Day 5 - Developing Project Network Diagram PDF
Day 5 - Developing Project Network Diagram PDF
FIGURE 6.1
WBS/WORK PACKAGE TO NETWORK
(CONT’D)
A B D
CONSTRUCTING A PROJECT
NETWORK
(CONT’D)
Terminology
Event: a point in time when an activity is started
or completed.
Burst Activity: an activity that has more than one activity
immediately following it (more than one dependency arrow
flowing from it).
B
Two Approaches
Activity-on-Node (AON)
Uses a node to depict an activity.
A C
Activity-on-Arrow (AOA)
Uses an arrow to depict an activity.
D
BASIC RULES
1. Networks typically flow from left to right.
2. An activity cannot begin until all preceding connected
activities are complete.
3. Arrows indicate precedence and flow
and can cross over each other.
4. Each activity must have a unique identify number that is
greater than any of its predecessor activities.
5. Looping is not allowed.
6. Conditional statements are not allowed.
7. Use common start and stop nodes.
ACTIVITY-ON-NODE FUNDAMENTALS
FIGURE 6.2
ACTIVITY-ON-NODE FUNDAMENTALS
(CONT’D)
TABLE 6.1
AUTOMATED WAREHOUSE
FIGURE 6.4
NETWORK INFORMATION
ACTIVITY-ON-NODE NETWORK
ACTIVITY-ON-NODE NETWORK FORWARD
PASS
ACTIVITY-ON-NODE NETWORK
BACKWARD PASS
FORWARD AND BACKWARD PASSES
COMPLETED WITH SLACK TIMES
PRACTICAL CONSIDERATIONS
Network Logic Errors
Activity Numbering
Use of Computers to Develop
Networks
Calendar Dates
Multiple Starts and Multiple
Projects
NETWORK LOGIC ERRORS
ILLOGICAL LOOP
FIGURE 6.9
6–37
AUTOMATED WAREHOUSE ORDER
PICKING SYSTEM NETWORK
AUTOMATED ORDER WAREHOUSE
PICKING SYSTEM BAR CHART
EXTENDED NETWORK TECHNIQUES
TO COME CLOSE TO REALITY
Laddering
Activities are broken into segments so the following activity
can begin sooner and not delay the work.
Lags
The minimum amount of time a dependent activity must be
delayed to begin or end.
Lengthy activities are broken down to reduce the delay
in the start of successor activities.
Lags can be used to constrain finish-to-start, start-to-start, finish-to-
finish, start-to-finish, or combination relationships.
EXAMPLE OF LADDERING
USE OF LAGS
Finish-to-Start Relationship
Start-to-Start Relationship
USE OF LAGS
(CONT’D)
Finish-to-Finish
Relationship
Start-to-Finish
Relationship
Combination
Relationship
NETWORK USING LAGS
Using Lag
The amount of time whereby a successor activity is required
to be delayed with respect to a predecessor activity”
HAMMOCK ACTIVITIES
Hammock Activity
Spans over a segment of a project.
Has a duration that is determined after the network plan is
drawn.
Is used to aggregate sections of the project to facilitate getting
the right amount of detail for specific sections of a project.
Is very useful in assigning and controlling indirect project costs.
HAMMOCK ACTIVITY EXAMPLE
Activity-on-Arrow Network Building Blocks
Activity-on-Arrow Network Fundamentals
Draw AOA
Draw AOA
Draw AOA
Draw AOA
Questions!