0% found this document useful (0 votes)
68 views4 pages

Final TempFacil Quo Revised

This document contains a bill of quantities and cost estimate for the construction of a temporary facility in Bonifacio Global City, Taguig. It provides a breakdown of material and labor costs for structural works including footings, columns, beams, slabs and masonry. It also includes costs for architectural works, doors, windows, roofing and other miscellaneous works. The total project cost is estimated to be [VALUE] and will take 30-45 days to complete, excluding electrical works. Payment will be made in two installments, with 50% as a down payment and 50% on progress billing.

Uploaded by

Neil San Juan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views4 pages

Final TempFacil Quo Revised

This document contains a bill of quantities and cost estimate for the construction of a temporary facility in Bonifacio Global City, Taguig. It provides a breakdown of material and labor costs for structural works including footings, columns, beams, slabs and masonry. It also includes costs for architectural works, doors, windows, roofing and other miscellaneous works. The total project cost is estimated to be [VALUE] and will take 30-45 days to complete, excluding electrical works. Payment will be made in two installments, with 50% as a down payment and 50% on progress billing.

Uploaded by

Neil San Juan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Title : TEMPORARY FACILITY DETAILS

Location : BONIFACIO GLOBAL CITY, TAGUIG


Owner : PHLIPPINE REALTY & HOLDING CORPORATION

BILL OF QUANTITIES

MATERIAL COST LABOR COST


ITEM #DESCRIPTION QTY UNIT AMOUNT
Per Unit Total Per Unit Total

I STRUCTURAL

A FOOTING
1.0 Cement 36 bags 250.00 9,000.00 100.00 3,600.00 12,600.00
2.0 Gravel plus 16 cu. m. 600.00 9,600.00 240.00 3,840.00 13,440.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 460 kgs 45.00 20,700.00 18.00 8,280.00 28,980.00
5.0 Tie Wire 5 kls 40.00 200.00 16.00 80.00 280.00

B COLUMN
1.0 Cement 36 bags 250.00 9,000.00 100.00 3,600.00 12,600.00
2.0 Gravel 15 cu. m. 600.00 9,000.00 240.00 3,600.00 12,600.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 202 kg 45.00 9,090.00 18.00 3,636.00 12,726.00
5.0 Tie Wire 5 kls 40.00 200.00 16.00 80.00 280.00
6.0 10 mm dia. 400 kgs 25.00 10,000.00 10.00 4,000.00 14,000.00
7.0 Phenolic 3 20 pcs 1400.00 28,000.00 560.00 11,200.00 39,200.00
8.0 2x2x12 42 pcs 380.00 15,960.00 152.00 6,384.00 22,344.00
FOOTINGCTIE BEAM , BEAM & GIRDER
1.0 Cement 100 bags 250.00 25,000.00 100.00 10,000.00 35,000.00
2.0 Gravel 9 cu. m. 600.00 5,400.00 240.00 2,160.00 7,560.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 2046 kg 45.00 92,070.00 18.00 36,828.00 ###
5.0 Tie Wire 16 kls 40.00 640.00 16.00 256.00 896.00
6.0 10 mm dia. 542 kgs 25.00 13,550.00 10.00 5,420.00 18,970.00

D SLAB & WF slab


1.0 Cement 36 bags 250.00 9,000.00 100.00 3,600.00 12,600.00
2.0 Gravel plu 23 cu. m. 600.00 13,800.00 240.00 5,520.00 19,320.00
3.0 Fine Sand 4 cu. m. 550.00 2,200.00 220.00 880.00 3,080.00
4.0 10 mm dia. 608 kgs 25.00 15,200.00 10.00 6,080.00 21,280.00
5.0 Tie Wire 9 kls 40.00 360.00 16.00 144.00 504.00

E MASONRY
1.0 100mm thk 3839 Pcs 15.00 57,585.00 6.00 23,034.00 80,619.00
2.0 Mortar and Plastering
Cement 175 bags 250.00 43,750.00 100.00 17,500.00 61,250.00
Sand 24 cu. m. 550.00 13,200.00 220.00 5,280.00 18,480.00
3.0 10mm Reb 540 kg 25.00 13,500.00 10.00 5,400.00 18,900.00
4.0 Tie wire 7 kls 25.00 175.00 10.00 70.00 245.00
5.0 .30x.30 Ord 200 sq m 2200.00 ### 250.00 50,000.00 ###
5.0 .30x.30 Or 96 sq m 2200.00 ### 250.00 24,000.00 ###

F ROOFING
1.0 Prepainted 276.92 sq. m. 420.00 ### 250.00 69,230.00 ###
Insulation 276.92 sq. m. 120.00 33,230.40 55.00 15,230.60 48,461.00

II ARCHITECTURAL

A WALL FINISHES
1.0 Dry wall
a.) Inner w 100.5 sq. m. 450.00 45,225.00 180.00 18,090.00 63,315.00
b.) Partitio 43.81 sq. m. 450.00 19,714.50 180.00 7,885.80 27,600.30
2.0 Painting Works
a.) Comple 686.41 sq. m. 140.00 96,097.40 150.00 ### ###
BCEILING FINISHES
1.0 Flat Ceili 201 sq. m. 300.00 60,300.00 200.00 40,200.00 ###

DOORS &IIIWINDOWS (Supply & Install)


A Wooden Doors
1.0 1.8m 1 set/s 7000.00 7,000.00 2,800.00 2,800.00 9,800.00
2.0 0.80m 2 set/s 3850.00 7,700.00 1,540.00 3,080.00 10,780.00
3.0 0.70m 5 set/s 3500.00 17,500.00 1,400.00 7,000.00 24,500.00
4.0 1.6m Doub 1 set/s 7000.00 7,000.00 2,800.00 2,800.00 9,800.00
B Door - Toilet Door
PVC
1.0 0.70m 8 set/s 3500.00 28,000.00 1,400.00 11,200.00 39,200.00
C Glass Sliding Windows
Plain
1.0 1.5 x 1.2 5 set/s 5000.00 25,000.00 2,000.00 10,000.00 35,000.00
2.0 1.2x 1.2 8 set/s 4000.00 32,000.00 1,600.00 12,800.00 44,800.00
3.0 Double 3 set/s 3000.00 9,000.00 1,200.00 3,600.00 12,600.00
4.0 Single 1 set/s 1500.00 1,500.00 600.00 600.00 2,100.00

Material Cost ###


Labor Cost ###
Mobilization / Demobilization ###
Clearing 50,000.00
Excavation 50,000.00
Miscellaneous 5% ###
Profit and Overhead 10% ###
Contractors profit 10% ###
SUB TOTAL COST ###
EWT 2% 57,627.61
GRAND TOTAL ###

NOTE:
1. THIS CONSTRUCTION COST ESTIMATE IS IN ACCORDANCE TO THE CURRENT SPECIFI
2. ITEMS NOT INCLUDED HEREIN SHALL BE CONSIDERED AS AN ADDITIONAL WORK

DURATION:
Thirty (30) to Forty Five (45) Calendar Days.

EXCLUSION:
1. Electrical Works

TERMS OF PAYMENT:
50% - Down Payment
50% - Progress Billing

You might also like