Braced Cut
Braced Cut
Deep excavation with vertical sides require lateral supports to prevent cave in of the earth and to
protect the adjacent areas against ground subsidence and lateral movement of the subsoil. When
excavations are shallow and ample space is available, the sides of the excavation can be sloped at
a safe angle to ensure stability. However, in deep excavations, especially in built up areas, there
may not be adequate space for providing safe slope. Moreover, it becomes uneconomical to
provide safe slopes because of large quantities the earth involved. Excavation which are laterally
supported are called ‘Braced Cuts’.
Cross Section of a Braced Cut:
Type I use of soldier beams
•Soldier beam is driven into the ground before excavation and is a vertical steel or timber beam.
•Laggings, which are horizontal timber planks, are placed between soldier beams as the
excavation proceeds.
•When the excavation reaches the desired depth, wales and struts (horizontal steel beams) are
installed. The struts are horizontal compression members.
Steel Sheet Pile: In this method, the steel sheet piles are driven along the sides of the
proposed excavation. As the soil is excavated from the enclosure, wales and struts are
placed. The wales are made of steel. The struts may be of steel or wood. As the
excavation progresses, another set of wales and struts is inserted. The process is
continued till the excavation is complete. It is recommended that the sheet piles should be
driven several meters below the bottom of excavation to prevent local heaves. If the width of a
deep excavation is large, inclined bracing may be used.
Tie Backs: In this method, no bracing in the form of struts or inclined rakers is provided.
Therefore, there is no hindrance to the construction activity to be carried out inside the excavated
area. The tie back is a rod or a cable connected to the sheeting or lagging on one side and
anchored into soil (or rock) outside the excavation area.
Inclined holes are drilled into the soil (or rock), and the hole is concreted. An enlargement or a
bell is usually formed at the end of the hole. Each tie back is generally prestressed the depth of
excavation is increased further to cope with the increased tension
Use of Slurry Trenches: An alternative to use of sheeting and bracing system, which is being
increasingly used these days, is the construction of slurry trenches around the area to be
excavated and is kept filled with heavy, viscous slurry of a bentonite clay-water mixture.
The slurry stabilizes the walls of the trench, and thus the excavation can be done without
sheeting and bracing. Concrete is then placed through a tremie. Concrete displaces the slurry.
Reinforcement can also be placed before concreting, if required. Generally, the exterior walls of
the excavation are constructed in a slurry trench.
Whichever is higher.
Solution:
Given,
= 18 KN/m3
C = 25 KN /m2
H = 8m
𝛾𝐻 18 𝑋 8
Now, = = 5.76> 4
𝐶 25
So, the earth pressure diagram will be:
4 𝑥 25
Pa = 18 x 8 [1-( )]
18 𝑥 8
= 44 KN
Or, Pa = 0.3 H
= 0.3 x 18 x 8
= 43.2 KN
So, Pa = 43.2 KN
The pressure distribution is shown in figure.
For calculating the strut force, each strut is assumed to carry the corresponding load based on a simple span.
Now from the first zone, taking moment at left bottom point,
∑𝑀 = 0
(R1 x 1.5) – (P1 x 1.833) – (P2 x 0.25) = 0
(R1 x 1.5) – (43.5 x 1.833) – (21.6 x 0.25) = 0
R1 = 56.757 KN
∑ 𝐹𝑥 = 0
R1 + R2’ – P1 – P2 = 0
56.757 + R2’– 43.5 – 21.6 = 0
R2’ = 8.343 KN
From the last part of the section, taking moment at left upper side,
(R5x1.5) - (P5x 1.25) = 0
(R5x1.5) - (108x 1.25) = 0
R5 = 90 KN
∑Fx = 0
R5+ R4’’-P5 = 0
90 + R4’-108 = 0
R4’= 108-90 = 18 KN
So R4 = 32.4+18 = 50.4 KN
Answer:
R1 = 56.757 KN
R2 = 40.743 KN
R3 = 64.8 KN
R4 = 50.4 KN
R5 = 90 KN