Final TempFacil Quo Revised
Final TempFacil Quo Revised
BILL OF QUANTITIES
I STRUCTURAL
A FOOTING
1.0 Cement 36 bags 250.00 9,000.00 100.00 3,600.00 12,600.00
2.0 Gravel plus 16 cu. m. 600.00 9,600.00 240.00 3,840.00 13,440.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 460 kgs 45.00 20,700.00 18.00 8,280.00 28,980.00
5.0 Tie Wire 5 kls 40.00 200.00 16.00 80.00 280.00
B COLUMN
1.0 Cement 36 bags 250.00 9,000.00 100.00 3,600.00 12,600.00
2.0 Gravel 15 cu. m. 600.00 9,000.00 240.00 3,600.00 12,600.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 202 kg 45.00 9,090.00 18.00 3,636.00 12,726.00
5.0 Tie Wire 5 kls 40.00 200.00 16.00 80.00 280.00
6.0 10 mm dia. 400 kgs 25.00 10,000.00 10.00 4,000.00 14,000.00
7.0 Phenolic 3 20 pcs 1400.00 28,000.00 560.00 11,200.00 39,200.00
8.0 2x2x12 42 pcs 380.00 15,960.00 152.00 6,384.00 22,344.00
FOOTINGCTIE BEAM , BEAM & GIRDER
1.0 Cement 100 bags 250.00 25,000.00 100.00 10,000.00 35,000.00
2.0 Gravel 9 cu. m. 600.00 5,400.00 240.00 2,160.00 7,560.00
3.0 Fine Sand 2 cu. m. 550.00 1,100.00 220.00 440.00 1,540.00
4.0 16 mm dia. 2046 kg 45.00 92,070.00 18.00 36,828.00 ###
5.0 Tie Wire 16 kls 40.00 640.00 16.00 256.00 896.00
6.0 10 mm dia. 542 kgs 25.00 13,550.00 10.00 5,420.00 18,970.00
E MASONRY
1.0 100mm thk 3839 Pcs 15.00 57,585.00 6.00 23,034.00 80,619.00
2.0 Mortar and Plastering
Cement 175 bags 250.00 43,750.00 100.00 17,500.00 61,250.00
Sand 24 cu. m. 550.00 13,200.00 220.00 5,280.00 18,480.00
3.0 10mm Reb 540 kg 25.00 13,500.00 10.00 5,400.00 18,900.00
4.0 Tie wire 7 kls 25.00 175.00 10.00 70.00 245.00
5.0 .30x.30 Ord 200 sq m 2200.00 ### 250.00 50,000.00 ###
5.0 .30x.30 Or 96 sq m 2200.00 ### 250.00 24,000.00 ###
F ROOFING
1.0 Prepainted 276.92 sq. m. 420.00 ### 250.00 69,230.00 ###
Insulation 276.92 sq. m. 120.00 33,230.40 55.00 15,230.60 48,461.00
II ARCHITECTURAL
A WALL FINISHES
1.0 Dry wall
a.) Inner w 100.5 sq. m. 450.00 45,225.00 180.00 18,090.00 63,315.00
b.) Partitio 43.81 sq. m. 450.00 19,714.50 180.00 7,885.80 27,600.30
2.0 Painting Works
a.) Comple 686.41 sq. m. 140.00 96,097.40 150.00 ### ###
BCEILING FINISHES
1.0 Flat Ceili 201 sq. m. 300.00 60,300.00 200.00 40,200.00 ###
NOTE:
1. THIS CONSTRUCTION COST ESTIMATE IS IN ACCORDANCE TO THE CURRENT SPECIFI
2. ITEMS NOT INCLUDED HEREIN SHALL BE CONSIDERED AS AN ADDITIONAL WORK
DURATION:
Thirty (30) to Forty Five (45) Calendar Days.
EXCLUSION:
1. Electrical Works
TERMS OF PAYMENT:
50% - Down Payment
50% - Progress Billing