Zealcon Engineering Pvt. LTD: Item # Direct Cost Civil Mech E & I Total Amount (PKR)
Zealcon Engineering Pvt. LTD: Item # Direct Cost Civil Mech E & I Total Amount (PKR)
LTD
Rev. 00 16-05-2019
Subcontracting
11 FABRICATION & ERECTION OF CS @ Rs. 1100 Dia Inch Dia Inch 5,500 - -
- 6,050,000 - - - 1,100 6,050,000
12 STEEL STRUCTURE (Fab Erection) @ Rs. 30,000 Kg Ton 40 - -
- 1,200,000 - - - - 30,000 1,200,000
13 Under Ground GRE Pipping @ 400 Dia Inch 500 2 -
- 200,000 - - 400 200,000
14 Trench Excavation @15 Cu ft 10,500 0.2 -
- 157,500 - - 15 157,500
15 NDT PAUT (10 trip @ 50,000) Dia Inch 2,500 1 -
- 500,000 - - 200 500,000
16 Corroguted sheets for Roof @ 2000 M2 250 8 -
- 500,000 - - 2,000 500,000
17 Sand Blasting and Painting of Above Supplied Steel Structure @ 1500 M2 1,500 2 -
- 2,250,000 - - 1,500 2,250,000
18 Sand Blasting and Painting @ 1500 M2 2,150 2 -
- 3,225,000 - - 1,500 3,225,000
Equipment Dismantling Ton
3,000,000
Grand Total - - 17,082,500 6,299,000 - - - 20,381,500
Days 45
- -
Project Month 1 2 3 4 5
PEAK MAN Fortnightly Salary Total Amount
Sr.No. Months
PERSONS MONTHS May June June July July (Fortnightly)
1 Supervisor Piping 5 14 1 2 5 5 1 40,000 560,000
2 Supervisor Steel Structure 3 9 1 1 3 3 1 40,000 360,000
3 Supervisor Equipment 2 7 1 1 2 2 1 40,000 280,000
4 Supervisor Rigging 4 14 2 2 4 4 2 40,000 560,000
5 Welder 16 48 6 8 16 16 2 30,000 1,440,000
6 Tack Welders 6 20 2 4 6 6 2 14,063 281,250
7 Fitter 40 102 12 8 40 40 2 14,063 1,434,375
8 Fabricator 20 64 6 16 20 20 2 15,625 1,000,000
9 Riggers 20 54 4 6 20 20 4 12,500 675,000
10 Helpers 40 116 12 20 40 40 4 11,250 1,305,000
11 Scaffolders 20 54 4 8 20 20 2 12,500 675,000
12 Millwrights 2 10 4 4 2 0 31,250 312,500
13 Equipment operators 30 84 6 12 30 30 6 15,000 -
14 Painters 1 5 1 1 1 1 1 15,000 75,000
15 Sandblaster 0 0 0 0 0 0 0 15,000 -
16 Electrician 4 18 4 4 4 4 2 18,750 337,500
40 Ton Crane for Equipment Erection 1 550,000 0 Rental 125,000 1,200 0 135 - 125,000
25 Ton Crane for Fab Shop 1 2 210,000 420,000 Owned 900 1,800 135 243,000 663,000
25 Ton Crane for Fab Shop/SBP/Loading 2 320,000 0 Rental 900 0 135 - -
07 Ton Crane for Fab Shop 1 2 100,000 200,000 Owned 100,000 450 900 135 121,500
25 Ton Crane for Erection Piping/Structure 4 320,000 0 Rental 900 0 135 - -
25 Ton Crane for Material Loading 2 320,000 0 Rental 900 0 135 - -
200 Kva Generator 2 100,000 0 Rental 7,200 0 135 - -
100 Kva Generator 1 2 150,000 300,000 Rental 50,000 4,800 9,600 135 1,296,000 1,646,000
45 Kva Generator 1 30,000 0 Owned 1,620 0 135 - -
Tralir 40ft 1 2 140,000 280,000 Rental 40,000 600 1,200 135 162,000 482,000
Compressor 700 2 4 150,000 600,000 Rental 40,000 600 2,400 135 324,000 964,000
Water Bowser 2 150,000 0 Rental 0 135 - -
Welding Rectifires (@ PKR. 105,000) 40 OWNED 120,000 120,000
Networking Cost
Quantity/M Rate Total
Item # Description
onth ( PKR) Amount(PKR)
1 Electrical Networking Lumsum -
2 Drainage Networking Lumsum -
3 Water Supply Network Lumsum -
Total -
ZEALCON ENGINEERING PVT. LTD
Furnishing Cost
Quantity/M Rate Total
Item # Description
onth ( PKR) Amount(PKR)
1 Cots 300 -
2 Beds 40 -
3 Dining Room Lumsum Available
4 Electronic Lumsum Available
5 Air Conditioners 40 Available
6 Water Coolers / ETC Lumsum Available
7 Soft furnishing Lumsum Available
Total -
ZEALCON ENGINEERING PVT. LTD
Air Travels
Quantity/M Rate Total
Item # Description
onth ( PKR) Amount(PKR)
1 Lahore - Khi - Lahore -
2 Rota - - -
Total -
SUPERVISION STAFF
Position No. of Persons Total Months Salary Total Salary
2.5
Project Management
Project Manager 1 3.0 400,000 1,200,000
Execution
CM Machanical 1 2.5 180,000 450,000
Area Engineers (Mech & Piping) 3 6.0 100,000 600,000
Surveyors 2 5.0 60,000 300,000
Astt Survey 4 10.0 25,000 250,000
Material Coordinators 3 8.0 50,000 400,000
Planning
I/c Planning 1 3.0 120,000 360,000
FEDC Engineer 1 2.0 80,000 160,000
Quantity Surveyor/Draftsman 1 2.0 100,000 200,000
System Administrator 1 3.0 50,000 150,000
Planning Engineer 1 3.0 60,000 180,000
Planning Supervisor 2 5.0 30,000 150,000
Finance
Accountants /Cashier 1 3.0 60,000 180,000
Admin
I.c Admin 1 3.0 60,000 180,000
Camp supervisor / Transport Superviser 2 5.0 40,000 200,000
Time keepers 2 5.0 40,000 200,000
Office Boy/Room Boy 4 8.0 18,000 144,000
Cook 2 6.0 30,000 180,000
Sweeper 6 10.0 16,000 160,000
Security Guards 12 30.0 20,000 600,000
Procurement
Purchaser 1 3.0 75,000 225,000
Client Warehose Helpers
Storekeeper type 2 5.0 35,000 175,000
Helpers 2 5.0 18,000 90,000
Store
I/c Store 1 3.0 75,000 225,000
Store Keepers & Fabricator 2 6.0 35,000 210,000
Helpers 5 9.0 18,000 162,000
Equipment & Plant
Supervisor 1 3.0 80,000 240,000
Mechanic 2 5.0 30,000 150,000
Auto Electrician 1 2.0 30,000 60,000
Power Electrician 2 5.0 30,000 150,000
Tyre Man 0 - 24,000 -
Helpers 2 5.0 18,000 90,000
Quality Control
I/C QA/QC 1 2.0 200,000 400,000
QC Supervisor 3 6.0 80,000 480,000
Inspectors for Paint 1 3.0 60,000 180,000
Inspectors 6 15.0 60,000 900,000
HSE
I/C HSE 1 3.0 120,000 360,000
HSE Supervisor/PTW 6 15.0 50,000 750,000
Inspectors 4 8.0 30,000 240,000
Flage Man 2 6.0 20,000 120,000
Doctor 1 3.0 80,000 240,000
Paramedic 2 5.0 40,000 200,000
Total 102 239.5
Miscellaneous Cost
Quantity/M Rate Total
Item # Description
onth ( PKR) Amount(PKR)
1 Running Expence P.Month (site) 2 -
2 Utility Water-Chiller 1 -
3 Drinking Water-RO 1 -
4 Insurance Lumsum - -
5 Performance Gurantee 1.4% PA -
6 Bank Charges -
Total -
ZEALCON ENGINEERING PVT. LTD
PM Toyota-Car 1 3 0 300 0 0
Ambulance 1 3 0 0 0 0
Security Cost
Quantity/M Rate Total
Item # Description
onth ( PKR) Amount(PKR)
1 Security Guards Local 75 - -
2 F.C Cost 150 - -
3 Food for FC 150 - -
Total -