0% found this document useful (0 votes)
720 views6 pages

4M Change Management-AL Check Sheet

This document is a checklist used to track changes across four main categories - Man, Machine, Material, and Method - for various processes in a manufacturing line. It includes boxes to check Yes or No for each category of change and space to record the date. There are sections for multiple lines and shifts to record information.

Uploaded by

Er Nitin Kamble
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
720 views6 pages

4M Change Management-AL Check Sheet

This document is a checklist used to track changes across four main categories - Man, Machine, Material, and Method - for various processes in a manufacturing line. It includes boxes to check Yes or No for each category of change and space to record the date. There are sections for multiple lines and shifts to record information.

Uploaded by

Er Nitin Kamble
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

4M Change Management-AL Check Sheet

4M Check Point Y /N Date


Contract/ Temporary Manpower
Extended shift working
Skill level change / Upgrade
Operator change (in between shift)
MAN

Quality awareness for Customer Complaints


Operator Joins after Planned leave
Operator Awareness wrt Process Parameters
Safety Awareness
Others (if specify)
Tool & Die Change
Jig & Fixture Change
Removal / Addition of Poka-Yoke
M/C & Testing Rig Parameter Change
MACHINE

Machine start up with fresh cycle (Power failure etc)


Machine or Fixture under gone any maintenance
Inspection Equipment Change / Breakdown
EOL Equipment spec or parameter change
Others (if specify)
Process Sequence Change (Verification Reqd)
Sub assembly process change (Verification Reqd)
Packaging & Transportation mode change
If any changes in Inspection method & frequency
Limit sample change
METHOD

Process Parameter Change (New or Additional)


Adequacy of Measuing instruments
Fixture & Gauges condition & Calibration.
Instrument error & breakdown
Effectiveness of Poka Yoke (Woring condition)
Others (if specify)
Raw material different Spec / Grade
Changes in Raw Material Source
MATERIAL

Child-part change or any deviation


Any Change through ECN
Changes to the existing tooling, jigs & fixtures
Others (if specify)
Line/Cell Name:
Line Actions / Contols Reviewed Approved
4M Change Control-Wabco, Chennai
Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C
Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder sub assy Flange sub assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others

Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C


Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder Sub Assy Flange sub assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others
Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C
Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder Sub Assy Flange Sub Assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others

Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C


Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder sub assy Flange sub assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others

Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C


Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder sub assy Flange sub assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others

Dt / Shift: Man A B C MC A B C MET A B C MAT A B C OTH A B C


Prod.
Process: Bearing Pressing Cyl.Greasing & Seal Cylinder sub assy Flange sub assy Twist lock station Sub Assy Testing Clampring assy Endfitting station Dry leak testing Wet leak testing Final assy Retightening station PDI & Packing Leader
Mfg Line: L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
Man
Machine
Material
Method
Others