km, 138 kV
submarine cable was energized in 1993 while its second circuit was energized in 2007. From
Negros Island, connected is the 18-km 138 kV Negros-Panay Interconnection, energized in
1990 with a rated capacity of 85 MW.
Connecting the island of Mactan to mainland Cebu is the 8.5-km 200 MW capacity cable that
was energized in 2005. It is laid underneath the Cebu-Mactan Bridge. Another island
interconnection is the Leyte-Bohol Interconnection, a submarine cable that allows a maximum
power flow of 90 MW to the island of Bohol since 2004.
145
d) Renewable and indigenous energy sources, such as wind, hydro and geothermal
potential sites suitable for energy generation may also be taken into consideration.
These are clean and sustainable sources of energy that may become attractive for
development by generation proponents as a result of a wider market due to island
interconnection.
Considering these salient and other intangible benefits, island interconnections become more
economically attractive in the long run. However, detailed studies should be undertaken to
quantify the overall benefits to the receiving island.
The following major considerations shall be taken into account in the project development of
island interconnections:
a) The depth of the seabed between two islands is always an issue in interconnecting
islands. This is due to mechanical stress that the cable must be designed to withstand
cable weight, sea current, bottom drag, etc. during installation and repairs;
b) The use of HVAC or HVDC transmission systems, the size and length of the cable, the
existing situation of the grid, estimated load growth, environmental impact and public
acceptance and the possibilities for the development of energy resources; and
c) On the operational side, single outage contingency or N-1 reliability criterion needs to be
clarified further if it will be economically beneficial to the power consumers.
Figure 11.1 shows the development of transmission backbones and island interconnections.
While some segments of the transmission backbones are already programmed for
implementation within the Fourth Regulatory Period (2016-2020), as discussed in Chapters 8, 9
and 10, other segments will still be subjected to a more thorough system analyses or even
Feasibility Study for some big and more complicated backbone projects.
For Major Island Interconnections, however, no dominant projects driver is deemed appropriate
to trigger its implementation. In this sense, both the Batangas-Mindoro and Visayas-Mindanao
Interconnection Projects would seem to require a strategic decision, which will deeply involve
both the oversight and regulatory agencies of the government, hence these island
interconnection projects fall under “Strategic Interconnection”. NGCP is conducting related
studies, e.g., economic, system and other studies to support its application to secure approval
of the ERC.
Figure 11.2 shows the Existing and Future Philippine Network Topology of an interconnected
grid.
146
11.2.1 Transmission Master Plan (TMP)
The formulation of the Transmission Master Plan (TMP) is guided by NGCP’s vision to build the
strongest power grid in Southeast Asia, to contribute to the social and economic development of
the country and to satisfy its stakeholders’ need. These are vital considerations to ensure that
the country has a transmission network that can support growth and competitive electricity
prices. This is done through a program that will significantly upgrade and expand the
transmission backbone in order to meet the forecast demand, support the entry of new
generating facilities and allow market competition.
The creation of an interconnected Philippine Grid will also be among the considerations. As the
Luzon and the Visayas Grids are already interconnected, connecting the Visayas and Mindanao
would create more open, liberalized and competitive market as Mindanao-based industry
players can participate freely in Wholesale Electricity Spot Market.
147
Figure 11.1 - Transmission Backbones and Island Interconnections
148
LUZON
300 MW (2021)
230 kV OHTL and Sub. Cable
440 MW (1998) – Monopolar
880 MW (Future) – Bipolar
±350 kV HVDC Leyte-Luzon Int.
Mindoro Island OHTL and Sub. Cable
VISAYAS
300 MW (Future)
HVDC or HVAC
Boracay Island OHTL and Sub. Cable
100 MW (2019)
40 MW (2006)
Samar Island
138 kV OHTL and
69 kV OHTL and Sub. Cable
Sub. Cable
90 MW (1989)
Panay Island 185 MW (1997) 180 MW (2019)
185 MW (2005) 138 kV OHTL
(with N-1)
85 MW (1990) 230 kV OHTL and Sub. Cable
138kV OHTL and
Sub. Cable Cebu Island Leyte Island
240/400MW
(2017) 200 MW (2005)
230kV OHTL and 138 kV XLPE 90 MW (2004)
Sub. Cable UGC / Sub. Cable 90 MW (Future)
240 MW (2015) 138 kV OHTL
Negros Island 230 kV OHTL and and Sub. Cable
Sub. Cable
90 MW (1993)
90 MW (2007) Mactan Is. Bohol Island
138 kV OHTL and (Lapu-lapu)
Sub. Cable
400 MW (2020)
230 kV OHTL and
Sub. Cable 100 MW (2020)
138 kV XLPE HVAC
OHTL and Sub. Cable
149
11.2.1 Batangas-Mindoro Interconnection Project (BMIP)
The power system of Mindoro Island, which is composed of 69 kV lines connected to several
power plants and various load-end substations, is presently being operated by Small Power
Utilities Group (SPUG) of the National Power Corporation (NPC). Power distribution to the
consumers is handled by Oriental Mindoro Electric Cooperative (ORMECO) and Occidental
Mindoro Electric Cooperative (OMECO). The major load center is in Calapan City in Oriental
Mindoro and the total peak demand of the island in 2015 was more than 60 MW already, based
on the combined total load of ORMECO and OMECO.
As the implementation of an interconnection project may take some time, further generation
capacity additions within Mindoro Island would still be required to be able to sustain the short-
term and medium term power supply requirements of its increasing load. The interconnection of
the island with the main Luzon Grid was envisioned to provide the island the access to bulk
generation sources in the main grid while at the same time providing the means to export
possible excess power once the generation potentials, including RE-based plants, within the
island have been developed. The improvement in reliability of supply is expected to result in
better economic growth as the island could attract more investors for industrial, commercial
loads and for the tourism industry.
Transmission line route investigation has been already conducted including the identification of
the possible cable terminal stations (CTS) at Batangas and Mindoro side. The nearest NGCP
Substation in the Luzon Grid that could serve as the connection point for the proposed
interconnection project is the Batangas Substation in Barangay Mahabang Parang, Batangas
City. Presently, the substation is serving Batangas II Electric Cooperative (BATELEC II), Manila
Electric Company (MERALCO) and various industries.
In Mindoro side, considering that the NPC-owned Calapan 69 kV Substation is the major bulk
power delivery point to Mindoro Island, it is appropriate to locate the 230 kV receiving-end
substation (RES) of the proposed interconnection project adjacent to the 69 kV substation in
Barangay Canubing (Simaron), Calapan City. At present, the 69 kV substation has two switch
bays arranged in one-and-a-half breaker scheme composed of six 69 kV Power Circuit Breakers
(PCBs) protecting two 69 kV lines, the Minolo (Mamburao) and Pinamalayan (Bansud) and two
power transformers rated at 30 MVA and 20 MVA, 69/13.8 kV.
While a hydrographic survey is still needed to determine the detailed seabed profile, it was
initially determined that the submarine power cables can be laid from Barangay Soloc, Lobo,
Batangas City to Barangay Mahal na Pangalan, Calapan, Oriental Mindoro across the Verde
Island Passage located in the Sulu-Sulawesi Seascape considered as a Marine Biodiversity
Conservation Corridor as declared in Executive Order No. 578. Therefore, laying of submarine
power cables shall also be coordinated with the Protected Area Management Board (PAMB),
tasked to implement this executive order.
The linear distance between Lobo CTS and Mahal na Pangalan CTS is approximately 23.85
km, while the length of the submarine power cables taking into consideration the sea bottom
topography is approximately 25 km. The maximum depth of water along this route is 500
meters.
150
The interconnection of Mindoro would only serve as the initial stage in the development of the
power system in the island. Calapan would serve as the interconnection point but given the
configuration of the island involving long 69 kV lines, in-land generators will still have to operate
to provide voltage regulation support. In the long term, a 230 kV backbone system within the
island could be developed as well as the future establishment of a loop to Panay Island thereby
providing another corridor for the Luzon and Visayas link.
The tangible benefits in terms of reduced investments in power generation due to the
implementation of VMIP are due to the following:
a) The benefit that is difficult to be quantified in monetary terms includes the attractiveness
of VMIP to power generation investments due to the bigger market through an
interconnected power network;
b) From a technical standpoint, VMIP will provide benefit to the system in terms of added
supply security, improved system reliability and improvement in the quality of power
supply; and
151
c) The optimized utilization of indigenous energy sources, such as natural gas in Luzon,
geothermal in the Visayas and hydro in Mindanao. VMIP will reduce the overall
generation of pollution as well as the dependency on the importation of fossils fuel, where
its availability and price are sensitive to the price in the world market.
The implementation of VMIP will also complement the ultimate operation of the Wholesale
Electricity Spot Market (WESM) in Mindanao. As a transition mechanism to the operation of the
WESM, the Interim Mindanao Electricity Market (IMEM) commercial operations was initially
launched in Davao City on September 20, 2013.
On 02 March 2011, more than a decade after the completion of the detailed design of the
Project, the DOE directed the National Grid Corporation of the Philippines (NGCP) “to lead the
conduct of the study relative to the Project and include such venture in the Transmission
Development Plan (TDP).” The review of the previous studies was brought by the updated
assumptions of the Leyte-Mindanao Interconnection. The economic, financial and pre-
engineering studies for the interconnection will involve substantial budget to complete.
Inasmuch as no relevant capital expenditures (CAPEX) were allotted for this Project in the Third
Regulatory Period, the NGCP filed the application for the issuance of Provisional Authority (PA)
with the Energy Regulatory Commission (ERC) in March 2011.
On August 15, 2011, NGCP was granted by the ERC under Case No. 2011-037RC the PA for
the implementation of Phase I of the Leyte-Mindanao Interconnection Project (LMIP), which
involves the preparation of an updated Project Feasibility Study.
In 2012, NGCP engaged the services of China Electric Power Research Institute (CEPRI) to
conduct the System Study to review the design and technical aspects of the interconnection
based on the latest supply-demand outlook, grid structure, emerging new technologies and
other key conditions.
Based on the results presented by EGS Asia Ltd. for the survey in the Eastern Route for Phase
I of the LMIP, NGCP found it necessary to investigate and explore the Western Route to be able
to arrive at a more prudent investment decision.
152
The conduct of Hydrographic Survey for the Western Route option aims to obtain the following
results:
• Determine the feasible routes for the proposed submarine cable interconnection;
• Assess engineering risks along the possible cable routes;
• Identify parameters and methods for the design and implementation of the submarine
cable laying; and
• Determine other factors that should be considered in the detailed design of the project.
The proposed VMIP, on the other hand, will have a capacity of 450 MW and will use bipolar HVDC
system. With long-term consideration, both the proposed VMIP and the existing Luzon-Visayas
Interconnection have provision for future additional 450 MW and 440 MW capacity, respectively.
Once the Visayas-Mindanao Interconnection Project is approved by the ERC, the implementation
of the project can proceed and the earliest project completion is Dec 2020.
The following are the feasibility/planning and conceptual design-related activities and other
information:
Except for Converter Stations, which are already based on December 2013 conceptual
design prepared by HVDC Experts from State Grid Corporation of China (SGCC), all
other major project components were based on System Study completed in January 2013
by China Electric Power Research Institute (CEPRI);
Stage 1 of the project has a capacity of 1-225 MW per pole, hence the total capacity of
the conventional bipolar Converter Stations is 450 MW. While Stage 2 of the project
requires an additional 1-225 MW per pole, hence the ultimate capacity of the Converter
Stations is 900 MW;
Both ±350 kV HVDC overhead lines and submarine cables will already be designed with
an ultimate or maximum power transfer capacity of 900 MW;
In a Conventional Bipolar Scheme, outage in one pole reduces the transfer capacity by
half (or 50%). Unlike in an HVAC system, single outage (N-1) contingency is not
considered due to sizeable amount involved (or it will not be economically viable);
The hydrographic/marine survey for the Eastern Option involving Surigao Strait was
undertaken in December 2013 to April 2014 by EGS (Asia) Inc., a Cebu-based Earth
Sciences and Surveying Company with regional hub in Hong Kong for its business
operations in South East Asia. EGS (Asia) Inc. has initially recommended an alternative
with lower environmental impact; and
The result of marine/hydrographic survey in the Surigao Strait for the Eastern Option
revealed the following major challenges:
b) Strong seabed currents ranging from 0.58 meter per second (m/s) to 2.00 m/s.
These would certainly be sufficient to move either a bare cable or cable in shells, thus
surface laying is not recommended. Generally, 0.50 m/s and below can be deemed
153
safe for surface laying. On the other hand, cable trenching is likewise not
recommended due to the existence of hard rocks with Ultimate Tensile Strength
(UTS) of over 60 Mega Pascals, which is beyond the rock cutting capability of
available cable trenching machines; and
d) Increase in the overall cost estimate given that the recommended cable
route is 67km, a distance that is longer compared to the shortest cable route
option 1 which is only 30km in distance.
With the above findings on the Eastern Option for VMIP, NGCP decided that it will be
prudent to consider exploring the Western Option, which includes the area between
Negros to Cebu Islands facing Mindanao (Zamboanga Del Norte and Misamis
Occidental). The corresponding implementation schemes are shown in Figure 11.3a and
11.3b.
Pending the completion of both Grid Impact Study (GIS) as well as the field investigation and
conceptual design for the Western Option, listed below are the initial project components, which
exclude length of submarine cables, overhead lines (consist of DC, AC and electrode lines) and
specific locations of Converter Stations (CS), Cable Terminal Stations (CTS) and Electrode
Stations (ES):
I Land Portion
b) Electrode Lines/Stations:
Mindanao CS–Mindanao ES 20 kV OHTL (2 Lines), 2-795 MCM ACSR Condor;
Mindanao ES; and
Visayas CS-Visayas ES, 20 kV OHTL (2 lines), 2-795 MCM ACSR Condor.
154
Oil immersed DC Smoothing Reactor; 2 groups of double-tuning passive DC filters and 2
large groups with 4 small groups AC filters;
DC Field Equipment including DC High-Speed Switches, Metallic Return Transfer
Breaker, Ground Return Transfer Switch, various DC Switches, DC Measuring equipment
and wall bushings; and
Secondary System including Operator Control, AC/DC Station Control, Pole Control, DC
Protection, Station Master Clock, Fault Recording, DC Line Fault Location, AC Protection,
Revenue Metering, Auxiliary System, Management Subsystems of Relay Protection and
Fault Information and Telecontrol and Telecommunication Equipment.
d) Substations:
S/S Expansion (Visayas): 6-230 kV PCB and associated equipment;
S/S Expansion (Mindanao): 2-300 MVA, 230/138-13.8 kV Power Transformers and
accessories; and
Other Equipment/Facilities identified based on the result of GIS, e.g., power
compensating equipment, etc.
II Marine Portion
Visayas CTS-Mindanao CTS, ±350 kV HVDC, Bipolar, 1,500 mm2 HVDC Mass Impregnated
(MI) submarine cable.
155
Figure 11.3a –Possible Connection on Western Route (Option 1)
156
Figure 11.3b – Possible Connection on Western Route (Option 2)
157
Results of the Hydrographic Survey for the Western Route
The offshore survey was conducted by EGS (Asia) Inc. from 14 October 2016 to 09 November
2016. The survey involved investigations of the topography at the landing sites, the bathymetry,
seabed features and shallow geology across the Dipolog Strait; and, meteorological and
oceanographic measurements for the design of the cables.
CEBU LANDING
POINT
NEGROS
LANDING POINT
CEBU-DIPOLOG ROUTE, 92 km
158
Summary and Recommendation
The figure below summarizes the Eastern and Western route options for VMIP with Table
comparing the length of transmission facilities as well as the maximum water depth.
Eastern Route
Hydrographic survey found
unusually high risks in this route
for power cable installation:
Western Route
Hydrographic survey found that
the route is marked by
generally low to moderate
gradients and avoids areas
with strong seawater current
230 m
Maximum Water Depth (m) 640 m 705 m (actual depth for cable
laying)
159
The result of the survey shows a favorable option along the Western Route. With this option, the
Mindanao-Cebu route is preferred as it is marked by generally low to moderate gradients and
avoids areas where strong seawater currents have exposed the rough, rocky seabed. Most
seabed sediments are loose to dense sand near Santander and fine sand over highly
weathered sedimentary rocks near Tagalo Point, which should not pose any problem during
construction. This preferred route has an estimated length of about 92 kilometers as shown in
Figure 11.5.
Inverter/
Converter
92 km
102
km
Inverter/
Converter
160
11.2.3 Small Island Interconnection Projects
A significant number of islands in the country remain isolated from the main grid. The power
system in the island is being operated and managed by the Small Power Utilities Group (SPUG)
of the National Power Corporation. Summarized in Table 11.3 below are the potential small
island interconnections indicating the length of the required facilities and the peak load in the
island:
It should be noted that further project assessments are required for the small island
interconnections listed above.
161
162
Chapter 12 - Appendices
163
Appendix 2 – ASEAN Power Grid (APG)
Realizing the importance of building a regional power grid among ASEAN member countries
through cross-border transmission links, the Heads of ASEAN Power Utilities/Authorities
(HAPUA) initiated the conduct of ASEAN Interconnection Master Plan Study (AIMS). It is
envisioned that the establishment of the ASEAN Power Grid would allow pooling of the energy
resources of the member countries and that the diversity in demand patterns and time zones
would provide opportunities for power sharing and greater optimization of generation capacity.
Moreover, this undertaking is also expected to promote sharing of experiences and close power
cooperation in the region.
As shown in Figure 11.6, the Philippine Grid will form part of System C and the identified
interconnection is the Philippine-Sabah Interconnection Project. The line will traverse within the
islands of Palawan and Mindoro and the proposed interconnection point is at Ilijan 500 kV
Substation in the Luzon Grid. In AIMS-II completed in 2010, this proposed ±500 kV HVDC
interconnection is at 500 MW capacity and the identified earliest commercial operation year is
2020. It should be noted, however, that this more than 800-km interconnection project will still
require further feasibility study. Also, the harmonization of the operational and regulatory
framework, tariff structure, as well as mechanism for pool rules among member countries will
still require further discussions.
164
Figure A2 - The ASEAN Power Grid
165
Appendix 3 – Other Renewable Energy Potential6
Table A3.2 Calculated Biomass Energy derived from Production Data (2011) with Total Potential Energy in
megawatt-hour units for Provinces in the Visayas
6
All data presented in Appendix 3 are sourced from DOE.
166
Table A3.3 HYDROPOWER SITES OFFERED FOR OCSP
No. Island Name of Project Location Max Output Annual Energy Type
(kW) Generation
(MWh)
1 Bohol Upper Manaba Garcia-Hernandez, Bohol 1,000 6,094 Run of River
2 Bohol Balite Baggao, Cagayan 1,000 6,997 Run of River
3 Bohol Lower Manaba Garcia-Hernandez, Bohol 800 4,826 Run of River
4 Bohol Odiong Jagna, Bohol 500 2,759 Run of River
5 Mindoro Sinambalan No. 1 Abra de Ilog, Occidental 3,000 17,946 Run of River
Mindoro
6 Mindoro Pagbahan No. 1 Sta. Cruz, Occ. Mind 6,000 31,946 Run of River
7 Negros Binalbagan No. 1 Moises Padilla, Neg. Occidental 13,000 64,506 Pondage
8 Negros Binalbagan No. 2 Moises Padilla, Neg. Occidental 5,000 35,546 Run of River
9 Negros Binalbagan No. 3 Moises Padilla, Neg. Occidental 4,000 27,934 Run of River
10 Negros Lag-il No. 1 Binalbagan, Negros Occidental 1,000 8,677 Run of River
11 Negros Lag-il No. 2 Binalbagan, Negros Occidental 2,000 13,750 Run of River
12 Negros Pangiplan Himamaylan, Neg. Occidental 1,000 8,407 Run of River
13 Negros Hilabangan No. 3 Himamaylan and Kabankalan, 4,000 29,360 Run of River
Negros Occidental
15 Negros Calatong No. 1 Sipalay, Negros Occidental 1,000 8,801 Run of River
16 Negros Calatong No. 2 Cauayan, Negros Occidental 2,000 11,747 Run of River
17 Negros Binulug Sipalay, Negros Occidental 3,000 21,932 Run of River
18 Negros Mona-ol Bana-ol, Negros Oriental 900 6,768 Run of River
19 Negros Cauitan Santa Catalina, Neg. Oriental 1,000 11,207 Run of River
20 Negros Canauay Zamboanguita, Neg. Oriental 600 4,255 Run of River
21 Negros Himogaan Calatrava, Negros Occidental 2,000 13,169 Run of River
22 Negros Guinoba-an No. 1 La Libertad, Negros Oriental 4,000 33,167 Run of River
23 Negros Pacuan La Libertad, Negros Oriental 4,000 31,174 Run of River
24 Negros Guinoba-an No. 2 La Libertad, Negros Oriental 3,000 27,157 Run of River
25 Negros San Jose La Libertad, Negros Oriental 600 4,310 Run of River
26 Negros Talaptap Bindoy, Negros Oriental 1,000 9,664 Run of River
27 Negros Hinotongan Sibulan, Negros Oriental 600 4,286 Run of River
30 Panay Dugayan Libertad, Antique 1,000 6,949 Run of River
31 Panay Bulanao No. 1 Libertad, Antique 1,000 6,561 Run of River
32 Panay Tibiao No. 2 Tibiao, Antique 2,000 9,191 Run of River
33 Panay Ulian No. 2 Lambunao, Iloilo 1,000 7,482 Run of River
34 Luzon Solsona Solsona, Ilocos Norte 3,000 11,121 Run of River
35 Luzon Madongan 1 Nueva Era, Ilocos Norte 4,000 15,457 Run of River
36 Luzon Madongan 2 Nueva Era, Ilocos Norte 5,000 19,375 Run of River
37 Luzon Nailiman 2 Nagtipunan, Quirino 3,000 16,230 Run of River
38 Luzon Dabubu No. 2 Maddela, Quirino 7,000 39,280 Run of River
39 Luzon Dibuluan No. 2 Maddela, Quirino 3,000 17,750 Run of River
40 Luzon Maplas Ilagan, Isabela 4,000 17,608 Run of River
41 Luzon Tuguegarao 2 Peñablaca, Cagayan 3,000 26,358 Run of River
42 Luzon Natulud 1 Peñablaca, Cagayan 2,000 40,153 Run of River
43 Luzon Natulud 2 Peñablaca, Cagayan 3,000 110,978 Reservoir
44 Luzon Pered 1 Peñablaca, Cagayan 3,000 21,797 Run of River
45 Luzon Immurung Baggao, Cagayan 1,000 20,549 Run of River
46 Luzon Tabo-an 2 Baggao, Cagayan 1,000 11,171 Run of River
47 Luzon Dikatayan San Pablo, Isabela 5,000 19,149 Run of River
167
Table A3.4 Sites under Wind Resource Assessment Project (WRAP)
1 Brgy. Malasin, San Jose City, Nueva Ecija
2 Brgy. Fatima, Pantabangan, Nueva Ecija
3 Brgy. Ibis, Bagac, Bataan
4 Puro, Magsingal, Ilocos Sur
5 East Poblacion, Pantabangan, Nueva Ecija
6 Malacapas, Dasol, Pangasinan
7 Cabusao, Camarines Sur
8 Happy Valley, San Isidro, Northern Samar
9 Mahawan, Kananga, Leyte
10 Poblacion Norte, Culasi, Antique
Note: Listed sites are subject for detailed analysis to determine its viability
168
Table A3.6 AWARDED HYDROPOWER PROJECTS
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Luzon CAR Benguet Tuba Abdao AV Garcia Power Systems Corp. 2.00
Luzon CAR Benguet Buguias Man-asok Benguet Electric Cooperative, Inc. 3.00
Oriental
Luzon IVB Baco Dulangan PNOC - Renewables Corp. 8.25
Mindoro
Barit Irrigation
Luzon V Camarines Sur Buhi NASCENT Technologies Corp. 0.40
Discharge
Luzon III Nueva Ecija Gabaldon Dupinga Constellation Energy Corporation 3.00
Sunwest Water & Electric Company,
Luzon V Catanduanes San Miguel Kapipian 2.40
Inc.
Luzon III Aurora Dingalan Davildavilan PTC Energy, Inc. 1.00
Sunwest Water & Electric Company,
Luzon II Cagayan Peñablanca Pinacanauan River 6.00
Inc.
Luzon CAR Mt. Province Bauko Ampassit Kadipo Bauko Hydro Power Corp. 1.20
Luzon CAR Ifugao Kiangan Asin Kiangan Mini Hydro Corporation 7.04
Oriental
Luzon IVB San Teodoro Inabasan Ormin Power, Inc 10.00
Mindoro
Luzon II Nueva Vizcaya Bambang Matuno Epower Technologies Corp. 8.00
Luzon CAR Ifugao Lagawe Ibulao Hydrocore, Inc. 4.50
Oriental
Luzon IVB Naujan Catuiran Catuiran Hydro Power Corp. 8.00
Mindoro
Oriental Catuiran (Upper
Luzon IVB Naujan Philnew Hydro Power Corp 8.00
Mindoro Cascade)
Luzon CAR Ifugao Tinoc Tinoc 1 Quadriver Energy Corporation 3.00
Luzon CAR Ifugao Tinoc Tinoc 2 Quadriver Energy Corporation 6.50
Luzon CAR Ifugao Tinoc Tinoc 3 Quadriver Energy Corporation 5.00
Luzon CAR Ifugao Tinoc Tinoc 4 Philnew Hydro Power Corp 6.00
Tumauini (Upper
Luzon II Isabela Tumauini Philnew Hydro Power Corp 14.00
Cascade)
Tumauini (Lower
Luzon II Isabela Tumauini Quadriver Energy Corporation 7.80
Cascade)
Green Energy Management (GEM) &
Luzon II Quirino Cabugao Diduyon 320.00
Holdings, Inc.
Cabarroguis & Pan Pacific Renewable Power
Luzon CAR Apayao Gened 1 600.00
Nagtipunan Philippine Corp.
Pan Pacific Renewable Power
Luzon II Cagayan Gonzaga Baua 1 4.44
Philippine Corp.
Pan Pacific Renewable Power
Luzon CAR Kalinga Tinglayan Tinglayan 4.32
Philippine Corp.
Luzon I Ilocos Sur Alilem Alilem HEP Philnewriver Power Corp. 16.20
Luzon I Ilocos Sur Sugpon Danac HEP Philnewriver Power Corp. 3.00
Luzon I Ilocos Sur Quirino Quirino HEP Philnewriver Power Corp. 11.50
Tinoc 5 (Lower
Luzon CAR Ifugao Tinoc Philnewriver Power Corp. 6.90
Luhong) HEP
Tinoc 6 (Wangwang)
Luzon CAR Ifugao Tinoc Philnewriver Power Corp. 8.00
HEP
San Mariano &
Luzon II Isabela Ilaguen Isabela Power Corp. 19.00
San Guillermo
Asiapac Green Renewable Energy
Luzon CAR Mt. Province Tadian Dicapan 3.00
Corporation
Asiapac Green Renewable Energy
Luzon CAR Mt. Province Natonin Lower Siffu 8.00
Corporation
Asiapac Green Renewable Energy
Luzon CAR Mt. Province Natonin Upper Siffu 8.00
Corporation
Luzon III Nueva Ecija General Tinio Balintingon HEP First Gen Luzon Power Corporation 30.00
169
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Pantabangan (Pump
Luzon III Nueva Ecija Pantabangan First Gen Prime Energy Corporation 300.00
Storage) HEP
Bineng 1-2B
Luzon CAR Benguet La Trinidad Hedcor, Inc. 19.00
Combination
Luzon IVB Palawan Narra Batang-Batang Langongan Power Corporation 3.50
Luzon CAR Mt. Province Bauko Boga Kadipo Bauko Hydro Power Corp. 1.00
Luzon CAR Mt. Province Bauko Enodey 1A Kadipo Bauko Hydro Power Corp. 1.80
Laguna & Pangil & Real &
Luzon IVA Siniloan Sierra Madre Water Corporation 35.00
Quezon Mauban
Isabela & San Agustin &
Luzon II Dabubu Greenpower Resources Corporation 4.50
Quirino Maddela
Luzon II Isabela San Agustin Dibuluan Greenpower Resources Corporation 5.50
Luzon II Isabela San Mariano Disabungan Greenpower Resources Corporation 5.50
Luzon II Nueva Vizcaya Ambaguio Matuno 1 Smith Bell Mini-Hydro Corp. 7.40
Luzon II Nueva Vizcaya Bambang Matuno 2 Smith Bell Mini-Hydro Corp. 7.90
Luzon CAR Mt. Province Bauko Enodey-Abit 1 Kadipo Bauko Hydropower Corp. 2.00
Southeast Asia Renewable Power
Luzon CAR Mt. Province Natonin Malecom 0.80
Corporation
Southeast Asia Renewable Power
Luzon CAR Mt. Province Natonin Malig 1.10
Corporation
Southeast Asia Renewable Power
Luzon III Bataan Mariveles Mariveles 1.10
Corporation
Southeast Asia Renewable Power
Luzon CAR Mt. Province Natonin Pantor 1.20
Corporation
Tubao Mini Hydro-Electric
Luzon I La Union Tubao Tubao 1.50
Corporation
Luzon IVA Quezon Lucban Maapon Renesons Energy Corporation 2.60
Alfonso
Luzon II Nueva Vizcaya Mangayngay United Hydro Power Builders 1.60
Castañeda
Luzon CAR Benguet Tuba Kanggas Goldlink Global Energy Corporation 3.00
Luzon CAR Benguet Tuba Tadiangan Goldlink Global Energy Corporation 4.70
Luzon CAR Mt. Province Bauko Enodey-Abit 2 Kadipo Bauko Hydropower Corp. 1.20
Luzon CAR Mt. Province Bauko Enodey-Abit 3 Kadipo Bauko Hydropower Corp. 2.00
Luzon CAR Ifugao Kiangan Ibulao 2 Enerhighlands Corporation 8.80
Luzon CAR Ifugao Kiangan Hungduan Kiangan Mini Hydro Corporation 4.04
Luzon CAR Ifugao Lamut Lamut Enerhighlands Corporation 6.00
Oriental Linao Cawayan Phase
Luzon IVB San Teodoro Mindoro Grid Corporation 1.00
Mindoro 2 (Tail-End)
Luzon II Nueva Vizcaya Kasibu Didipio 1 AT Dinum Company 2.10
Kasibu &
Luzon II Nueva Vizcaya Didipio 2 Alimit Hydro Corp. 9.40
Nagtipunan
Luzon II Isabela Nagtipunan Ilaguen 2 Isabela Power Corporation 14.00
Luzon II Isabela Echague Ilaguen 3 Isabela Power Corporation 11.00
Luzon II Isabela Echague Ilaguen 4 Isabela Power Corporation 10.00
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 1 5.00
Development Corporation (BREDCO)
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 2 7.00
Development Corporation (BREDCO)
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 3 4.50
Development Corporation (BREDCO)
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 1A 2.60
Development Corporation (BREDCO)
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 1B 1.70
Development Corporation (BREDCO)
BIMAKA Renewable Energy
Luzon CAR Mt. Province Besao Besao 2A 1.50
Development Corporation (BREDCO)
170
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Luzon CAR Abra Tubo Amtuagan Sta. Clara Power Corp. 8.50
Luzon CAR Abra Manabo Three Rivers Sta. Clara Power Corp. 10.00
Luzon CAR Abra Lagayan Tineg Sta. Clara Power Corp. 16.00
Luzon CAR Abra Tubo Gayaman (Tubo) Sta. Clara Power Corp. 8.50
Luzon I Ilocos Sur San Emilio Matibuey Sta. Clara Power Corp. 16.00
Luzon IVA Quezon Mauban Calmenue Sta. Clara Power Corp. 2.00
Luzon CAR Ifugao Kiangan Ibulao 1 Kiangan Mini Hydro Corporation 6.75
Luzon CAR Benguet Kibungan Kibungan Kibungan Hydropower Corporation 1,000.00
Dupax del Norte
Luzon II Nueva Vizcaya and Alfonso Casignan JRV Renewable Energy Corporation 5.00
Castañeda
Luzon IVA Quezon Real Kinanliman Municipality of Real, Quezon 1.60
Team (Philippines) Renewable Energy
Luzon I La Union Bagulin Baroro 1 1.00
Corporation
Team (Philippines) Renewable Energy
Luzon I La Union Bagulin Baroro 2 3.00
Corporation
Team (Philippines) Renewable Energy
Luzon I La Union Bagulin Baroro 3 1.50
Corporation
Kapangan and Cordillera Hydro Electric Power
Luzon CAR Benguet Kapangan 60.00
Kibungan Corporation
Buguias &
Luzon CAR Benguet Kabayan 1 Hedcor Benguet, Inc. 20.00
Kabayan
Luzon CAR Benguet Kabayan Kabayan 2 Hedcor Kabayan, Inc. 52.00
Luzon II Isabela Ramon Maris Main Canal 1 SN Aboitiz Power - Magat, Inc. 6.00
Luzon CAR Ifugao Ramon Maris Main Canal 2 SN Aboitiz Power - Magat, Inc. 1.75
Bulalakao 1 North Alternergy Viento Partners
Luzon IVB Palawan Alfonso Lista 0.34
River Corporation
Bulalakao 2 South Alternergy Viento Partners
Luzon IVB Palawan El Nido 0.44
River Corporation
Luzon II Quirino Cabarroguis Addalam Quirino Resources Development Corp. 26.00
Oriental Mag-asawang Tubig
Luzon IVB Naujan Philippine Hybrid Energy Systems, Inc. 1.00
Mindoro B
Wawa Pumped
Luzon IVA Rizal Rodriguez Olympia Violago Water & Power, Inc. 500.00
Storage 1
Wawa Pumped
Luzon IVA Rizal Rodriguez Olympia Violago Water & Power, Inc. 50.00
Storage 3
Wawa Pumped
Luzon IVA Rizal Rodriguez Olympia Violago Water & Power, Inc. 100.00
Storage 2
Luzon III Nueva Ecija San Jose SDC PNOC-Renewables Corporation 0.50
Oriental
Luzon IVB Sibagat Bongabong S&B Power Corporation 2.60
Mindoro
San Lorenzo Ruiz Piat Energy & Water,
Luzon CAR Kalinga Chico 150.00
Inc.
Luzon III Nueva Ecija Bongabon Calaanan Hydrokinetic Corp. 2.00
Luzon II Nueva Vizcaya Dupax del Sur Abaca JRV Renewable Energy Corporation 3.20
Luzon II Isabela Cabagan Balasig 1 Greenpower Resources Corporation 9.00
Luzon II Isabela Balasig Balasig 2 Greenpower Resources Corporation 7.00
Luzon IV-A Laguna Majayjay Majayjay Majayjay Hydropower Company, Inc. 2.20
Camarines Colasi Mini Hydro Electric Power Plant
Luzon V Mercedes Colasi 0.96
Norte Corporation
Luzon II Quirino Aglipay Addalam Quirino Power Energy Corporation 3.80
Labayat River (Upper Repower Energy Development
Luzon IVA Quezon Real 3.00
Cascade) Corporation
Repower Energy Development
Luzon IVA Quezon Real Piapi River 3.30
Corporation
171
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Labayat River (Lower Repower Energy Development 1.40
Luzon IVA Quezon Real
Cascade) Corporation
Tignoan River (Upper Repower Energy Development
Luzon IVA Quezon Real 1.50
Cascade) Corporation
Repower Energy Development
Luzon IVA Quezon Real Lalawinan 3.00
Corporation
Repower Energy Development
Luzon IVA Quezon Real Tibag 4.40
Corporation
Luzon CAR Benguet Bokod & Kabayan Kabayan-Bokod Hedcor Benguet, Inc. 27.00
Luzon CAR Kalinga Balbalan Biyao Biyao Hydro Power Corporation 0.80
Luzon III Tarlac Mayantoc Camiling 1 Northgreen Energy Corporation 5.40
Luzon III Aurora San Luis Diteki PTC Energy, Inc. 1.67
Luzon III Aurora Dinalungan Talaytay PTC Energy, Inc. 1.45
(Laguio) Laginbayan
Luzon IVA Quezon Mauban Enervantage Supplier's Co., Inc. 3.10
Malaki 2
Luzon V Sorsogon Sorsogon Cawayan 2 Sunwest Water and Electric Co., Inc. 0.99
Oriental
Luzon IVB Bansud & Gloria Bansud Sunwest Water and Electric Co., Inc. 1.50
Mindoro
Green Indigenous Environment
Luzon CAR Benguet Cattubo II 3.00
Development Corporation
Green Indigenous Environment
Luzon CAR Benguet Atok Cattubo I 2.00
Development Corporation
Green Indigenous Environment
Luzon I La Union Atok Bagulin I 9.00
Development Corporation
Luzon IVA Quezon Real Tignoan Aurora All Asia Energy Corporation 20.00
Alfonso
Luzon II Nueva Vizcaya Denip JRV Renewable Energy Corporation 2.30
Castañeda
Mountain Province Electric
Luzon CAR Mt. Province Bontoc Talubin 4.90
Cooperative, Inc.
Trans-Asia Oil and Energy
Luzon II Isabela Ilagan Ilagan 10.00
Development Corp,
Pililia Pumped Trans-Asia Oil and Energy
Luzon IVA Rizal Pililla 300.00
Storage Development Corp,
Luzon III Zambales Masinloc Coto 1 Coto Hydro Corp. 6.50
Luzon III Zambales Masinloc Coto 2 Coto Hydro Corp. 2.80
Luzon II Quirino Nagtipunan Gawagan 1 Gawagan Hydro Power Corp. 4.30
Luzon II Quirino Nagtipunan Gawagan 2 Gawagan Hydro Power Corp. 2.60
Luzon II Quirino Nagtipunan Geblem 1 Gawagan Hydro Power Corp. 0.70
Luzon CAR Ifugao Lagawe Alimit SN Aboitiz Power - Ifugao, Inc. 100.00
Lagawe & Alimit-Pumped
Luzon CAR Ifugao SN Aboitiz Power - Ifugao, Inc. 240.00
Mayoyao Storage
Luzon CAR Ifugao Ilagan Olilicon SN Aboitiz Power - Ifugao, Inc. 10.00
Lagawe &
Luzon II Isabela Abuan River 1 Greenpower Resources Corporation 10.80
Mayoyao
Bato-Bato (Kaliwa)
Luzon IV-B Palawan Narra AQA Global Power Inc. 12.00
HEP
Busuanga River 1
Luzon IV-B Palawan Busuanga AQA Global Power Inc. 8.00
HEP
Luzon IV-B Palawan Rizal Culasian River HEP AQA Global Power Inc. 10.00
Luzon IV-B Palawan Narra Estrella River HEP AQA Global Power Inc. 8.00
Luzon IV-B Palawan Puerto Princesa Inaguan River HEP AQA Global Power Inc. 12.00
Malasgao (Kaliwa)
Luzon IV-B Palawan Narra AQA Global Power Inc. 10.00
HEP
Luzon IV-B Palawan Bataraza Marangas River AQA Global Power Inc. 12.00
Luzon IV-B Palawan Brooke's Point Sologon River HEP AQA Global Power Inc. 12.00
Luzon V Camarines Sur Buhi Barit 2 People's Energy Services Inc. 0.60
172
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Luzon III Nueva Ecija Pantabangan Diaman United Hydro Power Builders 1.80
Luzon CAR Benguet Kabayan Eddet Adaoay 1 United Hydro Power Builders 1.00
Luzon CAR Benguet Kabayan Eddet Adaoay 2 United Hydro Power Builders 1.80
Oriental Alpaparay Resort & Development
Luzon IVB Baco San Ignacio 0.50
Mindoro Corporation
Oriental
Luzon IVB San Teodoro Alag Tributary 1 Constellation Energy Corporation 2.80
Mindoro
Oriental
Luzon IVB San Teodoro Alag Tributary 2 Constellation Energy Corporation 2.80
Mindoro
Indang &
Luzon IVA Cavite Indang Energywise Corporation 1.50
Maragondon
Luzon IVA Quezon Mauban Mauban Aurora All Asia Energy Corporation 10.00
Tublay & La
Luzon CAR Benguet Tublay 1 AT Dinum Company 0.90
Trinidad
Luzon III Nueva Ecija General Tinio Rio Chico LGU of Gen. Tinio 2.00
Luzon III Tarlac Mayantoc Camiling River 3 Northgreen Energy Corporation 3.40
San Lorenzo Ruiz Builders &
Luzon CAR Kalinga Tabuk Chico River 45.00
Developers Group, Inc.
Luzon II Isabela Cordon Magat F PhilCarbon Inc. 0.60
Laguio (Laginbayan)
Luzon IVA Quezon Mauban Enervantage Supplier's Co., Inc. 1.60
Malaki 1
Naguilian Mini-Hydro Electric
Luzon I La Union Naguilian Naguilian 6.10
Corporation
Oriental San Teodoro &
Luzon IVB Inabasan Phase II Ormin Power, Inc. 10.00
Mindoro Puerto Gallera
Luzon II Nueva Vizcaya Kasibu Namanaan AT Dinum Company 0.60
Luzon II Nueva Vizcaya Kasibu Edralin AT Dinum Company 1.20
Luzon IVA Laguna Majayjay Upper Botocan River Aurora All Asia Energy Corporation 8.64
San Roque Upper
Luzon CAR Benguet Itogon Strategic Power Development Corp. 600.00
East Pump Storage
San Roque West
Luzon CAR Benguet Itogon Strategic Power Development Corp. 400.00
Pump Storage
Luzon IVB Quezon General Nakar Kanan B-1 Energy World Kanan River, Inc. 150.00
Luzon II Quirino Nagtipunan Dakgan 1 Asiapacific Renewables Corporation 9.00
Luzon II Quirino Nagtipunan Dakgan 2 Asiapacific Renewables Corporation 12.00
Bakun &
Luzon CAR Benguet Mankayan 1 Hedcor, Inc. 12.70
Mankayan
Luzon IVB Palawan Puerto Princesa Langogan Langongan Power Corporation 6.80
Luzon CAR Mt. Province Bauko Lower Chico Kadipo Bauko Hydro Power Corp. 3.40
Nueva Ecija / Gabaldon / San
Luzon III Lingod River United Hydro Power Builders 2.50
Aurora Luis
Luzon IVA Quezon General Nakar Umiray 1 Laguna Hydroenergy Corporation 6.00
Luzon II Isabela San Pablo San Pablo Greenpower Resources Corporation 8.00
San Lorenzo Ruiz Builders &
Luzon III Nueva Ecija Pantabangan Sampaloc 14
Developers Group, Inc.
Majayjay & Repower Energy Development
Luzon IVA Laguna Balanac (Middle) 5.00
Magdalena Corporation
Luzon II Quirino Nagtipunan Dagkan United Hydro Power Builders 142
Luzon CAR Benguet Tublay Tublay 2 AT Dinum Company 6.00
Benguet & Bakun &
Luzon CAR & I Mankayan 2 Hedcor, Inc. 20.30
Ilocos Sur Cervantes
Luzon II Quirino Maddela Dabubu 2 Greenpower Resources Corporation 4.30
Luzon IVA Quezon General Nakar Umiray Site 2 River Laguna Hydroenergy Corporation 3.90
Luzon II Quirino Maddela Dibuluan 2 Greenpower Resources Corporation 3.2
Luzon IVA Quezon General Nakar Umiray Site 4 River Laguna Hydroenergy Corporation 2.80
Luzon CAR Mt. Province Bauko Upper Chico Kadipo Bauko Hydro Power Corp. 2.10
173
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
I-Magat Renewable Energy
Luzon CAR Kalinga Pasil Pasil B 14.00
Corporation
I-Magat Renewable Energy
Luzon CAR Kalinga Pasil Pasil C 11.00
Corporation
Luzon II Isabela San Pablo San Pablo Site 2 Greenpower Resources Corporation 3.00
Luzon II Isabela San Pablo San Pablo Site 3 Greenpower Resources Corporation 4.90
Luzon II Isabela Ilagan Abuan 2 Greenpower Resources Corporation 8.10
Luzon CAR Benguet Tublay Tublay 3 AT Dinum Company 1.00
Luzon Zambales Masinloc Coto 3 AT Dinum Company 2.20
Luzon CAR Apayao Conner Nabuangan River Strategic Power Development Corp. 10.00
Luzon Bulacan Norzagaray Angat Run-of-River Strategic Power Development Corp. 10.00
Dingalan Pumped-
Luzon III Aurora Dingalan Strategic Power Development Corp. 500.00
Storage
First Gen Mindanao Hydro Power
Luzon CAR Abra Tineg & Lagayan Binongan-Tineg 175.00
Corp.
Kibungan Pumped-
Luzon CAR Benguet Kibungan Coheco Badeo Corporation 500.00
Storage
Luzon I Ilocos Norte Dumalneg Bulo 2 Phildane Resources Corporation 5.00
Power Beacon Renewable Solutions,
Luzon III Pangasinan San Quintin Dipalo 2.50
Inc.
Luzon I Ilocos Sur Suyo Suyo 2 Satrap Power Corporation 3.00
San Roque Lower
Luzon Benguet Itogon Strategic Power Development Corp. 400.00
East Pumped-Storage
Oriental Energy and Power
Visayas VI Aklan Madalag Timbaban 18.00
Generation Corporation
Negros Hilabangan ( Upper
Visayas VI Kabankalan Century Peak Energy Corporation 4.80
Occidental Cascade)
Negros Hilabangan ( Lower
Visayas VI Kabankalan Century Peak Energy Corporation 3.00
Occidental Cascade)
Visayas VI Iloilo Igbaras Igbulo (Bais) Century Peak Energy Corporation 5.10
Maninila (Lower
Visayas VI Antique San Remigio Century Peak Energy Corporation 4.50
Cascade)
Maninila (Upper
Visayas VI Antique San Remigio Century Peak Energy Corporation 3.10
Cascade)
Sibalom (Upper
Visayas VI Antique San Remigio Century Peak Energy Corporation 4.20
Cascade)
Sibalom (Middle
Visayas VI Antique San Remigio Century Peak Energy Corporation 4.00
Cascade)
Sibalom
Visayas VI Antique San Remigio Century Peak Energy Corporation 3.30
(LowerCascade)
Visayas VII Negros Oriental La Libertad Pacuan-Guinobaan PNOC - Renewables Corp. 13.80
Visayas VII Cebu Badian Basak II Rapids Innoenergy, Inc. 0.50
Negros
Visayas VI Silay City Malugo Vivant-Malogo Hydropower, Inc. 6.00
Occidental
Visayas VI Antique Sebaste Caro-an Antique Electric Cooperative, Inc. 0.84
Visayas VI Antique Sebaste Ipayo Antique Electric Cooperative, Inc. 1.30
Sunwest Water & Electric Company,
Visayas VI Antique Bugasong Villasiga 8.00
Inc. 2
Sunwest Water & Electric Company,
Visayas VI Aklan Libacao Main Aklan 15.00
Inc.
Natural Power Sources
Visayas VII Negros Oriental Amlan Amlan (Plant A) 3.20
Intergration,Inc.
Natural Power Sources
Visayas VII Negros Oriental Amlan Amlan (Plant B) 1.50
Intergration,Inc.
Natural Power Sources
Visayas VII Negros Oriental Amlan Amlan (Plant C) 0.80
Intergration,Inc.
174
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
177
Potential
Island/Grid Region Province Municipality Name of Project Developer Capacity
(MW)
Mindanao XI Davao Oriental Caraga Manorigao LGS Renewable Energies Corporation 17.00
Mindanao X Bukidnon Valencia Manupali Matic Hydropower Corporation 9.00
Mindanao XI Davao Oriental Manay Casauman Global Sibagat Hydro Power Corp. 34.00
First Bukidnon Electric Cooperative,
Mindanao X Bukidnon Maramag Maramag Inc. transferred to Maramag Mini- 1.40
Hydro Corporation
Mindanao XI Davao del Sur Goa & Tigaon Guma Euro Hydro Power (Asia) Holdings, Inc. 1.70
Malabang &
Mindanao ARMM Lanao del Sur Maitling River HEP AQA Global Power Inc. 50.00
Tubaran
Mindanao ARMM Lanao del Sur Malabang Matadi River HEP AQA Global Power Inc. 27.00
Mindanao ARMM Lanao del Sur Pualas & Ganassi Lake Dapao HEP AQA Global Power Inc. 50.00
Mindanao ARMM Lanao del Sur Malabang Baras River HEP AQA Global Power Inc. 30.00
Mindanao XI Davao Oriental Baganga Cateel Global Sibagat Hydro Power Corp. 16.00
Mindanao X Lanao del Norte Iligan City Lower Bayug Euro Hydro Power (Asia) Holdings, Inc. 4.00
Mindanao X Lanao del Norte Iligan City Upper Bayug Euro Hydro Power (Asia) Holdings, Inc. 3.30
Zamboanga del
Mindanao IX Bayog Bayog Global Sibagat Hydro Power Corp. 6.00
Sur
Mindanao XI Davao Oriental Baganga Baganga River Global Sibagat Hydro Power Corp. 11.00
Governor
Mindanao XI Davao Oriental Osmena LGS Renewable Energies Corporation 2.00
Generoso
Mindanao X Lanao del Norte Iligan City Bulanog-Batang Bukidnon Hydro Energy Corporation 150.00
Mindanao IX Zamboanga City Patalon Everhydro Corporation 0.50
Mindanao IX Zamboanga City Alimpaya Everhydro Corporation 1.20
Mindanao IX Zamboanga City Tagpangi Everhydro Corporation 0.50
Mindanao IX Zamboanga City Ayala Everhydro Corporation 1.00
Zamboanga del
Mindanao IX Zamboanga City Saaz Meadowland Developers, Inc. 1.00
Sur
Governor
Mindanao XI Davao Oriental Tibanban LGS Renewable Energies Corporation 2
Generoso
Misamis
Mindanao X Calamba Langaran Kaltimex Langaran Hydro Inc. 3.60
Occidental
Mindanao X Bukidnon Impasugong Atugan 1 River Gerphil Renewable Energy, Inc. 2.40
Mindanao X Lanao del Norte Iligan City Agus VIII Modular Fu-Tai Philippines, Inc. 12.00
Repower Energy Development
Mindanao X Bukidnon Maramag Pulangui IV 10.00
Corporation
Misamis Cagayan de Oro
Mindanao X Umalag 1 Meadowland Developers, Inc. 1.80
Occidental City
Mindanao X Bukidnon Impasugong Atugan 4 Gerphil Renewable Energy, Inc. 3.50
Surigao del Sur II Electric Cooperative,
Mindanao XIII Surigao del Sur San Miguel Sagbayan 0.64
Inc.
Mindanao X Bukidnon Santiago Manolo Fortich 1 Hedcor Bukidnon, Inc. 43.40
Mindanao X Bukidnon Santiago Manolo Fortich 2 Hedcor Bukidnon, Inc. 25.40
Mindanao X Bukidnon Libona Umalag 2 Meadowland Developers, Inc. 2.50
Surigao del Sur II Electric Cooperative,
Mindanao XIII Surigao del Sur San Miguel Carromata 5.60
Inc.
Mindanao XI Davao del Sur Davao City Tamugan Hedcor, Inc. 11.50
Mindanao XI Davao City Apo Agua Apo Agua Infrastructura, Inc. 2.20
First Gen Mindanao Hydro Power
Mindanao X Lanao del Norte Iligan City Cagayan 1N 160.00
Corp.
First Gen Mindanao Hydro Power
Mindanao XI Davao Oriental Baganga Cateel 17.50
Corp.
10,476.62
178
Table A3.7 AWARDED BIOMASS PROJECTS
ISLAND / CITY / POTENTIAL
REGION PROVINCE PROJECT NAME COMPANY NAME
GRID MUNICIPALITY CAPACITY (MW)
14.8 MW Montalban
Landfill Methane Recovery Montalban Methane
Luzon IV-A Rizal Rodriguez 6.475
and Power Generation Power Corporation
Facility
24 MW San Jose City Rice
San Jose City I Power
Luzon III Nueva Ecija San Jose City Husk-Fired Biomass Power 12.00
Plant Project
Corporation
1 MW Pepsi Biomass
Luzon I La Union Rosario Sure PEP, Inc. 1.00
Power Plant Project
1.5 MW Payatas Landfill
Pangea Green Energy
Luzon NCR Metro Manila Quezon City Methane Recovery and 0.624
Power Generation Facility Philippines, Inc.
2.5 MW EMS Woody
EcoMarketSolutions,
Luzon III Aurora Dilasag Biomass Power Plant 2.50
Project Inc.
0.4 MW VMA Rice Husk-
Orriental V. M. Agbayani Rice
Luzon IV-B Bongabong Fired Biomass Power Plant 0.40
Mindoro Mill
Project
5 MW BBEC Rice Husk-
Bicol Biomass Energy
Luzon V Camarines Sur Pili Fired Biomass Power Plant 5.00
Project Corporation
8.8 MW Biogas Power
Luzon IV-A Batangas Lian AseaGas Corporation 8.80
Plant Project
2 MW ACNPC WTE
Asian Carbon Neutral
Luzon III Tarlac Tarlac City Biomass Power Plant 2.00
Project
Power Corporation
12 MW G2REC Napier
Grass Gold Renewable
Luzon III Nueva Ecija Llanera Grass-Fired Biomass 12.00
Power Plant Project Energy Corporation
1.5 MW Coconut Waste-
Renesons Energy
Luzon IV-A Quezon Polillo Fired Biomass Power Plant 1.50
Project
Polillo, Inc.
Natures Renewable
24 MW Biomass Power
Luzon II Cagayan Lal-lo Energy Development 24.00
Plant Project
Corporation
10 MW Biomass Power SATRAP Power
Luzon I Ilocos Sur Santa 10.00
Plant Project Corporation
5MW Biomass Power Isabela La Suerte Rice
Luzon II Isabela Aurora, 5.00
Plant Project Mill Corporation
20MW Waste-to-
CJ Global Green Energy
Luzon V Camarines Sur Naga City Energy Power Plant 20.00
Philippines Corporation
Project
63 MW VMCI Bagasse-
Negros Victorias Milling
Visayas NIR Victorias City Fired Cogeneration Power 29.00
Occidental Company Inc.
Plant
20 MW SCBPI Multi-
Negros San Carlos Biopower
Visayas NIR San Carlos City Feedstock Power Plant 20.00
Occidental Inc.
Project
28.58 MW HPCo Bagasse
Negros Hawaiian-Philippine
Visayas NIR Silay City Cogeneration Power Plant 20.58
Occidental Company
Project
12 MW Multi-Feedstock
Negros Himamaylan Megawatt Clean
Visayas NIR Biomass Power Plant 12.00
Occidental City Energy, Inc.
Project
25MW Cane Trash-fired
South Negros
Visayas Biomass Power Plant 25.00
Biopower, Inc.
Project
Negros 25MW Cogeneration Central Azucarera de
Visayas Bais City 25.00
Oriental Power Plant Project Bais
179
ISLAND / CITY / POTENTIAL
REGION PROVINCE PROJECT NAME COMPANY NAME
GRID MUNICIPALITY CAPACITY (MW)
Negros
Visayas NIR 48.5 MW Cogen Project BISCOM 48.50
Occidental
10 MW Malaybalay Multi
Malaybalay BioEnergy
Mindanao X Bukidnon Malaybalay Feedstock Biomass Power 10.00
Plant Project Corporation
15 MW LPC Rice Husk-
Lamsan Power
Mindanao ARMM Maguindanao Sultan Kudarat Fired Biomass Power Plant 15.00
Project Corporation
Agusan del 23.5 MW Woody Biomass CARAGA Renewable
Mindanao CARAGA Buenavista 23.50
Norte Power Plant Project Energy Corporation
Green Earth
3.5 GEEC MW Biomass
Mindanao ARMM Maguindanao Buluan Enersource 3.50
Cogeneration System
Corporation
12 MW Napier Grass-Fired Manolo Fortich
Mindanao X Bukidnon Manolo Fortich Biomass Power Plant Renewable Energy 12.00
Project Corporation
5.5 MW Biomass Power Lamsan Power
Mindanao ARMM Maguindanao Sultan Kudarat 5.50
Plant Project Corporation
360.879
180
Table A3.9 AWARDED GEOTHERMAL PROJECTS
POTENTIAL
ISLAND /
REGION PROVINCE PROJECT NAME COMPANY NAME CAPACITY
GRID
(MW)
Sal-lapadan-Boliney-
Bucloc-Tubo
LUZON CAR Abra Pan Pacific Power Phils. Corp.
Geothermal Power
Project
Clean Rock Renewable
Benguet / Nueva Daklan Geothermal
Energy Resources 60.00
Ecija Project
Corporation
Kalinga Geothermal Aragorn Power and Energy
Kalinga 120.00
Project Corporation
Ifugao, Benguet, East Mankayan
Mountain Geothermal Power Basic Energy Corp.
Province Project
Ilocos Sur / Mt.
Cervantes Geothermal
I Province / Pan Pacific Power Phils. Corp.
Power Project
Benguet
Cagua-Baua Geothermal
II Cagayan Pan Pacific Power Phils. Corp. 45.00
Power Project
Mariveles Geothermal
III Bataan Basic Energy Corp.
Power Project
Clean Rock Renewable
Mt. Natib Geothermal
Energy Resources 40.00
Project
Corporation
Negron-Cuadrado
Zambales, Negron Cuadrado
Geothermal Power
Pampanga Geothermal Inc.
Project
San Juan Geothermal San Juan Geothermal Power
IV-A Batangas 20.00
Power Project Inc.
Makban Geothermal Philippine Geothermal
Laguna/Batangas
Power Project Production Company, Inc.
Laguna / Quezon Tiaong Geothermal Tiaong Geothermal Power
/ Batangas Power Project Corp.
Mt. Puting Lupa
Laguna Filtech Energy Drilling Corp.
Geothermal Project
Tayabas - Lucban
Tayabas / Tayabas Geothermal Power
Geothermal Power
Laguna Inc.
Project
Talim Geothermal
Rizal Alco Steam Energy Corp.
Power Project
Oriental Montelago Geothermal Mindoro Geothermal Power
IV-B 40.00
Mindoro Project Corp.
Tiwi Geothermal Power Philippine Geothermal
V Albay
Project Production Company, Inc.
Quezon /
Mt. Labo Geothermal Energy Development
Camarines Norte 65.00
Project Corporation
& Sur
Southern Bicol
Sorsogon SKI Construction Group Inc. 40.00
Geothermal Project
181
POTENTIAL
ISLAND /
REGION PROVINCE PROJECT NAME COMPANY NAME CAPACITY
GRID
(MW)
West Bulusan
Geothermal Power Basic Energy Corp.
Project
Bacon-Manito
Energy Development
Sorsogon / Albay Geothermal Production
Corporation
Field
Camarines Sur, Iriga Geothermal Power
Basic Energy Corp.
Albay Project
LUZON Sum 430.00
Northern Negros
Negros Energy Development
VISAYAS VI Geothermal Production
Occidental Corporation
Field
Mandalagan Energy Development
20.00
Geothermal Prospect Corporation
Biliran Geothermal Biliran Geothermal
VIII Biliran 50.00
Project Incorporated
VISAYAS Sum 70.00
Zamboanga del
Sur / Zamboanga
Lakewood Geothermal Energy Development
MINDANAO IX del Norte / 40.00
Prospect Corporation
Zamboanga
Sibugay
Misamis
Occidental /
Zamboanga del Ampiro Geothermal Energy Development
IX / X 30.00
Norte / Power Project Corporation
Zamboanga del
Sur
Misamis Oriental Balatukan-Balingasag Energy Development
X 20.00
/ Bukidnon Geothermal Prospect Corporation
Mt. Sibulan-Kapatagan
XI Davao del Sur Geothermal Power Mount Apo Geopower, Inc.
Project
North Cotabato / Mt. Zion Geothermal Energy Development
XI / XII 20.00
Davao del Sur Power Project Corporation
Mt. Zion 2 Geothermal Energy Development
Power Project Corporation
North Cotabato Mt. Talomo-Tico
and Davao del Geothermal Power Mount Apo Geopower, Inc.
Sur Project
MINDANAO Sum 110.00
Grand Total 610.00
182
Appendix 4 – Changes from 2013 TDP to 2014 – 2015 TDP
Daraga S/S:
Daraga S/S
1-100 MVA 230/69 kV
transformer
* - Completed/ Energized
183
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Gumaca S/S:
Labrador S/S 1-50 MVA 230/69 kV
transformer
Luzon PCB ETC: 2014 ETC: Dec 2016 Reflecting actual
Replacement completion of the
project.
Santiago-Tuguegarao ETC: 2014 ETC: Dec 2016 Reflecting actual
230 kV Line 2 completion of the
project.
San Jose-Angat 115 kV ETC: 2015 ETC: June 2017 Due to updates in
Line Upgrading actual implementation
status.
San Jose-Quezon 230 ETC: 2015 ETC: Dec 2017 Due to updates in
kV Line 3 actual implementation
status.
Bataan-Cavite No ETC ETC: Dec 2017 Due to updates in
Transmission Line FS actual implementation
status.
Hermosa-Floridablanca ETC: 2018 ETC: Mar 2018 Due to updates in
69 kV T/L actual implementation
status.
Tuguegarao-Lal-lo ETC: 2017 ETC: Oct 2018 Due to updates in
(Magapit) 230 kV T/L actual implementation
status
Western 500 kV ETC: 2017 ETC: Dec 2018 Due to updates in
Backbone (Stage 1) actual implementation
status.
Eastern Albay 69 kV ETC: 2016 ETC: (Stage 2) June 2019 Originally packaged
Line Stage 2 together with Stage 1
under 2013 TDP.
Ambuklao-Binga 230kV ETC: 2015 ETC: Dec 2019 Due to updates in
T/L Upgrading actual implementation
status.
Binga-San Manuel 230 ETC: (Stage 1) 2014 ETC: Dec 2019 Due to updates in
kV T/L Stage 1 & 2 ETC: (Stage 2) 2015 actual implementation
status.
New Antipolo 230 kV ETC: 2015 ETC: Dec 2019 Due to updates in
Substation actual implementation
status.
Calaca-Dasmariñas ETC: 2018 ETC: Dec 2019 Due to updates in
500 kV Transmission actual implementation
Line status.
Pagbilao 500 kV Pagbilao 500 kV S/S Pagbilao 500 kV S/S Uprating of the
Substation 3-750 MVA, 500/230 kV 3-1000 MVA, 500/230 kV transformer capacity
Power Transformer, 8-500 Power Transformers, 8- considers anticipating
kV PCB and 8-230 kV PCB 500 kV PCBs and 11-230 future generation
kV PCB development in the
area.
Tayabas 500 kV S/S Tayabas 500 kV S/S
Expansion Expansion Update on the project
4-230 kV PCB 3-500 kV PCB and 1-230 components and
kV PCB transmission line
swinging already
Swinging of Naga-Tayabas based on the recent
EHV Line at Tayabas SS site development plan
ST-DC, 4-795 MCM and detailed
ACSR, 0.5 km engineering design.
184
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Pagbilao-Tayabas
connection to Naga-
Tayabas,
230 kV, ST-DC, 4-795
MCM ACSR, 2.75 km.
Hermosa-San Jose 500 ETC: 2020 ETC: May 2018 Considers using the
kV Transmission Line existing tower design
Hermosa-San Jose 500 kV Hermosa-San Jose 500 kV while maintaining the
T/L T/L same transfer
ST-DC, 6-795 MCM ST-DC, 4-410 mm2 capacity.
ACSR/AS, 83 km TACSR/AS, 82.41 km
Updates on the project
New Hermosa 500 kV S/S New Hermosa-Old Hermosa components were
2-750 500/230-13.8 kV Tie Line already based on the
Power Transformer, 10- SP-DC, 4-795 MCM recent site
500 kV PCB and 10-230 ACSR, 0.5 km development plan and
kV PCB detailed engineering
New Hermosa 500 kV S/S design.
New Hermosa 500 kV S/S 2-750 500/230-13.8 kV
1-90 MVAR 500 kV Power Transformer, 10-
Reactor 500 kV PCB and 12-230
kV PCB
Bolo 5th Bank ETC: 2018 ETC: June 2019 Due to updates in the
timeline and status of
Bolo 500 kV S/S Expansion Bolo Substation Expansion the generation
1-600 MVA, 500/230 kV 1x600 MVA 500/230 kV capacity additions that
Power Transformer, 3-500 Transformer and 3-500 kV trigger the
kV PCB, and 2-230 kV PCB implementation of the
PCB project.
185
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Mariveles-Hermosa 500 ETC: November 2019 Previously named as
kV Transmission Line Cabcaben-Hermosa
500 kV Transmission
Line
Northern Luzon 230 kV ETC: June 2024 Conceptualization of
Loop this project is included
in the 2013 TDP.
Sta Maria / Ibaan 500 ETC: October 2024 New Project under
kV Substation 2014-2015 TDP
Liberty-Nagsaag 230 kV ETC: 2020 ETC: December 2024 Due to updates in load
Transmission Line forecast and actual
Liberty 230 kV S/S Liberty 230 kV S/S implementation status.
1-50 MVA 230/69 kV 1-100 MVA 230/69 kV
Power Transformer Power Transformer
La Trinidad-Sagada 230 ETC: 2019 ETC: December 2024 Due to updates in load
kV Transmission Line forecast and actual
implementation status.
Pagbilao-Tayabas 500 ETC: December 2024 New Project under
kV Transmission Line 2014-2015 TDP
Manila (Navotas) 230 kV Manila 230 kV S/S Manila 230 kV S/S Updates on the project
Substation 2-300 MVA, 230/115-13.8 2-300 MVA, 230/115-13.8 components were
kV Power Transformer, 2- kV Power Transformers already based on the
50 MVAR, 115 kV and Accessories, 9-230 kV recent site
Capacitor Banks, 6-230 kV PCBs (GIS) and 15-115 kV development plan and
PCB (GIS) and 9-115 kV PCBs (GIS) detailed engineering
PCB (GIS) design.
186
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Mexico-San Simon 69 ETC: 2016 ETC: June 2020 Due to updates in load
kV Transmission Line forecast and actual
Mexico-San Simon 69 kV Mexico-San Simon 69 kV T/L implementation status.
T/L ST/SP-DC, 1-410 mm2
ST/SP-DC, 410 mm2 TACSR, 6.9 km
TACSR, 8.0 km
Mexico 69 kV S/S Expansion
Mexico S/S Expansion 9-69 kV PCB and
2-69 kV PCB and associated equipment
associated equipment
Pasay 230 kV ETC: 2019 ETC: July 2020 Due to updates in load
Substation forecast and actual
Pasay 230 kV S/S Pasay 230 kV S/S implementation status.
2-300 MVA, 230/115-13.8 5-230 kV PCBs (GIS) and
kV Power Transformer, 2- associated equipment Updates on the project
50 MVAR, 115 kV components were
Capacitor Banks, 6-230 kV Las Piñas-Pasay 230 kV T/L already based on the
PCB (GIS) and 9-115 kV 230 kV, 2-795 MCM recent site
PCB (GIS) ACSR/AS, SP-DC, 4.2 km development plan and
230 kV 2-1C-2,000 mm² detailed engineering
Las Piñas-Pasay 230 kV T/L XLPE, UG-DC, 3.9 km design.
SP-DC, 4-795 MCM
ACSR/AS, 21 km
Taguig 500 kV ETC: 2018 ETC: November 2020 Due to updates in load
Substation forecast and actual
Baras (Antipolo)-Taguig 500 Taguig 500 kV S/S implementation status.
kV T/L (initially energized at 2-1,000 MVA, 500/230-
230 kV) 13.8 kV Power Updates on the project
4-795 MCM ACSR/AS, Transformers and components were
ST-DC, 7.3 km, and 4-795 Accessories, 1-90 MVAR, already based on the
MCM ACSR/AS, SP-SC, 2- 500 kV Shunt Reactor and recent site
16 km Accessories, 3-100 MVAR, development plan and
230 kV Capacitor Banks detailed engineering
Baras (Antipolo) S/S and Accessories, 8-500 kV design.
Expansion PCBs (GIS), 10-230 kV
4-230 kV PCB and PCBs (GIS), and
associated equipment Associated Equipment
187
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Marilao 500 kV ETC: June 2023 New Project under
Substation 2014-2015 TDP
Porac 230 kV ETC: 2022 ETC: December 2024 Due to updates in load
Substation forecast and actual
Hermosa-Clark 230 kV T/L Porac 230 kV S/S implementation status.
ST/SP-DC, 795 MCM 1-300 MVA 230/69 kV
ACSR/AS, 53.8 km transformer, 5-230 kV
PCB, 9-69 kV PCB and
associated equipment
188
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Switch
La Trinidad 69 kV S/S
Expansion
1-69 kV PCB and
Associated Equipment
Tiwi Substation ETC: 2018 ETC: July 2019 Due to updates in load
Upgrading Project forecast and actual
Tiwi 230 kV S/S Tiwi A 230 kV S/S implementation status.
1-50 MVA, 230/69-13.8 kV 4-230 kV PCB
Power Transformer, 8-230
kV PCB, and 2-69 kV PCB Tiwi C 230 kV S/S
1-50 MVA, 230/69-13.8 kV
Power Transformer, 15-
230 kV PCB and 3-69 kV
PCB
Previously
conceptualized as
Currimao Substation
Expansion.
San Manuel-Nagsaag ETC: 2018 ETC: December 2021 Due to updates in load
230 kV Transmission forecast and actual
Line Nagsaag-San Manuel 230 kV San Manuel-Nagsaag 230 kV implementation status.
T/L Tie-Line Upgrading
SP-DC, 2-410 mm2 SP-DC, 2-410 mm2
TACSR, 1.0 km TACSR, 0.6 km
189
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Binga-San Manuel 230 kV Nagsaag 500 kV S/S
T/L Extension (Expansion)
SP/ST-DC, 2-795 MCM 3-200 MVA, 500/230-13.8
ACSR, 4 km kV Power Transformers
and Accessories, 2-500 kV
San Manuel S/S Expansion PCB and Associated
2-230 kV PCB and Equipment and 8-230 kV
associated equipment PCB and Associated
Equipment
Baras 500 kV Switching ETC: 2019 ETC: December 2024 Due to updates in load
Station forecast and actual
Antipolo-San Jose 500 kV Baras 500 kV S/S implementation status.
Line Extension 10-500 kV PCBs and
500 kV, ST-DC, 4-795 associated equipment
MCM ACSR, 9 km
Antipolo-Tayabas 500 kV
Line Extension
500 kV, ST-DC, 4-795
MCM ACSR, 8.5 km
Luzon Voltage ETC: 2018 ETC: January 2018/ June Due to updates in load
Improvement Project 3 – 2022 forecast and actual
Stage 1 / Stage 2 Laoag 230 kV S/S implementation status.
2-25 MVAR, 230 kV Shunt STAGE 1
Reactors Laoag 230 kV S/S
1-35 MVAR & 1-25 MVAR
San Esteban 230 kV S/S 230 kV Shunt Reactors
2-25 MVAR, 230 kV Shunt and Accessories, 2-25
Reactors MVAR 230 kV Capacitor
Banks and Accessories
Tuguegarao 230 kV S/S
1-25 MVAR Capacitor Cabanatuan 230 kV S/S
Bank and 1-25 MVAR, 230 2-50 MVAR, 230 kV
kV Shunt Reactor Capacitor Banks and
Accessories
Botolan 230 kV S/S
1-25 MVAR 230 kV Shunt Nagsaag 500 kV S/S
Reactor 1-90 MVAR, 500 kV Shunt
Reactor and Accessories
Mexico 230 kV S/S
1-100 MVAR 230 kV
Capacitor Bank
San Jose 230 kV S/S Tuguegarao 230 kV S/S
1-100 MVAR 230 kV 1-25 MVAR Capacitor
Capacitor Bank Bank and Accessories and
1-25 MVAR, 230 kV Shunt
Bantay 115 kV S/S Reactor and Accessories
1-7.5 MVAR, 115 kV
Capacitor Bank Baler Load-End 69 kV S/S
3-2.5 MVAR, 69 kV
Itogon Load-end 69 kV S/S Capacitor Bank and
1-7.5 MVAR, 69 kV Accessories
Capacitor Bank
191
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Pantabangan Load-end 69
Pantabangan Load-end 69 kV S/S
kV S/S 1-5 MVAR, 69 kV
2-5 MVAR, 69 kV Capacitor Bank and
Capacitor Banks Accessories
STAGE 2
San Esteban 230 kV S/S
2-25 MVAR, 230 kV
Capacitor Banks and
Accessories
Bayambang Load-end 69 kV
S/S
3-5 MVAR 69 kV Capacitor
Bank and Accessories
192
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Luzon Voltage ETC: 2018 ETC: December 2019/ June Due to updates in load
Improvement Project 4 – 2022 forecast and actual
Stage 1 / Stage 2 Ligao Switching Station implementation status.
3-5 MVAR, 69 kV STAGE 1
Capacitor Banks
Ligao Switching Station,
Balogo Switching Station 3-5 MVAR, 69 kV
3-5 MVAR, 69 kV Capacitor Banks and
Capacitor Banks Accessories
193
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Visayas Projects
CNP 230 kV Backbone ETC: 2017 ETC: Dec 2018 Change of
Project - Stage 2 (Cebu components was for
Substation 230 kV Cebu 230 kV S/S Cebu 230 kV S/S N-1 contingency.
Upgrading) 2-300 MVA 230/138 KV 3-300 MVA 230/138 KV
Power Transformers and Power Transformers and
1-138 kV PCB 3-138 kV PCB
Cebu – Negros – Panay ETC: 2016 ETC: Dec 2017 Substation
230 kV Backbone reconfiguration was
(Stage 1) Barotac Viejo S/S Barotac Viejo S/S Expansion due to ERC approval
Expansion 5-138 kV PCB of Eastern Panay
6-138 kV PCB Transmission Project
E.B. Magalona – Cadiz E.B. Magalona – Cadiz 138 Not included in the
138 kV T/L kV T/L 2014-2015 TDP
because it can be
addressed by CNP 3
Umapad 230 kV ETC :2017 ETC : Jun 2023 Due to updates in
Substation Project actual implementation
Umapad 230 kV S/S Umapad 230 kV S/S status.
4-138 kV PCB, 4-69 kV 7-230 kV PCB, 5-69 kV
PCB PCB
Laray 230 kV Substation SRP 138 kV Substation Laray 230 kV Substation SRP was changed to
Project Project Laray due to
ETC : 2018 ETC : Nov 2020 Transmission line
SRP 230 kV S/S Laray 230 kV S/S (New) ROW difficulty.
2-300 MVA 230/69-13.8 kV 2-150 MVA 230/69-13.8 kV
Power Transformers, 5- Power Transformers, 6- Transformer capacity
230 kV PCB (GIS) and 4- 230 kV PCB (GIS), 5-69 kV was reduced as per
69 kV PCB (GIS) and PCB (GIS) and associated coordination with
associated equipment equipment VECO.
194
Project Name 2013 TDP 2014 – 2015 TDP Remarks
of 50 MW capacity at 69
kV, 1km
Campetic-Campetic 69 kV
T/L
ST-DC, 1-336.4 MCM, 1
km
195
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Visayas Substation Panay Substations Visayas Substation Visayas Substation
Upgrading Project Upgrading Project Upgrading Project (VSUP) upgrading is divided
(VSUP) ETC : 2018 ETC : Dec 2021 into two due to
Cebu Substation Upgrading prioritization issues.
Project
ETC : 2019
Samar Substation
Upgrading Project
ETC : 2019
Bohol Substations
Upgrading Project
ETC : 2020
Negros Substations
Upgrading Project
ETC : 2019
Leyte Substation Upgrading
Project
ETC : 2018
Leyte – Bohol Line 2 Leyte – Bohol Line 2 Not included in the
(2022) 2014-2015 TDP but
included as an option
in the Cebu-Bohol
Interconnection
project.
Upgrading of Ormoc / Permanent Restoration of Upgrading of Ormoc / The original project
Tongonan - Isabel 138 Panitan-Nabas and Tongonan - Isabel 138 kV was split into two
kV Transmission Line Ormoc-Isabel 138 kV lines Transmission Line different projects.
Naga (Visayas) Naga 138 kV Substation Naga (Visayas) Substation Other components
Substation Upgrading Upgrading Upgrading Project moved to Colon
Project Substation upgrading
ETC : 2018 ETC : Mar 2019 (Remaining Works)
197
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Maasin-Javier 138 kV ETC : 2019 ETC : Jun 2025 Due to updates in
Transmission Line actual implementation
Project Maasin-Javier 138 kV T/L Maasin-Javier 138 kV T/L status.
ST-DC, 1-795 MCM ST-DC, 1-795 MCM
ACSR, 105 km ACSR, 105 km
Umapad CTS
Cable Sealing End
Structures, 3-138 kV
Disconnect Switches
CNP 230 kV Backbone Conceptualization of
Project - Stage 3 this project is included
(Negros-Cebu in the 2013 TDP
Interconnection)
Sta. Barbara-Dingle 138 New project under
kV Line 3 Project 2014 – 2015 TDP
199
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Visayas Substation New project under
Upgrading Project - 2 2014 – 2015 TDP
Mindanao Projects
Mindanao Substation ETC: 2014 ETC: March 2016 Transformer
Reliability I Bunawan S/S Bunawan S/S transferred to
1-50 MVA Transformer “Maramag – Bunawan
230kV Transmission
Project”
Transformer intended
Lugait S/S Lugait S/S for Lugait substation
1-75 MVA Transformer was installed in Opol
Substation instead.
Opol 138 kV S/S ETC: 2015 ETC: Jun 2016 Reflecting actual
completion of the
project.
Sultan Kudarat (Nuling) ETC: 2014 ETC: Dec 2016 Due to updates in
Capacitor Project actual implementation
status
200
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Balo-i-Kauswagan- ETC: 2019 ETC: Dec 2022 Due to updates in
Aurora 230 kV T/L actual implementation
(Phase 2) status
201
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Zamboanga Peninsula MSUP Repackaging of
Substations Upgrading projects
ETC: 2018 ETC: 2022
Polanco S/S Polanco S/S
2–138kV PCB including 3-138 kV PCB, 1-69 kV
associated equipment PCB and associated
equipment
Pitogo S/S
2–138 kV PCB and Pitogo S/S
associated equipment 1-138 kV PCB, 1-69kVPCB
and associated equipment
Zamboanga S/S
2-138 kV PCB and Zamboanga S/S
associated equipment 3-138 kV PCB, 2-69 kV
PCB and associated
Naga Mindanao S/S equipment
2-138 kV PCB and
associated equipment Naga Mindanao S/S
2-69kV PCB and
associated equipment
202
Project Name 2013 TDP 2014 – 2015 TDP Remarks
203
Project Name 2013 TDP 2014 – 2015 TDP Remarks
Placer S/S Placer S/S
1-138 kV PCB and 1-138 kV PCB and
associated equipment associated equipment
204
Appendix 5 – Abbreviations and Acronyms
Development Plans:
Electric Cooperatives:
Electricity Market:
206
PGC Philippine Grid Code
QMS Quality Management System
RE Law Renewable Energy Law
Power Plants:
207
MERALCO Manila Electric Company
SFELAPCO San Fernando Electric Light and Power Company
Regions/Areas:
Regulatory:
208
DR Dispatchable Reserve
FRR Frequency Regulating Reserve
GDP Gross Domestic Product
GRDP Gross Regional Domestic Product
IMF International Monetary Fund
LoLp Loss, Load Probability
SPD System Peak Demand
Transmission System/Projects:
209
S/S Substation
TACSR Thermal Aluminum Cable Steel Reinforced
T/L Transmission Line
Unit of Measure:
ckt-km Circuit-kilometer
km kilometer
kV kilo-Volt
MVA Mega-Volt Ampere
MVAR Mega-Volt Ampere Reactive
MW Mega-Watt
UTS Ultimate Tensile Strength
210
Appendix 6 – Contact Details
For all inquiries regarding the TDP, you may contact any of the following:
211