Piping Fabrication 5
Piping Fabrication 5
Complete Piping Fabrication, Pressure and NDT testing, Cleaning and Painting
CONTRACTOR shall fabricate piping spools in accordance with the attached
piping isometric drawings. Piping shall be 100% prefabricated, there shall be no
field welds.
CLIENT shall free issue the pipe, fittings and flanges to the CONTRACTOR
CONTRACTOR to supply remaining materials to complete the work
(consumables, hydro test materials - plugs, gaskets, stud bolts etc)
Pressure testing by water shall be conducted for all spools.
NDT examination shall be conducted for a percentage of spools
Visual Inspection – 100%
Radiography – 10%, as per specification
Liquid Penetrant – 10% of all fillet welds, plus one weld from each heat
Piping spools shall be cleaned by acid cleaning process before sealing the spools
for transport.
Spools shall undergo surface preparation before painting. Spools shall be free
from dirt, dust or grease before painting.
Pipe Support Material Supply, Fabrication, Testing and Cleaning and Painting
CONTRACTOR shall supply the pipe support materials based on the
requirements from the attached piping support drawings.
CONTRACTOR shall fabricate the pipe supports in accordance with the attached
specification (AFE361318-ENG-PIP-SPC-0001-R0)
Pipe supports shall be supplied with loose shimming plates for shimming on site.
Pipe supports shall be attached to existing structures by bolting.
3. Documentation
QAQC
ITP
WPS
PQR
Equipment & Material (Consumables & Paint) Test Certs
Marked up Fabrication Isometrics (Weld No’s, Spool IDs, Heat Nos etc)
Project Management / Planning
Fabrication Schedule
Weekly Progress Reports (including, but not limited to: % Complete, Photos,
Schedule)