QUANTITY FOR A BEAM
H: 0.38 m
W: 0.38 m
Given Data:
Length: 106.68 m, width: 0.38 m, Height: 0.38 m
Grade of Concrete: M20:1:1.5:3
Sum of Ratio= 1+1.5+3= 5.5
Dry Volume: 54%
Solution:
Wet Volume=L x W x H
=106.68x0.38x0.38
= 15.41 m3
Dry Volume= Wet Volume x 1.54
= 15.41 x 1.54
= 23.73 m3
𝑪𝒆𝒎𝒆𝒏𝒕 𝑹𝒂𝒕𝒊𝒐
Cement: x Dry Volume x bag volume OR
𝑺𝒖𝒎 𝒐𝒇 𝑹𝒂𝒕𝒊𝒐
𝑪𝒆𝒎𝒆𝒏𝒕 𝑹𝒂𝒕𝒊𝒐
Cement: x Dry Volume x Density of Cement
𝑺𝒖𝒎 𝒐𝒇 𝑹𝒂𝒕𝒊𝒐
Density of 1 m3: 1440 Kg
1 bag of Cement: 50 Kg
1440
Volume of 1 bag of Cement: = 28.8
50
1
Cement=
5.5
x 23.73 x 28.8= 124.25 Bags
1
Cement=5.5 x 23.73 x 1440= 6213 Kg
𝑺𝒂𝒏𝒅 𝑹𝒂𝒕𝒊𝒐
Sand: x Dry Volume
𝑺𝒖𝒎 𝒐𝒇 𝑹𝒂𝒕𝒊𝒐
1.5
Sand= 5.5 x 23.73
Sand= 6.47 m3 OR
Sand= 6.47 x 35.32 1 m3 = 35.32 CFT
Sand= 228.52 CFT
𝑨𝒈𝒈𝒓𝒆𝒈𝒂𝒕𝒆 𝑹𝒂𝒕𝒊𝒐
Aggregate: x Dry Volume
𝑺𝒖𝒎 𝒐𝒇 𝑹𝒂𝒕𝒊𝒐
3
Aggregate= 5.5 x 23.73
Aggregate= 12.94 m3 OR
Aggregate= 12.94 x 35.32
Aggregate= 457.17 CFT
Req Quantities:
Cement: 124.25 Bags (6213 Kg)
Sand: 6.47 m3 (228.52 CFT)
Aggregate: 12.94 m3 (457.17 CFT)
Cross Check:
Total Volume= Volume of Cement + Volume of Sand + Volume of Coarse Aggregate
23.73= 4.31 + 6.47 + 12.94
23.73=23.72