RCC Railing To OHSR
RCC Railing To OHSR
Name of Work: Providing Single Village Scheme to Lingareddy Kottala Village of Proddatur Mandal in YSR
2 Provision for Unseen items such as increase in power charges, road crossings,
escalation of prices, execution adjustments
Project Manager
DPSU, APRWSSP, Kadapa
AL ABSTRACT ESTIMATE
Rate Amount
#REF! #REF!
Total Rs #REF!
I. SKILLED CATEGORY:
1 Bar bender 300.00
2 Black smith / Tin smith / Rivetor 285.00
3 Blaster ( Licensed ) 310.00
4 Carpenter Cl- I 285.00
5 Electrician ( Licensed ) 310.00
6 Fitter Cl- I 285.00
7 Floor Polisher / Tile Layer 285.00
8 Foreman 310.00
9 Gauge reader 260.00
Maistry / Work Inspector with Non-technical Qualification
10 275.00
SSLC/SSC/HSC
11 Mason Cl- I / Brick layer Cl- I 285.00
12 Mechanic Cl- I 285.00
13 Operator Air compressor / DG set 285.00
14 Operator Batching plant 310.00
15 Operator Bus/Ambulance/ Lorry/ Tanker 285.00
16 Operator Concrete / Asphalt mixer 285.00
17 Operator Concrete / Asphalt paver 285.00
18 Operator Concrete pump / Placer/ ice plant 285.00
19 Operator Core drilling machine 310.00
20 Operator Crane/ Tower crane/ Cable way 310.00
21 Operator Drilling jumbo / Loco / Winch 285.00
22 Operator Grouting/ Guniting/ Shotcreting 285.00
23 Operator Jackhammer/Pneumatic tamper 285.00
24 Operator Pump / Ventilation fan 285.00
25 Operator Lathe/Drilling/Shearing machine 310.00
26 Operator Bending / Planing machine 285.00
27 Operator Road roller 285.00
28 Operator Shovel / Scraper / Dozer 310.00
29 Operator Spillway / Sluice gate 285.00
30 Operator Crusher / Conveyor / Mucker 285.00
31 Operator Tipper / Dumper / Transit mixer 310.00
32 Operator Concrete vibrator 285.00
33 Operator Vibratory plain / pad foot roller 285.00
34 Operator Wagon drill / Drifter 310.00
35 Painter Cl- I 300.00
36 Plumber ( Licensed ) / Pipe fitter 285.00
37 Sarang / Khalasi 285.00
38 Spun pipe moulder 285.00
39 Stone chiseller CI- I / Stone cutter Cl- l 285.00
40 Struct. steel Fabricator / Marker / Erector 310.00
41 Welder / Gas Cutter 285.00
42 Welder (X-ray quality) 310.00
Andhra pradesh Municipal Voyants Solutions Pvt Ltd
Development Project (APMDP)
Comprehensive Planning of Water supply Service
Final Detailed Project Report
Improvements in Vizianagaram Municipality
Description of Conveyanc
S.No Unit Source of supply
material e charges
(Excluding Add 25%
13.615% for Total
Lead in contractor Initial Blasting crushed Seiniorag amount
KMs profit) cost charges metal e charges (Rs.)
Pennar River
1 Sand for filling cum 38 438.41 95.00 0.00 0.00 50.00 583.41
Chennur
Penna River
2 Sand for mortor cum 38 438.41 95.00 0.00 0.00 50.00 583.41
Chennur
20 mm HBG SS
3 cum Muddanur 60 647.54 1036.00 70.00 259.00 75.00 2087.54
M/c Metal
Certified that the above leads are correct to the best of my knowledge
Earth work excavation in B.C soils, Red Earth and ordinary gravelly soils for pipe line trench of size 0.7 X 1.00 Mt using 2/3 quantity with
1 machinery and 1/3 quantity with manual including cost of sand filling of 100 mm thick sand bed and refilling the trench with excavated earth
including all labour charges etc complete.,
Earth work with Mechanical means (machinery) of 2/3 quantity, rates as per
0.467 cum 82.53 1 cum 38.54
A.P standard data calculation
Earth work with manual of 1/3 quantity, rates as per A.P standard data
0.233 cum 127.40 1cum 29.68
calculation
Add 75% for narrow trenches on manual only 22.26
0.07 cum Sand for filling including cost, conveyance and seigniorage charges 583.41 1cum 40.84
0.07 cum Labour charges for sand filling (0.31 days X Rs.350) 108.50 1 cum 7.60
TOTAL 138.92
Earth work with Mechanical means (machinery) of 2/3 quantity, rates as per
0.720 cum 82.53 1 cum 59.42
A.P standard data calculation
Earth work with manual of 1/3 quantity, rates as per A.P standard data
0.36 cum 127.40 1cum 45.86
calculation
TOTAL 105.29
Superintending Engineer
RWS&S, Circle Kadapa
s including lowering, laying,
1.10m
200 mm
ineer
sion
DATA SHEET - IV
PVC Pipes Data based on 2016-17 common SSR
PVC Resin rate: Rs.68825/- Per MT Cost of specials : 1.20 %
Amount
Rate Per
(Rs.)
73.00 Kg 730.00
89.00 Kg 1780.00
91508.00
13195.00
104703.00
Assistant Engineer
RWS&S Proddatur
DATA SHEET BASED ON SSR 2017-18
S.No Qnty Unit Description of item Rate (Rs.) Unit Rate (Rs.)
Cement concrete(1:1.5:3) prop using 20mm gauge HG metal including cost and conveyance of all materials and labour
1
charges,seignorage charges etc complete.
0.9 cum 20mm HBG graded metal Rs. 2087.54 cum 1878.79
0.45 cum Sand for concrete Rs. 583.41 cum 262.53
400 Kgs Cement Rs. 3882.00 MT 1552.80
0.133 day 1st Class Mason Rs. 465.00 day 61.85
0.267 day 2nd Class Mason Rs. 420.00 day 112.14
3.6 day Mazdoor (Both Men and Women) Rs. 370.00 day 1332.00
1 hour Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity Rs. 352.50 hour 352.50 bldg.21-A
0.133 Liters Cost of Diesel for Miller Rs. 61.73 Liters 8.21
0.667 Liters Cost of Petrol for Vibrator 71.68 Liters 47.81
1.2 kl Water (including for curing) 77.00 kl 92.40
5701.03
Overheads & cp 13.615% 776.19
Total rate per cum 6477.22
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges, centering etc., complete but
2
excluding cost of steel and its fabrication charges
1.00 Cum Cost of CC (1:1.5:3) 5701.03 1 Cum 5701.03
1.00 Cum Centering charges for RCC Pedestals 1068.00 1 Cum 1068.00
--- Sub-Total 6769.03
Overheads & cp 13.615% 921.60
Total 7690.63
Calculating cost of Executed quantities of RCC Railing of Staircase, Landing portion and on Top Slab of 20KL OHSR
vertical standposts of
2 staircase using VRCC 1 X 49 0.55 0.785 0.01 0.21156 Cum 7690.63
(1:1.5:3) with 20mm HBG
metal
vertical standposts of
3 staircase using VRCC 1 X 13 0.98 0.785 0.01 0.10001 Cum 7690.63
(1:1.5:3) using 20mm HBG
metal on landing portion
vertical standposts of
4 staircase using VRCC 1 X 18 0.96 0.785 0.01 0.13557 Cum 7690.63
(1:1.5:3) using 20mm HBG
metal on Top slab
TOTAL
nd on Top Slab of 20KL OHSR
Amount
Per
(Rs.)
1 Cum 1112
1 Cum 1627
1 Cum 769
1 Cum 1043
1 Kg 14458
1 Kg 12591
1 Kg 1295
1 Kg 1776
1 Kg 808
1 Kg 1119
36598