0% found this document useful (0 votes)
361 views2 pages

MP Sepang Planning Permission Checklist

This document provides a checklist of required documents for planning permission approval from the Sepang Municipal Council. It lists the documents needed from the land owner/developer, planner, civil and structural engineer, M&E engineer, land surveyor, and architect. The checklist includes the number of copies required for documents like site plans, reports, calculations, clearances, forms, and drawings. It also notes additional document requirements like pre-consultation, concurrent submission of certain plans, online and hardcopy submission requirements to various technical departments.

Uploaded by

nazrin90
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
361 views2 pages

MP Sepang Planning Permission Checklist

This document provides a checklist of required documents for planning permission approval from the Sepang Municipal Council. It lists the documents needed from the land owner/developer, planner, civil and structural engineer, M&E engineer, land surveyor, and architect. The checklist includes the number of copies required for documents like site plans, reports, calculations, clearances, forms, and drawings. It also notes additional document requirements like pre-consultation, concurrent submission of certain plans, online and hardcopy submission requirements to various technical departments.

Uploaded by

nazrin90
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

CHECKLIST FOR PLANNING PERMISSION(KM) APPROVAL

MAJLIS PERBANDARAN SEPANG

LAND OWNER / DEVELOPER


LIST OF DOCUMENTS COPY STATUS
1. Land tittle (Certified True Copy by Land Office) 1 copy
2. Official Search (Original – valid for 6 months ) 1 copy
3. Latest Assessment Receipt 1 copy
Letter from MPSpg Valuation Department (if no 1 copy
4.
assessment receipt)
5. Quit Rent Receipt 1 copy
Power Attorney (if any) – registered with high court & 1 copy
6.
land office
7. Consent letter (if caveated or charged to bank) 1 copy
8. M&A Company, Form 49 & Form 24 1 copy
9. Identity Card of Land owner or company director 1 copy
10. Valuation report 1 copy
Gross Development Value (GDV), Gross Development 1 copy
11.
Cost (GDC) & Gross Development Profit (GDP)
12. Processing Fee / Submission Fee 1 copy
13. Appointment Letter of Town Planner & Engineer (M&E) 1 copy
PLANNER
1. Borang A 1 copy
2. Site Plan – A1 Size (a copy of Linen) 22 copies
3. Site Plan – A3 Size 22 copies
4. Borang Fee 15 copies
5. Laporan Cadangan Pemajuan (LCP) 10 copies
6. Borang Perihal Tanah (OSC 3.0) 3 copies
7. PSP Certificate 1 copy
C&S ENGINEER
1. MASMA Report and OSD Plan 5 copies
2. R&D Plan 5 copies
3. Sewerage Engineering report & Form PDC 1, Sijil Span 1 copy
4. Water Demand Calculation & HSL 4 copies
5. Cross Section of land (hilly areas) 1 copy
6. Surat Pra – rundingan SYABAS (OSC 3.0) 1 copy
7. Cover letter from C&S address to IWK 2 copies
** all document also required in softcopy for submission online
M&E ENGINEER
1. Electric demand Calculation 1 copy
2. Manhole Cabinet Infrastructure Plan 1 copy
3. SKMM Info in Excel Format 1 copy
4. Telekom Clearance letter 1 copy
5. Telecommunication Service Provider clearance letter 1 copy
6. Surat sokongan TNB & SKMM (OSC 3.0) 1 copy
** all document also required in softcopy for submission online
LAND SURVEYOR
1. Certified Plan 1 copy
2. Detailed survey (spot level, BM, ODL) 18 copies
** all document also required in softcopy for submission online
ARCHITECT
1. Detailed floor area calculation softcopy
2. Side, front & rear elevation /section softcopy
3. Floor plan softcopy
4. Perspective softcopy

**An addition document will inform letter


1. Pre-consult for confirmation KM layout with Jabatan Perancang, MPSepang
2. Pelan Kerja Tanah & Pelan Bangunan must be submitted concurrently with
Kebenaran Merancang
3. OSC 3.0 – Clearance letter form SYABAS, TNB, Land Office & SKMM
4. Online Submission for 9 technical departments (Jab Kejuruteraan, Jab.
Bangunan, Jab. Landskap, JPBD, JAS, TNB, SYABAS, JMG & SKMM)
5. Hardcopy submission at counter OSC for 6 technical departments (OSC, JAB.
Perancang, JKR, JPS, IWK, Jab. Penilaian)

You might also like