Project: MECP, Delhi Month: Apr'18 Daywise Workplan: Note Work Hampered Due To Rain (08-04-2018)

This document contains a workplan for the month of April 2018 for the MECP project in Delhi. It provides details of the total planned and completed quantities for various construction activities under the flyover and underpass sections. As of April 8th, 2018 pier construction was ongoing for the flyover with 5.5 piers completed that month, while retaining wall construction progressed with 25.5 cubic meters completed for the underpass. Several activities like girder erection and crash barriers installation were still significantly behind schedule according to the workplan.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views1 page

Project: MECP, Delhi Month: Apr'18 Daywise Workplan: Note Work Hampered Due To Rain (08-04-2018)

This document contains a workplan for the month of April 2018 for the MECP project in Delhi. It provides details of the total planned and completed quantities for various construction activities under the flyover and underpass sections. As of April 8th, 2018 pier construction was ongoing for the flyover with 5.5 piers completed that month, while retaining wall construction progressed with 25.5 cubic meters completed for the underpass. Several activities like girder erection and crash barriers installation were still significantly behind schedule according to the workplan.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project : MECP, Delhi

Month : Apr'18
Daywise Workplan 8-Apr-18
Completed Month
Sl. Till 31st Mar Today Completed Balance As
Total planned Qty: UOM Total Actual Till
No. 2018 Actual Till Date on Date
Date
Flyover
1 Pile No.s 502 502 - - 502.00 -
3 Pilecap: No.s 104 104 - - 104.00 -
4 Open foundation: No.s 35 34 - - 34.00 1.00
5 Pier: No.s 139 110 1.00 5.50 115.50 23.50
6 Pier cap: No.s 17 17 - - 17.00 -
7 Portal beam: No.s 61 30 - - 30.00 31.00
8 Girder Supply MT 5,470 2,990 - - 2,990.00 2,480.00
9 Girder Fabrication MT 5,470 1,782 - - 1,782.00 3,688.00
10 Transportation MT 5,470 584 21.48 657.75 1,241.75 4,228.25
11 Girder Erection MT 5,470 300 - - 300.00 5,170.00
12 RE wall erection: sqm 3,700 3,214 - - 3,214.00 486.00
13 RE wall filling: Cum 12,596 10,956 - - 10,956.00 1,640.00
Underpass :
1 Raft: Rmtrs 1,287 527 - - 527.00 760.00
2 Retaining wall: Cum 2,574 254 - 25.50 279.00 2,295.00
3 Crash barrier type2: Rmtrs 1,287 419 - - 419.00 868.00
4 Friction slab: Rmtrs 2,574 534 - - 534.00 2,040.00
5 Crash barrier type1: Rmtrs 2,574 - - - - 2,574.00
6 Skywalk pier: No.s 43 18 - - 18.00 25.00
7 Skywalk piercap: No.s 43 3 1.00 1.00 4.00 39.00
Note * Work hampered Due
to Rain (08-04-2018)