This document outlines the tasks and timeline for decommissioning an oil production vessel (MV14) over a 507 day period from January 2018 to June 2019. It involves 5 phases: 1) engineering definition and scope, 2) procurement, 3) deliverables, 4) pre-execution, and 5) execution. Key tasks include riser pull out, towing arrangements, tank cleaning, and removal of mooring and offloading equipment. The decommissioning requires coordination of engineering, procurement, planning and execution activities across multiple contractors and teams.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100%(2)100% found this document useful (2 votes)
289 views1 page
Decommissioning of FPSO
This document outlines the tasks and timeline for decommissioning an oil production vessel (MV14) over a 507 day period from January 2018 to June 2019. It involves 5 phases: 1) engineering definition and scope, 2) procurement, 3) deliverables, 4) pre-execution, and 5) execution. Key tasks include riser pull out, towing arrangements, tank cleaning, and removal of mooring and offloading equipment. The decommissioning requires coordination of engineering, procurement, planning and execution activities across multiple contractors and teams.
1 MV14 - Decommissioning (Draft Version as preliminary info only) 507,83 days 01/01/18 2 STOP OF PRODUCTION 0 days 30/06/18 30/06 3 SAIL AWAY 0 days 24/03/19 24/03 4 PB Contract Definition and Agreement for Demob 0 days 30/03/18 30/03 5 SPC Pending Clarifications regarding FPSO Destination 0 days 30/03/18 30/03 6 PHASE 1 - Engineering Detail Scope Definition 238,83 days 01/01/18 7 Chain Jack System Refurbshiment 176 days 16/02/18 20 Sea Water Lift Hose 0 days 25/08/18 25/08 22 Mooring Disconnection 1,17 days 01/07/18 26 Oceanic Towing 56,83 days 02/07/18 31 Riser Pull Out 76 days 03/03/18 38 HPUs Maintenance 0 days 02/07/18 02/07 40 NORM Mapping 182 days 01/01/18 43 Topside Cleaning Up 0 days 14/05/18 14/05 46 Cargo Tank Cleaning 0 days 06/04/18 06/04 48 Offloading Hose Removal 0 days 02/07/18 02/07 50 Advisor Service 91 days 02/04/18 53 FPSO Equipment Transfer to MdB 74 days 20/02/18 57 Power Generation 0 days 31/05/18 31/05 59 PHASE 2 - Procurement 390 days 01/01/18 60 Service Procurement 390 days 01/01/18 61 Chain Jack System Refurbshiment 204 days 08/03/18 95 Sea Water Lift Hose 18 days 25/08/18 100 Mooring Disconnection 94 days 01/07/18 113 Oceanic Towing 116 days 19/09/18 130 Riser Pull Out 94 days 03/03/18 151 HPUs Maintenance 18 days 14/10/18 156 NORM Mapping 390 days 01/01/18 165 Topside Cleaning Up 18 days 14/05/18 174 Cargo Tank Cleaning 18 days 06/04/18 179 Offloading Hose Removal 18 days 31/10/18 184 Advisor Service 236,83 days 02/04/18 197 FPSO Equipment Transfer to MdB 18 days 05/05/18 202 Power Generation 18 days 31/05/18 207 Rescue Team (3rd Party) 15 days 01/06/18 210 Material Procurement 262,83 days 18/04/18 211 Chain Jack Refurbshiment Material 13 days 18/04/18 215 Sea Water Lift Hose Removal Material 5 days 29/08/18 218 Mooring Disconnection Material 5 days 03/10/18 221 Station Keeping Acessories Material 5 days 03/10/18 224 Towing Acessories Construction Material 5 days 07/10/18 227 Riser Pull Out Equipment Material and Spares 5 days 26/04/18 230 Topside Cleanning Up 5 days 26/05/18 233 Cargo Tank Cleaning 5 days 11/06/18 236 Sea Fastening Material 5 days 01/01/19 239 FPSO Access Ladder 5 days 06/12/18 242 Messenger Chain Procurement 5 days 24/09/18 244 PHASE 3 - Deliverables 279,83 days 01/05/18 245 Document Contractors Delivery (Plans and Procedures) 253,83 days 01/05/18 254 Material Delivery 279,83 days 01/05/18 267 PHASE 4 - Pre Execution 367,83 days 21/03/18 268 HPU Repair 30 days 01/11/18 270 Messenger Chain Installation 15 days 25/10/18 272 Riser Pull-Out Preparative 106 days 21/03/18 281 Chain Jack System 215,17 days 11/04/18 295 Preparative for Oceanic Towing 43 days 09/02/19 300 Preparative for Station Keeping 44 days 23/12/18 303 PHASE 5 - Execution 394,83 days 24/04/18 304 Others 67 days 03/10/18 307 Riser Pull-Out 95 days 30/06/18 310 Top Side Cleaning 192 days 30/06/18 405 Offloading Hose Removal 6,67 days 08/01/19 408 Hull Tanks Integrity x Decommissioning 329,83 days 24/04/18 457 Mooring Lines Disconnection 47 days 05/02/19 461 Licences and Permits 90 days 24/12/18 467 Oceanic Towing to ASIA 60 days 25/03/19