Kirby Building Systems: Preventive Maintenance Manual

This document is Kirby Building Systems' preventative maintenance manual. It provides guidelines for maintaining the structural steel, secondary framing, roof, walls and panel finishes of Kirby buildings. Key areas covered include inspecting for and addressing rust, loose bolts, debris on the roof, lap joint seals, and cleaning or repairing scratches on the panel finishes. Safety precautions are emphasized, especially around skylights.

Uploaded by

Lalaine Ramos
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
298 views

Kirby Building Systems: Preventive Maintenance Manual

This document is Kirby Building Systems' preventative maintenance manual. It provides guidelines for maintaining the structural steel, secondary framing, roof, walls and panel finishes of Kirby buildings. Key areas covered include inspecting for and addressing rust, loose bolts, debris on the roof, lap joint seals, and cleaning or repairing scratches on the panel finishes. Safety precautions are emphasized, especially around skylights.

Uploaded by

Lalaine Ramos
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

Kirby Building

Systems
124 Kirby Drive – Portland, TN. 37148
www.kirbybuildingsystems.com

Preventive
Maintenance
Manual

Revised 7/30/14

124 Kirby Drive


Introduction
Kirby Building Systems would like to take this opportunity to again thank you for your
recent purchase of a Kirby building. The purpose of this manual is to assist your efforts in
maintaining and protecting your new building. Just as with your home, your Kirby
building will occasionally need attention to maintain current aesthetic appeal, warranty
coverage, weather tightness and proper working order of accessory items. Please use and
follow appropriate Safety guidelines when performing any maintenance activities.

Section 1 – Structural Steel


Rusting – Structural steel normally requires no maintenance, except in the event of rust.
Should rust occur, clean the affected area and re-paint with primer supplied by Kirby
Building Systems or a compatible substitute primer.

Loose Bolts – Structural bolts also normally require no maintenance except in instances
where the structure is exposed to vibration, such as a building with an overhead crane. In
this instance bolts should be inspected at least once a year or per OSHA requirements.
Crane bracing should also be checked at least once a year.

Additional Loads – Before hanging any items from the building’s framing or adding any
additional loads to the roof (piping, roof top units, jib cranes, etc.), call your local Kirby
Building Systems authorized Builder. In the event an authorized Builder is not available,
contact the Customer Service Department of Kirby Building Systems for assistance.

Crane Loads – If the initial engineering and design of your building included an overhead
crane, your building would have been designed in strict accordance with specific load
requirements. Your local Kirby Building Systems authorized Builder must verify any
change to the building from the original design. In the event an authorized Builder is not
available, contact the Customer Service Department of Kirby Building Systems before
proceeding.

Bracing – Kirby bracing is critical to the structural integrity of the building and should
remain in place. No bracing should be relocated or removed without verification by your
local Kirby Building Systems authorized Builder. In the event an authorized Builder is not
available, contact the Customer Service Department of Kirby Building Systems for
assistance.

Section 2 – Secondary Framing


Loose Bolts – Secondary-framing connections should be checked periodically in areas of
high vibration, such as areas around overhead cranes and overhead or sliding doors. If
loose bolts are found, they should be tightened and re-inspected annually.

1
Section 3 – Roof and Walls
Roof and Walls In General – Your roof and wall panels should not come in contact with
wood, lead, copper, unprotected steel, graphite, concrete or harsh chemicals. Never allow
air conditioning condensation to drain onto your roof, trim or wall panels! Roof and wall
panels should be kept clear of dirt and soil.

Roof Debris – At least once a year, clean the roof and gutters of leaves or other debris
which would trap or pond water on the roof. Wash dirt and debris from the panel surface
annually. Local conditions will govern the frequency of these cleanings.

Ice and Snow Buildup – Excessive ice and snow should be removed from the roof areas.
This is particularly important in gutter areas (eaves and valleys) and in areas of the roof
sheltered from the wind (behind facades, step roof conditions, etc.). Reference pages 8, 9,
& 10 for specific snow removal procedures.

Roof Traffic - Roof traffic is a leading cause of roof leaks. If routine traffic is
unavoidable, have your builder install a walkway designed for use with your roof panel.

When walking on the roof is required:


Avoid stepping on the ridge caps
Avoid stepping on lap joints in roof panels and flashings
Avoid walking near roof curbs or other roof penetrations
Avoid stepping on panel ribs between purlins
Do not step in or on gutters or the gutter hanging system
Do not step on or near skylights

Foliage – While shrubs and trees enhance the appearance of any building, their contact
with the wall panel can produce scratches in the painted surface that will eventually cause
problems. Keep shrubs and trees trimmed back from the panel surfaces.

Yearly Lap Joint Inspection – Once a year check lap joints in the metal for proper seal or
loose fasteners. Should repair be required, have your Builder remove fasteners, take
connection apart, clean out existing sealant, install new tape mastic and/or polyurethane
sealant to form a continuous gasket and reattach the connection using new and/or larger
long life fasteners as necessary. Care should be taken to ensure the new gasket is in the old
screw line or to the weather side of the screws.

!!! CAUTION !!! If skylights are present in your roof, extreme care should be exercised
when working in those areas. NEVER STEP DIRECTLY ON A SKYLIGHT, OR IN
THE SURROUNDING AREA ADJACENT TO A SKYLIGHT. Skylights may not
support the weight of a worker, and bodily harm could result from a fall. Please follow all
OSHA and/or other state and local safety guidelines applicable for the particular
jurisdiction.
2
Section 4 – Panel Finishes

Always test cleaning procedures in a small inconspicuous area before use on a large
scale.

Routine Washing – (IMPORTANT WARRANTY NOTICE: If located within a 1000


feet of a saltwater shoreline, painted roofing or siding must be washed with potable
water annually to maintain warranty coverage.) A log sheet has been provided on page
12 to record annual washing data, necessary for continued warranty coverage. A 5%
solution of commonly used commercial detergents can be used on heavily soiled areas and
will not harm your panel surface. Always rinse thoroughly with water. Do not use wire
brushes, steel wool, sandpaper, abrasives or similar cleaning tools which will mechanically
abrade the coating surface. Use a cloth, sponge or a soft bristle brush for application. For
best results, cleaning should be done in the shade or on a mild cloudy day.

Rust – Once a year inspect the panels for rust. Should any rust or rust stains be found,
determine the source, such as steel filings from drilling, sawing, grinding, etc. and remove
them. The rust stain can generally be cleaned off with one of the following: soap and
water, mineral spirits, or a mild polishing compound as used on a car finish.

Paint Scratches – Scratches to the paint should be brush touched (artist brush) with
touchup paint. If the scratched area has not rusted, the paint may be applied without
surface preparation. If the area is rusted, remove the rust; prime the affected area and brush
with color matched touchup paint. Primer and additional touchup paint is available from
your Kirby Building Systems authorized Builder or from Kirby Building Systems.

Mildew Removal – Mildew can be expected in areas of high humidity. Mildew is more of
an appearance problem than an actual threat to the paint finish. Mildew can be removed by
using a basic solution of the following:

1/3 cup of detergent


2/3 cup trisodium phosphate
1 quart sodium hypochloride, 5 % solution
3 quarts of water

Rinse with clean water immediately after use.

Non-Water Soluble Deposits On Zinc-Aluminum Finishes – Use mineral spirits to


remove non water soluble deposits (tar, grease, oil, paint, graffiti, etc.) from the panel
surface.

3
Non Water Soluble Deposits On Kynar paint finishes – Solvents that may be used to
remove these items from Kynar paint panel finishes include:

Alcohols - Not aesthetically detrimental when properly applied


Denatured Alcohol (Ethanol)
Isopropyl (Rubbing) Alcohol
Methanol (Wood Alcohol)-Note: Methanol is toxic

Petroleum Solvents - Not aesthetically detrimental when properly applied


VM & P Naphtha
Mineral Spirits
Turpentine (Wood or Gum Spirits)

Aromatic and Other- Use with caution on Diamond Kote


Xylol (Xylene)
Toluol (Toluene)

Limit contact time to 5 minutes maximum and test before


using.

Ketones, Esters, Lacquer Thinner – Use very cautiously on Kynar paint surfaces.
Limit contact time to 1 minute maximum and test before using. Kirby Building
Systems is not responsible for damage caused by unrestricted use.

DO NOT use acetone paint remover, Methyl Ethyl Ketone, or Methyl Isobutyl
Ketone on Kynar paint surfaces. Continued contact with these products could result
in blemishes detrimental to the aesthetics of your metal building.

Most organic solvents are flammable and/or toxic and must be handled
accordingly. Keep away from open flames, sparks and electric motors. Use
adequate ventilation, protective clothing and goggles.

Sealant Removal – Precautions should be taken to prevent sealants from getting on the
Kynar paint surface, as they may be difficult to remove. Sealants should be removed
promptly with a solvent such as alcohol or a naphtha type of solvent. Caution: It may be
possible for solvents to extract materials from sealants that could stain the painted surface
or could prove harmful to the sealants. Test a small inconspicuous area first, before wide
spread use.

4
Section 5 – Trim
Gutter and Downspouts – Clear all debris (leaves, dirt, etc.) from gutters and downspouts
as required. The frequency required is dependent on the building’s surroundings.

Damaged Trim – Trim around openings sometimes gets damaged by vehicle traffic.
Replacement trim can be obtained through your local Kirby Building Systems authorized
Builder.

Section 6 – Accessories
Walk Doors – Walk doors should be checked periodically to assure tightness of locksets,
closure hardware and door hinges. Any loose bolts or screws should be tightened. Any
moving parts that start to stick or squeak should be properly lubricated.

Windows – Caulking in windows will deteriorate in time, usually resulting in window


leakage. If this happens remove the old caulk and apply new caulk in its place. Windows
that become hard to slide should have the track area thoroughly cleaned and a light coat of
lubricant applied to the tracks.

Overhead Doors – Periodically check the attachment bolts around an overhead door and
tighten as required. Call the door manufacturer should the door get out of alignment or the
mechanical parts within the door become hard to operate.

Sliding Door - Periodically clean the sliding door tracks and lubricate the rollers to help
assure ease of use.

Roof Vents – Hard to operate roof vents are usually the result of pulleys and damper rods
needing lubrication or the chains and cords not being on track. Check operating hardware
and lubricate as needed.

Louvers – The operating hardware within a louver occasionally needs to be cleaned and a
new light coat of oil or grease applied. This will improve the ease of operation.

Roof Curbs – Heavy vibration from a mechanical unit can cause water leakage around a
roof curb. Should this occur, check the sealant and fasteners around the curb. Any loose
fasteners should be tightened or replaced with the next larger size. Any sealant or mastic
that has deteriorated should be removed and replaced with new. If possible, isolate the unit
from the curb to minimize vibration to the curb.

Windows, doors, vents, and louvers should be checked yearly for loose fasteners and any
moving parts lubricated as necessary.

5
Section 7 – Insulation
**Inspect the exterior of your building for exposed insulation and call your contractor
immediately if found. Exposed insulation will wick and hold water against the ends
and back side of the panels, causing rust to occur.

Insulation Facings – Insulation facings should be monitored continuously and a thorough


inspection made once a year. Any holes or tears in the facing should be repaired with patch
tape as supplied by the insulation supplier. Remember, even a perfectly installed barrier is
not a perfect vapor barrier.

Condensation – If your building is experiencing excessive condensation, consult your


HVAC contractor to assure that humidity levels and air movement are as projected. Also,
have your building contractor check to make sure there are no obvious openings in the
insulation splices.

Section 8 – Roof Leaks


Should you observe evidence of a roof leak, such as water on the floor, stained ceiling tiles
or a bubble in the insulation vapor barrier, contact your building contractor immediately.
After the leak has been repaired, have your contractor cut the vapor barrier where the water
has collected to allow the wet insulation to drain. Once the insulation has thoroughly dried,
repair the vapor barrier with patch tape available from the insulation supplier. There are
various reasons a roof leak might occur, such as:

 Improper installation
 A lack of routine maintenance
 Damage to a component
 Deterioration of a component

It is also possible that a leak might not be the result of the above referenced conditions, but
rather the result of a strong negative pressure inside the building from an improperly
balanced HVAC system.

Section 9 – Replacement Parts or Service


Replacement parts or service can be obtained through your local Kirby Building Systems
authorized Builder. In the event an authorized Builder is not available call Kirby Building
Systems at (615) 325-4165 and ask for Customer Service. When calling Kirby, have the
original job number, year built, name of the project and original Builder handy. This will
help us identify and locate your specific building and aid us in supplying replacement parts.

6
Section 10 – Primer Touchup Procedures /Field Painting
Shop Coat Primer – General

The coat of shop primer is intended to protect the steel framing for only a short period of
exposure to ordinary atmospheric conditions. The coat of shop primer does not provide the
uniformity of appearance, or the durability and corrosion resistance of a field applied finish
coat of paint over a shop primer. Minor abrasions to the shop coat caused by handling,
loading, shipping, unloading and erection after painting are unavoidable.

Field Primer Touchup – Procedures

All surfaces to receive touch up primer must be cleaned of loose rust, scale, dirt and other
foreign matter by using the hand tool cleaning method SSPC-SP2 (Society for Protective
Coatings) prior to touch up. Power tool cleaning, sandblasting, flame cleaning, or chemical
cleaning is not required or recommended.
Only a water-based or latex primer may be used to touch up steel framing. Application of
touch up primer may be through the use of spray equipment or standard brushes and rollers.
Primer can be purchased through your local Kirby Building Systems authorized Builder or
contact the Components Department of Kirby Building Systems.

Field Applied Finish Paint

Steel Framing or Sheeting Wash Coat


Any water based latex paints may be used. Do not use shop coat primers that either contain
over 10% aromatic solvents or that contain ketone or acetate solvents. Typical enamels
that contain mineral spirits or VM and P Naphtha solvents may be used.
If top coating with epoxy or ketone based coatings is required, it is recommended that a
barrier coating primer be used. Check with your paint supplier before top coating with
epoxy or ketone based coatings.
Always test paint in an inconspicuous area to ensure good results before painting entire
structure.

Sheeting Finish Coat


It is recommended that you contact a reputable paint supplier for instruction and suggested
materials to use for painting over any sheeting finish coat.

7
SNOW REMOVAL PROCEDURES

Introduction
One of the most detrimental climatological conditions to metal buildings is snow and ice
buildup on the roof. Snow buildup to any significant depth greatly increases loads on the
roof. While much of the snow will tend to slide off steeper roofs, (4:12 slope), much will
remain that falls on a cold surface or previously covered surface. Snow will tend to slide
more readily on a warm roof, caused either from sunshine or heat loss through the roof.
Relatively little snow will slide off roofs with low slope.

Drainage
Gutters, downspouts and interior roof drains allow for the controlled removal of water from
a roof system. They must be kept open and free flowing to work. During cold temperature
conditions gutters, downspouts and drains can freeze solid allowing for ice build-up on the
roof. This ice build-up causes additional water back up on the roof deck. These
circumstances create extreme loading conditions on the roof system and building. Freezing
conditions are particularly likely on the north side of a building and in shaded areas of a
building.

One recommended precaution is to have heat tape installed in gutters and downspouts.
This will help maintain open and flowing gutters and downspouts. However, in extremely
low temperature conditions, heat tapes may not be 100% effective and should be checked
regularly.

When to Remove Snow


Defining a specific depth of snow that a building has been designed to support is not
possible because the density of snow is variable and dependent upon weather conditions
both during and after a snowfall. With the variability of snow density, it is possible for
conditions to exist that exceed the designs specified by the building codes. Snow density
also changes as the snow melts. Not all water drains off the roof as the underlying snow
absorbs some water from the melted snow above. This leads to ice build-up on the roof as
the temperature varies from day to night.

8
Normal snowfall weighs between 10 and 12 pounds per cubic foot (pcf) but will greatly
increase as it compacts and becomes heavier with water. When there is snow on the roof of
a building and rainy conditions occur, excessive loads can develop rapidly. Snow acts as a
sponge in these conditions and loads can approach the weight of water, 62.4 pcf or 5.2
pounds per square foot (psf) per inch of depth. Rarely will a cubic foot of snow and ice
equal the weight of water due to the expansion that takes place as water freezes. However,
these conditions must be monitored with extreme caution.

Snow will build up in areas around firewalls, parapet walls, valleys, dormers and on lower
roof levels where a step in the roof occurs. All current building codes require design for
snow build-up conditions so that the structural systems in these areas can support the
additional loads. However, due to the variability of snow density, as noted above, it is
possible for conditions to exist that exceed the design specified by the building codes.

While it is not possible to accurately determine a specific depth of snow that is considered
a safe maximum, an approximation can be made. The first step is for the building owner to
obtain information as to the snow load that the building has been designed to carry. For
example, a building designed for a 30 psf snow load can be assumed to be overloaded with
three feet of snow weighting 10 to 12 pcf and could be overloaded with just one foot of
snow under wet conditions. While a 30 psf design snow load may allow roughly 45 to 50
psf before the possibility of collapse exists, there is such a wide variation in snow density
that it would be unwise to allow this much snow load to accumulate. Cleaning the roof is,
of course, the only way to relieve this. It is a common industry practice that roofs be
cleared of snow when half of the safe maximum snow depth is reached. The maximum
snow depth can be estimated based on the design snow load and the density of the snow
and/or ice buildup.

Snow/Ice Removal Procedure


Following are some suggestions, which generally apply; however, it is recommended that
the building manufacturer or a structural engineer be consulted before snow removal is
initiated.

1. Remove all hanging icicles from eaves and gutters. These will be quite heavy and if
snow hangs up on them during removal, it can only increase this load. Care must be
exercised to not damage the building and not endanger pedestrians.

2. Always provide proper safety precautions when working on the roof. If possible,
remove snow by not getting on the roof. This can sometimes be done by using
draglines through the snow, working from the end walls.

3. Place ladders at the end of the building so sliding snow will not dislodge them.

4. Never send one person alone on a roof to remove snow.

9
5. Remove snow in a pattern that does not cause an unbalanced loading condition. Avoid
large differences in snow depth between adjacent areas of the roof. Do not remove all
of the snow from small areas and then move on to another area. Instead, remove the
snow in layers from all over the roof. This gradually decreases the load.

6. Remove drifted areas first, down to a level with other snow. If an area has drifted four
feet deep and the main roof is two feet deep, trim off the drifts to two feet before
proceeding.

7. Remove snow from the eave towards the ridge, sliding the snow off the roof over the
gutter.

8. Progress from each end of the building towards the center. On larger roof areas,
additional people working from the center of the building towards the ends is
recommended.

9. On gable buildings, remove snow on both sides of the ridge at the same time.

10. Never use metal shovels on any type of roof. Do not use picks, axes or other sharp
tools to break up ice on the roof. It is quite easy to damage the roofing with these tools.

11. Do not remove snow to less than a 3” depth over roof sheets. Care must be taken to
eliminate hitting panel fasteners, snow guards, etc. If an ice layer is next to a panel, it
should be left if not extraordinarily thick.

12. Care must be taken in removal of ice and snow around ventilator bases, pipe flashings,
and HVAC units, due to the ease of damaging neoprene boots, pipes, conduits, etc.

13. Be cautious of snow or ice breaking away and sliding down the roof, even on low slope
roof buildings.

14. Use extreme care when working along the edge of the roof.

15. Watch for extreme deflections and listen for unusual noises when snow and ice build-
up conditions exist.

!!! CAUTION !!! If skylights are present in your roof, the snow you are in the process
of removing may conceal their location. Extreme care should be exercised when working
in those areas. NEVER STEP DIRECTLY ON A SKYLIGHT, OR IN THE
SURROUNDING AREA ADJACENT TO A SKYLIGHT. Skylights may not support
the weight of a worker, and bodily harm could result from a fall. Please follow all OSHA
and/or other state and local safety guidelines applicable for the particular jurisdiction.

10
BUILDING MAINTENANCE LOG
(WASH YOUR BUILDING ANNUALLY, IF WITHIN 1000' OF SEASHORE)

YEAR DATE SIGNATURE YEAR DATE SIGNATURE


1 19
2 20
3 21
4 22
5 23
6 24
7 25
8 26
9 27
10 28
11 29
12 30
13 31
14 32
15 33
16 34
17 35
18

COMMENTS: