Assignment 3 Pem Due Date 10nov2010
Assignment 3 Pem Due Date 10nov2010
Deadline: 10/11/2010
ASSIGNMENT 3
PROJECT PLANNING & SCHEDULING (PROBABILISTIC)/ PROJECT
MONITORING & CONTROL/ PROJECT IMPLEMENTATION
1. A Beta distribution is assumed for activity times in PERT. For this distribution
(a) Estimate the value of the constant K in terms of the shape and location
parameters.
(b) Derive the mean and variance of this distribution
(c) For what values of the shape parameters do you get the formulas for the
mean and variance that are typically assumed in PERT.
2. For the following probability distributions calculate the mean and variance
TABLE A
Job Predecessors Duration
A -- 10
B -- 4
C A 66
D A 8
E A 8
F B,C 6
G D,F 15
H D,F 4
I E,H 7
1
4. Perform the computations of 3 under the following situation
(a) Each activity has a Beta distribution with a,c,b, value of 4,8,12
(b) Each activity has a Uniform distribution with a,b values of 4,12
(c) Each activity has a Triangular distribution with a,m,b values of 4,8,12.
(d) Each activity has an Exponential distribution with mean of 8
(e) Each activity has a Normal distribution with mean 8 and variance 1.44…
(f) Each activity has a discrete distribution 6,7,8,9,10 with equal
probabilities.
5. For the network in Table A with triangular distribution for all activities assumed as in
Question 4 (c) use chance constrained programming to determine all the node times such that
for all jobs the probability of completion is
(a) 90%
(b) 95%
(c) 99%
Compare these results with the corresponding values under standard PERT assumptions showing
how optimistic PERT is under these circumstances.
6. The jobs of the following network have the indicated time estimates
2
7. For the small network given below
3 5
1 4 6
(a) If all activities have a triangular distribution with a=5, m=a, b=20 what are the
node times such that each activity duration is accommodated with 95%
confidence?
(b) What are the corresponding times under standard PERT assumptions?
Assume that the jobs can be done at either normal or fail pass, but not at any pace in between.
Plot the relationship between project completion time and minimum total project cost. (Solve by
path enumeration and heuristic reasoning).
A. Compare the pattern of expenditure for both an early start and a late start schedule.
B. If the rate of interest is 10% compute the NPV for both the early and the late start
schedules.
C. Time and phasing of expenditure from now onwards?
3
D. The late start schedule is chosen for implementation and the progress is monitored after 6
months. The following status is observed:
10. You are exposed to following situations. As an experienced project manager, justify
your decisions in each case.
Situation 1: Below are several factors that can result in project delays and cost overruns. Explain
how these problems can be overcome.
A. Poorly defined milestones
B. Poor estimating techniques
C. A missing PERT/CPM chart
D. Functional managers not having a clear understanding of what has to be done
E. Poor programming procedures and techniques
F. Changes constantly being made deep in the project's life cycle
Situation 2: Alpha Company has implemented a plan whereby functional managers will be held
totally responsible for all cost overruns against their (the functional managers') original estimates.
Furthermore, all cost overruns must come out of the functional managers' budgets, whether they
be overhead or otherwise, not the project budget. What are the advantages and disadvantages of
this approach?
Situation 3: Karl has decided to retain a management reserve on a $400,000 project that includes
a $60,000 profit. At the completion of the project, Karl finds that the management reserve fund
contains $40,000. Should Karl book the management reserve as excess profits (i.e., $100,000), or
should he just book the target profit of $60,000 and let the functional managers "sandbag" on the
slush fund until it is depleted?
4
E. Ability to update status as events are completed
F. Understanding the reasons for the need of trade-offs
G. Centralization of decision making
H. Short-term resource control
I. Ability to assimilate large amounts of data
J. Variety and frequency of political changes
K. Variety and frequency of economic changes
L. Governmental supporting-policy measures
M. Inadequacies of subcontractors
N. Lack of accurate information
11. Speciality Services, Inc., is a field computer repair operation serving the small commercial
industry in seven states. Speciality Services has one operation in each state, and they vary in
size from 50 to 240 employees. A disturbing trend has been developing for the last couple of
years that Speciality Service management wishes to stop. The incidence of tardiness and
absenteeism is on the increase. Both are extremely disruptive in a custom packing operation.
Speciality Service is nonunion in all seven locations, and since management wants to keep
this situation, it wants a careful, low-key approach to the problem. Jason Horn, assistant
personnel manager, has been appointed project manager to recommend a solution. All seven
operations managers have been assigned to work with him on this problem. Jason has had no
problem interfacing with the operations mangers. They have very quickly agreed that three
steps must be taken to solve the problem:
A. Institute a uniform daily attendance report that is summarized weekly and
forwarded to the main office. (Current practice varies from location to location, but
comments on attendance are normally included in monthly operations reports)
B. Institute a uniform disciplinary policy, enforced in a uniform manner
C. Initiate an intensive employee education program to emphasize the importance of
good attendance.
The team has further decided that the three-point program should be tested before a final
recommendation is presented. They have decided to test the program at one location for two
months. Jason wishes to control and evaluate the test by having the daily attendance report
transmitted to him directly at headquarters, from which he will make the final decision on
whether to present the program in its current format or not.
Questions:
a) Does this monitoring and control method appear adequate?
b) What are the potential problems?