Background of The Company
Background of The Company
1500 V DC
Railway electrification in India began with the first electric train (1500 V DC),
between Bombay Victoria Terminus and Kurla on the Great Indian Peninsula Railway's
(GIPR) Harbour Line, on 3 February 1925. Steep grades on the Western Ghats necessitated
the introduction of electric traction on the GIPR to Igatpuri on the North East Line and
to Pune on the South East Line. 1500 V DC traction was introduced on the suburban section
of the Bombay, Baroda and Central India Railway between Colaba and Borivili on 5 January
1928, and between Madras Beach and Tambaram of the Madras and Southern Mahratta
Railway on 11 May 1931, to meet growing traffic needs. The last sections of 1500 V DC in
India, from Chatrapati Shivaji Terminus Mumbai to Panvel and Thane to Vashi, were
upgraded to 25 kV AC in April 2016.
3000 V DC
25 kV AC
Conversion
Considering the limitations of the existing DC traction system, a decision was made to
convert to 25 kV AC traction in 1996-97. Conversion from DC to AC traction was completed
in 2012 by Western Railway and in 2016 by Central Railway. With this, the entire electrified
mainline rail network in India uses 25 kV AC; DC is used only for metros and trams.
The electrification office was established in Calcutta as Project Office for Railway
Electrification (PORE) in 1951, when electrification of the Howrah–Burdwan section of the
Eastern Railway was begun. A general manager headed the Railway Electrification
Organisation, established in Calcutta in 1959. In 1961, the Northern Railway electrification
office (headed by an engineer-in-chief) was established in Allahabad for the electrification of
the Mughalsarai–New Delhi section. In accordance with the 1978 .
Organisation Structure
Human resources
Staff are classified into gazetted (Groups A and B) and non-gazetted (Groups C and
D) employees. Gazetted employees carry out executive / managerial / officer level tasks. As
of March 2017, the number of personnel (Groups A & B) constitutes 1.2% of the total
strength, while Group C & D account for 92.6% and 6.2% respectively.
The training of all groups is shared among seven centralized zonal training institutes and 295
training centres located all over India.
Production Services
The Indian Railways manufactures a lot of its rolling stock and heavy engineering
components. This is largely due to historical reasons. As with most developing economies,
the main reason is import substitution of expensive technology related products. This was
relevant when the general state of the national engineering industry was immature.
Production Units, the manufacturing plants of the Indian Railways, are managed directly by
the ministry. The General Managers of the PUs report to the Railway Board. The Production
Units are
The Indian Railways is among the world’s 3rd largest rail networks. The Indian
Railways route length network is spread over 115,000 km, with 12,617 passenger
trains and 7,421 freight trains each day from 7,349 stations plying 23 million
travellers and 3 million tonnes (MT) of freight daily. India's railway network is
recognised as one of the largest railway systems in the world under single
management.
The railway network is also ideal for long-distance travel and movement of bulk
commodities, apart from being an energy efficient and economic mode of conveyance
and transport. Indian Railways was the preferred carrier of automobiles in the country
with loading from automobiles traffic growing 16 per cent in 2017-18.
The Government of India has focused on investing on railway infrastructure by
making investor-friendly policies. It has moved quickly to enable Foreign Direct
Investment (FDI) in railways to improve infrastructure for freight and high-speed
trains. At present, several domestic and foreign companies are also looking to invest
in Indian rail projects.
Market Size
Indian Railways’ revenues increased at a CAGR of 6.20 per cent during FY07-FY18
to US$ 27.71 billion in FY18. Earnings from the passenger business grew at a CAGR
of 6.43 per cent during FY07-FY18 to reach US$ 7.55 billion in 2017-18P. Freight
revenue rose at a CAGR of 6.36 per cent during FY07-FY18 to reach US$ 18.16
billion in 2017-18.
India was among the top 20 exporters of railways globally, as of 2017. India’s exports
of railways have grown at a CAGR of 27.05 per cent during 2010-2017 to US$
303.29 million. Exports of railways in 2018 stood at US$ 454.99 million.
TRAINING DESCRIPTION
Power Supply
25 kV, AC, 50 Hz single phase power supply for electric traction is derived from the
grid of State Electricity Boards through traction sub-stations located along the route of the
electrified sections at distance of 35 to 50 km apart. The distance between adjacent
substations may however be even less depending on intensity of traffic and load of trains.
At present there are broadly four different arrangements in existence as under
1. The Supply Authorities supply power at 220/132/110/66 kV Extra High Voltage (EHV) at
each traction substation which is owned, installed, Operated and maintained by the Railways.
2. The Railway receives 3-phase power supply from the supply Authority at a single point
near the grid substation from where the Railway runs its own transmission lines providing its
own traction sub-stations.
3. All EHV and 25 kV equipment is owned, installed, operated and maintained by the Supply
Authority except 25 kV feeder circuit breakers which are owned, installed, operated and
maintained by the Railway.
4. All EHV and 25 kV equipment is owned, installed, operated and maintained by the Supply
Authority but 25 kV feeder circuit breakers alone are operated on remote control by the
Traction Power Controller (TPC).
Duplicate Supply
1. To ensure continuity of supply under all conditions, the high voltage feed to the traction
substations is invariably arranged wither from two sources of power or by a double
transmission line, so that if one source fails the other remains in service. Suitable protective
equipment is installed at the substations to ensure rapid isolation of any fault in transmission
lines and substation equipment, so that the power supply for electric traction is maintained
under all conditions.
2. At each traction substation, normally two single phase transformers are installed, one
which is in service and the other is 100% stand by. The present standard capacity is 21.6
MVA (ONAN)/30.2 MVA (ONAF).
However transformers of capacity 13.5 MVA (ONAN)/10.8 MVA (ONAN) have also
been used at many of the substations. These transformers step down the grid voltage to 25 kV
for feeding the traction overhead equipment (OHE). 25 kV feeders carry the power from the
substations to feeding posts located near the tracks. Each feeder is controlled by a single pole
circuit breaker equipped with protective devices.
Voltage Regulation
The permissible variation of the bus bar voltage on the bus bars at the grid substations
is +10% and -5% i.e. between 27,500 V and 23750 V. The tapings on the transformers are on
the secondary winding and set to ensure the voltage is maintained as high as possible but not
exceeding 27.5 kV at the feeding post at any time.
25 kV Supply at Traction Substations
1. On the secondary side one transformer circuit breaker and one feeder circuit breaker are
installed with associated double pole isolator the bus bar connections being such that full
flexibility of operation is assured.
2. The traction substation is designed for remote operation.
3. The facilities exist to change over from one feeder to the other by means of isolator/bus
coupler.
4. One end of the secondary winding of the transformer is solidly earthed at the substation
and is connected to track/return feeder through buried rail.
POSTS IN ELECTRIFICATION
Electrical power is generated in three phases with each phase having a phase shift of
1200. The utility power supply system also expects equal loading on all phases. Traction
power system works on single phase 25kV traction system. It now becomes important to use
all the three phases equally and convert them into one phase traction supply. This is achieved
by feeding single phase supply to the adjacent traction substation which is separated by a
neutral section. Each feed covers a distance of about 30-40Km feeding all the trains in that
zone. By the theory of probability, equal numbers of trains in feed zone are expected,
drawing same load current. In this way un-balancing on utility power supply system is
avoided
The neutral section is a dead zone and therefore, the locomotive has to negotiate the
section in momentum. The locomotive is switched off while negotiating the neutral section to
avoid flash over at the time of exit and re-entering the live zone. For this, warning board at
500M, 250M and final board for switching OFF and ON are provided. The assistant loco
pilot speak out the approaching neutral section loudly to alert the loco pilot. Loco pilot also
acknowledges the voice by repeating the approaching neutral section and is in readiness to act
so that he should not enter the neutral section with DJ/VCB in ON condition.
TRANSFORMER IN ELECTRIFICATION
Next to transformer, the other important equipment at any substation is the circuit
breaker. Circuit breakers play an important role in the control and performance of a power
supply system. From consideration of cost aspect also the circuit breakers constitute as a
major item. Power circuit breakers are designed not only to carry the rated normal currents
continuously but isolate the faulty section of the system under all normal and abnormal
condition, and shall also be capable of interrupting load currents, capacitive and small
inductive currents. They must be capable of clearing terminal and short line fault and shall
also be capable to operate reliably under all ambient temperatures, under severe polluted
conditions and at high attitudes. Voltages induced in the system due to switching operations
shall be minimum.
Different types of circuit breakers use different types of quenching medium like oil,
compressed air, SF6 gas and vacuum bottles. Till recently Indian Railways were using oil
circuit breakers for control of traction power supply system. In the initial stages of a.c.
electrification these breakers were imported but later on these were procured from reputed
indigenous manufacturers. The maintenance cost of oil circuit breakers particularly when
used as feeder circuit breaker, various from Rs.3000/- to Rs.40,000/- per annum depending
upon the number of trappings. Experience has shown that at some of the traction. substation
oil circuit breakers are just not able to meet the required duty due to very high cost of
maintenance.
To minimise the rising maintenance cost and to keep the down time of the breaker to bare
minimum, Indian Railways have adopted switchgear based on modern technology i.e. SF6
gas and vacuum. In all future electrification schemes, so far as 25 kV feeder circuit breakers
are concerned, will be either of SF6 gas type or vacuum type.